CN108019051B - Reinforced concrete structure deep pore reinforced construction method - Google Patents
Reinforced concrete structure deep pore reinforced construction method Download PDFInfo
- Publication number
- CN108019051B CN108019051B CN201710970757.7A CN201710970757A CN108019051B CN 108019051 B CN108019051 B CN 108019051B CN 201710970757 A CN201710970757 A CN 201710970757A CN 108019051 B CN108019051 B CN 108019051B
- Authority
- CN
- China
- Prior art keywords
- bar planting
- hole
- drill bit
- concrete structure
- planting hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0203—Arrangements for filling cracks or cavities in building constructions
- E04G23/0211—Arrangements for filling cracks or cavities in building constructions using injection
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
- Processing Of Stones Or Stones Resemblance Materials (AREA)
Abstract
The present invention proposes a kind of reinforced concrete structure deep pore reinforced construction method, and step has: 1, the positioning of bar planting hole;2, bar planting drilling;2.1,100~200 millimeters and hydraulic pressure return slag in reinforced concrete structure are pierced using big drill bit water drilling puncher;2.2, small drill bit replaces big drill bit, continues drilling and hydraulic pressure return slag, and 50~100 millimeters of drilling depth become bar planting prebored hole;2.3, big drill bit replaces small drill bit, makes borehole enlargement to the aperture in bar planting hole along bar planting preboring hole drilling;It is repeated in step 2.2 and 2.3, until pore-forming;3, borehole cleaning;4, the injecting glue into bar planting hole, until stopping injecting glue behind 200~300 millimeters of aperture apart from bar planting hole;5, bar planting guarantees not disturb for 24 hours under room temperature, and bar planting is completed after 48 hours.The present invention answers drilled as holes technology by repeatedly change drill bit and effectively ensures deep pore reinforced construction efficiency and quality.
Description
Technical field
The present invention relates to building construction technologies, specifically implement deep pore reinforced construction party on reinforced concrete structure
Method.
Background technique
Application No. is 200710053610.8 Chinese patents to propose a kind of mass concrete structure deep pore reinforced construction
Method, step are: 1, determining the plan-position of reinforcing bar in concrete structure, drilled with drilling machine;2, hole wall feather plucking and borehole cleaning;3,
Bar planting reinforcing bar and injected rubber hose are placed in bar planting hole using centering bracket;4, injected rubber hose is extracted on marginal not glue side out, until anchoring adhesive is perfused
The gap of full bar planting reinforcing bar and bar planting hole inner wall;5, bar planting reinforcing bar is not disturbed in 24 hours, bar planting is completed after 48 hours.This method
The verticality of bar planting when effectively ensuring deep pore reinforced, but there is also following technological difficulties: pore-forming mistake when for deep hole pore-forming
Concrete inner core in journey near drill bit is easy to be broken by shake, and the larger position of break is deeper, is difficult the side by hydraulic pressure return slag
Formula clears out, and is difficult to bore these broken breaks if continuing to use former drill bit, is easily destroyed bar planting hole inner wall instead.It is therefore desirable to
It improves.
Summary of the invention
The purpose of the present invention is to propose to a kind of reinforced concrete structure deep pore reinforced construction methods, by repeatedly becoming drill bit
Multiple drilled as holes technology, realizes the dual construction effect for boring gravel-concrete inner core break and reducing concrete inner core break,
It effectively ensures and carries out deep pore reinforced construction efficiency and construction quality on reinforced concrete structure.
The purpose of the present invention can be achieved through the following technical solutions:
Reinforced concrete structure deep pore reinforced construction method comprising following steps:
Step 1, inbuilt reinforcement location in reinforced concrete structure is determined according to design drawing, it is inclined further according to site operation
Difference and bar planting hole parameter determine bar planting hole site, and bar planting hole parameter includes bar planting bore dia and bar planting hole depth, bar planting
Bore dia is 25~40 millimeters, and bar planting hole depth is 600~850 millimeters, and bar planting hole site is to avoid in reinforced concrete structure
Reinforcing bar is to determine principle, goes out bar planting hole drill hole location in reinforced concrete structure surface markers later.
Step 2, bar planting drilling is carried out.
Step 2.1, in the bar planting hole drill hole location on reinforced concrete structure surface, the water drilling puncher of big drill bit, institute are used
The drilling diameter for stating big drill bit is suitable with bar planting bore dia, first light to bore field planting muscle hole location, then bores into reinforced concrete structure
Hole and hydraulic pressure return slag;Big drill bit water drilling puncher pierces in reinforced concrete structure 100~200 millimeters, makes in concrete structure
Bar planting hole with 100~200 millimeters deeps.
Step 2.2, the big drill bit of water drilling puncher is changed to small drill bit, the drilling diameter of the small drill bit is bar planting hole
The 1/2~2/3 of diameter is continued along bar planting hole to reinforced concrete structure internal drilling and hydraulic pressure return slag;Small drill bit water drilling puncher
50~100 millimeters are pierced in reinforced concrete structure, makes that there is bar planting prebored hole in concrete structure.
Step 2.3, the small drill bit of water drilling puncher is changed to big drill bit, along bar planting preboring hole drilling and hydraulic pressure return slag,
Make aperture of the big drill bit water drilling puncher by the borehole enlargement of bar planting prebored hole to bar planting hole;
It is repeated in step 2.2 and step 2.3, until bar planting hole depth reaches the depth of pore forming of design.
In boring procedure, water drilling puncher should keep vertical, slow and uniform drilling operation as far as possible, drill while using
Water drilling puncher progress hydraulic pressure return slag will bore to mince in hole clears out hole.
Step 3, after the pore-forming of bar planting hole, the mud in bar planting hole is washed away completely with clear water, then wiped bar planting hole with staple
Only.
Step 4, after the bar planting hole of step 3 is dried, anchoring adhesive, the note of filling device are fed into bar planting hole using filling device
Jiao Zui is protruded near the bottom hole in bar planting hole, and the gluing nozzle of filling device is extracted on marginal not glue side out, and anchoring adhesive is perfused to apart from bar planting hole
Behind 200~300 millimeters of aperture, stops injecting glue and be fully drawn out the gluing nozzle of filling device.
Step 5, bar planting immediately after the completion of the injecting glue of step 4, bar planting reinforcing bar is slowly inserted into bar planting hole, and edge is inserted on side
Certain orientation slowly rotates, and keeps anchoring adhesive and bar planting rebar surface and bar planting hole inner wall bonding closely knit;The insertion of bar planting reinforcing bar is planted
Guarantee not disturb for 24 hours after the bottom hole of muscle hole, under room temperature, bar planting is completed after 48 hours.
Prioritization scheme does bar planting hole using heating rod after being cleaned bar planting hole with staple in step 3 of the invention
Dry processing.
The present invention has substantive distinguishing features and significant progress following prominent: the present invention is drilled to again using repeatedly change drill bit
Big drill bit is changed to small drill bit, one can effectively avoid the generation of hole inner concrete inner core when drilling to certain depth by hole technology
Fracture, one can be broken will pass through the discharge of hydraulic pressure return slag by the concrete inner core drilled out by big drill bit brill, effectively ensures bar planting hole
Hole quality and pore-forming efficiency, be very suitable to deep pore reinforced drilling construction.
Specific embodiment
Below by embodiment, the invention will be further described.
Embodiment
A kind of reinforced concrete structure deep pore reinforced construction method comprising following steps:
Step 1, inbuilt reinforcement location in reinforced concrete structure is determined according to design drawing, it is inclined further according to site operation
Difference and bar planting hole parameter determine bar planting hole site, and bar planting hole parameter includes bar planting bore dia and bar planting hole depth, this reality
Apply that the bar planting bore dia in example is 32 millimeters, bar planting hole depth is 810 millimeters, bar planting hole site is to avoid reinforced concrete structure
Interior reinforcing bar is to determine principle, goes out bar planting hole drill hole location in reinforced concrete structure surface markers later.
Step 2, bar planting drilling is carried out.
Step 2.1, in the bar planting hole drill hole location on reinforced concrete structure surface, the water drilling puncher of big drill bit, institute are used
The drilling diameter of big drill bit is stated as 32 millimeters, first light brill field planting muscle hole location, then to armored concrete suitable with bar planting bore dia
Structure internal drilling and hydraulic pressure return slag;Big drill bit water drilling puncher pierces in reinforced concrete structure 200 millimeters, makes concrete structure
Inside there is the bar planting hole of 200 millimeters deeps.
Step 2.2, the big drill bit of water drilling puncher is changed to small drill bit, the drilling diameter of the small drill bit is 18 millis
Rice continues along bar planting hole to reinforced concrete structure internal drilling and hydraulic pressure return slag;Small drill bit water drilling puncher pierces reinforced concrete
50~100 millimeters in soil structure, make that there is bar planting prebored hole in concrete structure.
Step 2.3, the small drill bit of water drilling puncher is changed to big drill bit, along bar planting preboring hole drilling and hydraulic pressure return slag,
Make aperture of the big drill bit water drilling puncher by the borehole enlargement of bar planting prebored hole to bar planting hole;
It is repeated in step 2.2 and step 2.3, until bar planting hole depth reaches the depth of pore forming of design.
In boring procedure, water drilling puncher should keep vertical, slow and uniform drilling operation as far as possible, drill while using
Water drilling puncher progress hydraulic pressure return slag will bore to mince in hole clears out hole.
Step 3, after the pore-forming of bar planting hole, the mud in bar planting hole is washed away completely with clear water, then wiped bar planting hole with staple
Only, bar planting hole is dried using heating rod later.
Step 4, after the bar planting hole of step 3 is dried, anchoring adhesive, the note of filling device are fed into bar planting hole using filling device
Jiao Zui is protruded near the bottom hole in bar planting hole, and the gluing nozzle of filling device is extracted on marginal not glue side out, and anchoring adhesive is perfused to apart from bar planting hole
Behind 270 millimeters of aperture, stops injecting glue and be fully drawn out the gluing nozzle of filling device.
Step 5, bar planting immediately after the completion of the injecting glue of step 4, bar planting reinforcing bar is slowly inserted into bar planting hole, and edge is inserted on side
Certain orientation slowly rotates, and keeps anchoring adhesive and bar planting rebar surface and bar planting hole inner wall bonding closely knit;The insertion of bar planting reinforcing bar is planted
Guarantee not disturb for 24 hours after the bottom hole of muscle hole, under room temperature, bar planting is completed after 48 hours.
In the reinforced concrete structure deep pore reinforced construction method of the present embodiment, when drilling to 200 meters of depth, big drill bit
Continue deeper into and easily concrete inner core caused to be broken, therefore big drill bit is changed to small drill bit, effectively to avoid coagulation in hole
Native inner core is broken.The present invention is first bored concrete inner core with small drill bit broken so as to hydraulic pressure return slag, then is led to big drill bit pore-forming, is made
With the concrete inner core break occurred in big drill bit boring procedure, can be bored by the small drill bit then replaced broken so as to hydraulic pressure
Return slag makes deep pore reinforced smooth, efficient, high quality completion through the invention.
Claims (2)
1. reinforced concrete structure deep pore reinforced construction method comprising following steps:
Step 1, inbuilt reinforcement location in reinforced concrete structure is determined according to design drawing, further according to site operation deviation and
Bar planting hole parameter determines bar planting hole site, and bar planting hole parameter includes bar planting bore dia and bar planting hole depth, and bar planting hole is straight
Diameter is 25~40 millimeters, and bar planting hole depth is 600~850 millimeters, and bar planting hole site is to avoid reinforcing bar in reinforced concrete structure
To determine principle, go out bar planting hole drill hole location in reinforced concrete structure surface markers later;
Step 2, bar planting drilling is carried out;Bar planting hole drill hole location on reinforced concrete structure surface, is carried out using water drilling puncher
It drills, in boring procedure, water drilling puncher should keep vertical, slow and uniform drilling operation as far as possible, drill while using water
Brill puncher progress hydraulic pressure return slag will bore to mince in hole clears out hole;
Step 3, after the pore-forming of bar planting hole, the mud in bar planting hole is washed away completely with clear water, then cleaned bar planting hole with staple;
Step 4, after the bar planting hole of step 3 is dried, anchoring adhesive, the gluing nozzle of filling device are fed into bar planting hole using filling device
It protrudes near the bottom hole in bar planting hole, the gluing nozzle of filling device is extracted on marginal not glue side out, and anchoring adhesive is perfused to the aperture apart from bar planting hole
After 200~300 millimeters, stops injecting glue and be fully drawn out the gluing nozzle of filling device;
Step 5, bar planting immediately after the completion of the injecting glue of step 4, bar planting reinforcing bar is slowly inserted into bar planting hole, and it is certain that edge is inserted on side
Direction slowly rotates, and keeps anchoring adhesive and bar planting rebar surface and bar planting hole inner wall bonding closely knit;Bar planting reinforcing bar is inserted into bar planting hole
Guarantee not disturb for 24 hours after bottom hole, under room temperature, bar planting is completed after 48 hours;
It is characterized by: the bar planting drilling of step 2 has specifically included following steps;
Step 2.1, described big using the water drilling puncher of big drill bit in the bar planting hole drill hole location on reinforced concrete structure surface
The drilling diameter of drill bit is suitable with bar planting bore dia, first light to bore field planting muscle hole location, then simultaneously to reinforced concrete structure internal drilling
Hydraulic pressure return slag;Big drill bit water drilling puncher pierces in reinforced concrete structure 100~200 millimeters, makes to have in concrete structure
The bar planting hole of 100~200 millimeters deeps;
Step 2.2, the big drill bit of water drilling puncher is changed to small drill bit, the drilling diameter of the small drill bit is bar planting bore dia
1/2~2/3, continue along bar planting hole to reinforced concrete structure internal drilling and hydraulic pressure return slag;Small drill bit water drilling puncher pierces
50~100 millimeters in reinforced concrete structure, make that there is bar planting prebored hole in concrete structure;
Step 2.3, the small drill bit of water drilling puncher is changed to big drill bit, continues drilling and hydraulic pressure return slag along bar planting prebored hole,
Make aperture of the big drill bit water drilling puncher by the borehole enlargement of bar planting prebored hole to bar planting hole;
It is repeated in step 2.2 and step 2.3, until bar planting hole depth reaches the depth of pore forming of design.
2. reinforced concrete structure deep pore reinforced construction method according to claim 1, it is characterised in that: used in step 3
After staple cleans bar planting hole, bar planting hole is dried using heating rod.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710970757.7A CN108019051B (en) | 2017-10-18 | 2017-10-18 | Reinforced concrete structure deep pore reinforced construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710970757.7A CN108019051B (en) | 2017-10-18 | 2017-10-18 | Reinforced concrete structure deep pore reinforced construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108019051A CN108019051A (en) | 2018-05-11 |
CN108019051B true CN108019051B (en) | 2019-11-01 |
Family
ID=62079532
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710970757.7A Active CN108019051B (en) | 2017-10-18 | 2017-10-18 | Reinforced concrete structure deep pore reinforced construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108019051B (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108952200A (en) * | 2018-08-13 | 2018-12-07 | 浙江科技学院 | The construction method that building steel-bar-planting is reinforced under wet environment |
CN110130585A (en) * | 2019-05-21 | 2019-08-16 | 上海森信建设集团有限公司 | A kind of Large-size rebar free end docking facilities and its application method |
CN112627251A (en) * | 2020-12-30 | 2021-04-09 | 中国化学工程第十六建设有限公司 | Deep hole bar planting construction method for reinforced concrete structure |
CN113073854A (en) * | 2021-04-14 | 2021-07-06 | 上海市城市建设设计研究总院(集团)有限公司 | Horizontal bar planting structure and construction method |
CN113404084A (en) * | 2021-06-01 | 2021-09-17 | 杭州固特建筑加固技术工程有限公司 | Bar planting process in humid and open water environment |
CN114215381B (en) * | 2021-12-30 | 2023-04-11 | 中铁大桥局武汉桥梁特种技术有限公司 | Concrete structure ultra-deep post-anchoring construction method |
CN115522484B (en) * | 2022-09-30 | 2023-08-15 | 杭州鑫固建筑特种技术有限公司 | Secondary reinforcement bar planting improvement method |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103556711A (en) * | 2013-10-15 | 2014-02-05 | 南京工业大学 | Fabricated wood structure embedded steel bar joint and construction method thereof |
CN104594640A (en) * | 2014-12-01 | 2015-05-06 | 中建七局第四建筑有限公司 | High-rise building secondary structure foam concrete cast-in-situ bar planting technology and construction method thereof |
CN204455872U (en) * | 2014-12-02 | 2015-07-08 | 中航天建设工程有限公司 | Pile foundation type bar planting constructs |
CN106121264A (en) * | 2016-06-23 | 2016-11-16 | 青岛海川建设集团有限公司 | Postinstalled chemically rebar construction technology |
-
2017
- 2017-10-18 CN CN201710970757.7A patent/CN108019051B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN108019051A (en) | 2018-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108019051B (en) | Reinforced concrete structure deep pore reinforced construction method | |
CN105890998B (en) | Have crannied rock fracture simulation sample and preparation method, the simulation test device and method | |
BR112013018620A2 (en) | CIRCULATION SUB OPERATED BY TELEMETRY | |
CN103867119B (en) | Coal seam reservoirs completion remodeling method | |
NO320304B1 (en) | Tools and methods for injecting treatment fluids into a subsurface formation | |
MX2012001983A (en) | Method of drilling a subterranean borehole. | |
RU2558058C1 (en) | Interval hydraulic fracturing of carbonate formation in horizontal wellbore with bottom water | |
EP1853789A4 (en) | A method of geothermal loop installation | |
ATE386240T1 (en) | METHOD FOR PRODUCING A GETHER HEAT PROBE | |
CN105239957A (en) | Expanded tube leaking stoppage device capable of being assembled and released | |
CN107747312A (en) | A kind of method of sand and gravel stratum well cementing construction | |
CN107762451A (en) | Well completion method is transformed in a kind of coal bed gas horizontal well payzone underbalance reaming | |
US8490695B2 (en) | Method for drilling and fracture treating multiple wellbores | |
CN110529047A (en) | A kind of self-advancing type pipe canopy drilling tool excavated for tunnel soft rock | |
CN107387056A (en) | A kind of casing programme of the horizontal docking geothermal well of heat exchange type | |
RU68052U1 (en) | Borehole Hydraulic Vibrator | |
CN106437522A (en) | Deep-level and high-ground-stress coal uncovering and drilling construction device and method | |
CN107939444A (en) | A kind of casing programme and installation and application that chamber is made for salt hole air reserved storeroom | |
US20170247990A1 (en) | Method for drilling and fracture treating multiple wellbores | |
CN109322621B (en) | Broken layer pipe fixing and grouting method | |
CN205713982U (en) | A kind of pile foundation construction drilling equipment being applicable to karst area | |
JP4916758B2 (en) | Ground improvement method by high-pressure jet agitation | |
KR101442822B1 (en) | Apparatus for inserting steel pipe and simultaneous horizontal high pressure jet-grouting in a tunnel supporting, and Method for inserting steel pipe and high pressure jet grouting with it | |
CN206246061U (en) | Deep level, high-ground stress exposed coal drilling construction device | |
KR100842924B1 (en) | Grouting apparatus and grouting method using the same |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |