CN108033354B CN201711439246.9A CN201711439246A CN108033354B CN 108033354 B CN108033354 B CN 108033354B CN 201711439246 A CN201711439246 A CN 201711439246A CN 108033354 B CN108033354 B CN 108033354B
Authority
CN
China
Prior art keywords
point
hanging ring
telescopic rod
fixed plate
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711439246.9A
Other languages
Chinese (zh)
Other versions
CN108033354A (en
Inventor
杨建冲
吴云鹏
汪楚亮
陈新
周环宇
唐明刚
郭大维
吴多贵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co ltd Of Cccc Fourth Harbor Enginering Co ltd
CCCC Fourth Harbor Engineering Co Ltd
Original Assignee
Third Engineering Co ltd Of Cccc Fourth Harbor Enginering Co ltd
CCCC Fourth Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co ltd Of Cccc Fourth Harbor Enginering Co ltd, CCCC Fourth Harbor Engineering Co Ltd filed Critical Third Engineering Co ltd Of Cccc Fourth Harbor Enginering Co ltd
Priority to CN201711439246.9A priority Critical patent/CN108033354B/en
Publication of CN108033354A publication Critical patent/CN108033354A/en
Application granted granted Critical
Publication of CN108033354B publication Critical patent/CN108033354B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention relates to the technical field of a protective surface block, in particular to a novel breakwater protective surface block removing device, which comprises the following components: rope, fixing plate, temporary fixing belt and hanging ring releasing device; wherein, the two ends of the rope are respectively provided with a first hanging ring and a second hanging ring; the hanging ring release device comprises a telescopic rod which can be driven by power; the temporary securing strap binding a position on the rope to the first point; according to the invention, the first hanging ring is hung on the fixed plate through penetrating the second hanging ring with the rope to form a lasso structure, then the second hanging ring is sleeved on the telescopic rod, the second hanging ring is equivalent to a movable joint of the lasso structure, the second hanging ring can be released by controlling the telescopic rod to stretch, the lasso structure is tightened by pulling the power arm, and the limbs of the protective block are tightly sleeved, so that the protective block is hung and removed.

Description

Novel breakwater facing block removes device
Technical Field
The invention relates to the technical field of facing blocks, in particular to a novel breakwater facing block removing device.
Background
In China, the common artificial facing blocks include quadrangle cone-shaped, twisted I-shaped blocks, twisted king blocks, fence plates and the like, and in recent years, the twisted king blocks are widely used. The turning block is partially modified and optimized by Chinese scholars after learning and digesting AccropodeTM II outside the country in the last 80 th century, and has become one of the most popular artificial facing blocks in China after development for more than thirty years. The research and application of the artificial block are very extensive overseas, the hooked block mainly comprises AccropodeII type, core-Loc I type and Xbloc@mainly at present, the block has good robustness, good wave attenuation and strong stability, and can be constructed in a single layer, and the application is very extensive, wherein the AccropodeI type is one of the most popular artificial protection blocks worldwide so far.
In the installation process of the facing block, the block can be unhooked or displaced unintentionally due to problems such as unhooking devices, steel wire ropes, severe sea conditions, operation reasons and the like, and the block needs to be lifted for removal and reinstallation, or the installed block is found to not meet the installation standard and requirement after the installation is completed, and the block needs to be lifted for removal and reinstallation. The conventional method for removing the block underwater is that a diver drops a hook for removing, and the defects of high requirements on sea conditions, low efficiency, high cost, high safety risk, poor timeliness and the like exist.
Disclosure of Invention
In view of the above, the present invention provides a novel breakwater facing block removing device for solving the problems in the prior art.
The invention solves the problems by the following technical means:
a novel breakwater facing block removal device comprising: rope, fixing plate, temporary fixing belt and hanging ring releasing device; wherein, the two ends of the rope are respectively provided with a first hanging ring and a second hanging ring;
the bottom of the fixed plate is provided with a first point and a second point, the first point is arranged on the first end of the fixed plate, and the second point is arranged at a position far away from the first end; the hanging ring release device comprises a telescopic rod which can be driven by power;
the first hanging ring is hung on the second point by passing through the second hanging ring along the rope, and the second hanging ring is sleeved on the telescopic rod;
the temporary fixing belt is made of a material with certain strength, the temporary fixing belt is broken when being stretched by certain external force, and the temporary fixing belt binds a certain position on the rope on the first point;
the top of the fixed plate is connected with a power arm, and the power arm is powered by a driving device.
In detail, the second point is arranged at the middle position of the fixed plate, and the power arm is symmetrically arranged with the second point through the fixed plate.
In detail, the temporary securing strap binds a first location on the cord to the first point, the first location being proximate to the second link, the cord between the first point and the second link being in an approximately straightened state.
In detail, a first protruding edge is arranged on the first point, a first hole is formed in the first protruding edge, and the temporary fixing strap passes through the first hole to bind and fix the rope on the first point.
In detail, a second protruding edge is arranged on the second point, a second hole is formed in the second protruding edge, and the first hanging ring is hung on the second point through forming a ring buckle with the second hole.
In detail, the temporary fixing strap is a tie.
In detail, a through groove is formed near the second end of the fixed plate, and the first point, the second point and the through groove are sequentially arranged on the fixed plate; the telescopic rod is arranged at the top of the fixed plate; the second hanging ring penetrates through the through groove and is sleeved and hung on the telescopic rod.
In detail, a supporting block for supporting the telescopic rod is arranged at the top of the fixing plate, and the telescopic rod is in sliding fit with the supporting block.
In detail, the telescopic link also comprises a third hanging ring, the third hanging ring is connected with the second hanging ring in a ring buckle mode, the third hanging ring is sleeved on the telescopic link, and the second hanging ring is indirectly sleeved on the telescopic link through being connected with the third hanging ring in a ring buckle mode.
In detail, a through groove is formed near the second end of the fixed plate, and the first point, the second point and the through groove are sequentially arranged on the fixed plate; the telescopic rod is arranged at the top of the fixed plate; the third hanging ring passes through the through groove and is sleeved and hung on the telescopic rod.
According to the invention, the first hanging ring is hung on the fixed plate through penetrating the second hanging ring with the rope to form a lasso structure, then the second hanging ring is sleeved on the telescopic rod, the second hanging ring is equivalent to a movable joint of the lasso structure, the second hanging ring can be released by controlling the telescopic rod to stretch, the lasso structure is tightened by pulling the power arm, and the limbs of the protective block are tightly sleeved, so that the protective block is hung and removed.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for the description of the embodiments will be briefly described below, and it is apparent that the drawings in the following description are only some embodiments of the present invention, and other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
FIG. 1 is a schematic view of a first embodiment of the present invention;
fig. 2 is a schematic structural diagram of a second embodiment of the present invention.
Reference numerals illustrate:
1. a rope; 2. a fixing plate; 3. a temporary fixing band; 4. a first hanging ring; 5. a second hanging ring; 6. a telescopic rod; 7. a power arm; 8. a facing block; 9. a first flange; 10. a second flange; 11. and a third hanging ring.
Detailed Description
In order to make the above objects, features and advantages of the present invention more comprehensible, the following detailed description of the technical solution of the present invention refers to the accompanying drawings and specific embodiments. It should be noted that the described embodiments are only some embodiments of the present invention, and not all embodiments, and that all other embodiments obtained by persons skilled in the art without making creative efforts based on the embodiments in the present invention are within the protection scope of the present invention.
It should be appreciated that the orientation or positional relationship indicated by the terms "top," "bottom," and the like are based on the orientation or positional relationship shown in the drawings, and are merely for convenience in describing the present invention and simplifying the description, and are not indicative or implying that the apparatus or elements being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore should not be construed as limiting the present invention.
The terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defining "a first", "a second", or a third "may explicitly or implicitly include one or more such feature. In the description of the present invention, unless otherwise indicated, the meaning of "a group" is two or more.
Example 1
As shown in fig. 1, a novel breakwater facing block removing device includes: rope 1, fixing plate 2, temporary fixing belt 3 and hanging ring releasing device; wherein, the two ends of the rope 1 are respectively provided with a first hanging ring 4 and a second hanging ring 5;
the bottom of the fixed plate 2 is provided with a first point and a second point, the first point is arranged on the first end of the fixed plate 2, and the second point is arranged at a position far away from the first end; the hanging ring release device comprises a telescopic rod 6 which can be driven by power;
the first hanging ring 4 is hung on the second point by penetrating the second hanging ring 5 with the rope 1, and the second hanging ring 5 is sleeved on the telescopic rod 6;
the temporary fixing strap 3 is made of a material with certain strength, the temporary fixing strap 3 is broken when being stretched by certain external force, and the temporary fixing strap 3 binds a certain position on the rope 1 on the first point;
the top of the fixed plate 2 is connected with a power arm 7, and the power arm 7 is powered by a driving device (such as a working arm of the excavator).
In detail, the second point is disposed at a middle position of the fixed plate 2, and the power arm 7 is symmetrically disposed with the second point through the fixed plate 2; thus, the fixing plate 2 is more stable during operation.
In detail, the temporary securing strap 3 binds a first position on the cord 1, which is close to the second suspension loop 5, to the first point, the cord 1 between the first point and the second suspension loop 5 being in an approximately straightened state, such that by straightening the length of cord 1, a larger lasso is formed by the cord 1, facilitating the lasso to be slipped over the limb of the facing block 8.
In detail, a first protruding edge 9 is arranged on the first point, a first hole is formed in the first protruding edge 9, and the temporary fixing strap 3 passes through the first hole to fix the rope 1 on the first point in a binding mode, so that the binding work of the temporary fixing strap 3 is facilitated.
In detail, the second point is provided with a second protruding edge 10, the second protruding edge 10 is provided with a second hole, the first hanging ring 4 is hung on the second point through being buckled with the second hole, and through the design, the moving range of the first hanging ring 4 is more free.
In detail, the temporary fixing strap 3 is a binding strap, the binding strap is low in price and good in binding effect, and can be broken when being pulled by certain external force, so that the requirement of the temporary fixing strap 3 is met.
In detail, a through groove is formed near the second end of the fixed plate 2, and the first point, the second point and the through groove are sequentially arranged on the fixed plate 2; the telescopic rod 6 is arranged at the top of the fixed plate 2; the second hanging ring 5 is sleeved and hung on the telescopic rod 6 through the through groove; by limiting the second hanging ring 5 in the space of the through groove, the second hanging ring 5 is firmly locked by the telescopic rod 6 in the hoisting process, and cannot fall off from the telescopic rod 6 due to the change of the external force direction.
In detail, a supporting block for supporting the telescopic rod 6 is arranged at the top of the fixed plate 2, and the telescopic rod 6 is in sliding fit with the supporting block.
The invention is further described by combining the working process, firstly, the lasso consisting of the rope 1, the first hanging ring 4 and the second hanging ring 5 is sleeved on the limb of the protective surface block 8 to be removed, then the power arm 7 pulls the first hanging ring 4 to move towards the direction which forms a certain inclination angle with the limb of the protective surface block 8, in the moving process, the stress of the rope 1 is larger and larger, when the force reaches a certain degree, the temporary fixing belt 3 is broken, then the rope 1 is continuously stressed and tightened, after the rope 1 is tightened to a certain degree, the telescopic rod 6 is contracted to release the second hanging ring 5, then the rope 1 can rapidly drive the second hanging ring 5 to move under the action of the pretightening force, so that the movable joint of the lasso structure is moved and tightened, the limb of the protective surface block 8 is tightly sleeved, and then the protective surface block 8 is hung by the power arm 7 to remove.
According to the invention, the first hanging ring is hung on the fixed plate through penetrating the second hanging ring with the rope to form a lasso structure, then the second hanging ring is sleeved on the telescopic rod, the second hanging ring is equivalent to a movable joint of the lasso structure, the second hanging ring can be released by controlling the telescopic rod to stretch, the lasso structure is tightened by pulling the power arm, and the limbs of the protective block are tightly sleeved, so that the protective block is hung and removed.
Example two
As shown in fig. 2, the present embodiment is different from the first embodiment in that: the telescopic link is characterized by further comprising a third hanging ring 11, wherein the third hanging ring 11 is connected with the second hanging ring 5 in a ring buckle mode, the third hanging ring 11 is sleeved on the telescopic link 6, and the second hanging ring 5 is indirectly sleeved on the telescopic link 6 through the ring buckle connection with the third hanging ring 11.
In detail, a through groove is formed near the second end of the fixing plate 3, and the first point, the second point and the through groove are sequentially arranged on the fixing plate; the telescopic rod 6 is arranged at the top of the fixed plate 3; the third hanging ring 11 is hung on the telescopic rod 6 through the through groove.
The foregoing examples illustrate only a few embodiments of the invention and are described in detail herein without thereby limiting the scope of the invention. It should be noted that it will be apparent to those skilled in the art that several variations and modifications can be made without departing from the spirit of the invention, which are all within the scope of the invention. Accordingly, the scope of protection of the present invention is to be determined by the appended claims.

Claims (8)

1. A novel breakwater facing block removal device, comprising: rope, fixing plate, temporary fixing belt and hanging ring releasing device; wherein, the two ends of the rope are respectively provided with a first hanging ring and a second hanging ring;
the bottom of the fixed plate is provided with a first point and a second point, the first point is arranged on the first end of the fixed plate, and the second point is arranged at a position far away from the first end; the hanging ring release device comprises a telescopic rod which can be driven by power;
the first hanging ring is hung on the second point by passing through the second hanging ring along the rope, and the second hanging ring is sleeved on the telescopic rod;
the temporary fixing belt is made of a material with certain strength, the temporary fixing belt is broken when being stretched by certain external force, and the temporary fixing belt binds a certain position on the rope on the first point;
the top of the fixed plate is connected with a power arm, and the power arm is powered by a driving device;
the second point is arranged at the middle position of the fixed plate, and the power arm is symmetrically arranged with the second point through the fixed plate;
the temporary securing strap binds a first location on the cord at the first point, the first location being proximate to the second link, the cord between the first point and the second link being in an approximately straightened state.
2. The novel breakwater facing block removal device of claim 1, wherein a first flange is provided on the first point, a first hole is provided on the first flange, and the temporary fixing strap passes through the first hole to bind and fix the rope on the first point.
3. The novel breakwater facing block removal device of claim 1, wherein a second flange is provided at the second point, a second hole is provided at the second flange, and the first hanging ring is hung at the second point by forming a loop with the second hole.
4. The novel breakwater facing block removal device of claim 1, wherein the temporary securing strap is a tie.
5. The novel breakwater facing block removal device according to any one of claims 1 to 4, wherein a through groove is formed near the second end of the fixing plate, and the first point, the second point and the through groove are sequentially arranged on the fixing plate; the telescopic rod is arranged at the top of the fixed plate; the second hanging ring penetrates through the through groove and is sleeved and hung on the telescopic rod.
6. The novel breakwater facing block removal device of claim 5, wherein a support block for lifting the telescopic rod is arranged at the top of the fixing plate, and the telescopic rod is in sliding fit with the support block.
7. The novel breakwater facing block removal device of any of claims 1-4, further comprising a third link, the third link forming a loop connection with the second link, the third link being looped over the telescoping rod, the second link being indirectly looped over the telescoping rod by being looped over the third link.
8. The novel breakwater facing block removal device of claim 7, wherein a through groove is formed near the second end of the fixed plate, and the first point, the second point and the through groove are sequentially arranged on the fixed plate; the telescopic rod is arranged at the top of the fixed plate; the third hanging ring passes through the through groove and is sleeved and hung on the telescopic rod.
CN201711439246.9A 2017-12-27 2017-12-27 Novel breakwater facing block removes device Active CN108033354B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711439246.9A CN108033354B (en) 2017-12-27 2017-12-27 Novel breakwater facing block removes device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711439246.9A CN108033354B (en) 2017-12-27 2017-12-27 Novel breakwater facing block removes device

Publications (2)

Publication Number Publication Date
CN108033354A CN108033354A (en) 2018-05-15
CN108033354B true CN108033354B (en) 2023-08-29

Family

ID=62101419

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711439246.9A Active CN108033354B (en) 2017-12-27 2017-12-27 Novel breakwater facing block removes device

Country Status (1)

Country Link
CN (1) CN108033354B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110438945A (en) * 2019-08-15 2019-11-12 中交第四航务工程局有限公司 Breakwater armor block 360 degree rotation and automatically de- chain suspender

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009107740A (en) * 2007-10-26 2009-05-21 Nishimuragumi:Kk Bucket and block recovery method using this bucket
CN201416420Y (en) * 2009-05-11 2010-03-03 江苏中油天工机械有限公司 Oil pumping machine safety belt hanging device
CN103395708A (en) * 2013-08-13 2013-11-20 徐州重型机械有限公司 Crane, counterweight device and rope hanging mechanism
JP2014118237A (en) * 2012-12-14 2014-06-30 Aomi Construction Co Ltd Remote unslinging device
CN205294605U (en) * 2015-12-28 2016-06-08 中国石油天然气股份有限公司 Jack -up lifting device
CN207658931U (en) * 2017-12-27 2018-07-27 中交第四航务工程局有限公司 A kind of Novel breakwater armour removal device

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100417102B1 (en) * 2001-12-28 2004-02-05 두산중공업 주식회사 Mechanical ANTI-SNAG Device for Container Crane
US20100201141A1 (en) * 2007-09-28 2010-08-12 Walter Peter Wright Lasso handling device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009107740A (en) * 2007-10-26 2009-05-21 Nishimuragumi:Kk Bucket and block recovery method using this bucket
CN201416420Y (en) * 2009-05-11 2010-03-03 江苏中油天工机械有限公司 Oil pumping machine safety belt hanging device
JP2014118237A (en) * 2012-12-14 2014-06-30 Aomi Construction Co Ltd Remote unslinging device
CN103395708A (en) * 2013-08-13 2013-11-20 徐州重型机械有限公司 Crane, counterweight device and rope hanging mechanism
CN205294605U (en) * 2015-12-28 2016-06-08 中国石油天然气股份有限公司 Jack -up lifting device
CN207658931U (en) * 2017-12-27 2018-07-27 中交第四航务工程局有限公司 A kind of Novel breakwater armour removal device

Also Published As

Publication number Publication date
CN108033354A (en) 2018-05-15

Similar Documents

Publication Publication Date Title
CN108946516A (en) A kind of towing combined into one apparatus
CN105283405A (en) Shackle
CN108033354B (en) Novel breakwater facing block removes device
CN205319615U (en) Frame double hook turn -buckle that high altitude construction takes off with antiskid
CN105398545B (en) A kind of tensioning method of mooring anchor leg
CN105197188B (en) Mooring anchor leg hanging dynamic tie back tool and tieback method under water
CN201670644U (en) Roof truss hoisting device
CN207658931U (en) A kind of Novel breakwater armour removal device
CN109835807A (en) The unmanned draw off gear and implementation method of floating body are carried in automatic positioning
CN202190019U (en) Aerial earth wire ratchet wrench type two-point lifting tool
CN109775554A (en) Water pump lifts by crane auxiliary hitch
CN204474191U (en) The jib body dumping mechanism of tower crane
CN105712173B (en) A kind of multi-joint packing tank moduleization lifting and transport bracing means
CN209702118U (en) Water pump lifts by crane auxiliary hitch
CN210973657U (en) Marine crane with fixing device
CN201296598Y (en) Convenient-safe lifting device
JP2000247573A (en) Underwater suspended matter lifting support device and method
CN209617385U (en) Water floating drum recycles lowering system in a kind of deep water single point mooring
CN209114718U (en) A kind of building-supporting steel beam structure
CN206643902U (en) One kind drags for material instrument
CN209780257U (en) Steel structure high altitude construction device
CN106081873A (en) A kind of suspender for changing linear tension electric pole and replacing options
CN101898691B (en) Method for replacing pitching steel wire ropes of ship loader
CN202190023U (en) Wire bracing device for overhead wire
CN110789669A (en) System and method for recycling and putting down reclaimed water buoy in deep water single-point mooring

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant