CN108035369A - Build underground water drop row and reuse method - Google Patents

Build underground water drop row and reuse method Download PDF

Info

Publication number
CN108035369A
CN108035369A CN201711283188.5A CN201711283188A CN108035369A CN 108035369 A CN108035369 A CN 108035369A CN 201711283188 A CN201711283188 A CN 201711283188A CN 108035369 A CN108035369 A CN 108035369A
Authority
CN
China
Prior art keywords
well
water level
water
reuse method
underground water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711283188.5A
Other languages
Chinese (zh)
Inventor
林晓林
夏树杰
徐东彬
于海舰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201711283188.5A priority Critical patent/CN108035369A/en
Publication of CN108035369A publication Critical patent/CN108035369A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The present invention provides one kind building underground water drop row and reuse method, include the following steps:Embedded catch pit:Planned according to the well of predeterminated position and bury catch pit;Lay drainage pipeline:Drainage pipeline laying is carried out according to default path;Water level control:Set in the well to control the water level control system of water level in well;Purification recycles:Recycled after the water sedimentation that the water level control system is discharged is purified.Building underground water drop row and reuse method in the present invention, by embedded catch pit, water level control system and purification reutilization system, on the one hand effectively realize the collection to natural precipitation and on the other hand ensure that control to height of water level in well;More achieve the purpose that to save water resource.

Description

Build underground water drop row and reuse method
Technical field
The present invention relates to technical field of buildings, in particular to one kind building underground water drop row and reuse method.
Background technology
At present, the application of deep basal pit is more and more extensive in architectural engineering.In deep foundation pit construction, generally use well-points dewatering skill Art, well-points dewatering can extract flood tide underground water out.On the one hand, the underground water of extraction is discharged into city sewer, has both caused water resource unrestrained Take, also increase the burden of sewerage system;On the other hand, engineering construction needs to consume substantial amounts of tap water, and deep base again It is longer to cheat construction period.In addition, in Practical Project, some units in charge of construction are using brick or concreting sedimentation basin come to underground Water is handled, but brick sedimentation basin easy to leak, and dismounting brick setting or concrete also increase building waste after completion.
The content of the invention
In consideration of it, the present invention proposes a kind of building underground water drop row and reuse method, it is intended to solves existing structure The problem of underground water drop arranges and reuses difficulty.
On one side, the present invention proposes a kind of building underground water drop row and reuse method, includes the following steps:
Embedded catch pit:Planned according to the well of predeterminated position and bury catch pit;
Lay drainage pipeline:Drainage pipeline laying is carried out according to default path;
Water level control:Set in the well to control the water level control system of water level in well;
Purification recycles:Recycled after the water sedimentation that the water level control system is discharged is purified.
Further, above-mentioned building underground water is dropped in row and reuse method, described during above-mentioned embedded catch pit Well determines spacing, diameter and the depth of well in planning according to building level of ground water and soil property situation.
Further, above-mentioned building underground water is dropped in row and reuse method, is placed with the wellhole of the well some Pipe of concrete.
Further, above-mentioned building underground water is dropped in row and reuse method, and the well bottom is equipped with for filtering The sandstone filter layer of impurities in water.
Further, above-mentioned building underground water is dropped in row and reuse method, during above-mentioned laying drainage pipeline, institute Preset path is stated to be determined according to building and municipal drain web portal.
Further, above-mentioned building underground water is dropped in row and reuse method, the drainage pipeline and the catch pit string Connection.
Further, above-mentioned building underground water is dropped in row and reuse method, during above-mentioned water level control, the water Level controlling system includes the immersible pump being arranged in well, the switch being connected respectively with the immersible pump and water level control relay Device.
Further, above-mentioned building underground water is dropped in row and reuse method, during above-mentioned water level control, when water in well When position exceedes pre-set height of water level, pump drainage of diving under water described in the level relay switch power control;When water in well When position is less than pre-set height of water level, the level relay switch circuit breaking controls the immersible pump to stop draining.
Further, above-mentioned building underground water is dropped in row and reuse method, described during above-mentioned purification recycling Discharge water first imports progress precipitation purification processing in the sedimentation basin being pre-designed, and is carried out again after reaching discharge and recycling standard Utilize.
Further, above-mentioned building underground water is dropped in row and reuse method, and the sedimentation basin is second-level settling pond.
Compared with prior art, the beneficial effects of the present invention are building underground water drop row provided by the invention and again profit With method, by burying catch pit, and it is connected by drainpipe with the well planned and accomplished fluently in advance, it is effective to realize Collection to natural precipitation.
Especially, building underground water of the invention drop row and reuse method, by setting water level control system in well System, when water level exceedes pre-set height of water level in well, level relay switch power control diving pump drainage;When in well When water level is less than pre-set height of water level, level relay switch circuit breaking control immersible pump stops draining, effective to realize Control to height of water level in well.
Further, the present invention purifies reutilization system by setting, by what is discharged in well by water level control system Water carries out two-stage precipitation purified treatment, is reused after reaching discharge and recycling standard, has effectively saved water Resource, achievees the purpose that water-saving.
Brief description of the drawings
By reading the detailed description of hereafter preferred embodiment, it is various other the advantages of and benefit it is common for this area Technical staff will be clear understanding.Attached drawing is only used for showing the purpose of preferred embodiment, and is not considered as to the present invention Limitation.And in whole attached drawing, identical component is denoted by the same reference numerals.In the accompanying drawings:
Fig. 1 is building underground water drop row provided in an embodiment of the present invention and reuse method flow chart;
Fig. 2 is the floor plan of building underground water drop row provided in an embodiment of the present invention and reuse method;
Fig. 3 is the diagrammatic cross-section of building underground water drop row provided in an embodiment of the present invention and reuse method;
In figure;1 is building, and 2 be well, and 3 be catch pit, and 4 be drainpipe, and 5 be two level settling tank, and 6 be pressure pump, and 7 are Valve, 8 be total valve, and 9 be municipal specific drainage well, and 21 be power controling box, and a is relay upper limit site, and b is under relay Limit point, c are nature ground.
Embodiment
The preferred embodiment of the present invention described with reference to the accompanying drawings.It will be apparent to a skilled person that this A little embodiments are used only for explaining the technical principle of the present invention, it is not intended that limit the scope of the invention.
It should be noted that in the description of the present invention, the instruction such as term " on ", " under ", "left", "right", " interior ", " outer " Direction or the term of position relationship be to be based on direction shown in the drawings or position relationship, this is intended merely to facilitate description, and It is not instruction or implies that described device or element there must be specific orientation, with specific azimuth configuration and operation, therefore not It is understood that as limitation of the present invention.
In addition it is also necessary to explanation, in the description of the present invention, unless otherwise clearly defined and limited, term " peace Dress ", " connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected or be detachably connected, or integratedly Connection;Can mechanically connect or be electrically connected;It can be directly connected, can also be indirectly connected by intermediary, It can be the connection inside two elements.To those skilled in the art, it can understand that above-mentioned term exists as the case may be Concrete meaning in the present invention.
As shown in fig.1, for the building underground water drop row of the embodiment of the present invention and reuse method flow chart, it is included such as Lower step:Embedded catch pit:Planned according to the well of predeterminated position and bury catch pit;Lay drainage pipeline:According to default Path carries out drainage pipeline laying;Water level control:Set in the well to control the water level control system of water level in well System;Purification recycles:Recycled after the water sedimentation that the water level control system is discharged is purified.
Specifically, before burying catch pit, the position planning of well is first carried out, and is beaten according to well planning chart Well.During well-digging, according to building level of ground water and the situation of soil property, determine spacing between well and well, well it is straight Depth of footpath and well etc..After well is accomplished fluently, prefabricated pipe of concrete is put into wellhole, and sandstone mistake is laid with shaft bottom Filtering layer.Then plan catch pit burial place further according to the position of well, and select suitable catch pit to be buried, in order to Collection to precipitation.It should be noted that catch pit can select the PVC catch pits of finished product, can also be during construction Carry out concreting.
In the present embodiment, with building level of ground water throughout the year in -2m or so, rich groundwater, soil permeability coefficient compared with Greatly, building foundation is dug exemplified by deep -5m, and well spacing is 30m, a diameter of 400mm of well, well depth are -20m;Often saved in wellhole prefabricated mixed The length of solidifying soil pipe is 1m, and a diameter of 300mm, the sandstone filter layer in shaft bottom is 30cm;Catch pit using PVC material make and Into being divided into two kinds of A and B, wall thickness is 10mm, and the length, width and height of wherein catch pit A are respectively 700mm, 700mm and 1000mm;Collection Puddle B length, width and height are respectively 1000mm, 1000mm and 1200mm.Catch pit A is connected with well, easy to by catch pit B Water imports, and catch pit B is arranged on trunk roads, is on the one hand flowed into easy to water excessive in catch pit, and the opposing party can converge water Enter settling tank.
Specifically, if drainage pipeline, the laying of drainage pipeline is determined according to the entrance of building and municipal drainage pipe network Path, and according to the laying of the suitable drainage pipeline of path progress, drainage pipeline is together in series with catch pit, make catch pit In water can be flowed by pipeline stream.Meanwhile when drainpipe is laid, pipeline is set to keep certain continuous slope Degree, to ensure the circulation of water in pipe.It is understood that drainage pipeline is used as connection catch pit with well or catch pit with catchmenting Interface channel between hole, can either import the water being imported into catch pit in well, and can ensure will be more in catch pit Remaining ponding is flowed into adjacent catch pit, to ensure the water balance in whole system.
In the present embodiment, the drainpipe selected according to displacement is divided into supervisor and branch pipe, wherein supervisor uses diameter The bellows of 300mm, is arranged on trunk roads, that is, is arranged between catch pit B and catch pit B, settling tank, and effective guarantee can To pass through enough water;Branch pipe is managed using diameter 110mmPVC, is arranged between catch pit A and catch pit A, well, for current It is dynamic.Meanwhile the sustained grade between pipeline is 1%, to ensure that water can continuously flow.It is understood that by being managed in laying Pipeline is set to certain gradient during road, is conducive to water and is flowed in pipe, and successfully import catch pit.
Specifically, water level control, is put into an immersible pump in every mouthful of well saliva well, and every immersible pump sets a power supply control Case processed, has switch, earth leakage protective device, water level control relay in case.Water level reaches setting relay at water pump upper surface in well Device lower limit control point, relay control switch, which automatically powers off, when water level reaches this stops pumping.Water level, which reaches, in well sets Place sets relay upper limit control point below the bottom absolute altitude of meter hole, and when water level reaches this, relay control switch, which is powered, to be started Draw water, until water level is dropped in the range of bound.It is understood that the extreme position up and down of water level can be set according to actual conditions Put, as long as being able to ensure that dewatering effect reaches design requirement.
In the present embodiment, water level reaches setting relay lower limit control point, water at the 0.5m of water pump upper surface in well Relay control switch, which automatically powers off, when position reaches this stops pumping;Water level reaches below the bottom absolute altitude of design hole at 3m in well Relay upper limit control point is set, and when water level reaches this, relay control switch, which is powered, to be started to draw water.
Specifically, purification recycles, and builds a second-level settling pond in the venue first, precipitation and passes through water level control system The water of system discharge, imports in sedimentation basin after two-stage precipitation is handled by drainpipe, after reaching discharge and recycling standard, leads to It is overpressurized water pump and pipeline is respectively used to scene greening spray, airborne dust flushing, construction water etc. and is recycled.It is appreciated that It is that control valve can be set on pipeline, to carry out the control of water size and switch;Relay control is provided with pressure pump Water level elevation processed, water level automatically power off when being less than water pump.
In the present embodiment, sedimentation basin be a length and width, it is deep be respectively that the two level of 6000mm, 4000mm and 3000mm is sunk Shallow lake pond, side wall are brick setting 240mm thickness walls, and inner wall is plastered.Hole bottom is 100mm thickness C15 concrete cushions.
Obviously can draw, building underground water drop row provided by the invention and reuse method, are catchmented by embedded Hole, and it is connected by drainpipe with the well planned and accomplished fluently in advance, effectively realize the collection to natural precipitation.
Especially, building underground water of the invention drop row and reuse method, by setting water level control system in well System, when water level exceedes pre-set height of water level in well, level relay switch power control diving pump drainage;When in well When water level is less than pre-set height of water level, level relay switch circuit breaking control immersible pump stops draining, effective to realize Control to height of water level in well.
Further, the present invention purifies reutilization system by setting, by what is discharged in well by water level control system Water carries out two-stage precipitation purified treatment, is reused after reaching discharge and recycling standard, has effectively saved water Resource, achievees the purpose that water-saving.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art God and scope.In this way, if these modifications and changes of the present invention belongs to the scope of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to comprising including these modification and variations.

Claims (10)

1. one kind building underground water drop row and reuse method, it is characterised in that include the following steps:
Embedded catch pit:Planned according to the well of predeterminated position and bury catch pit;
Lay drainage pipeline:Drainage pipeline laying is carried out according to default path;
Water level control:Set in the well to control the water level control system of water level in well;
Purification recycles:Recycled after the water sedimentation that the water level control system is discharged is purified.
2. building underground water drop row according to claim 1 and reuse method, it is characterised in that catchment in above-mentioned bury During hole, the well in planning according to building level of ground water and soil property situation determine the spacing of well, diameter and Depth.
3. building underground water drop row according to claim 2 and reuse method, it is characterised in that the wellhole of the well In be placed with some pipe of concretes.
4. building underground water drop row according to claim 3 and reuse method, it is characterised in that the well bottom paving Equipped with the sandstone filter layer for filtering impurities in water.
5. building underground water drop row according to claim 1 and reuse method, it is characterised in that in above-mentioned laying draining In pipe process, the preset path is determined according to building and municipal drain web portal.
6. it is according to claim 5 building underground water drop row and reuse method, it is characterised in that the drainage pipeline with The catch pit series connection.
7. building underground water drop row according to claim 1 and reuse method, it is characterised in that in above-mentioned water level control During, the water level control system includes the immersible pump being arranged in well, the switch being connected respectively with the immersible pump And water level control relay.
8. building underground water drop row according to claim 7 and reuse method, it is characterised in that in above-mentioned water level control During, when water level exceedes pre-set height of water level in well, diving described in the level relay switch power control Pump drainage;When water level is less than pre-set height of water level in well, the level relay switch circuit breaking controls the diving Pump stops draining.
9. building underground water drop row according to claim 1 and reuse method, it is characterised in that sharp again in above-mentioned purification During, the discharge water first imports progress precipitation purification processing in the sedimentation basin being pre-designed, and reaches discharge and recycling Reused after standard.
10. building underground water drop row according to claim 9 and reuse method, it is characterised in that the sedimentation basin is Second-level settling pond.
CN201711283188.5A 2017-12-07 2017-12-07 Build underground water drop row and reuse method Pending CN108035369A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711283188.5A CN108035369A (en) 2017-12-07 2017-12-07 Build underground water drop row and reuse method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711283188.5A CN108035369A (en) 2017-12-07 2017-12-07 Build underground water drop row and reuse method

Publications (1)

Publication Number Publication Date
CN108035369A true CN108035369A (en) 2018-05-15

Family

ID=62096117

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711283188.5A Pending CN108035369A (en) 2017-12-07 2017-12-07 Build underground water drop row and reuse method

Country Status (1)

Country Link
CN (1) CN108035369A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109763552A (en) * 2018-12-27 2019-05-17 中建三局集团有限公司 A kind of basis is dark to apply gravity type draining regeneration application system and its construction method
CN109933114A (en) * 2019-04-19 2019-06-25 中国地质科学院水文地质环境地质研究所 A kind of water table measure and regulator control system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1657712A (en) * 2005-03-22 2005-08-24 无锡市建筑设计研究院有限责任公司 Drainage and anti-float method for underground building and its used device
CN203174633U (en) * 2013-04-27 2013-09-04 国家电网公司 Water accumulation prevention cable well
CN203947484U (en) * 2014-06-04 2014-11-19 中国建筑第二工程局有限公司 A kind of drainage of foundation pit and circulating water utilization system
CN204298837U (en) * 2014-11-14 2015-04-29 中国建筑第八工程局有限公司 Bright, dark drainage system
CN106120831A (en) * 2016-08-06 2016-11-16 安徽华力建设集团有限公司 A kind of building automation drainage system and construction method
CN205954649U (en) * 2016-08-26 2017-02-15 中国二十冶集团有限公司 Execute automatic precipitation system of recycling on industrial area ground
CN107313469A (en) * 2017-07-07 2017-11-03 中国十七冶集团有限公司 Especially big & deep basement anti-floating pressure relief water collects the method prevented and treated for airborne dust

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1657712A (en) * 2005-03-22 2005-08-24 无锡市建筑设计研究院有限责任公司 Drainage and anti-float method for underground building and its used device
CN203174633U (en) * 2013-04-27 2013-09-04 国家电网公司 Water accumulation prevention cable well
CN203947484U (en) * 2014-06-04 2014-11-19 中国建筑第二工程局有限公司 A kind of drainage of foundation pit and circulating water utilization system
CN204298837U (en) * 2014-11-14 2015-04-29 中国建筑第八工程局有限公司 Bright, dark drainage system
CN106120831A (en) * 2016-08-06 2016-11-16 安徽华力建设集团有限公司 A kind of building automation drainage system and construction method
CN205954649U (en) * 2016-08-26 2017-02-15 中国二十冶集团有限公司 Execute automatic precipitation system of recycling on industrial area ground
CN107313469A (en) * 2017-07-07 2017-11-03 中国十七冶集团有限公司 Especially big & deep basement anti-floating pressure relief water collects the method prevented and treated for airborne dust

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109763552A (en) * 2018-12-27 2019-05-17 中建三局集团有限公司 A kind of basis is dark to apply gravity type draining regeneration application system and its construction method
CN109933114A (en) * 2019-04-19 2019-06-25 中国地质科学院水文地质环境地质研究所 A kind of water table measure and regulator control system

Similar Documents

Publication Publication Date Title
CN203947484U (en) A kind of drainage of foundation pit and circulating water utilization system
CN107938692B (en) Drainage and recharging construction method and structure
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN110805022B (en) Mud solidification treatment device and method for matching electroosmosis well point with well point dewatering
CN102433886A (en) Construction method for adding water lowering well in water collecting well
CN102418347A (en) Drainage construction method for blind drain and sump wells in deep foundation pit
CN107100227A (en) A kind of pergola on the city road LID biologies are detained ditch construction method
CN104847010A (en) Urban miniature underground reservoir and construction method
WO2023103651A1 (en) Drainage pressure relief anti-floating system for weakly permeable soft stratum
CN104234089B (en) The construction method that a kind of basement guarded drainage combines
CN108035369A (en) Build underground water drop row and reuse method
CN207633496U (en) A kind of super large square sponge city Integral rain recycling system
CN210737511U (en) Tower type groundwater pressure recharge equipment
CN204899978U (en) Shaft excavation to interface water layer drainage system
CN104328836B (en) A kind of environment-friendly type prefabricated pair of case deep hole type catch pit and construction method thereof
CN207828994U (en) It is a kind of draining and recharge constructing structure
CN114855822A (en) Construction method for deep foundation pit of rain sewage pipeline on highway
CN104088352A (en) Ground rainwater comprehensive utilization structure
CN206477382U (en) Rainwater recycle comprehensively utilizes structure
CN209585078U (en) A kind of forced-ventilated water system for super-sized foundation pit
CN211735347U (en) Mud solidification treatment device for electroosmosis well point and well point dewatering matching
CN107386320A (en) Pass through the construction method of the underground pipe gallery of buried concrete waterpipe
CN103898920B (en) Foundation ditch falls, water discharge method
CN109555141A (en) A kind of forced-ventilated water system and construction method for super-sized foundation pit
CN110258603A (en) The stealthy precipitation engineering method of local ultra-deep foundation pit in deep basal pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180515