The content of the invention
The problem to be solved in the present invention is to provide a kind of concrete bone for the above-mentioned deficiency in the presence of the prior art
Material feeding system facilitates aggregate feeding.
To achieve the above object, present invention employs following technical solutions:A kind of aggregate feeding system, including
Upper material strip, collecting bin, the first sub-material band, the second sub-material band, the 3rd sub-material band, the first sub-material storehouse, the second sub-material storehouse, the 3rd sub-material
Storehouse, the first storage bin, the second storage bin, the 3rd storage bin, the first spare storehouse, the second spare storehouse, material strip, the second feeding on first
Material strip on band and the 3rd;Collecting bin described in the feeding band connection, the collecting bin are equipped with the sub-sieve that can separate three kinds of aggregates
Device, the separating screen device connect the first sub-material band, the second sub-material band and the 3rd sub-material band, the first sub-material band, the
Two sub-material bands and the 3rd sub-material band connect the first sub-material storehouse, the second sub-material storehouse and the 3rd sub-material storehouse respectively;Described first point
Feed bin connects first storage bin and the first spare storehouse, and the second sub-material storehouse connects second storage bin, first
Spare storehouse and the second spare storehouse, the 3rd sub-material storehouse connect the 3rd storage bin and the second spare storehouse;Described first
Material strip on described first, the are equipped with below storage bin, the second storage bin, the 3rd storage bin, the first spare storehouse and the second spare storehouse
Material strip on material strip and the 3rd on two, first storage bin, the second storage bin, the 3rd storage bin, the first spare storehouse and second are standby
The material leakage cylinder rotated is driven by motor with being equipped on material strip on storehouse and described first, second on material strip and the 3rd between material strip,
The material leakage cylinder is equipped with drain spout, and the drain spout of rotation can material strip, material strip and the on second on described first respectively
Switching above three feeding bands, the drain spout are equipped with the control valve of control drain spout size.
Further, the separating screen device includes the first cutting plate, the second cutting plate, the 3rd cutting plate, motor group, L-shaped gear
Plate, discharge port, spring and positioning pin;First cutting plate, the second cutting plate, the 3rd cutting plate pass through the first support respectively
Axis, the second support shaft, the 3rd support shaft are movably connected in the collecting bin, first cutting plate, the second cutting plate, the 3rd
Cutting plate is arranged above and below successively, and first cutting plate, the second cutting plate, the 3rd cutting plate outer wall are equipped with tooth, the motor group
Coordinated by gear and the tooth, three L-shaped baffles are respectively positioned at first cutting plate, the second cutting plate and the 3rd point
Below flitch, the positioning pin is full of the spring and is connected to below the L-shaped baffle, the L-shaped baffle be equipped with it is described go out
The corresponding material path of material mouth, three discharge ports connect the first sub-material band, the second sub-material band and the 3rd sub-material band respectively,
First cutting plate, the second cutting plate are respectively equipped with the first hole, the second hole and that internal diameter is gradually reduced on the 3rd cutting plate
Three holes.
Further, the collecting bin is equipped with funnel, and the funnel is located above first cutting plate, and the funnel connects
It is connected to vibration motor.
Further, tank is equipped with below the 3rd cutting plate, nozzle, the nozzle pair are installed on the tank
Answer corresponding first hole, the second hole and the 3rd hole up and down.
Further, a kind of aggregate feeding system further includes the first cylinder and that rotation is driven by motor
Two cylinders, first cylinder and the second cylinder are cased with the first jacket casing and the second jacket casing, and it is logical that first cylinder is equipped with first
Hole, first jacket casing are equipped with a pair of second through hole corresponding with the first through hole, and second through hole corresponds to described the
One storage bin and the first spare storehouse, second through hole correspond to the 3rd storage bin and the second spare storehouse, second jacket casing
On set there are three third through-hole, the third through-hole corresponds to second storage bin, the first spare storehouse and the second spare storehouse respectively.
Compared with the prior art, the present invention has the advantages that:Upper material strip of the present invention is to be driven by motor
Rubble after lorry ships rubble, is poured into the collecting bin by the upper material strip, passes through the collecting bin by the crawler belt of walking
Rubble is divided into three kinds of great Shi, middle stone and gravelstone aggregates by the separating screen device being inside equipped with, and three kinds of aggregates pass through described first point
Material strip, the second sub-material band, the 3rd sub-material band transport the first sub-material storehouse, the second sub-material storehouse and the 3rd sub-material storehouse to, and described first
Sub-material band, the second sub-material band, the 3rd sub-material band are the crawler belt that walking is driven by motor, and screening can be used in the separating screen device
Machine;The aggregate in the first sub-material storehouse is sent to first storage bin by belt, is sent after first storage bin has been expired
Toward the first spare storehouse, directly the first sub-material storehouse can also be arranged on above first storage bin and the first spare storehouse,
A pair of of valve of blanking is equipped on the first sub-material storehouse, opening different valves, to drain to the first sub-material storehouse material described
First storage bin or the first spare storehouse;The aggregate in the 3rd sub-material storehouse is sent to the 3rd storage bin by belt, when
3rd storage bin is sent to the second spare storehouse after having expired, and can also the 3rd sub-material storehouse be directly arranged on the 3rd storage
Above feed bin and the second spare storehouse, a pair of of valve of blanking is equipped on the 3rd sub-material storehouse, opening different valves makes institute
It states the 3rd sub-material storehouse material and drains to the 3rd storage bin or the second spare storehouse;The aggregate in the second sub-material storehouse is passed through into belt
Second storage bin is sent to, the first spare storehouse and the second spare storehouse are sent to after second storage bin has been expired, it can also be straight
It connects and the second sub-material storehouse is arranged on above second storage bin and the first spare storehouse and the second spare storehouse, described second
Sub-material storehouse is equipped with a pair of of valve of blanking, and opening different valves makes the second sub-material storehouse material drain to second storage bin
Or first spare storehouse and the second spare storehouse;The first spare storehouse and the second spare storehouse needed when switching different aggregates by
The aggregate of front has been handled;By material strip on material strip and the 3rd on material strip on described one, second by first storage bin, second
Storage bin, the 3rd storage bin, the first spare storehouse and the second spare aggregate having of storing in a warehouse carry out feeding supply concrete stirring and set
Standby, the material leakage cylinder is separately positioned on first storage bin, the second storage bin, the 3rd storage bin, the first spare storehouse and second
The spare storage side of leaving, in first storage bin, the second storage bin, the 3rd storage bin, the first spare storehouse and the second spare storehouse
The drain spout of aggregate from the material leakage cylinder leak down, by motor the material leakage cylinder is driven to rotate, enables the drain spout
Respectively with material strip is corresponding on material strip and the 3rd on material strip on described first, second, material strip on described first, material strip and on second
Material strip is disposed adjacent on three, and the drain spout is equipped with the control valve of control drain spout size, and the drain spout is placed in maximum inner diameter
When can cover material strip on described first simultaneously, material strip on material strip and the 3rd on second, enable aggregate simultaneously under the drain spout
To fall into material strip on described first, material strip on material strip and the 3rd on second, make material strip on described first, material strip and the 3rd on second
Upper material strip works at the same time quickening feeding;By material on the feeding band and pass through the separating screen device and divide aggregate, finally from institute
State material strip on first, on second material strip and the 3rd feeding band feeding make feeding speed faster, accelerate process.
Part is illustrated to embody by further advantage, target and the feature of the present invention by following, and part will also be by this
The research and practice of invention and be understood by the person skilled in the art.
Specific embodiment
In order to which the technological means, creation characteristic, the reached purpose that realize the present invention more understand and are apparent to acting on,
The present invention is further elaborated with reference to the accompanying drawings and detailed description:
The present invention proposes a kind of aggregate feeding system, including upper material strip 1, collecting bin 2, the first sub-material band 3,
Two sub-material bands 4, the 3rd sub-material band 5, the first sub-material storehouse 6, the second sub-material storehouse 7, the 3rd sub-material storehouse 8, the storage of the first storage bin 9, second
Feed bin 10, the 3rd storage bin 11, the first spare storehouse 12, material strip 15 and the 3rd on material strip 14, second on the second spare storehouse 13, first
Upper material strip 16;The upper material strip 1 connects the collecting bin 2, and the collecting bin 2 is equipped with the sub-sieve dress that can separate three kinds of aggregates
It puts, the separating screen device connects the first sub-material band 3, the second sub-material band 4 and the 3rd sub-material band 5, the first sub-material band 3,
Second sub-material band 4 and the 3rd sub-material band 5 connect the first sub-material storehouse 6, the second sub-material storehouse 7 and the 3rd sub-material storehouse 8 respectively;It is described
First sub-material storehouse 6 connects first storage bin 9 and the first spare storehouse 12, and the second sub-material storehouse 7 connects described second
Storage bin 10, the first spare 12 and second spare storehouse 13 of storehouse, the 3rd sub-material storehouse 8 connect the 3rd storage bin 11 and described
Second spare storehouse 13;First storage bin 9, the second storage bin 10, the 3rd storage bin 11, the first spare storehouse 12 and second are spare
13 lower section of storehouse is equipped on described first on material strip 14, second material strip 16, first storage bin 9, second on material strip 15 and the 3rd
Storage bin 10, the 3rd storage bin 11, material strip on material strip 14, second on the first spare 12 and second spare storehouse 13 of storehouse and described first
The material leakage cylinder 17 that rotation is driven by motor is equipped on 15 and the 3rd between material strip 16, the material leakage cylinder 17 is equipped with drain spout
18, the drain spout 18 of rotation can be respectively on described first on material strip 14, second on material strip 15 and the 3rd above material strip 16
Switching, the drain spout are equipped with the control valve of control 18 size of drain spout.
Upper material strip of the present invention is the crawler belt that walking is driven by motor, after lorry ships rubble, on described
Rubble is poured into the collecting bin by material strip, by the separating screen device that is equipped in the collecting bin by rubble be divided into great Shi, in
Three kinds of aggregates of stone and gravelstone, three kinds of aggregates transport described first to by the first sub-material band, the second sub-material band, the 3rd sub-material band
Sub-material storehouse, the second sub-material storehouse and the 3rd sub-material storehouse, the first sub-material band, the second sub-material band, the 3rd sub-material band are to pass through motor
The crawler belt of walking is driven, screening machine can be used in the separating screen device;The aggregate in the first sub-material storehouse is sent to institute by belt
The first storage bin is stated, the first spare storehouse is sent to after first storage bin has been expired, it can also be directly the first sub-material storehouse
It is arranged on above first storage bin and the first spare storehouse, a pair of of valve of blanking is equipped on the first sub-material storehouse, is beaten
Opening different valves makes the first sub-material storehouse material drain to first storage bin or the first spare storehouse;By the 3rd sub-material
The aggregate in storehouse is sent to the 3rd storage bin by belt, is sent to the second spare storehouse after the 3rd storage bin has been expired, also may be used
Directly the 3rd sub-material storehouse is arranged on above the 3rd storage bin and the second spare storehouse, on the 3rd sub-material storehouse
A pair of of valve equipped with blanking, opening different valves makes the 3rd sub-material storehouse material drain to the 3rd storage bin or second
Spare storehouse;The aggregate in the second sub-material storehouse is sent to second storage bin by belt, when second storage bin is full
After be sent to the first spare storehouse and the second spare storehouse, can also directly the second sub-material storehouse be arranged on second storage bin and
Above first spare storehouse and the second spare storehouse, a pair of of valve of blanking is equipped on the second sub-material storehouse, opens different valves
Door makes the second sub-material storehouse material drain to second storage bin or the first spare storehouse and the second spare storehouse;Described first is spare
Storehouse and the second spare storehouse need to have handled in the aggregate of front when switching different aggregates;Pass through material strip, second on described one
Material strip is spare by first storage bin, the second storage bin, the 3rd storage bin, the first spare storehouse and second on upper material strip and the 3rd
The aggregate that has of storing in a warehouse carries out feeding supply concrete batch plant, the material leakage cylinder be separately positioned on first storage bin,
Second storage bin, the 3rd storage bin, the first spare storehouse and the second spare storage side of leaving, first storage bin, the second storing
The drain spout of aggregate from the material leakage cylinder in storehouse, the 3rd storage bin, the first spare storehouse and the second spare storehouse is leaked down, and is passed through
Motor drives material leakage cylinder rotation, enable the drain spout respectively on material strip on described first, second on material strip and the 3rd
Material strip corresponds to, and material strip on described first, material strip is disposed adjacent on material strip and the 3rd on second, and the drain spout is equipped with control material leakage
The control valve of mouthful size, material strip on described first can be covered when the drain spout is placed in maximum inner diameter simultaneously, on second material strip and
Material strip on 3rd enables aggregate to get off to fall into material strip on described first from the drain spout simultaneously, on second on material strip and the 3rd
Material strip makes material strip on described first, material strip works at the same time quickening feeding on material strip and the 3rd on second;By on the feeding band
Material simultaneously passes through the separating screen device and divides aggregate, finally from material strip and the 3rd feeding band feeding on material strip on described first, second
Make feeding speed faster, accelerate process.
As specific embodiment, the separating screen device includes the first cutting plate 21, the second cutting plate 22, the 3rd cutting plate
23rd, motor group 28, L-shaped baffle 29, discharge port 31, spring 32 and positioning pin 33;First cutting plate 21, the second cutting plate
22nd, the 3rd cutting plate 23 is movably connected in the collection by the first support shaft 24, the second support shaft 25, the 3rd support shaft 26 respectively
In feed bin 2, first support shaft 24, the second support shaft 25,26 upper end of the 3rd support shaft divide cup and first cutting plate 21,
Second cutting plate 22, the 3rd cutting plate 23 are fixedly connected, first support shaft 24, the second support shaft 25, the 3rd support shaft 26
It is directly put in the groove that 2 bottom of collecting bin is equipped with, first support shaft 24, the second support shaft 25, the 3rd support shaft
26 are placed in the groove while limit first support shaft 24, the second support shaft 25,26 horizontal-shift of the 3rd support shaft,
First cutting plate 21, the second cutting plate 22, the 3rd cutting plate 23 are arranged above and below successively, first cutting plate 21, second
Cutting plate 22,23 outer wall of the 3rd cutting plate are equipped with tooth, and the motor group 28 is coordinated by gear and the tooth, the collecting bin 2
Be equipped with for gear activity gear grooved 27, the motor group 28 including respectively with 21, second points of first cutting plate
Flitch 22,23 corresponding first motor of the 3rd cutting plate, the second motor and the 3rd motor, first motor, the second motor and
Between 3rd motor and first cutting plate 21, the second cutting plate 22, the 3rd cutting plate 23 by the gear drive so as to
First cutting plate 21, the second cutting plate 22, the 3rd cutting plate 23 is driven to rotate, passes through first cutting plate 21, second
Cutting plate 22, the rotation of the 3rd cutting plate 23 make on first cutting plate 21, the second cutting plate 22, the 3rd cutting plate 23
Aggregate screening is more thorough, and three L-shaped baffles 29 are located at first cutting plate 21, the second cutting plate 22 and the 3rd respectively
23 lower section of cutting plate, the L-shaped baffle 29 are connected by the straight panel of orthogonal connection with riser, and the straight panel is located at described first
Cutting plate 21, the second cutting plate 22 and the lower section of the 3rd cutting plate 23, the positioning pin 33 be full of the spring 32 be connected to it is described
Below straight panel, the elasticity having by the spring 32 makes first cutting plate 21, the second cutting plate 22, the 3rd cutting plate 23
Energy adjusting position, first cutting plate 21, the second cutting plate 22, the 3rd cutting plate in the amount of elastic deformation of the spring 32
23 lower sections are respectively provided at least L-shaped baffle 29 described in three groups, and first cutting plate 21, the are supported by the L-shaped baffle 29
Two cutting plates 22, the 3rd cutting plate 23, the L-shaped baffle 29 be equipped with the 31 corresponding material path 30 of discharge port, it is described fixed
Position pin 33 is equipped with the winding for controlling 28 rotating speed of motor group, when first cutting plate 21, the second cutting plate 22, the 3rd point
Flitch 23 illustrates that first cutting plate 21, the second cutting plate 22, the loading on the 3rd cutting plate 23 are excessive when moving down, pass through institute
It states winding and the rotation of the motor group 28 offer breakneck acceleration is provided, three discharge ports 31 connect the first sub-material band respectively
3rd, the second sub-material band 4 and the 3rd sub-material band 5, great Shi aggregates, middle stone aggregate and gravelstone aggregate divide cup from three discharge ports 31
It out and is rolled on the first sub-material band 3, the second sub-material band 4 and the 3rd sub-material band 5,21, second points of first cutting plate
It is respectively equipped with the first hole, the second hole and the 3rd hole that internal diameter is gradually reduced on flitch 22, the 3rd cutting plate 23, material is from described
Leak down the aggregate of middle stone and gravelstone in first hole of one cutting plate, and great Shi aggregates are rested on first cutting plate 21, in
Stone aggregate is blocked by second cutting plate 22, and gravelstone aggregate leaks down from second hole onto the 3rd cutting plate 23, institute
It states the 3rd penetration hole diameter that the 3rd cutting plate 23 is equipped with and leaks down fine particle to the described 3rd than the diameter smaller of gravelstone aggregate
Then 23 lower section of cutting plate is still further handled.
As specific embodiment, the collecting bin 2 is equipped with funnel 19, and the funnel 19 is equipped with a circle flanging 20, institute
It states 2 inner wall of collecting bin and is equipped with the step placed for the flanging 20, the funnel 19 is located at 21 top of the first cutting plate,
The funnel 19 is connected with vibration motor 34, and by the vibration motor 34 material of the funnel 19 is driven constantly to shake makes
Material is looser.
As specific embodiment, 23 lower section of the 3rd cutting plate is equipped with tank, and nozzle is equipped on the tank
35, the nozzle 35 corresponds to corresponding first hole, the second hole and the 3rd hole up and down, when needing to clean the separating screen device
When, make first hole, the second hole and the 3rd hole corresponding up and down respectively by adjusting the motor group 28, then pass through the spray
First 35 water outlet is cleaned.
As specific embodiment, a kind of aggregate feeding system, which is further included, drives the first of rotation by motor
36 and second cylinder 37 of cylinder, first cylinder 36 are connected with 6 and the 3rd sub-material storehouse 8 of the first sub-material storehouse, and described second
Cylinder 37 is connected with sub-material storehouse 7, and first cylinder 36 is located at 9 and first spare 12 top of storehouse of the first storage bin, described
First cylinder 36 is located at 11 and second spare 13 top of storehouse of the 3rd storage bin, and second cylinder 37 is located at the described second storage
Feed bin 10, the first spare 12 and second spare 13 top of storehouse of storehouse, 36 and second cylinder 37 of the first cylinder are cased with the first jacket casing
38 and second jacket casing, first cylinder 36 be equipped with first through hole, first jacket casing 38 is equipped with and the first through hole
Corresponding a pair of second through hole 39, second through hole 39 correspond to the 9 and first spare storehouse 12 of the first storage bin, and described second
Through hole 39 corresponds to the 11 and second spare storehouse 13 of the 3rd storage bin, is set on second jacket casing there are three third through-hole 41, institute
State the second cylinder 37 be equipped with the 41 corresponding fourth hole 40 of third through-hole, the third through-hole 41 respectively correspond to described in
Second storage bin 10, the first spare 12 and second spare storehouse 13 of storehouse, make the first through hole by rotating first cylinder 36
Corresponding second through hole 39 and then discharging positioned at the one side of first storage bin 9, after first storage bin 9 has been expired
Rotating first cylinder 36 makes the first through hole with connecting positioned at the second through hole 39 described in the one side in the described first spare storehouse 12
It is logical, by rotating first cylinder 36 first through hole is made to correspond to described the positioned at the one side of the 3rd storage bin 9
Two through holes 39 and then discharging, rotation first cylinder 36 makes the first through hole and position after the 3rd storage bin 11 has been expired
It is connected in the second through hole 39 described in the one side in the described second spare storehouse 13;The principle of second cylinder 37 and first cylinder
36 operation principles are identical, and three third through-holes 41 correspond to second storage bin 10, the first spare storehouse 12 and second respectively
Spare storehouse 13,36 and second cylinder 37 of the first cylinder can also be controlled by electric rotating magnet valve to be rotated.
Finally illustrate, the above embodiments are merely illustrative of the technical solutions of the present invention and it is unrestricted, although with reference to compared with
The present invention is described in detail in good embodiment, it will be understood by those of ordinary skill in the art that, it can be to the skill of the present invention
Art scheme is modified or replaced equivalently, and without departing from the objective and scope of technical solution of the present invention, should all be covered at this
Among the right of invention.