steel wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711209093.9A
Other languages
Chinese (zh)
Inventor
蒋花
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201711209093.9A priority Critical patent/CN108083130A/en
Publication of CN108083130A publication Critical patent/CN108083130A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C19/00Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries
    • B66C19/007Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries for containers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/52Details of compartments for driving engines or motors or of operator's stands or cabins
    • B66C13/54Operator's stands or cabins
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C5/00Base supporting structures with legs
    • B66C5/02Fixed or travelling bridges or gantries, i.e. elongated structures of inverted L or of inverted U shape or tripods
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C7/00Runways, tracks or trackways for trolleys or cranes
    • B66C7/08Constructional features of runway rails or rail mountings
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C9/00Travelling gear incorporated in or fitted to trolleys or cranes
    • B66C9/08Runners; Runner bearings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

The invention discloses a kind of container cranes with double luffing mechanisms of crane field,Left back crossbeam is provided on the left-hand door mount structure,The first running gear for trolley is movably set on the left back crossbeam,Left crossbeam is movably set on the right side of the left back crossbeam,The other end of first steel wire rope connects the right side at the top of left crossbeam,Crossbeam behind the right side is provided in the right doorframe structure,Behind the right side the second running gear for trolley is movably set on crossbeam,Behind the right side right crossbeam is movably set on the left of crossbeam,The other end of second steel wire rope connects the left side at the top of right crossbeam,Double luffing mechanisms reduce the travel time of running gear for trolley,Two groups of running gear for trolley accelerate the speed of container handling,And when one group of running gear for trolley needs maintenance and inspection,Also one group of running gear for trolley can be with normal operation,The jagged stair frame gradient is smaller to make climbing personnel more effortless.

Description

A kind of container crane and its handling method with double luffing mechanisms
Technical field
The present invention relates to crane fields, are specially a kind of container crane with double luffing mechanisms and its handling side Method.
Background technology
Now with the continuous growth of Container Transport amount, higher will be proposed to the performance configuration of container handling device It asks, to improve harbour handling ship operating efficiency, shortens container ship in port stopping time, so as to reduce logistics transportation cost, raising Harbour benefit uses in the world along bank formula arrangement at present in the container terminal of operation, and the container crane of configuration unifies cloth It puts in harbour one side, and container crane is single luffing mechanism, luffing mechanism includes preceding crossbeam, hinge and steel wire rope, After container ship leans on docking, container crane completes container by the container spreader in crossbeam structure before being suspended on Ship-discharging operation is filled, since container crane is arranged in ship one side, a set of luffing mechanism is set so that preceding crossbeam structure is very It is long, cause complete machine structure unbalance loading big;Suspender round trip operation stroke distances are long, cause duty cycle long, and operating efficiency declines, To improve container terminal loading and unloading ship operating efficiency, a kind of new container crane need to be developed.
The content of the invention
It is an object of the invention to provide a kind of container crane and its handling method with double luffing mechanisms, with solution Certainly the problems mentioned above in the background art.
To achieve the above object, the present invention provides following technical solution:A kind of container lifting with double luffing mechanisms Machine including cart walking mechanism, is provided with left-hand door mount structure, the right side big garage at the top of the cart walking mechanism of left side It walks to be provided with right doorframe structure at the top of mechanism, top is connected between the left-hand door mount structure and the adjacent surface of right doorframe structure Beam is provided with left back crossbeam on the left-hand door mount structure, the first running gear for trolley, institute is movably set on the left back crossbeam It states and the first power set is provided at the top of left back crossbeam, left crossbeam is movably set on the right side of the left back crossbeam, and it is left back Crossbeam and left crossbeam are flexibly connected by left axis pin, are connected with the first steel wire rope on the right side of first power set, and described The other end of one steel wire rope connects the right side at the top of left crossbeam, and the top on the right side of the left-hand door mount structure is provided with the first pull rod, The other end of first pull rod connects one end that left crossbeam is abutted against the first steel wire rope, and the left side top of the left-hand door mount structure is set The first back stay is equipped with, and the other end of the first back stay connects the left side at the top of left back crossbeam, is set in the right doorframe structure Be equipped with crossbeam behind the right side, it is described it is right after be movably set with the second running gear for trolley on crossbeam, first running gear for trolley and The bottom of second running gear for trolley is both provided with sling lifting mechanism, and the left side of the first running gear for trolley and the second trolley Be both provided with driver's cabin on the right side of walking mechanism, it is described it is right after be provided with the second power set at the top of crossbeam, it is described it is right after it is big Right crossbeam is movably set on the left of beam, and crossbeam and right crossbeam are flexibly connected by right axis pin behind the right side, the second power dress The left side put is connected with the second steel wire rope, and the other end of second steel wire rope connects the left side at the top of right crossbeam, the right door Top on the left of mount structure is provided with the second pull rod, and the other end of second pull rod connects right crossbeam and is abutted against the second steel wire rope One end, the right hand top of the right doorframe structure are provided with the second back stay, and big behind the other end connection right side of the second back stay The right side in back portion.
Preferably, first steel wire rope is bypassed from the top of left-hand door mount structure, and second steel wire rope is from right doorframe knot The top of structure bypasses, and is respectively arranged at the top of the left-hand door mount structure and right doorframe structure and the first steel wire rope and the second steel wire The directive wheel that rope matches, and directive wheel is provided with anti-falling device for steel wire rope.
Preferably, it is both provided with and running gear for trolley phase on crossbeam and right crossbeam behind the left back crossbeam, left crossbeam, the right side Matched carriage walking track, and the carriage walking track when left crossbeam and right crossbeam are laid flat on left crossbeam and right crossbeam is seamless Docking.
Preferably, stair frame, the horizontal stroke of the stair frame are both provided on front side of the left-hand door mount structure and right doorframe structure Section is serrated, and is provided with lobby on front side of stair frame.
Preferably, the bottom of the left-hand door mount structure and right doorframe structure is both provided with anchoring device.
Preferably, first pull rod and the second pull rod are folding pull rod.
Preferably, a kind of handling method of the container crane with double luffing mechanisms based on the device:
Step 1:First power set wind the first steel wire rope, and the folding and unfolding for passing through the first steel wire rope control left crossbeam around Left axis pin rotates, and the second power set wind the second steel wire rope, and the folding and unfolding for passing through the second steel wire rope controls right crossbeam around right pin Axis rotates;
Step 2:After left crossbeam and right crossbeam are laid flat, the success of carriage walking orbital docking, the first power set control the One running gear for trolley is walked on carriage walking track, and the second power set control the second running gear for trolley in carriage walking It walks on track;
Step 3:After the first running gear for trolley and the second running gear for trolley are gone to above container, the first power Device control sling lifting mechanism drops to packaging upper box part, is lifted by crane after being fixed sling lifting mechanism and container with lock pin, The first running gear for trolley drives container level to move to the surface of goods stock after container slings one end height, then controls Sling lifting mechanism processed declines, and container is placed on goods stock, and the second power set control sling lifting mechanism drops to Packaging upper box part lifts by crane after being fixed sling lifting mechanism and container with lock pin, and it is small that container slings after the height of one end first Vehicle walking mechanism drives container level to move to the surface of goods stock, then sling lifting mechanism is controlled to decline, by packaging Case is placed on goods stock;
Step 4:The first running gear for trolley is responsible for the handling of cargo-container ship upper left side container under normal circumstances, the Two running gear for trolley are responsible for the handling of right side container on cargo-container ship, when one group of running gear for trolley needs maintenance and inspection When, there is one group of running gear for trolley with normal operation to container can be transported to the one side pulled in shore, reduce walking distance.
Compared with prior art, the beneficial effects of the invention are as follows:The apparatus structure is simple, easy to use, double luffing mechanisms Reducing the travel time of running gear for trolley, two groups of running gear for trolley accelerate the speed of container handling, and when one group When running gear for trolley needs maintenance and inspection, there is one group of running gear for trolley can be with normal operation, on left crossbeam and right crossbeam Carriage walking track can the first running gear for trolley and the second running gear for trolley be allow in left and right crossbeam with slitless connection Upper arbitrarily walking, the jagged stair frame gradient is smaller to make climbing personnel more effortless, and lobby facilitates rest, and directive wheel plays Guiding role, anti-drop device prevent that steel wire rope from coming off directive wheel.
Description of the drawings
Fig. 1 is schematic structural view of the invention;
Fig. 2 is side view of the present invention;
Fig. 3 is left crossbeam of the invention and right crossbeam pull-up structure diagram.
In figure:1 cart walking mechanism, 11 left-hand door mount structures, 12 right doorframe structures, 13 top beams, 14 stair framves, 15 anchoring dresses It puts, is 2 left back crossbeams, 21 first running gear for trolley, 22 sling lifting mechanisms, 23 driver's cabins, 3 first power set, 4 left big Crossbeam, 51 second carriage walking machines behind beam, 41 left axis pins, 42 first steel wire ropes, 43 first pull rods, 44 first back stays, 5 right sides Structure, 6 second power set, 7 right crossbeams, 71 right axis pins, 72 second steel wire ropes, 73 second pull rods, 74 second back stays.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other without making creative work Embodiment belongs to the scope of protection of the invention.
- 3 are please referred to Fig.1, the present invention provides a kind of technical solution:A kind of container crane with double luffing mechanisms, Including cart walking mechanism 1, the top of the left side cart walking mechanism 1 is provided with left-hand door mount structure 11, the right side cart The top of walking mechanism 1 is provided with right doorframe structure 12, between the left-hand door mount structure 11 and the adjacent surface of right doorframe structure 12 Top beam 13 is connected with, left back crossbeam 2 is provided on the left-hand door mount structure 11, first is movably set on the left back crossbeam 2 Running gear for trolley 21, the top of the left back crossbeam 2 are provided with the first power set 3, the right side activity of the left back crossbeam 2 Left crossbeam 4 is provided with, and left back crossbeam 2 and left crossbeam 4 are flexibly connected by left axis pin 41, the right side of first power set 3 Side is connected with the first steel wire rope 42, and the other end of first steel wire rope 42 connects the right side at left 4 top of crossbeam, the left doorframe The top on 11 right side of structure is provided with the first pull rod 43, and the other end of first pull rod 43 connects left crossbeam 4 and is abutted against the first steel One end of cord 42, the left side top of the left-hand door mount structure 11 is provided with the first back stay 44, and the first back stay 44 is another One end connects the left side at 2 top of left back crossbeam, is provided with crossbeam 5 behind the right side in the right doorframe structure 12, it is described it is right after on crossbeam 5 It is movably set with the second running gear for trolley 51, the bottom of 21 and second running gear for trolley 51 of the first running gear for trolley Sling lifting mechanism 22 is both provided with, and the left side of the first running gear for trolley 21 and the right side of the second running gear for trolley 51 are equal Be provided with driver's cabin 23, it is described it is right after the top of crossbeam 5 be provided with the second power set 6, it is described it is right after crossbeam 5 left side activity Right crossbeam 7 is provided with, and crossbeam 5 and right crossbeam 7 are flexibly connected by right axis pin 71 behind the right side, a left side for second power set 6 Side is connected with the second steel wire rope 72, and the other end of second steel wire rope 72 connects the left side at right 7 top of crossbeam, the right doorframe The top in 12 left side of structure is provided with the second pull rod 73, and the other end of second pull rod 73 connects right crossbeam 7 and is abutted against the second steel One end of cord 72, the right hand top of the right doorframe structure 12 is provided with the second back stay 74, and the second back stay 74 is another The right side at 5 top of crossbeam after one end connection is right.
Wherein, first steel wire rope 42 is bypassed from the top of left-hand door mount structure 11, and second steel wire rope 72 is from You Men The top of mount structure 12 bypasses, and the top of the left-hand door mount structure 11 and right doorframe structure 12 is respectively arranged with and the first steel wire rope 42 and second directive wheel that matches of steel wire rope 72, and directive wheel is provided with anti-falling device for steel wire rope, directive wheel plays guiding Effect, anti-drop device prevent that steel wire rope from coming off directive wheel, the left back crossbeam 2, left crossbeam 4, it is right after crossbeam 5 and right crossbeam 7 On be both provided with the carriage walking track to match with running gear for trolley, and the left crossbeam when left crossbeam 4 and right crossbeam 7 are laid flat 4 and right crossbeam 7 on carriage walking track slitless connection, make the first running gear for trolley 21 and the second running gear for trolley 51 can Arbitrarily to walk on left crossbeam 4 and right crossbeam 7, the front side of the left-hand door mount structure 11 and right doorframe structure 12 is both provided with building Ladder 14, the cross section of the stair frame 14 are serrated, and the front side of stair frame 14 is provided with lobby, jagged stair 14 gradient of frame is smaller to make climbing personnel more effortless, and lobby facilitates rest, the left-hand door mount structure 11 and right doorframe structure 12 Bottom be both provided with anchoring device 15,43 and second pull rod 73 of the first pull rod is folding pull rod.
A kind of handling method of the container crane with double luffing mechanisms based on the device:
Step 1:First power set 3 wind the first steel wire rope 42, and the folding and unfolding control for passing through the first steel wire rope 42 is left big Beam 4 is rotated around left axis pin 41, and the second power set 6 wind the second steel wire rope 72, and passes through the folding and unfolding control of the second steel wire rope 72 Right crossbeam 7 is rotated around right axis pin 71;
Step 2:After left crossbeam 4 and right crossbeam 7 are laid flat, carriage walking orbital docking success, the first power set 3 are controlled It makes the first running gear for trolley 21 to walk on carriage walking track, the second power set 6 control the second running gear for trolley 51 It walks on carriage walking track;
Step 3:After the first running gear for trolley 21 and the second running gear for trolley 51 are gone to above container, first Power set 3 control sling lifting mechanism 22 to drop to packaging upper box part, are consolidated sling lifting mechanism 22 and container with lock pin It is lifted by crane after fixed, the first running gear for trolley 21 drives container level moving to goods stock just after container slings one end height Then top controls sling lifting mechanism 22 to decline, container is placed on goods stock, the second power set 6 control suspender Elevating mechanism 22 drops to packaging upper box part, is lifted by crane after being fixed sling lifting mechanism 22 and container with lock pin, container crane The first running gear for trolley 21 drives container level to move to the surface of goods stock after playing one end height, then controls suspender Elevating mechanism 22 declines, and container is placed on goods stock;
Step 4:The first running gear for trolley 21 is responsible for the handling of cargo-container ship upper left side container under normal circumstances, Second running gear for trolley 51 is responsible for the handling of right side container on cargo-container ship, when one group of running gear for trolley needs to check During repair, there is one group of running gear for trolley with normal operation to container can be transported to the one side pulled in shore, reduce walking distance.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with Understanding without departing from the principles and spirit of the present invention can carry out these embodiments a variety of variations, modification, replace And modification, the scope of the present invention is defined by the appended.

Claims (7)

1. a kind of container crane with double luffing mechanisms, including cart walking mechanism (1), it is characterised in that:Left side institute It states and left-hand door mount structure (11) is provided at the top of cart walking mechanism (1), the top of the right side cart walking mechanism (1) is set There is right doorframe structure (12), top beam is connected between the left-hand door mount structure (11) and the adjacent surface of right doorframe structure (12) (13), left back crossbeam (2) is provided on the left-hand door mount structure (11), it is small to be movably set with first on the left back crossbeam (2) Vehicle walking mechanism (21) is provided with the first power set (3), the right side of the left back crossbeam (2) at the top of the left back crossbeam (2) Side is movably set with left crossbeam (4), and left back crossbeam (2) and left crossbeam (4) are flexibly connected by left axis pin (41), and described first The first steel wire rope (42) is connected on the right side of power set (3), the other end of first steel wire rope (42) connects left crossbeam (4) The right side at top, the top on the right side of the left-hand door mount structure (11) are provided with the first pull rod (43), first pull rod (43) The other end connects one end that left crossbeam (4) is abutted against the first steel wire rope (42), and the left side top of the left-hand door mount structure (11) is set There is the first back stay (44), and the other end of the first back stay (44) connects the left side at the top of left back crossbeam (2), the right doorframe Be provided with crossbeam (5) behind the right side in structure (12), it is described it is right after be movably set with the second running gear for trolley (51) on crossbeam (5), The bottom of first running gear for trolley (21) and the second running gear for trolley (51) is both provided with sling lifting mechanism (22), And first running gear for trolley (21) left side and the second running gear for trolley (51) on the right side of be both provided with driver's cabin (23), institute State and be provided with the second power set (6) behind the right side at the top of crossbeam (5), it is described it is right after be movably set on the left of crossbeam (5) it is right big Beam (7), and crossbeam (5) and right crossbeam (7) are flexibly connected by right axis pin (71) behind the right side, a left side for second power set (6) Side is connected with the second steel wire rope (72), and the other end of second steel wire rope (72) connects the left side at the top of right crossbeam (7), described Top on the left of right doorframe structure (12) is provided with the second pull rod (73), and the other end of second pull rod (73) connects right crossbeam (7) it is abutted against one end of the second steel wire rope (72), the right hand top of the right doorframe structure (12) is provided with the second back stay (74), And second back stay (74) other end connection it is right after right side at the top of crossbeam (5).
2. a kind of container crane with double luffing mechanisms according to claim 1, it is characterised in that:Described first Steel wire rope (42) is bypassed from the top of left-hand door mount structure (11), and second steel wire rope (72) is from the top of right doorframe structure (12) It bypasses, is respectively arranged at the top of the left-hand door mount structure (11) and right doorframe structure (12) and the first steel wire rope (42) and second The directive wheel that steel wire rope (72) matches, and directive wheel is provided with anti-falling device for steel wire rope.
3. a kind of container crane with double luffing mechanisms according to claim 1, it is characterised in that:It is described left back Behind crossbeam (2), left crossbeam (4), the right side trolley to match with running gear for trolley is both provided on crossbeam (5) and right crossbeam (7) Walk track, and the carriage walking track when left crossbeam (4) and right crossbeam (7) are laid flat on left crossbeam (4) and right crossbeam (7) without Seam docking.
4. a kind of container crane with double luffing mechanisms according to claim 1, it is characterised in that:The left-hand door Stair frame (14) is both provided on front side of mount structure (11) and right doorframe structure (12), the cross section of the stair frame (14) is in saw Dentation, and it is provided with lobby on front side of stair frame (14).
5. a kind of container crane with double luffing mechanisms according to claim 1, it is characterised in that:The left-hand door The bottom of mount structure (11) and right doorframe structure (12) is both provided with anchoring device (15).
6. a kind of container crane with double luffing mechanisms according to claim 1, it is characterised in that:Described first Pull rod (43) and the second pull rod (73) are folding pull rod.
7. a kind of container crane with double luffing mechanisms according to claim 1-6, it is characterised in that:A kind of base In the handling method of the container crane with double luffing mechanisms of the device:
Step 1:First power set (3) wind the first steel wire rope (42), and the folding and unfolding control for passing through the first steel wire rope (42) is left Crossbeam (4) is rotated around left axis pin (41), and the second power set (6) wind the second steel wire rope (72), and pass through the second steel wire rope (72) folding and unfolding controls right crossbeam (7) to be rotated around right axis pin (71);
Step 2:After left crossbeam (4) and right crossbeam (7) are laid flat, the success of carriage walking orbital docking, the first power set (3) The first running gear for trolley (21) is controlled to walk on carriage walking track, the second power set (6) control the second carriage walking Mechanism (51) walks on carriage walking track;
Step 3:After the first running gear for trolley (21) and the second running gear for trolley (51) are gone to above container, first Power set (3) control sling lifting mechanism (22) drops to packaging upper box part, with lock pin by sling lifting mechanism (22) sum aggregate It is lifted by crane after vanning is fixed, the first running gear for trolley (21) drives container level to move to shipping after container slings one end height Then the surface of vehicle controls sling lifting mechanism (22) to decline, container is placed on goods stock, the second power set (6) sling lifting mechanism (22) is controlled to drop to packaging upper box part, is fixed sling lifting mechanism (22) and container with lock pin After lift by crane, container slings the first running gear for trolley (21) after the height of one end and container level is driven to move to goods stock just Then top controls sling lifting mechanism (22) to decline, container is placed on goods stock;
Step 4:The first running gear for trolley (21) is responsible for the handling of cargo-container ship upper left side container under normal circumstances, the Two running gear for trolley (51) are responsible for the handling of right side container on cargo-container ship, when one group of running gear for trolley needs to check During repair, there is one group of running gear for trolley with normal operation to container can be transported to the one side pulled in shore, reduce walking distance.
CN201711209093.9A 2017-11-27 2017-11-27 A kind of container crane and its handling method with double luffing mechanisms Pending CN108083130A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711209093.9A CN108083130A (en) 2017-11-27 2017-11-27 A kind of container crane and its handling method with double luffing mechanisms

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711209093.9A CN108083130A (en) 2017-11-27 2017-11-27 A kind of container crane and its handling method with double luffing mechanisms

Publications (1)

Publication Number Publication Date
CN108083130A true CN108083130A (en) 2018-05-29

Family

ID=62172254

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711209093.9A Pending CN108083130A (en) 2017-11-27 2017-11-27 A kind of container crane and its handling method with double luffing mechanisms

Country Status (1)

Country Link
CN (1) CN108083130A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109160420A (en) * 2018-10-31 2019-01-08 青岛海西重机有限责任公司 A kind of crane suspended-type movable drivers' cab
CN110540139A (en) * 2019-08-15 2019-12-06 王静波 Gantry type bidirectional grab ship loading and unloading machine

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040027804A (en) * 2004-03-08 2004-04-01 홍금식 Container crane possible rotating of level and vertical
US20040126205A1 (en) * 2000-12-11 2004-07-01 Amoss W. J. Jim Container cargo transfer system
CN103407900A (en) * 2013-07-30 2013-11-27 华电重工股份有限公司 Efficient loading and unloading system and process for harbor containers
CN105417394A (en) * 2015-12-23 2016-03-23 三一海洋重工有限公司 Quayside container crane
CN105836629A (en) * 2016-05-13 2016-08-10 中交第三航务工程勘察设计院有限公司 Container crane with double pitching mechanisms and loading and unloading method of container crane

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040126205A1 (en) * 2000-12-11 2004-07-01 Amoss W. J. Jim Container cargo transfer system
KR20040027804A (en) * 2004-03-08 2004-04-01 홍금식 Container crane possible rotating of level and vertical
CN103407900A (en) * 2013-07-30 2013-11-27 华电重工股份有限公司 Efficient loading and unloading system and process for harbor containers
CN105417394A (en) * 2015-12-23 2016-03-23 三一海洋重工有限公司 Quayside container crane
CN105836629A (en) * 2016-05-13 2016-08-10 中交第三航务工程勘察设计院有限公司 Container crane with double pitching mechanisms and loading and unloading method of container crane

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109160420A (en) * 2018-10-31 2019-01-08 青岛海西重机有限责任公司 A kind of crane suspended-type movable drivers' cab
CN110540139A (en) * 2019-08-15 2019-12-06 王静波 Gantry type bidirectional grab ship loading and unloading machine
CN110540139B (en) * 2019-08-15 2020-11-20 王静波 Gantry type bidirectional grab ship loading and unloading machine

Similar Documents

Publication Publication Date Title
CN102267664B (en) Method for installing bridge crane using load-supporting roof beam for hoisting and usage thereof
CN208200113U (en) A kind of easy container hoisting device
CN103663168A (en) Special crane for transporting fan blade
CN107738995A (en) Build assembling light crane
CN108083130A (en) A kind of container crane and its handling method with double luffing mechanisms
CN104326283A (en) Grab ship unloader suitable for multi-point material distribution device
CN114835026A (en) Double-deck container bank bridge of dolly liftable
CN205973518U (en) Track portal jib crane
CN106829781A (en) Mobile shipment crane and its operating method of one kind
CN213085256U (en) Single-beam portal crane with suspended trolley
CN103407900A (en) Efficient loading and unloading system and process for harbor containers
CN105731268B (en) A kind of cargo transport lifts transporter
CN207404737U (en) Build assembling light crane
CN104709833B (en) Novel luffing rib ropewalking crawler crane
CN203529773U (en) High-efficiency loading and unloading system of containers at ports
CN214269987U (en) Hoisting device applied to high-rise building roof elevator shaft
CN102730575A (en) Quayside cable crane
CN205275061U (en) Semi -portal crane
CN204150734U (en) Be applicable to the grab bucket ship unloader being with multiple spot distributing device
CN105752853B (en) Port and pier cargo transportation device
CN206529220U (en) Draw raising gantry crane
CN205526360U (en) Prefab conveyer
CN205419582U (en) Floor hoist
CN107245957B (en) Method and equipment for erecting stiffening beam of suspension bridge in air without track
CN205471273U (en) Prefab production conveyor system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180529

WD01 Invention patent application deemed withdrawn after publication