CN108019209A - The drawing anchor construction method deformed suitable for the overlying solum settlement of shallow tunnel - Google Patents

The drawing anchor construction method deformed suitable for the overlying solum settlement of shallow tunnel Download PDF

Info

Publication number
CN108019209A
CN108019209A CN201711148458.1A CN201711148458A CN108019209A CN 108019209 A CN108019209 A CN 108019209A CN 201711148458 A CN201711148458 A CN 201711148458A CN 108019209 A CN108019209 A CN 108019209A
Authority
CN
China
Prior art keywords
anchor
tunnel
slip casting
construction method
overlying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711148458.1A
Other languages
Chinese (zh)
Other versions
CN108019209B (en
Inventor
邵生俊
朱丹丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Technology
Original Assignee
Xian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Technology filed Critical Xian University of Technology
Priority to CN201711148458.1A priority Critical patent/CN108019209B/en
Publication of CN108019209A publication Critical patent/CN108019209A/en
Application granted granted Critical
Publication of CN108019209B publication Critical patent/CN108019209B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Abstract

The drawing anchor construction method that overlying solum settlement disclosed by the invention suitable for shallow tunnel deforms, comprises the following steps:Step 1, pre-processed before tunneling;Step 2, a grouted anchor bar is respectively applied at the spandrel position of overburden layer or so on tunnel;Step 3, apply grade beam in the adjacent ground surface of tunnel upper and carry out fixing anchor bar anchor head;Step 4, using three benching tunnelling method tunneling of upper, middle and lower.The present invention draws anchor construction method to be connected by applying anchor pole at tunnel spandrel, and with grade beam, applies an anchor-hold to overburden layer on tunnel, plays the role of drawing anchor;Effectively reinforce loose, play the role of limitation, reduction well to the stratum shallow tunnel overlying solum settlement deformation, the construction method short time limit, low cost, construction efficiency is high, and the out-of-balance force that produced by tunnel excavation can dissipate, adjust strain regime, slow down the development of deformation, realize itself confinement effect, there is good practical value.

Description

The drawing anchor construction method deformed suitable for the overlying solum settlement of shallow tunnel
Technical field
The invention belongs to shallow soft stratum method and technology field, and in particular to a kind of upper overburden layer suitable for shallow tunnel The drawing anchor construction method of sedimentation and deformation.
Background technology
In recent years, urban population densification aggravates so that ground usable floor area is more and more limited, and traffic above-ground is increasingly gathered around Squeeze, so as to promote the quick popularization and progress of Urban Underground railway.As urban track traffic reaches its maturity, either subway Tunnel or vcehicular tunnel, are obtained for preferable development in each area, but the problem of producing therewith is also more and more.
The fast-developing of subway undoubtedly alleviates sizable congested in traffic problem to each big city, and pole is brought for people Big facility.But just there is a worry here, for subway buried depth generally all at 10-20 meters, shallow tunnel is in the majority, its excavation will certainly Disturbance and destruction can be produced to surrounding soil, overburden layer on tunnel different degrees of sedimentation and deformation is occurred, this is directly influenced The intensive building in ground, pavement of road and the safe handling of municipal works, the phenomenon are more prominent in loose, soft stratum.Cause This, in order to ensure that above ground structure safety, traffic above-ground are normally orderly, then must be strictly controlled the overlying caused by tunnel excavation Solum settlement deforms.Control the sedimentation and deformation method very much, including improve soil strength variation, reduce the discharge capacity of underground water, according to Formation condition selects construction method, rationally determines to excavate drilling depth, immediate support measure and engineering reinforcement measure etc. should during selection As far as possible rationally effectively, serious consequence will otherwise be caused.
The content of the invention
The object of the present invention is to provide the drawing anchor construction method that a kind of overlying solum settlement suitable for shallow tunnel deforms, solution The problem of deformation of overlying solum settlement easily occurs when excavating for existing shallow tunnel of having determined.
The technical solution adopted in the present invention is, suitable for the drawing anchor construction party of the overlying solum settlement deformation of shallow tunnel Method, comprises the following steps:
Step 1, pre-processed before tunneling
It will do shortly above the tunnel excavation face in the range of consolidation process, and carry out pore-forming operation using ordi-nary drilling machine, so Advanced tubule is inserted into simultaneously slip casting in hole afterwards, forms advance bonding course;
Step 2, grouted anchor bar is applied
Step 2.1, at the spandrel position in the tunnel handled through step 1, ordi-nary drilling machine edge and Vertical tunnel center line are used One group of drilling is symmetrically crept into the direction of 30 ° of -45 ° of angles, then cleaning drilling;
Step 2.2, using the hollow grouting anchor of head installation anchor head, it is then inserted into the drilling of step 2.1, together When hollow grouting anchor is tangled with the hangnail on anchor head;Installation sleeve, stop grouting plug, pad successively on hollow grouting anchor at this time The injected hole of hollow grouting anchor afterbody, is then connected by plate and nut with slip casting machine;
Step 2.3, slip casting operation is carried out to hollow grouting anchor by slip casting machine and injected hole, obtains grouted anchor bar;
Step 3, the grouted anchor bar anchor head handled through step 2 is fixed
Step 3.1, concrete cushion is built in the tunnel upper after step 2 processing, then draws the ground that will be applied The center line of Ji Liang and sideline, the datum line as later stage formwork supporting plate;
Step 3.2, reinforcing bar as defined in meeting is made and according to demand in corresponding site assembling reinforcement, then according to step 3.1 center line and sideline installation wooden model;
Step 3.3, watering moistening processing is carried out to wooden model, then wooden model and embedded anchor head are carried out with armored concrete Pour and smash operation, anchor head is fixed in the grade beam in wooden model, solidifying no less than wooden model is removed after 24h, even if anchor head is fixed In grade beam;
Step 4, the tunnel handled through step 3 is excavated using three benching tunnelling method of upper, middle and lower, that is, obtains preventing overburden layer from deforming Shallow tunnel.
It is of the invention to be further characterized in that,
Advanced tubule is seamless steel pipe in step 1, specifically includes the slip casting entrance being connected with each other successively, slip casting Duan Gang Pipe and only slurry section steel pipe;
Wherein slip casting entrance is in coniform that the slip casting hole arranged in plum blossom-shaped is provided with slip casting section steel pipe.
Advanced tubule internal diameter 30-50mm, length 3-5mm, the spacing of adjacent slip casting hole is 100-150mm, adjacent super The spacing of preceding ductule is 300-500mm.
The specific installation operation of advanced tubule is:
Advanced tubule is headed into using pneumatic pick or with being installed after mechanical hole building, and outside along tunnel longitudinal direction excavation contour line With 10 ° -30 ° of extrapolation angular bit hole, stratum is then squeezed into;After installing, in advanced tubule mouth of pipe flax silk and anchor Gu agent blocks its gap between hole, and end socket and orifice valves are installed at the advanced tubule mouth of pipe.
The length of hollow grouting anchor insertion drilling is no less than the 95% of its total length in step 2;Backing plate is adjacent to tunnel and faces Empty face.
Wooden model is first clean by its surface clean before use in step 3, then paints demoulding grease, is propped up again after its drying Wooden model.
Poured in step 3 and smash operation and use poker vibrator, vibrating time 10-15s.
Step 4 concretely comprises the following steps:
Step 4.1, top bar uses Ring Cutting provided core soil method, and on tunnel top, section first digs arc hole, then Excavate central core soil and set up steel arch-shelf, the once supporting and arch springing slip casting lock foot anchor tube of appropriate section, control are set in it The sedimentation and deformation of lining cutting at initial stage processed;
Step 4.2, middle step divides left and right sides to excavate, and sets up steel arch-shelf in time and sets the once supporting and wall of appropriate section Subscript slurry lock foot anchor tube, controls the sedimentation and deformation of lining cutting at initial stage;
Step 4.3, the excavation that carries out getting out of a predicament or an embarrassing situation constructs tunnel inverted arch, sets the once supporting of appropriate section, makes arch wall initial stage Lining cutting, vault lining cutting at initial stage and inverted arch lining cutting at initial stage are connected as an entirety, form closed circular lining cutting at initial stage;
Step 4.4, sheet plastic separation layer is set up as waterproof layer, successively tunnel inverted arch and arch wall is carried out building mould coagulation Soil operation, completes secondary lining and vault backfill slip casting.
The beneficial effects of the invention are as follows:The present invention is suitable for the drawing anchor construction method that the overlying solum settlement of shallow tunnel deforms It is connected by applying anchor pole at tunnel spandrel, and by them with the grade beam of adjacent ground surface, overburden layer on tunnel is applied One anchor-hold, plays the role of drawing anchor;Loose, soft stratum structure can be effectively reinforced, to overburden layer on the stratum shallow tunnel Sedimentation and deformation plays the role of limitation, reduction well, and the short time limit of the construction method, low cost, construction efficiency is high, and energy will be because of tunnel Road excavates the out-of-balance force produced and dissipates, and adjusts strain regime, slows down or postpone the development of deformation, realize itself confinement effect, With higher economic benefit and social benefit, there is good practical value.
Brief description of the drawings
Fig. 1 is the excavation construction flow chart that the present invention draws tunnel in anchor construction method;
Fig. 2 is the structure diagram of A-A sections in Fig. 1 of the present invention;
Fig. 3 is that the present invention draws tunnel in anchor construction method to draw anchor construction schematic diagram;
Fig. 4 is the structure diagram that the present invention draws hollow grouting anchor in anchor construction method;
Fig. 5 is the flow chart that the present invention draws hollow grouting anchor construction technology in anchor construction method.
In figure, 1. advanced tubules, 2. steel arch-shelfs, 3. arch springing slip castings lock foot anchor tube, 4. foundation slip castings lock foot anchor tube, 5. 1 Secondary supporting, 6. sheet plastic separation layers, 7. form concretes, 8. hollow grouting anchors, 9. grade beams, 10. injected holes, 11. spiral shells Mother, 12. exhausting-gas holes, 13. stop grouting plugs, 14. backing plates, 15. sleeves, 16. anchor heads, 17. drillings.
Embodiment
The present invention is described in detail with reference to the accompanying drawings and detailed description.
The present invention is suitable for the drawing anchor construction method that the overlying solum settlement of shallow tunnel deforms, and comprises the following steps:
Step 1, pre-processed before tunneling
It will do shortly above the tunnel excavation face in the range of consolidation process, and carry out pore-forming operation using ordi-nary drilling machine, such as Shown in Fig. 1 and Fig. 2, advanced tubule 1 is then inserted into hole simultaneously slip casting, forms advance bonding course;
Wherein advanced tubule 1 is seamless steel pipe, specifically includes the slip casting entrance being connected with each other successively, slip casting section steel pipe With only slurry section steel pipe;Slip casting entrance is in coniform, and the slip casting hole arranged in plum blossom-shaped is provided with slip casting section steel pipe;It is advanced small 1 internal diameter 30-50mm of conduit, length 3-5mm, the spacing of the adjacent slip casting hole of each two are 100-150mm, each two adjacent advance The spacing of ductule 1 is 300-500mm;Wherein, injection slurry is specifically determined according to formation condition etc.;
The specific installation operation of advanced tubule 1 is:Advanced tubule 1 is headed into using pneumatic pick or with pacifying after mechanical hole building Dress, and along tunnel longitudinal direction excavation contour line stratum is then squeezed into outwards with 10 ° -30 ° of extrapolation angular bit hole;Install Afterwards, its gap between hole is blocked with flax silk and Anchor Agent in 1 mouth of pipe of advanced tubule, and at 1 mouth of pipe of advanced tubule End socket and orifice valves are installed.
Step 2, grouted anchor bar is applied
Step 2.1, at the spandrel position in the tunnel handled through step 1, ordi-nary drilling machine edge and Vertical tunnel center line are used One group of drilling 17 is symmetrically crept into the direction of 30 ° of -45 ° of angles, then cleaning drilling 17;
Step 2.2, as shown in Figure 3 and Figure 4, using the hollow grouting anchor 8 of head installation anchor head 16, it is then inserted into In the drilling 17 of step 2.1, while hollow grouting anchor 8 is tangled with the hangnail on anchor head 16;At this time in hollow grouting anchor 8 On installation sleeve 15, stop grouting plug 13, backing plate 14 and nut 11 successively, then by the injected hole 10 of 8 afterbody of hollow grouting anchor with Slip casting machine is connected;Its 8 afterbody of hollow grouting anchor is additionally provided with exhausting-gas hole 12;The wherein insertion of hollow grouting anchor 8 drilling 17 Length be no less than its total length 95%;Backing plate 14 is adjacent to tunnel free face;
Step 2.3, slip casting operation is carried out to hollow grouting anchor 8 by slip casting machine and injected hole 10, to carry out pressure Slip casting improves soil layer construction, it is only necessary to waits the pointer on pressure gauge to be raised to designed pressure, obtains grouted anchor bar, in detail As shown in Figure 5.
Step 3, the grouted anchor bar anchor head 16 handled through step 2 is fixed
Step 3.1, concrete cushion is built in the tunnel upper after step 2 processing, is then ejected on it with the line of ink marker The center line for the grade beam 9 that will be applied and sideline, the datum line as later stage formwork supporting plate;
Step 3.2, reinforcing bar as defined in meeting is made and according to demand in corresponding site assembling reinforcement, then according to step 3.1 center line and sideline installation wooden model;Wherein wooden model is first clean by its surface clean before use, then paints mould oil Fat, the Zhi Mumo again after its drying;
Step 3.3, watering moistening processing is carried out to wooden model, then with armored concrete to wooden model and embedded anchor head 16 into Row, which pours, smashes operation, makes in the grade beam 9 that anchor head 16 is fixed in wooden model, is solidifying no less than wooden model is removed after 24h, even if anchor head 16 are fixed in grade beam 9, and poker vibrator, vibrating time 10-15s are used wherein pouring and smashing operation;
Grade beam 9 build should subterranean tunnel excavation after stress space outside so as to note could be passed through Starch anchor pole and apply anchor drawing effect;The position of grade beam 9, size and arrangement of reinforcement etc. are determined with specific reference to tunnel size, use reinforcing bar Concrete foundation beam 9 carrys out fixing anchor bar;The reinforcing bar of grade beam 9 is all connected using binding, during binding should in sequence successively into Row binding.
Step 4, the tunnel handled through step 3 is excavated using three benching tunnelling method of upper, middle and lower, that is, obtains preventing overburden layer from deforming Shallow tunnel:
Step 4.1, top bar uses Ring Cutting provided core soil method, and as illustrated in fig. 1-3, on tunnel top, section is first Dig arc hole 1., then excavate central core soil 2. and set up steel arch-shelf 2,5 He of once supporting of appropriate section is set in it Arch springing slip casting lock foot anchor tube 3, controls the sedimentation and deformation of lining cutting at initial stage;
Step 4.2, middle step divides left and right sides to excavate, and first excavates left side 3., then excavates right side 4., sets up steel arch-shelf 2 in time And the once supporting 5 and corner slip casting lock foot anchor tube 4 of appropriate section are set, control the sedimentation and deformation of lining cutting at initial stage;
Step 4.3,5. the excavation that carries out getting out of a predicament or an embarrassing situation constructs tunnel inverted arch, the once supporting 5 of appropriate section is set, at the beginning of making arch wall Phase lining cutting, vault lining cutting at initial stage and inverted arch lining cutting at initial stage are connected as an entirety, form closed circular lining cutting at initial stage;
Step 4.4, set up sheet plastic separation layer 6 and be used as waterproof layer, successively tunnel inverted arch and arch wall are carried out building mould and mixed Solidifying soil 7 operates, and completes secondary lining and vault backfill slip casting.
In construction method of the present invention, tunnel excavation uses three benching tunnelling method of upper, middle and lower, and wherein top bar is reserved with Ring Cutting Core local method, leaves Core Soil due to digging process middle and upper part and carries excavation face, can timely do first branch to vault rapidly Face stability is excavated in shield, increase;The excavation project of Core Soil and lower part all carries out under the protection of arch initial support, safety Property is good;The middle step point left and right sides applies, and reduces excavated section, and the scope of excavation disturbance soil layer is also relatively small, during closing Between it is short, structure is soon in overall preferable stress;The construction method, which coordinates, draws anchor Treatment process to controlling upper earthing The sedimentation and deformation of layer also functions to certain control action.

Claims (8)

1. the drawing anchor construction method deformed suitable for the overlying solum settlement of shallow tunnel, it is characterised in that comprise the following steps:
Step 1, pre-processed before tunneling
It will do shortly above the tunnel excavation face in the range of consolidation process, pore-forming operation is carried out using ordi-nary drilling machine, then will Simultaneously slip casting in advanced tubule (1) insertion hole, forms advance bonding course;
Step 2, grouted anchor bar is applied
Step 2.1, at the spandrel position in the tunnel handled through step 1, using ordi-nary drilling machine along with Vertical tunnel center line into Symmetrically one group of drilling (17) of drilling, then cleaning drill (17) in the direction of 30 ° of -45 ° of angles;
Step 2.2, using the hollow grouting anchor (8) of head installation anchor head (16), it is then inserted into the drilling of step 2.1 (17) in, while hollow grouting anchor (8) is tangled with the hangnail on anchor head (16);At this time on hollow grouting anchor (8) according to Secondary installation sleeve (15), stop grouting plug (13), backing plate (14) and nut (11), then by the slip casting of hollow grouting anchor (8) afterbody Hole (10) is connected with slip casting machine;
Step 2.3, slip casting operation is carried out to hollow grouting anchor (8) by slip casting machine and injected hole (10), obtains grouted anchor bar;
Step 3, the grouted anchor bar anchor head (16) handled through step 2 is fixed
Step 3.1, concrete cushion is built in the tunnel upper after step 2 processing, then draws the grade beam that will be applied (9) center line and sideline, the datum line as later stage formwork supporting plate;
Step 3.2, reinforcing bar as defined in meeting is made and according to demand in corresponding site assembling reinforcement, then according to step 3.1 Center line and sideline installation wooden model;
Step 3.3, watering moistening processing is carried out to wooden model, then wooden model and embedded anchor head (16) are carried out with armored concrete Pour and smash operation, anchor head (16) is fixed in the grade beam in wooden model (9), solidifying no less than wooden model is removed after 24h, even if anchor Head (16) is fixed in grade beam (9);
Step 4, the tunnel handled through step 3 is excavated using three benching tunnelling method of upper, middle and lower, that is, obtains preventing overburden layer from deforming shallow Bury tunnel.
2. the drawing anchor construction method that the overlying solum settlement according to claim 1 suitable for shallow tunnel deforms, its feature It is, advanced tubule (1) is seamless steel pipe in the step 1, specifically includes the slip casting entrance being connected with each other successively, slip casting Duan Gangguan and only slurry section steel pipe;
Wherein slip casting entrance is in coniform that the slip casting hole arranged in plum blossom-shaped is provided with slip casting section steel pipe.
3. the drawing anchor construction method that the overlying solum settlement according to claim 1 suitable for shallow tunnel deforms, its feature It is, advanced tubule (1) the internal diameter 30-50mm, length 3-5mm, the spacing of the adjacent slip casting hole is 100- 150mm, the spacing of the adjacent advanced tubule (1) is 300-500mm.
4. the drawing anchor construction method deformed according to any overlying solum settlements suitable for shallow tunnel of claim 1-3, It is characterized in that, the specific installation operation of the advanced tubule (1) is:
Advanced tubule (1) is headed into using pneumatic pick or with being installed after mechanical hole building, and outside along tunnel longitudinal direction excavation contour line With 10 ° -30 ° of extrapolation angular bit hole, stratum is then squeezed into;After installing, in advanced tubule (1) mouth of pipe flax silk and Anchor Agent blocks its gap between hole, and end socket and orifice valves are installed at advanced tubule (1) mouth of pipe.
5. the drawing anchor construction method that the overlying solum settlement according to claim 1 suitable for shallow tunnel deforms, its feature It is, the length of hollow grouting anchor (8) insertion drilling (17) is no less than the 95% of its total length in the step 2;The pad Plate (14) is adjacent to tunnel free face.
6. the drawing anchor construction method that the overlying solum settlement according to claim 1 suitable for shallow tunnel deforms, its feature It is, wooden model is first clean by its surface clean before use in the step 3, then paints demoulding grease, after its drying again Zhi Mumo.
7. the drawing anchor construction method that the overlying solum settlement according to claim 1 suitable for shallow tunnel deforms, its feature It is, is poured in the step 3 and smash operation and use poker vibrator, vibrating time 10-15s.
8. the drawing anchor construction method that the overlying solum settlement according to claim 1 suitable for shallow tunnel deforms, its feature It is, the step 4 concretely comprises the following steps:
Step 4.1, top bar uses Ring Cutting provided core soil method, and on tunnel top, section first digs arc hole, then excavates Central core soil simultaneously sets up steel arch-shelf (2), and the once supporting (5) and arch springing slip casting lock foot anchor tube of appropriate section are set in it (3), the sedimentation and deformation of lining cutting at initial stage is controlled;
Step 4.2, middle step divides left and right sides to excavate, in time set up steel arch-shelf (2) and set appropriate section once supporting (5) and Corner slip casting lock foot anchor tube (4), controls the sedimentation and deformation of lining cutting at initial stage;
Step 4.3, the excavation that carries out getting out of a predicament or an embarrassing situation constructs tunnel inverted arch, sets the once supporting (5) of appropriate section, makes arch wall lining at initial stage Build, vault lining cutting at initial stage and inverted arch lining cutting at initial stage are connected as an entirety, formation closed circular lining cutting at initial stage;
Step 4.4, set up sheet plastic separation layer (6) and be used as waterproof layer, successively tunnel inverted arch and arch wall are carried out building mould coagulation Native (7) operation, completes secondary lining and vault backfill slip casting.
CN201711148458.1A 2017-11-17 2017-11-17 The drawing anchor construction method of upper overburden layer sedimentation and deformation suitable for shallow tunnel Active CN108019209B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711148458.1A CN108019209B (en) 2017-11-17 2017-11-17 The drawing anchor construction method of upper overburden layer sedimentation and deformation suitable for shallow tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711148458.1A CN108019209B (en) 2017-11-17 2017-11-17 The drawing anchor construction method of upper overburden layer sedimentation and deformation suitable for shallow tunnel

Publications (2)

Publication Number Publication Date
CN108019209A true CN108019209A (en) 2018-05-11
CN108019209B CN108019209B (en) 2019-09-27

Family

ID=62079941

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711148458.1A Active CN108019209B (en) 2017-11-17 2017-11-17 The drawing anchor construction method of upper overburden layer sedimentation and deformation suitable for shallow tunnel

Country Status (1)

Country Link
CN (1) CN108019209B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114876494A (en) * 2022-04-12 2022-08-09 中铁十二局集团第七工程有限公司 Shallow tunnel ground beam and tie rod combined settlement inhibiting device and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102345463A (en) * 2011-10-19 2012-02-08 中交第一公路工程局有限公司 Support structure for large-span shallow-buried underground tunnel in urban sensitive area
CN102606168A (en) * 2012-03-16 2012-07-25 西安理工大学 Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
KR20140007309A (en) * 2013-12-17 2014-01-17 (주)현이앤씨 Method of pre-supported tunnel costructed in a soft ground
RU2504618C1 (en) * 2012-06-19 2014-01-20 Закрытое акционерное общество "ЭРКОН" Shallow tunnel in soft water-saturated ground conditions
CN105781582A (en) * 2016-04-11 2016-07-20 长安大学 Novel shallow-buried tunnel support structure applicable to urban sensitive areas and construction method of novel shallow-buried tunnel support structure applicable to urban sensitive areas
CN206581939U (en) * 2017-01-11 2017-10-24 中铁隧道勘测设计院有限公司 A kind of the minimum depth compound stratum shield tunnel construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102345463A (en) * 2011-10-19 2012-02-08 中交第一公路工程局有限公司 Support structure for large-span shallow-buried underground tunnel in urban sensitive area
CN102606168A (en) * 2012-03-16 2012-07-25 西安理工大学 Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
RU2504618C1 (en) * 2012-06-19 2014-01-20 Закрытое акционерное общество "ЭРКОН" Shallow tunnel in soft water-saturated ground conditions
KR20140007309A (en) * 2013-12-17 2014-01-17 (주)현이앤씨 Method of pre-supported tunnel costructed in a soft ground
CN105781582A (en) * 2016-04-11 2016-07-20 长安大学 Novel shallow-buried tunnel support structure applicable to urban sensitive areas and construction method of novel shallow-buried tunnel support structure applicable to urban sensitive areas
CN206581939U (en) * 2017-01-11 2017-10-24 中铁隧道勘测设计院有限公司 A kind of the minimum depth compound stratum shield tunnel construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114876494A (en) * 2022-04-12 2022-08-09 中铁十二局集团第七工程有限公司 Shallow tunnel ground beam and tie rod combined settlement inhibiting device and construction method
CN114876494B (en) * 2022-04-12 2024-02-23 中铁十二局集团第七工程有限公司 Shallow-buried tunnel ground beam tie bar combined sinking inhibition device and construction method

Also Published As

Publication number Publication date
CN108019209B (en) 2019-09-27

Similar Documents

Publication Publication Date Title
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN105649089B (en) A kind of excavation of foundation pit closes on existing shallow foundation protection structure construction method
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN107503257A (en) One kind is close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN107965325B (en) A kind of small interval shallow tunnel just branch arch replacement construction method
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN103758123A (en) Method for constructing protecting wall lining of cast-in-place manual hole digging pile
CN104632227B (en) Subway station excavation technology of single-layer beam arch structure
CN110284885A (en) Shield inspection-pit construction method
CN107288642A (en) PBA construction technologies
CN111119128B (en) Danger-removing, reinforcing and seepage-proofing method for natural rock-fill dam of barrier lake
CN110778328B (en) Loess tunnel entrance section construction method for passing through landslide body
CN103321235A (en) Composite soil nailing wall slope support method
CN107905798A (en) The method that flat top wall boring construction is carried out using central drift method
CN105672241A (en) Device and method for treating deep seismic subsidence loess by combination of loess breakage by air injection and loess squeezing by air bag
CN211340827U (en) Structure for newly building bridge by passing through existing bridge piles in subway tunnel
CN102304927B (en) Prestress anchor cable buttress-type parapet suitable for rock substrate
CN109973115B (en) Construction method for drainage of vault of tunnel in karst area
CN110847207A (en) Structure and construction method for newly-built bridge with subway tunnel passing through existing bridge piles
CN101153494A (en) Underground beam-pile frame construction for reinforcing side slope
CN204311456U (en) Foundation ditch strengthening structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant