US2727734A - Method of and apparatus for cooling concrete aggregates - Google Patents

Method of and apparatus for cooling concrete aggregates Download PDF

Info

Publication number
US2727734A
US2727734A US231561A US23156151A US2727734A US 2727734 A US2727734 A US 2727734A US 231561 A US231561 A US 231561A US 23156151 A US23156151 A US 23156151A US 2727734 A US2727734 A US 2727734A
Authority
US
United States
Prior art keywords
aggregates
compartments
aggregate
conveyor
spraying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US231561A
Inventor
Archie J Vincent
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SC Johnson and Son Inc
C S JOHNSON Co
Original Assignee
SC Johnson and Son Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SC Johnson and Son Inc filed Critical SC Johnson and Son Inc
Priority to US231561A priority Critical patent/US2727734A/en
Application granted granted Critical
Publication of US2727734A publication Critical patent/US2727734A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28CPREPARING CLAY; PRODUCING MIXTURES CONTAINING CLAY OR CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28C7/00Controlling the operation of apparatus for producing mixtures of clay or cement with other substances; Supplying or proportioning the ingredients for mixing clay or cement with other substances; Discharging the mixture
    • B28C7/0007Pretreatment of the ingredients, e.g. by heating, sorting, grading, drying, disintegrating; Preventing generation of dust
    • B28C7/0023Pretreatment of the ingredients, e.g. by heating, sorting, grading, drying, disintegrating; Preventing generation of dust by heating or cooling
    • B28C7/0038Cooling, e.g. using ice

Definitions

  • the present invention relates to a method of and apparatus for cooling concrete aggregates. More specifically, the invention relates to a method of and apparatus for the selective precooling of the relatively coarse constituents of a concrete batch to a temperature which is at least as low as the degree of temperature necessary to attain a desired placement temperature of the final mix.
  • silos for chilling the coarse aggregates has also been resorted to wherein the silos are partially filled with chilled water, the ggregates then introduced, and circulation of water by means of a pumping system maintained for a predetermined period of time, followed by drainage of the silos and discharge of the contents thereof.
  • Such an inundation process has involved transportation di-fiiculties and associated cooling problems.
  • provisions have had to be made to maintain the storage and transfer areas at a low temperature.
  • this has required the erection of an insulated building to enclose the overhead bins as well as an insulated enclosure for the aggregate conveyor line leading from the cooling plant to .the mixing plant.
  • An air conditioning unit has been employed in the cooling plant building to circulate cooling air throughout the areas where the cooled aggregates .are stored or handled.
  • the present invention is designed to overcome the above noted limitations, principally of manpower and equipment, that are attendant upon the use of present day practice in the 'precooling of aggregates prior to mixing Various installations have employed ice and subsequent placement thereof, and toward this end it contemplates, briefly, the provision of a spray bin in advance of the mixer installation to consolidate practically all of the necessary handling of the aggregates prior to the mixing thereof in one location and to thereby eliminate much of the heretofore necessary equipment and manpower. According to the present invention it is contemplated that one workman shall be required to direct the material into the areas provided for it and to dispatch the material from the stock pile of aggregates, while a second workman is required to control the direction of water flow and to operate the discharge gates employed in connection with the process.
  • the equipment employed involves a .conveyor for conducting coarse aggregates to the spray bin assembly from the stock pile, a bypass conveyor for conducting fine aggregate such as sand from the stock pile, and a mixer plant feed conveyor for receiving the cooled aggregate and sand from the spray bin assembly and the bypass conveyor, respectively, and for conducting them jointly to the mixer plant wherein they may be further treated by conventional processes prior to and during the mixing operation preparatory to placement of the batch.
  • the equipment also may include a settling pond or surge tank, to which fresh coolant water may be supplied and to which expended coolant water resulting from the spraying operation may be returned, a refrigeration plant or heat exchanger for cooling the water.
  • a shaker screen apparatus for equalizing the distribution of residual moisture in the aggregate after spraying thereof, a waste pond or the like for receiving the waste products such as silt from the shaker screen, together with such equipment as the necessary coolant conduits, valves for controlling or directing the flow of .the coolant, and gates and other directional control mechanism for the aggregate material.
  • Another object is to provide such a method and apparatus by means of which selective control of the treatment of the material may be obtained in order that aggregates of uniform water content may be forwarded to the mixing plant from the precooling station.
  • a further object of the invention is to provide a novel apparatus for precooling the relatively coarse aggregates preparatory to the mixing of the concrete batch, together with means for insulating the precooled material during the transfer .to the mixing plant in order that there shall be no transfer .of heat from the ambient atmosphere to the precooled materials prior to their arrival at the mix in plant.
  • Yet another object is to provide .a method and apparatus for precooling aggregates which, in addition to very materially reducing the manpower and equipment necessary to obtain the desired results, affords a system of operation which is highly selective in its treatment of the materials and which may be conducted with a minimum of effort on the part of the operators thereof.
  • Figure l is a flow chart illustrating the method employed in connection with .the invention and showing schematically a novel type of spray bin assembly employed in practicing the same.
  • Fig. 2 is a side elevational view, almost entirely schematic in its representation, of the spray bin assembly as utilized in a typical installation.
  • Fig. 3 is a schematic plan "iew of the installation of Fig. 2.
  • Fig. 4 is a circuit diagram of an electric distribution control system which may be employed in connection with the invention.
  • Fig. 5 is an hydraulic circuit diagram of a gate control system which may be employed in connection with the invention.
  • Fig. 6 is a time chart showing a purely arbitrary schedule of operations of the apparatus for a selected concrete installation.
  • the central mixing plant installation may be of any suitable design and will be availed of the usual features associated with such plants including the material batchers 12, cement tank 14, aggregate compartments 16, charging hopper and distributor 17, collector cone 18 and all the other accoutrements common to such installations.
  • the installation may include a refrigeration and ice plant 20, ice elevator 22, ice screw 24 and ice batcher and chute 26, all for delivery of batched ice to the batch materials in order to maintain the low delivery temperature of the precooled aggregate materials conducted to the mixing plant according to the present invention and to further lower this temperature, if necessary, to attain the required low placing temperature of the mixed concrete materials.
  • the character of the central mixing plant 10 may vary widely for different installations and no claim is made herein to any novelty associated therewith. It is simply the aim of the present invention to deliver the materials undergoing batching, particularly the coarse aggregates delivered to the aggregate compartments 16, at the lowest temperature practicable for further treatment at the mixing plant.
  • One type of installation with which the present invention may be associated has been disclosed by illustration and description in a publication entitled Johnson Concrete Plants, Portable and Stationary, which is a catalogue of the C. S. Johnson Company of Champaign, Illinois. This installation is illustrated on page 13 of the publication and is widely known as the Johnson Octo-Bin.
  • the installation illustrated at 10 is of the Octo-Bin type and is illustrated in Figs. 1, 2 and 3 as having six aggregate compartments although the enclosure for the compartments is provided with eight sides. Obviously, a greater or lesser number of aggregate compartments may be provided if desired.
  • the materials of a batch to be charged into any one of the batchers 12 are carried to and fed into the distributing hopper 17 by means of a conveyor 28 leading from a spray bin installation or assembly 30 by means of which the coarse aggregates are cooled according to the present invention.
  • the supply sources of the different aggregate materials such as stone of different sizes, gravel of dilferent sizes, sand, etc. These sources may be stock piles or bins, such being immaterial to the present invention and the sources are designated at 32.
  • the supply sources for the aggregates are disposed above a conveyor 34 and a series of measuring batchers 35 may be provided, one for each supply source. Suitable means may be provided for operating the batchers 35 in accordance with the demand for the dilferent aggregate materials required at the spray bin assembly and at the mixing plant.
  • the conveyor 34 terminates at its discharge end in a pivoted distributor 36 which may be either manually operated or operated electrically, pneumatically, hydraulically or otherwise by remote control.
  • remote control of the distributor 36 is desirable in order that the same may be operated under the control of a workman at the spray bin assembly 30, all in a manner that will become clear presently.
  • An electrical control mechanism for the pivoted distributor 36 has been shown in Fig. 4 and will be described presently.
  • the pivoted distributor 36 is adapted to selectively discharge materials from the stock pile conveyor 34 onto the receiving end of an inclined conveyor 38 leading to the spray bin installation 30 or onto the receiving end of a by-pass conveyor 40 which in turn discharges the material fed thereto onto the receiving end of the conveyor 28 so that materials may be conducted directly from the stock pile 32 to the mixing plant 10 without being subjected to precooling treatment.
  • the conveyor 38 is employed for the purpose of conducting the coarser aggregates to the spray bin installation 30 for cooling purposes while the finer aggregates, such as sand, are directed to the conveyor 40 for bypassing directly to the mixing plant 10.
  • the spray bin installation 30 has associated therewith means for supplying chilled water for spraying over the coarse aggregates conducted thereto by the conveyor 38 and toward this end a refrigeration plant 42 may be located adjacent the spray bin installation and is adapted to receive a supply of coolant water from a surge tank 44 which in turn receives the heat-expended coolant water from the spray bin installation 30.
  • a water supply source 46 is provided for replenishing any coolant water which may be lost in the process.
  • the spray bin installation 30 which will be described in detail presently, includes a shaker screen mechanism for screening the chilled aggregate to insure a more uniform moisture content of the aggregate before it is conveyed to the mixer installation, and the rejected moisture-laden residue from this shaker screen construction may be discharged to a waste pond 48.
  • the precooling spray bin installation 30 is similar in its general organization to the above mentioned Octo-Bin installation 10 and includes a frame-like structure 52 having a tower section 54 provided with side walls 56 of which there are preferably eight in number.
  • the tower structure 54 also includes a roof 58 and penthouse arrangement 60 in which there is disposed a pivoted distributor hopper 62 designed for receiving the coarse aggregates issuing from the discharge end of the conveyor 38 and for selectively distributing them into any one of a number of aggregate compartments 64 (Figs. 1 and 3) of which there may be six in number.
  • the six aggregate compartments 64 are arranged radially in the tower structure 54 and the usual cement tank such as is shown at 14 in the mixer installation 10 has been omitted.
  • the aggregates are selectively distributed to their respective compartments by means of the pivoted distributor hopper 62.
  • the sides of the aggregate compartments 64 slope steeply and provide for free and fast flowing of the aggregates.
  • Each compartment 64 is provided with a gate 66 which may be of clamshell type and which may be electrically, pneumatically, hydraulically, or otherwise controlled.
  • One pneumatic control for one of the gates 66 is disclosed in Fig. 5 and will be described in detail subsequently.
  • the lower ends of the aggregate compartments 64 communicate with a collector cone 68 which is common to all of the gates 66 and the lower end of the cone discharges onto a shaker screen assembly 70. Coarse materials issuing from the screen are conducted directly onto the conveyor '28, the receiving end of which underlies the discharge end of the screen. An imperforate tray 72 which coextensively underlies the screen discharges waste materials for conduction to the waste pond 48.
  • the gates 66 are not watertight and, during the time that coolant water is being sprayed into the various compartments which are filled with coarse aggregate, the heat expended coolant water may trickle or flow through the closed clamshell gates and be received upon a tiltable deilector plate 67 (see also Fig. for selective directioninto a manifold trough or moat 69 encircling the installation from whence it may be conducted to the surge tank 44.
  • the pivoted deflector plate '67 may be so positioned as to direct the aggregate, when the gates 66 are open, into the collector -cone 68 after coolant water has been drained from compartment 64.
  • the coolant water is conducted from the refrigeration plant 42 to a vertical standpipe 80 which leads updirecting coolant fluid "downwardly onto the aggregates contained within the respective compartments.
  • one workman shall 'be stationed at a ground location adjacent the spray bin installation and that another workman shall be stationed in the tower 54 thereof.
  • the ground workman, the tower workman and such workmen as are employed 'at the central mixing plant 10 and at the stock pile 32, may be in constant communication with one another through a suitable telephonic communication system so that each may be appraised of the requirements of the others in the performance of his respective duties.
  • the ground workman may be provided with suitable controls for operating the pivoted distributor 36 for the selective discharge of materials from the conveyor 34 to the conveyors 38 and '40 and "he may also be provided with controls for operating the various gates '66 and deflector plates 67 associated with "the respective aggregate compartments 64.
  • FIG. 4 A simplified control diagram for selective operation e of 'the pivoted distributor '36 is shown in Fig. 4.
  • the pivoted distributor 36 is shown as being in the form or a gate member mounted on a vertical shaft 37 which carries a worm wheel 39 meshing with a worm 41 mounted .on the motor shaft "4 3 of a reversible motor M.
  • the gate member or distributor 361s movable from the full line position wherein materials issuing from the conveyor 34 are directed to the 'conveyori38, to the dotted 'line position wherein the materials are directed to the conveyor 40.
  • the motor 'M is connected through leads a and b to a conventional reversing switch S to which eurrentmay'be supplied from a suitable source, nots'hown. It is obvious that selective movements of the pivoted distributor 36 may be controlled from the ground station of the spray bin installation 30 by other means whether electric, hydraulic or otherwise.
  • a simplified control diagram for selective operation of the various gates 66 and defiec'tor'pla'tes 67 at the bottom of the aggregate compartments 64 is shown.
  • the aggregate compartments are shown as being arranged linearly but it will be "understood, of course, that actually they are arranged radially about the central arr-is of the tower 56.
  • Each or the aggregate compartments '"64 is shown as being providcd an :air ram 90.
  • Differential air pressure is available to control the operations of the air ram for'the various aggregate compartments.
  • a source of pressure as for example, :a tank or reservoir 92 wherein the pressure is maintained at fifty pounds.
  • a conduit or pipe 94 Leading from this tank is a conduit or pipe 94 which connects with the inlet port 96 of a control valve V located at the ground station of the spray ib'in assembly 3 0.
  • Branches n, a, 'c', d, e and f lead from the valve to the various air rams 90.
  • the valve V is provided with a core :98 having a directional passage 100 therein capable of selective communication with the inlet port 96 and 'a series of outlet ports 1102 communicating with the respective branches a, b, c, etc.
  • the gate 66 may normally remain closed under the influence of gravity and upon operation of the individual air rams "90, the respective gates -66 are moved to their open positionswhile at the same time the deflector plates '67 are moved so as to dedeer material visuing trorn the compartments 64 into the collector cone 68.
  • the ground operator at the spray bin assembly 30, being apprised of the requirements at the mixing plant 10 will ordinarily call for the requisite quantity :and character of the coarse aggregate from the stock pile 32 which, when loaded at the receiving end of he conveyor 34, travels to the discharge end thereof where it is directed by the pivoted distributor 36 onto'the conveyor 38.
  • This pivoted distributor is operated under the control of the ground op- :enator by manipulation of "the reverse swi'tdh 'S to a posi- :tion wherein the vertical shaft 37 is rotated in a counterclockwise direction, as viewed in Fig. 4, to bring the gate to one of its extreme limiting positions.
  • the material placed on the conveyor .38 is elevated to the tower structure of the spray bin assembly lrrom whence it may be distributed to the various raggre'gate compartments 64 by proper manipulation :of the pivoted distributor hopper 62.
  • Two adjacent compartments '64 may be filled with the coarse material, two other adjacent compartments may be filled with the intermediate material, and the remaining two adjacent compartments may be filled with the line grade of material.
  • all of the shut-0E valves 83 may be ojpemd and coolant water allowed to new simultaneously onto the aggregate .in all of the compartments. The length of time during which this simultaneous spraying is maintained will vary :for 'difierent sizes of aggregates.
  • the compartments A and B may contain the coarser aggregates
  • the compartments C and D may contain the intermediate aggregates
  • the compartments E and F may contain the smaller aggregates.
  • the spray bin apparatus may be started upon its regular hourly cycle basis.
  • the shut-off valve 83 of the compartment A is completely closed and this compartment is allowed to drain for approximately ten minutes, after which time the ground operator, by manipulation of the valve V, may open the clamshell gates 66 associated with this compartment and allow the drained but still moist, cooled material in the compartment to issue to the collector cone 68 beneath the gate.
  • the material which passes through the collector cone 68 is deposited upon the shaker screen 70 and the aggregate is thereby further relieved of a large portion of its remaining moisture content and also of any silt or other small sediment of attrition which passes through the screen, and this material is directed by the imperforate screen tray 72 to the waste pond 48.
  • the sprayer may then perform the necessary operations for draining the material in the compartment B which also contains relatively coarse aggregate.
  • the supply of coolant water issuing to this compartment is completely shut off and the aggregate is allowed to drain for approximately ten minutes after which time the gates 66 are opened and the material therein is emptied into the collector cone 68 for conduction to the shaker screen 70.
  • the purpose of the shaker screen 70 is to provide a more uniform moisture content of the aggregate before it is conveyed to the mixer plant 10.
  • the shaker screen is designed to throw off, to a large extent, the surface moisture remaining on the aggregate materials.
  • the screen mesh of the shaker screen is sufficiently small as to serve for all sizes of material issuing from the aggregate compartments.
  • this compartment is then ready to receive another charge of the material.
  • the alternate spraying operation lasting approximately fifty minutes and the draining operation lasting approximately ten minutes is carried out continuously.
  • Treatment of the intermediate material in the compartments C and D is similar to that accorded the coarser material in the compartments A and B with the exception that the spraying and draining portions of the regular cycle are varied slightly. Inasmuch as it does not require quite as long a period of spraying time to reduce the intermediate aggregate to the desired low temperature, this aggregate may be subjected to the spraying operation for approximately forty minutes.
  • the intermediate aggregate since it is possessed of smaller interstices, will require a longer period of draining time and thus the operations performed upon the large aggregate in the compartments A and B may likewise be performed upon the aggregates in the compartments C and D utilizing a forty minute period for spray and a twenty minute period of drain to complete the regular apparatus cycle.
  • the spraying and draining of the materials in the compartments C and D may likewise be conducted alternately just as in the case of the compartments A and B.
  • the fine material in the compartments E and F may be conducted'sirnultaneously with the treatment of the intermediate material and with the treatment of the coarse material.
  • a shorter spraying time of thirty minutes and a longer draining time of thirty minutes is resorted to thus completing a regular cycle for the small aggregate.
  • the coarse material in the compartments A and B, the intermediate material in the compartments C and D, and the fine material in the compartments E and F are each subjected to alternate, but different, periods of spraying and draining time, respectively, and that the operations on these pairs of compartments are conducted simultaneously so that once during each hour cycle of the apparatus as a whole, a discharge of the partially drained material from each individual compartment to the collector cone takes place. It is not necessary that any definite pattern of sequential. operation as regards the six compartments be placed in effect although for smooth and continuous operation it is contemplated that the various spraying and draining operations resorted to may take place according to a predetermined time chart.
  • the operator will in his best judgment vary the period of spraying time, of draining time, or both, to attain the-desired low temperature and moisture content of the materials leaving the precooling apparatus and deposited upon the conveyor 28 leading to the main mixing plant.
  • a purely arbitrary and more specific hour schedule has been illustrated for an installation calling for approximately forty-five minutes spraying time for each of the coarse cobble aggregate compartments A and B, approximately ten minutes draining time, four minutes filling time, and allowing one minute discharge time; forty minutes spraying time for each of the intermediate cobble aggregate compartments C and D, fifteen minutes draining time, with the same filling and discharge time being allotted thereto; and approximately thirty minutes spraying time and twenty-five minutes draining time for the smaller cobble aggregate compartments E and F.
  • the preliminary setting-up time consumes approximately one hour. This includes simultaneous spraying of the aggregates in all of the compartments 64.
  • a short period of time for example two minutes, is allowed for discharging of the first compartment A and three minutes may be allowed for the refilling thereof.
  • the spraying of the coarse material in the compartment A may commence and about this time the pivoted distributor 36 may be switched over to deliver sand to the by-pass conveyor 40.
  • the spraying operation continues until fifty minutes in the cycle when draining of the compartment A is initiated by closing the valve 83 which controls the spraying of the compartment A.
  • the gate 66 of the compartment A is opened to discharge the contents thereof weaves.
  • compartrnent B also containing coarse cobble material receives its spraying operation from fifteen minutes in the first cycle until the end of the cycle and the draining operation is conducted during the first ten minutes of the next cycle. Discharge of the compartment B takes place at ten minutes in the succeeding cycle and recharging thereof takes place from twelve to fifteen minutes in this latter cycle.
  • the operations for compartments A and B are continuous throughout the various cycles.
  • the treatment of intermediate materials in the compartments C and D is substantially the same as for the compartments A and B with the exception that the period of spraying time involved is forty minutes with a fifteen minute period for draining as shown in the chart. Similarly, the treatment of the fine materials is shown in the chart as involving thirty minutes for the spraying operation and twenty-five minutes for draining time. In the case of each grade of material, the same alternate or staggered spraying and draining periods are maintained with the treatment accorded the three grades of materials overlapping one another.
  • the conveyor 34 leading from the stock pile 32 is in intermittent operation, supplying sand and cobble materials to the conveyors 40 and 38, respectively, in alternate fashion.
  • the cooling plant and conveyor discharge to a common point or collecting station on the conveyor 28 which thus carries at alternate times both the untreated sand and the cooled aggregates. That is, the conveyor 28 leading to the mixing plant 10 is in substantially continuous operation supplying the discharged precooled materials or the untreated sand alternately to the mixing plant 10.
  • the deflector plates 67 and the clamshell gates 66 operate under the same controls and the plates 67 direct expended coolant water to the surge tank 44 each time the gates 66 corresponding thereto are closed during the spraying and the draining periods of the respective compartments.
  • a cyclically operable method of precooling a plurality of aggregates of dilferent sizes prior to mixing the aggregates to form concrete each cycle of said method comprising the steps of assembling segregated quantities of the aggregates, spraying the aggregates with cold water for diiferent fractions of the cycle in proportion to the sizes of the agregates, draining the respective aggregates for the remaining portions of the cycle, said remaining portions thereby being inversely proportional to the sizes of the aggregates, and removing said quantities of the aggregates after draining, said spraying being initiated for the respective aggregates in staggered rotation throughout said cycle so that said assembling and removing operations for the respective aggregates will also be staggered along said cycle.
  • a series of sector-shaped aggregate compartments arranged in closely grouped relationship about a vertical .axis, there being a drain anddischarge opening at the bottom of each compartment, a liquid-permeable gate for each drain and discharge opening and operable when closed to retain aggregate Within the compartment while permitting liquid to escape therefrom and operable when open to discharge the contents from said compartment, a collector funnel common to all of said gates for receiving the discharged contents of said compartments, a shaker screen disposed beneath said collector funnel for receiving material discharged therefrom, means operable when said gates are closed for diverting liquid issuing from said compartments from said collector funnel and operable when said gates are open to discharge the contents of the compartments into said collector funnel, means for actuating said shaker screen, means for operating said gates, and means for selectively supplying coolant liquid to said compartments for cooling the contents thereof by direct heat transfer.
  • an apparatus for withdrawing size-graded aggregates from a stockpile, precooling the coarser aggregates, and delivering all of the withdrawn aggregates to a mixing plant comprising a cooling plant located intermediate said stock pile and mixing plant, a distributing station located intermediate the cooling plant and stock pile, a conveyor for conducting aggregates from said stock pile to said distributing station, a conveyor for coarse aggregates extending from said distributing station to said cooling plant, a collecting station adjacent said cooling plant, a conveyor for delivering materials received at said collecting station to said mixing plant, a conveyor extending from said distributing station to said collecting station for transporting fine aggregates from said distributing station to said collecting station, means at said cooling plant for cooling coarse aggregates delivered thereto, means at said cooling plant for discharging the cooled coarse aggregates to said collecting station, and means for actuating all of said conveyors.
  • an apparatus for withdrawing size-graded aggregates from a stock pile, precooling the coarse aggregates, and delivering all of the aggregates to a mixing plant comprising a precooling plant located intermediate said stock pile and said mixing plant, a distributing station located intermediate said precooling plant and said stock pile, a first conveyor extending from the stock pile to said distributing station, a second conveyor for coarse aggregates extending from said distributing station to said precooling plant for delivering coarse aggregates thereto, a collecting station positioned adjacent said precooling plant, a third conveyor extending from said distributing station to said collecting station for delivering fine aggregates to the latter, a fourth conveyor leading from said collecting station to said mixing plant, a distributor element adjacent the forward end of said first conveyor movable from one extreme position wherein aggregate issuing from said first conveyor is directed onto said second conveyor to another extreme position wherein the aggregate is delivered to said third conveyor, means at said precooling plant for effecting cooling of the aggregate delivered thereto, means for discharging cooled aggregates from said pre
  • an apparatus for precooling a plurality of different concrete aggregates comprising an elevated bin having a plurality of compartments for holding quantities of the different aggregates, means for filling said compartments in rotation with the different aggregates, said compartments having respective gates for discharging the aggregates from said compartments in rotation, means for selectively spraying cooling Water over the aggregates in said respective compartments for cooling the aggregates, the water draining out of said compartments, means for collecting the aggregates from said gates, and means for diverting the draining water from said last mentioned means.
  • an apparatus for precooling a plurality of concrete aggregates of different size grades comprising an elevated bin having a plurality of compartments for holding quantities of the ditferent aggregates, a conveyor for raising the aggregates to the top of the bin, means for selectively loading said conveyor with any of the different aggregates, means for selectively directing the aggregates from said conveyor into any of said compartments to fill said compartments in rotation with the different aggregates, respective gates at the bottoms of said compartments for discharging the different aggregates therefrom in rotation, means for selectively spraying cooling water into said compartments for cooling the aggregates in rotation, said gates being liquid permeable so that the water will drain therethrough from said compartments, a collector funnel underlying all of said gates for receiving the cooled aggregates therefrom, said compartments having respective diverting means operative when said gates are closed to divert the water fromsaid funnel, a shaker screen for receiving the aggregates discharged by said funnel and removing excess water from the aggregates, means for receiving and carrying 01f the cooled aggregates from

Landscapes

  • Chemical & Material Sciences (AREA)
  • Dispersion Chemistry (AREA)
  • Preparation Of Clay, And Manufacture Of Mixtures Containing Clay Or Cement (AREA)

Description

Dec. 20, 1955 A. J. VINCENT 2,727,734
METHOD OF AND APPARATUS FOR COOLING CONCRETE AGGREGATES Filed June 14, 195] 3 Sheets-Sheet l 32 STOCKPILE WATER SUPPLY SURGE TANK REFRIGERATION PLANT WASTE POND MIXER INVENTOR. (lrchie J. Vincenl BY M -don @J \MALOTA haw ATT'YS Dec. 20, 1955 J; v 2,727,734
METHOD OF AND APPARATUS FOR COOLING CONCRETE AGGREGATES Filed June 14, 1951 5 Sheets-Sheet 2 FIG?) In INVENTOR.
QrBhIQ J. Vincent BY AT T'YS United States Patent 0 bed METHOD OF AND APPARATUS FOR COOLING CONCRETE AGGREGATES Archie J. Vincent, Champaign, Ill., assignor to The C. S. glohnson Company, Champaign, 11L, a corporation of linois Application June 14, 1951, Serial No. 231,561
8 Claims. (Cl. 259-155) The present invention relates to a method of and apparatus for cooling concrete aggregates. More specifically, the invention relates to a method of and apparatus for the selective precooling of the relatively coarse constituents of a concrete batch to a temperature which is at least as low as the degree of temperature necessary to attain a desired placement temperature of the final mix.
Modern specifications for large installations, particularly where concrete dams are concerned, require that the concrete shall not be placed if the temperature of the final mix exceeds a predetermined specified temperature. accommodate these specifications, recent practice involves various methods of which the most prevalent are: (l) the use of cold air blasts for cooling the aggregate; (2) the cooling of the mix water, and (3) the use of ice for batching purposes. these three expedients, either singly or in combination, in an effort to attain the desired placement temperature. In many instances it has been found that even when all three expedients have been resorted to, the desired low placement temperature cannot be attained.
in addition to the frequentinefiectiveness of such methods of cooling, the fact that extremely complicated, expensive and cumbersome equipment, as well as additional manpower, must be employed has lead to rather discouraging results. Since each large installation presents special problems and new methods of approach, a detailed discussion of all the many cooling expedients that have heretofore been resorted to is not within the scope of this specification, and it is deemed sufiicient to state that in certain instances not only have the coarse aggregates been cooled but additionally heat exchangers have been provided whereby the fine aggregate or dry sand has been cooled with the sand flowing through water-jacketed fines. The use of silos for chilling the coarse aggregates has also been resorted to wherein the silos are partially filled with chilled water, the ggregates then introduced, and circulation of water by means of a pumping system maintained for a predetermined period of time, followed by drainage of the silos and discharge of the contents thereof. Such an inundation process has involved transportation di-fiiculties and associated cooling problems. In order to maintain the low temperature attained in the precooling process outlined above while transporting the aggregates and storing them in the overhead bins at the mixing plant, provisions have had to be made to maintain the storage and transfer areas at a low temperature. In one instance, this has required the erection of an insulated building to enclose the overhead bins as well as an insulated enclosure for the aggregate conveyor line leading from the cooling plant to .the mixing plant. An air conditioning unit has been employed in the cooling plant building to circulate cooling air throughout the areas where the cooled aggregates .are stored or handled.
The present invention is designed to overcome the above noted limitations, principally of manpower and equipment, that are attendant upon the use of present day practice in the 'precooling of aggregates prior to mixing Various installations have employed ice and subsequent placement thereof, and toward this end it contemplates, briefly, the provision of a spray bin in advance of the mixer installation to consolidate practically all of the necessary handling of the aggregates prior to the mixing thereof in one location and to thereby eliminate much of the heretofore necessary equipment and manpower. According to the present invention it is contemplated that one workman shall be required to direct the material into the areas provided for it and to dispatch the material from the stock pile of aggregates, while a second workman is required to control the direction of water flow and to operate the discharge gates employed in connection with the process.
In addition to the multiple bin construction briefly outlined above, the equipment employed involves a .conveyor for conducting coarse aggregates to the spray bin assembly from the stock pile, a bypass conveyor for conducting fine aggregate such as sand from the stock pile, and a mixer plant feed conveyor for receiving the cooled aggregate and sand from the spray bin assembly and the bypass conveyor, respectively, and for conducting them jointly to the mixer plant wherein they may be further treated by conventional processes prior to and during the mixing operation preparatory to placement of the batch. The equipment also may include a settling pond or surge tank, to which fresh coolant water may be supplied and to which expended coolant water resulting from the spraying operation may be returned, a refrigeration plant or heat exchanger for cooling the water. supplied from the surge tank to the spray bin construction, a shaker screen apparatus for equalizing the distribution of residual moisture in the aggregate after spraying thereof, a waste pond or the like for receiving the waste products such as silt from the shaker screen, together with such equipment as the necessary coolant conduits, valves for controlling or directing the flow of .the coolant, and gates and other directional control mechanism for the aggregate material.
The provision of a method of and apparatus for cooling aggregates of the character briefly outlined above being the principal object of the invention, another object is to provide such a method and apparatus by means of which selective control of the treatment of the material may be obtained in order that aggregates of uniform water content may be forwarded to the mixing plant from the precooling station.
A further object of the invention is to provide a novel apparatus for precooling the relatively coarse aggregates preparatory to the mixing of the concrete batch, together with means for insulating the precooled material during the transfer .to the mixing plant in order that there shall be no transfer .of heat from the ambient atmosphere to the precooled materials prior to their arrival at the mix in plant.
Yet another object is to provide .a method and apparatus for precooling aggregates which, in addition to very materially reducing the manpower and equipment necessary to obtain the desired results, affords a system of operation which is highly selective in its treatment of the materials and which may be conducted with a minimum of effort on the part of the operators thereof.
Other objects and advantages, not at this time set forth, will become more readily apparent as the nature of the invention is better understood.
In the accompanying two sheets of drawings forming .a part of this specification, a preferred embodiment of the invention has been shown.
In these drawings:
Figure lis a flow chart illustrating the method employed in connection with .the invention and showing schematically a novel type of spray bin assembly employed in practicing the same.
Fig. 2 is a side elevational view, almost entirely schematic in its representation, of the spray bin assembly as utilized in a typical installation.
Fig. 3 is a schematic plan "iew of the installation of Fig. 2.
Fig. 4 is a circuit diagram of an electric distribution control system which may be employed in connection with the invention.
Fig. 5 is an hydraulic circuit diagram of a gate control system which may be employed in connection with the invention, and
Fig. 6 is a time chart showing a purely arbitrary schedule of operations of the apparatus for a selected concrete installation.
While the invention is susceptible of various modifications and alternative constructions, there is shown in the drawings and will herein be described in detail the preferred embodiment, but it is to be understood that it is not thereby intended to limit the invention to the form disclosed, but it is intended to cover all modifications and alternative constructions falling within the spirit and scope of the invention as expressed in the appended claims.
Referring now to the drawings in detail and in particular to Fig. 2, the central mixing plant installation, designated in its entirety at 10, may be of any suitable design and will be availed of the usual features associated with such plants including the material batchers 12, cement tank 14, aggregate compartments 16, charging hopper and distributor 17, collector cone 18 and all the other accoutrements common to such installations. In the present in stance the installation may include a refrigeration and ice plant 20, ice elevator 22, ice screw 24 and ice batcher and chute 26, all for delivery of batched ice to the batch materials in order to maintain the low delivery temperature of the precooled aggregate materials conducted to the mixing plant according to the present invention and to further lower this temperature, if necessary, to attain the required low placing temperature of the mixed concrete materials.
The character of the central mixing plant 10 may vary widely for different installations and no claim is made herein to any novelty associated therewith. It is simply the aim of the present invention to deliver the materials undergoing batching, particularly the coarse aggregates delivered to the aggregate compartments 16, at the lowest temperature practicable for further treatment at the mixing plant. One type of installation with which the present invention may be associated has been disclosed by illustration and description in a publication entitled Johnson Concrete Plants, Portable and Stationary, which is a catalogue of the C. S. Johnson Company of Champaign, Illinois. This installation is illustrated on page 13 of the publication and is widely known as the Johnson Octo-Bin.
The installation illustrated at 10 is of the Octo-Bin type and is illustrated in Figs. 1, 2 and 3 as having six aggregate compartments although the enclosure for the compartments is provided with eight sides. Obviously, a greater or lesser number of aggregate compartments may be provided if desired.
The materials of a batch to be charged into any one of the batchers 12 are carried to and fed into the distributing hopper 17 by means of a conveyor 28 leading from a spray bin installation or assembly 30 by means of which the coarse aggregates are cooled according to the present invention.
Located more or less remotely in relation to the central mixing plant 10, and also to the spray bin installation 36 are the supply sources of the different aggregate materials such as stone of different sizes, gravel of dilferent sizes, sand, etc. These sources may be stock piles or bins, such being immaterial to the present invention and the sources are designated at 32. The supply sources for the aggregates are disposed above a conveyor 34 and a series of measuring batchers 35 may be provided, one for each supply source. Suitable means may be provided for operating the batchers 35 in accordance with the demand for the dilferent aggregate materials required at the spray bin assembly and at the mixing plant. The conveyor 34 terminates at its discharge end in a pivoted distributor 36 which may be either manually operated or operated electrically, pneumatically, hydraulically or otherwise by remote control. According to a preferred embodiment of the invention, remote control of the distributor 36 is desirable in order that the same may be operated under the control of a workman at the spray bin assembly 30, all in a manner that will become clear presently. An electrical control mechanism for the pivoted distributor 36 has been shown in Fig. 4 and will be described presently.
The pivoted distributor 36 is adapted to selectively discharge materials from the stock pile conveyor 34 onto the receiving end of an inclined conveyor 38 leading to the spray bin installation 30 or onto the receiving end of a by-pass conveyor 40 which in turn discharges the material fed thereto onto the receiving end of the conveyor 28 so that materials may be conducted directly from the stock pile 32 to the mixing plant 10 without being subjected to precooling treatment.
The conveyor 38 is employed for the purpose of conducting the coarser aggregates to the spray bin installation 30 for cooling purposes while the finer aggregates, such as sand, are directed to the conveyor 40 for bypassing directly to the mixing plant 10.
Referring now to Fig. l, the spray bin installation 30 has associated therewith means for supplying chilled water for spraying over the coarse aggregates conducted thereto by the conveyor 38 and toward this end a refrigeration plant 42 may be located adjacent the spray bin installation and is adapted to receive a supply of coolant water from a surge tank 44 which in turn receives the heat-expended coolant water from the spray bin installation 30. A water supply source 46 is provided for replenishing any coolant water which may be lost in the process. The spray bin installation 30, which will be described in detail presently, includes a shaker screen mechanism for screening the chilled aggregate to insure a more uniform moisture content of the aggregate before it is conveyed to the mixer installation, and the rejected moisture-laden residue from this shaker screen construction may be discharged to a waste pond 48.
Referring now to Figs. 1, 2 and 3, the precooling spray bin installation 30 is similar in its general organization to the above mentioned Octo-Bin installation 10 and includes a frame-like structure 52 having a tower section 54 provided with side walls 56 of which there are preferably eight in number. The tower structure 54 also includes a roof 58 and penthouse arrangement 60 in which there is disposed a pivoted distributor hopper 62 designed for receiving the coarse aggregates issuing from the discharge end of the conveyor 38 and for selectively distributing them into any one of a number of aggregate compartments 64 (Figs. 1 and 3) of which there may be six in number.
The six aggregate compartments 64 are arranged radially in the tower structure 54 and the usual cement tank such as is shown at 14 in the mixer installation 10 has been omitted. The aggregates are selectively distributed to their respective compartments by means of the pivoted distributor hopper 62. The sides of the aggregate compartments 64 slope steeply and provide for free and fast flowing of the aggregates. Each compartment 64 is provided with a gate 66 which may be of clamshell type and which may be electrically, pneumatically, hydraulically, or otherwise controlled. One pneumatic control for one of the gates 66 is disclosed in Fig. 5 and will be described in detail subsequently.
The lower ends of the aggregate compartments 64 communicate with a collector cone 68 which is common to all of the gates 66 and the lower end of the cone discharges onto a shaker screen assembly 70. Coarse materials issuing from the screen are conducted directly onto the conveyor '28, the receiving end of which underlies the discharge end of the screen. An imperforate tray 72 which coextensively underlies the screen discharges waste materials for conduction to the waste pond 48.
The gates 66 are not watertight and, during the time that coolant water is being sprayed into the various compartments which are filled with coarse aggregate, the heat expended coolant water may trickle or flow through the closed clamshell gates and be received upon a tiltable deilector plate 67 (see also Fig. for selective directioninto a manifold trough or moat 69 encircling the installation from whence it may be conducted to the surge tank 44. Alternatively, the pivoted deflector plate '67 may be so positioned as to direct the aggregate, when the gates 66 are open, into the collector -cone 68 after coolant water has been drained from compartment 64.
The coolant water is conducted from the refrigeration plant 42 to a vertical standpipe 80 which leads updirecting coolant fluid "downwardly onto the aggregates contained within the respective compartments.
in practicing the method of the present invention, it is contemplated that one workman shall 'be stationed at a ground location adjacent the spray bin installation and that another workman shall be stationed in the tower 54 thereof. The ground workman, the tower workman and such workmen as are employed 'at the central mixing plant 10 and at the stock pile 32, may be in constant communication with one another through a suitable telephonic communication system so that each may be appraised of the requirements of the others in the performance of his respective duties. The ground workman may be provided with suitable controls for operating the pivoted distributor 36 for the selective discharge of materials from the conveyor 34 to the conveyors 38 and '40 and "he may also be provided with controls for operating the various gates '66 and deflector plates 67 associated with "the respective aggregate compartments 64.
A simplified control diagram for selective operation e of 'the pivoted distributor '36 is shown in Fig. 4. In this diagram, the pivoted distributor 36 is shown as being in the form or a gate member mounted on a vertical shaft 37 which carries a worm wheel 39 meshing with a worm 41 mounted .on the motor shaft "4 3 of a reversible motor M. The gate member or distributor 361s movable from the full line position wherein materials issuing from the conveyor 34 are directed to the 'conveyori38, to the dotted 'line position wherein the materials are directed to the conveyor 40. The motor 'M is connected through leads a and b to a conventional reversing switch S to which eurrentmay'be supplied from a suitable source, nots'hown. It is obvious that selective movements of the pivoted distributor 36 may be controlled from the ground station of the spray bin installation 30 by other means whether electric, hydraulic or otherwise.
Referring now to Fig. 5., a simplified control diagram for selective operation of the various gates 66 and defiec'tor'pla'tes 67 at the bottom of the aggregate compartments 64 is shown. In this view the aggregate compartments are shown as being arranged linearly but it will be "understood, of course, that actually they are arranged radially about the central arr-is of the tower 56. Each or the aggregate compartments '"64 is shown as being providcd an :air ram 90. Differential air pressure is available to control the operations of the air ram for'the various aggregate compartments. Toward. this end, there is diagrammatically illustrated a source of pressure, as for example, :a tank or reservoir 92 wherein the pressure is maintained at fifty pounds. Leading from this tank is a conduit or pipe 94 which connects with the inlet port 96 of a control valve V located at the ground station of the spray ib'in assembly 3 0.
Branches n, a, 'c', d, e and f lead from the valve to the various air rams 90. The valve V is provided with a core :98 having a directional passage 100 therein capable of selective communication with the inlet port 96 and 'a series of outlet ports 1102 communicating with the respective branches a, b, c, etc. The gate 66 may normally remain closed under the influence of gravity and upon operation of the individual air rams "90, the respective gates -66 are moved to their open positionswhile at the same time the deflector plates '67 are moved so as to dedeer material visuing trorn the compartments 64 into the collector cone 68.
iln practicing the invention for a particular installation, and for starting up operations, the ground operator at the spray bin assembly 30, being apprised of the requirements at the mixing plant 10, will ordinarily call for the requisite quantity :and character of the coarse aggregate from the stock pile 32 which, when loaded at the receiving end of he conveyor 34, travels to the discharge end thereof where it is directed by the pivoted distributor 36 onto'the conveyor 38. This pivoted distributor, as previously de scribed, is operated under the control of the ground op- :enator by manipulation of "the reverse swi'tdh 'S to a posi- :tion wherein the vertical shaft 37 is rotated in a counterclockwise direction, as viewed in Fig. 4, to bring the gate to one of its extreme limiting positions.
for purposes of illustration, will the assumed that three grades of coarse aggregate material are required in the final mixing and :are to :be cooled by the spray bin equipment at the installation 30. These materials have been designated as fine, intermediate and coarse, respectively.
The material placed on the conveyor .38 is elevated to the tower structure of the spray bin assembly lrrom whence it may be distributed to the various raggre'gate compartments 64 by proper manipulation :of the pivoted distributor hopper 62. Two adjacent compartments '64 may be filled with the coarse material, two other adjacent compartments may be filled with the intermediate material, and the remaining two adjacent compartments may be filled with the line grade of material. After the compar-tments :64 have been filled, all of the shut-0E valves 83 may be ojpemd and coolant water allowed to new simultaneously onto the aggregate .in all of the compartments. The length of time during which this simultaneous spraying is maintained will vary :for 'difierent sizes of aggregates. However, many installations will accommodate cyclic operation of the apparatus in such a mannor that a quantity of aggregate equal to the entire capacity of :all of the bins passes from the stock spile to the final mixing plant during the course of approximately one hour and ten minutes, allowing ten minutes for-the material in transit. This involves an hourly cycle of operation for the spraying bin assembly and such cyclic operation :of the apparatus will accommodate a large variety of conditions. For illustrative purposes, however, an instance has been selected wherein the temperature of the aggregate arriving at the tower of the spray bin assembly is between 70 and F. and wherein a reduction in the temperature of the aggregate to approximately 43 F. is required when the cooled aggregatereaches themixer storage bins at the mixing station 10. Obviously for certain other conditions the machine may be run on afa'ster or slower cycle or the hourly cycle may be maintained and the spraying and draining time for the aggregate may bevaried.
and F reading in a clockwise direction.
7 For descriptive purposes, in Figs. 1 and 3, the six aggregate compartments have been labelled A, B, C, D, E
The compartments A and B may contain the coarser aggregates, the compartments C and D may contain the intermediate aggregates, while the compartments E and F may contain the smaller aggregates.
Under the conditions outlined above and assuming that the apparatus is to be operated upon the basis of an hourly cycle wherein material issuing from the stock pile 32 will arrive at the mixing plant 10 in the course of one hour and ten minutes, it may be assumed that five minutes will be required for passage of the material from the stock pile to the various aggregate compartments 64 and that another five minutes must be allowed for passage of the cooled material along the inclined conveyor 28 to the mixing plant 10. This leaves a full hour for treatment of the material in the precooling apparatus 30. It has been found that in order to effectively reduce the temperature of the coarser aggregates in the bins A and B to the desired low temperature, approximately fifty minutes of spraying time will be required. For the intermediate grade of aggregate in the bins C and D, forty minutes may sutfice. For the relatively small aggregate in the bins E and F, one-half hour of spraying time is sufiicient.
After the preliminary, simultaneous spraying of the aggregates in the various bins 64, and immediately prior to the commencement of regular mixing operations at the mixing plant 10, the spray bin apparatus may be started upon its regular hourly cycle basis. Thus after the coarse aggregates in the bins A and B have been sprayed by the coolant fluid for approximately fifty minutes, the shut-off valve 83 of the compartment A is completely closed and this compartment is allowed to drain for approximately ten minutes, after which time the ground operator, by manipulation of the valve V, may open the clamshell gates 66 associated with this compartment and allow the drained but still moist, cooled material in the compartment to issue to the collector cone 68 beneath the gate. The material which passes through the collector cone 68 is deposited upon the shaker screen 70 and the aggregate is thereby further relieved of a large portion of its remaining moisture content and also of any silt or other small sediment of attrition which passes through the screen, and this material is directed by the imperforate screen tray 72 to the waste pond 48.
The sprayer may then perform the necessary operations for draining the material in the compartment B which also contains relatively coarse aggregate. Thus, by closing the valve 83 associated with this compartment, the supply of coolant water issuing to this compartment is completely shut off and the aggregate is allowed to drain for approximately ten minutes after which time the gates 66 are opened and the material therein is emptied into the collector cone 68 for conduction to the shaker screen 70.
The purpose of the shaker screen 70 is to provide a more uniform moisture content of the aggregate before it is conveyed to the mixer plant 10. The shaker screen is designed to throw off, to a large extent, the surface moisture remaining on the aggregate materials. The screen mesh of the shaker screen is sufficiently small as to serve for all sizes of material issuing from the aggregate compartments.
As soon as the cobble material has been discharged from the cobble compartment A, this compartment is then ready to receive another charge of the material. As regards the two compartments A and B, the alternate spraying operation lasting approximately fifty minutes and the draining operation lasting approximately ten minutes is carried out continuously.
Treatment of the intermediate material in the compartments C and D is similar to that accorded the coarser material in the compartments A and B with the exception that the spraying and draining portions of the regular cycle are varied slightly. Inasmuch as it does not require quite as long a period of spraying time to reduce the intermediate aggregate to the desired low temperature, this aggregate may be subjected to the spraying operation for approximately forty minutes. By the same token, the intermediate aggregate, since it is possessed of smaller interstices, will require a longer period of draining time and thus the operations performed upon the large aggregate in the compartments A and B may likewise be performed upon the aggregates in the compartments C and D utilizing a forty minute period for spray and a twenty minute period of drain to complete the regular apparatus cycle. The spraying and draining of the materials in the compartments C and D may likewise be conducted alternately just as in the case of the compartments A and B.
In a similar manner, the fine material in the compartments E and F may be conducted'sirnultaneously with the treatment of the intermediate material and with the treatment of the coarse material. However, due to the smaller interstices of the fine material in the compartments E and F, a shorter spraying time of thirty minutes and a longer draining time of thirty minutes is resorted to thus completing a regular cycle for the small aggregate.
From the above description it will be seen that the coarse material in the compartments A and B, the intermediate material in the compartments C and D, and the fine material in the compartments E and F are each subjected to alternate, but different, periods of spraying and draining time, respectively, and that the operations on these pairs of compartments are conducted simultaneously so that once during each hour cycle of the apparatus as a whole, a discharge of the partially drained material from each individual compartment to the collector cone takes place. It is not necessary that any definite pattern of sequential. operation as regards the six compartments be placed in effect although for smooth and continuous operation it is contemplated that the various spraying and draining operations resorted to may take place according to a predetermined time chart. As the character of the aggregate reaching the spray bin assembly varies slightly from time to time, the operator will in his best judgment vary the period of spraying time, of draining time, or both, to attain the-desired low temperature and moisture content of the materials leaving the precooling apparatus and deposited upon the conveyor 28 leading to the main mixing plant.
in the timing chart of Fig. 6, a purely arbitrary and more specific hour schedule has been illustrated for an installation calling for approximately forty-five minutes spraying time for each of the coarse cobble aggregate compartments A and B, approximately ten minutes draining time, four minutes filling time, and allowing one minute discharge time; forty minutes spraying time for each of the intermediate cobble aggregate compartments C and D, fifteen minutes draining time, with the same filling and discharge time being allotted thereto; and approximately thirty minutes spraying time and twenty-five minutes draining time for the smaller cobble aggregate compartments E and F.
As previously described, the preliminary setting-up time consumes approximately one hour. This includes simultaneous spraying of the aggregates in all of the compartments 64. When cyclic operation is in effect, a short period of time, for example two minutes, is allowed for discharging of the first compartment A and three minutes may be allowed for the refilling thereof. At five minutes in the cycle the spraying of the coarse material in the compartment A may commence and about this time the pivoted distributor 36 may be switched over to deliver sand to the by-pass conveyor 40. The spraying operation continues until fifty minutes in the cycle when draining of the compartment A is initiated by closing the valve 83 which controls the spraying of the compartment A. At the end of the cycle the gate 66 of the compartment A is opened to discharge the contents thereof weaves.
9 and the discharge consumes approximately two minutes in the next succeeding cycle.
'While the compartment A is thus being treated, compartrnent B also containing coarse cobble material receives its spraying operation from fifteen minutes in the first cycle until the end of the cycle and the draining operation is conducted during the first ten minutes of the next cycle. Discharge of the compartment B takes place at ten minutes in the succeeding cycle and recharging thereof takes place from twelve to fifteen minutes in this latter cycle. The operations for compartments A and B are continuous throughout the various cycles.
The treatment of intermediate materials in the compartments C and D is substantially the same as for the compartments A and B with the exception that the period of spraying time involved is forty minutes with a fifteen minute period for draining as shown in the chart. Similarly, the treatment of the fine materials is shown in the chart as involving thirty minutes for the spraying operation and twenty-five minutes for draining time. In the case of each grade of material, the same alternate or staggered spraying and draining periods are maintained with the treatment accorded the three grades of materials overlapping one another.
It is to be noted that the conveyor 34 leading from the stock pile 32 is in intermittent operation, supplying sand and cobble materials to the conveyors 40 and 38, respectively, in alternate fashion. As shown in Fig. 2, the cooling plant and conveyor discharge to a common point or collecting station on the conveyor 28 which thus carries at alternate times both the untreated sand and the cooled aggregates. That is, the conveyor 28 leading to the mixing plant 10 is in substantially continuous operation supplying the discharged precooled materials or the untreated sand alternately to the mixing plant 10. The deflector plates 67 and the clamshell gates 66 operate under the same controls and the plates 67 direct expended coolant water to the surge tank 44 each time the gates 66 corresponding thereto are closed during the spraying and the draining periods of the respective compartments.
By practicing the invention as above presented, there is obtained a synchronized control of the movement of the batched materials supplied from the stock pile 32 in conjunction with the batch charging device 62 at the precooling plant and the batch charging device 17 at the mixing plant, and also in conjunction with the conveyor belts employed in connection with the invention. By fol lowing the predetermined sequence of operations, the possibility of over-charging the aggregate compartments or any of the receivers associated with the invention is minimized. In this manner, the various aggregate charges are properly separated in transit to and from the precooling apparatus 30 as well as being properly separated while undergoing cooling treatment.
I claim as my invention:
1. A cyclically operable method of precooling a plurality of aggregates of dilferent sizes prior to mixing the aggregates to form concrete, each cycle of said method comprising the steps of assembling segregated quantities of the aggregates, spraying the aggregates with cold water for diiferent fractions of the cycle in proportion to the sizes of the agregates, draining the respective aggregates for the remaining portions of the cycle, said remaining portions thereby being inversely proportional to the sizes of the aggregates, and removing said quantities of the aggregates after draining, said spraying being initiated for the respective aggregates in staggered rotation throughout said cycle so that said assembling and removing operations for the respective aggregates will also be staggered along said cycle.
2. In an apparatus for precooling concrete aggregates, a series of closely grouped aggregate compartments, a liquid permeable gate at the bottom of each compartment operable when closed to retain aggregate in the compartmer t while permitting drainage of liquid therethrough,
closing said gates.
3. in an apparatus for precooling concrete aggregates, a series of closely grouped aggregate compartments, a liquid permeable gate at the bottom of each compartment operable when closed to retain aggregate in the compartment whilepermitting drainage of liquid therethrough, a collector funnel common to all of said gates for receiving the discharged aggregate from the various compartments when their respective gates are opened, a shaker screen disposed beneath said collector funnel, a movable deflector plate disposed beneath each gate and movable to selectively direct material discharged from its respective compartment into said funnel or to divert the same from the latter, means operatively connecting said gates and deflector plates for positioning the latter in their material-diverting positions when the gates are closed, means for selectively spraying coolant liquid over the aggregate in each compartment, means for opening and closing said gates, and means for actuating said shaker screen.
4. In an apparatus for precooling concrete aggregates, a series of sector-shaped aggregate compartments arranged in closely grouped relationship about a vertical .axis, there beinga drain anddischarge opening at the bottom of each compartment, a liquid-permeable gate for each drain and discharge opening and operable when closed to retain aggregate Within the compartment while permitting liquid to escape therefrom and operable when open to discharge the contents from said compartment, a collector funnel common to all of said gates for receiving the discharged contents of said compartments, a shaker screen disposed beneath said collector funnel for receiving material discharged therefrom, means operable when said gates are closed for diverting liquid issuing from said compartments from said collector funnel and operable when said gates are open to discharge the contents of the compartments into said collector funnel, means for actuating said shaker screen, means for operating said gates, and means for selectively supplying coolant liquid to said compartments for cooling the contents thereof by direct heat transfer.
5. In an apparatus for withdrawing size-graded aggregates from a stockpile, precooling the coarser aggregates, and delivering all of the withdrawn aggregates to a mixing plant, said apparatus comprising a cooling plant located intermediate said stock pile and mixing plant, a distributing station located intermediate the cooling plant and stock pile, a conveyor for conducting aggregates from said stock pile to said distributing station, a conveyor for coarse aggregates extending from said distributing station to said cooling plant, a collecting station adjacent said cooling plant, a conveyor for delivering materials received at said collecting station to said mixing plant, a conveyor extending from said distributing station to said collecting station for transporting fine aggregates from said distributing station to said collecting station, means at said cooling plant for cooling coarse aggregates delivered thereto, means at said cooling plant for discharging the cooled coarse aggregates to said collecting station, and means for actuating all of said conveyors.
6. In an apparatus for withdrawing size-graded aggregates from a stock pile, precooling the coarse aggregates, and delivering all of the aggregates to a mixing plant, said apparatus comprising a precooling plant located intermediate said stock pile and said mixing plant, a distributing station located intermediate said precooling plant and said stock pile, a first conveyor extending from the stock pile to said distributing station, a second conveyor for coarse aggregates extending from said distributing station to said precooling plant for delivering coarse aggregates thereto, a collecting station positioned adjacent said precooling plant, a third conveyor extending from said distributing station to said collecting station for delivering fine aggregates to the latter, a fourth conveyor leading from said collecting station to said mixing plant, a distributor element adjacent the forward end of said first conveyor movable from one extreme position wherein aggregate issuing from said first conveyor is directed onto said second conveyor to another extreme position wherein the aggregate is delivered to said third conveyor, means at said precooling plant for effecting cooling of the aggregate delivered thereto, means for discharging cooled aggregates from said precooling plant directly onto said fourth conveyor, and means for selectively operating said distributor element.
7. In an apparatus for precooling a plurality of different concrete aggregates, the combination comprising an elevated bin having a plurality of compartments for holding quantities of the different aggregates, means for filling said compartments in rotation with the different aggregates, said compartments having respective gates for discharging the aggregates from said compartments in rotation, means for selectively spraying cooling Water over the aggregates in said respective compartments for cooling the aggregates, the water draining out of said compartments, means for collecting the aggregates from said gates, and means for diverting the draining water from said last mentioned means.
8. In an apparatus for precooling a plurality of concrete aggregates of different size grades, the combination comprising an elevated bin having a plurality of compartments for holding quantities of the ditferent aggregates, a conveyor for raising the aggregates to the top of the bin, means for selectively loading said conveyor with any of the different aggregates, means for selectively directing the aggregates from said conveyor into any of said compartments to fill said compartments in rotation with the different aggregates, respective gates at the bottoms of said compartments for discharging the different aggregates therefrom in rotation, means for selectively spraying cooling water into said compartments for cooling the aggregates in rotation, said gates being liquid permeable so that the water will drain therethrough from said compartments, a collector funnel underlying all of said gates for receiving the cooled aggregates therefrom, said compartments having respective diverting means operative when said gates are closed to divert the water fromsaid funnel, a shaker screen for receiving the aggregates discharged by said funnel and removing excess water from the aggregates, means for receiving and carrying 01f the cooled aggregates from said shaker screen, and means for carrying off the water from said diverting means.
References Cited in the file of this patent UNITED STATES PATENTS 713,671 Oliver Nov. 18, 1902 1,304,619 Stamp May 27, 1919 1,704,268 Venable Mar. 5, 1929 1,828,458 Butler Oct. 20, 1931 1,871,166 Fahrbach Aug. 9, 1932 2,138,277 Johnson Nov. 29, 1938 2,183,896 Rupp et al. Dec. 19, 1939 2,276,471 Eberhart Mar. 17, 1942 2,397,959 Gephart Apr. 9, 1946 2,480,727 Greyson Aug. 30, 1949

Claims (1)

1. A CYCLICALLY OPERABLE METHOD OF PRECOOLING A PLURALITY OF AGGREGATES OF DIFFERENT SIZES PRIOR TO MIXING THE AGGREGATES TO FORM CONCRETE, EACH CYCLE OF SAID METHOD COMPRISING THE STEPS OF ASSEMBLING SEGREGATED QUANTITIES OF THE AGGREGATES, SPRAYING THE AGGREGATES WITH COLD WATER FOR DIFFERENT FRACTIONS OF THE CYCLE IN PROPORTION TO THE SIZES OF THE AGREGATES, DRAINING THE RESPECTIVE AGGREGATES FOR THE REMAINING PORTIONS OF THE CYCLE, SAID REMAINING PORTIONS THEREBY BEING INVERSELY PROPORTIONAL TO THE SIZES OF THE AGGREGATES, AND REMOVING SAID QUANTITITES OF THE AGGREGATES AFTER DRAINING, SAID SPRAYING BEING INITIATED FOR THE RESPECTIVE AGGREGATES IN STAGGERED ROTATION THROUGHOUT SAID CYCLE SO THAT SAID ASSEMBLING AND REMOVING OPERATIONS FOR THE RESPECTIVE AGGREGATES WILL ALSO BE STAGGERED ALONG SAID CYCLE.
US231561A 1951-06-14 1951-06-14 Method of and apparatus for cooling concrete aggregates Expired - Lifetime US2727734A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US231561A US2727734A (en) 1951-06-14 1951-06-14 Method of and apparatus for cooling concrete aggregates

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US231561A US2727734A (en) 1951-06-14 1951-06-14 Method of and apparatus for cooling concrete aggregates

Publications (1)

Publication Number Publication Date
US2727734A true US2727734A (en) 1955-12-20

Family

ID=22869747

Family Applications (1)

Application Number Title Priority Date Filing Date
US231561A Expired - Lifetime US2727734A (en) 1951-06-14 1951-06-14 Method of and apparatus for cooling concrete aggregates

Country Status (1)

Country Link
US (1) US2727734A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3127031A (en) * 1964-03-31 stauffer
US3207559A (en) * 1962-08-23 1965-09-21 Engineered Plastics Inc Article collection system
US4196020A (en) * 1978-11-15 1980-04-01 Avco Corporation Removable wash spray apparatus for gas turbine engine
US4473532A (en) * 1981-11-30 1984-09-25 Rose Shirley M Ore leaching structure
EP0436140A1 (en) * 1989-12-14 1991-07-10 Linde Aktiengesellschaft Process and apparatus for cooling a particulate material
US5152605A (en) * 1991-01-22 1992-10-06 Ushio Co., Ltd. Apparatus for making cooled concrete
US6036352A (en) * 1997-05-06 2000-03-14 Kabushiki Kaisha Remic-Asano Method of and device for improving the quality of fresh concrete and preventing adhesion and hardening of the fresh concrete in a mixer drum of a concrete mixer truck or of a concrete mixing plant
US7520137B2 (en) * 2002-12-02 2009-04-21 Alstom Technology Ltd Method of controlling the injection of liquid into an inflow duct of a prime mover or driven machine

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US713671A (en) * 1902-08-26 1902-11-18 Maurice Joyce Machine for washing matrices preparatory to electrotyping.
US1304619A (en) * 1919-05-27 Method fob conveying concrete aggregate
US1704268A (en) * 1925-03-31 1929-03-05 Blawknox Company Art of making cementitious mixtures
US1828458A (en) * 1929-02-11 1931-10-20 Morgan R Butler Material handling equipment
US1871166A (en) * 1929-06-25 1932-08-09 Fahrbach Harry Regenerator
US2138277A (en) * 1937-03-25 1938-11-29 Charles S Johnson Apparatus for handling materials
US2183896A (en) * 1937-06-01 1939-12-19 Colorado Fuel & Iron Corp Method of filtering or dewatering
US2276471A (en) * 1939-10-20 1942-03-17 American Can Co Method of conveying and treating metallic sheets
US2397959A (en) * 1942-03-30 1946-04-09 Ferman E Gephart Portable conveyer
US2480727A (en) * 1944-01-22 1949-08-30 Kaiser Company Inc Method for cooling

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1304619A (en) * 1919-05-27 Method fob conveying concrete aggregate
US713671A (en) * 1902-08-26 1902-11-18 Maurice Joyce Machine for washing matrices preparatory to electrotyping.
US1704268A (en) * 1925-03-31 1929-03-05 Blawknox Company Art of making cementitious mixtures
US1828458A (en) * 1929-02-11 1931-10-20 Morgan R Butler Material handling equipment
US1871166A (en) * 1929-06-25 1932-08-09 Fahrbach Harry Regenerator
US2138277A (en) * 1937-03-25 1938-11-29 Charles S Johnson Apparatus for handling materials
US2183896A (en) * 1937-06-01 1939-12-19 Colorado Fuel & Iron Corp Method of filtering or dewatering
US2276471A (en) * 1939-10-20 1942-03-17 American Can Co Method of conveying and treating metallic sheets
US2397959A (en) * 1942-03-30 1946-04-09 Ferman E Gephart Portable conveyer
US2480727A (en) * 1944-01-22 1949-08-30 Kaiser Company Inc Method for cooling

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3127031A (en) * 1964-03-31 stauffer
US3207559A (en) * 1962-08-23 1965-09-21 Engineered Plastics Inc Article collection system
US4196020A (en) * 1978-11-15 1980-04-01 Avco Corporation Removable wash spray apparatus for gas turbine engine
US4473532A (en) * 1981-11-30 1984-09-25 Rose Shirley M Ore leaching structure
EP0436140A1 (en) * 1989-12-14 1991-07-10 Linde Aktiengesellschaft Process and apparatus for cooling a particulate material
US5152605A (en) * 1991-01-22 1992-10-06 Ushio Co., Ltd. Apparatus for making cooled concrete
US6036352A (en) * 1997-05-06 2000-03-14 Kabushiki Kaisha Remic-Asano Method of and device for improving the quality of fresh concrete and preventing adhesion and hardening of the fresh concrete in a mixer drum of a concrete mixer truck or of a concrete mixing plant
US7520137B2 (en) * 2002-12-02 2009-04-21 Alstom Technology Ltd Method of controlling the injection of liquid into an inflow duct of a prime mover or driven machine

Similar Documents

Publication Publication Date Title
US4792234A (en) Portable concrete batch plant
US2073652A (en) Central mixing plant
US2727734A (en) Method of and apparatus for cooling concrete aggregates
US2460605A (en) Apparatus for feeding flowable material from a plurality of containers
US3905586A (en) Mini-plant for batching and mixing materials
US4375335A (en) Silo combination for mixing stored material
US2174089A (en) Mixing apparatus
US2491194A (en) Process for altering the temperature of aggregates
US4433055A (en) Decomposing plant
US2199289A (en) Central mixing plant
US3473788A (en) Batch-compounding of comminuted materials
GB2095569A (en) Plant for mixing the constituents of a settable building material composition
KR101574299B1 (en) Manufacturing device of reinforcing ground material for improving surface layer
EP0114118B1 (en) Process and apparatus for manufacture of asphalt
JP2001270378A (en) Washing and loading methods for concrete mixer truck
US3856275A (en) Apparatus for making and storing hot asphalt paving material
US2618374A (en) Means for moving and distributing free flowing materials
US3148864A (en) Pneumatic conveying and reclaiming method and apparatus
US3462130A (en) Method and apparatus for blending bulk solids
US3216595A (en) Apparatus for charging coke ovens
US2138277A (en) Apparatus for handling materials
US1872457A (en) Storage system
CA1049067A (en) Discharging device for flat-bottomed bulk-material silos
US3345044A (en) Method of and transit apparatus for delivering concrete materials
US1176878A (en) Process and apparatus for charging furnaces.