CN108005083B - Anchor cable processing method within the scope of a kind of foundation pit enclosure structure - Google Patents

Anchor cable processing method within the scope of a kind of foundation pit enclosure structure Download PDF

Info

Publication number
CN108005083B
CN108005083B CN201711136658.5A CN201711136658A CN108005083B CN 108005083 B CN108005083 B CN 108005083B CN 201711136658 A CN201711136658 A CN 201711136658A CN 108005083 B CN108005083 B CN 108005083B
Authority
CN
China
Prior art keywords
rope saw
hydraulic
anchor cable
grooving machine
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711136658.5A
Other languages
Chinese (zh)
Other versions
CN108005083A (en
Inventor
张士强
杨公正
王起飞
贺望宇
陈桐民
底龙飞
李俊洋
阮树林
刘锐
田文成
程现伟
王西林
王波
张南
苗欲田
周海松
程鑫
唐文周
吴琼
刘璞旭
舒明江
倪健
付永阁
李壮理
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Guanglian Environmental & Geotechnical Engineering Co Ltd
China Railway 16th Bureau Group Co Ltd
Beijing Rail Transit Engineering Construction Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
Shanghai Guanglian Environmental & Geotechnical Engineering Co Ltd
China Railway 16th Bureau Group Co Ltd
Beijing Rail Transit Engineering Construction Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Guanglian Environmental & Geotechnical Engineering Co Ltd, China Railway 16th Bureau Group Co Ltd, Beijing Rail Transit Engineering Construction Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical Shanghai Guanglian Environmental & Geotechnical Engineering Co Ltd
Priority to CN201711136658.5A priority Critical patent/CN108005083B/en
Publication of CN108005083A publication Critical patent/CN108005083A/en
Application granted granted Critical
Publication of CN108005083B publication Critical patent/CN108005083B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses anchor cable processing methods within the scope of a kind of foundation pit enclosure structure, belong to anchor cable processing technology field.Anchor cable processing method disclosed by the invention removes the arrangement and method for construction of anchor cable using hydraulic grooving machine grab bucket plus sawing of restricting, before encountering anchor cable, using hydraulic grooving machine grooving operation, after encountering anchor cable, rope saw frame is detachably mounted in hydraulic grooving machine grab bucket by dismounting facility A, hydraulic grooving machine grab bucket and rope saw frame, rope saw, hydraulic grab handling system is collectively formed in dismounting facility A, then hydraulic grooving machine fluid power system is connect with rope saw drive system, rope saw cut anchor cable is driven using hydraulic grooving machine fluid power system, after cutting off anchor cable, hydraulic grooving machine fluid power system and rope saw drive system are disconnected, remove rope saw frame, hydraulic grooving machine continues grooving operation.Anchor cable processing method disclosed by the invention cuts anchor cable while grooving to reach processing intent, and safety is good, short time limit, strong operability.

Description

Anchor cable processing method within the scope of a kind of foundation pit enclosure structure
Technical field
The invention belongs to anchor cable processing technology fields, and in particular to anchor cable processing side within the scope of a kind of foundation pit enclosure structure Method.
Background technique
In the process of China's urban construction, with being increasing for deep-foundation pit engineering, prestress anchorage cable is once used as civil engineering Foundation pit enclosure structure construction a kind of economical and effective means and be widely applied.Compared with other support technologies, anchor cable has valence Lattice are cheap, construction is simple is mature, speed is fast, it is safe and reliable, be not take up the advantages that main body construction work.Meanwhile facing as one kind When property supporting measure, anchor cable protective function failure after can not recycle, permanently buried together with the structures built in underground without Method is taken out, and forms underground garbage, causes underground environmental pollution, pile foundation construction, excavation of foundation pit to adjacent plot, the municipal administration of surrounding Construction, subway work, the long-term plan in city and sustainable development cause to seriously affect.Especially as the gradually hair of urban construction The development and utilization of exhibition and the underground space, originally foundation pit cable bolting become subsequent underground space construction especially foundation pit enclosure structure The obstacle of construction, must handle the anchor cable constructed in advance, just can guarantee the smooth implementation of foundation pit enclosure structure.
For anchor cable encountered in base pit engineering handle problem, generallyd use during construction activity at present as Lower method is handled: 1, utilizing cutting machine imderwater cutting anchor cable;2, anchor cable is thrust using impact drill impulse force.
There are the following problems for above-mentioned anchor cable processing method: 1, abolishing existing building structure, project amount is larger, and it is difficult to coordinate;2, Original geologic structure is destroyed, large area is caused to collapse, backfill influences building enclosure construction quality;3, impact drill cannot be guaranteed hole Verticality, and efficiency is lower.So there are still the constructions of significant unsatisfied urban construction to need, it would be highly desirable to exploitation more preferably anchor Rope processing method.
Summary of the invention
In order to solve the above technical problems, the present invention provides anchor cable processing method within the scope of a kind of foundation pit enclosure structure.
The present invention solves technical solution used by above-mentioned technical problem:
Anchor cable processing method within the scope of a kind of foundation pit enclosure structure, sawing of being grabbed bucket plus restricted using hydraulic grooving machine is except anchor cable Arrangement and method for construction, can by dismounting facility A by rope saw frame after encountering anchor cable using hydraulic grooving machine grooving operation before encountering anchor cable It releasably installs to hydraulic grooving machine grab bucket, hydraulic grooving machine is grabbed bucket, and (7) are sawed with rope saw frame, rope, dismounting facility A is collectively formed Then hydraulic grooving machine fluid power system connect with rope saw drive system, utilizes hydraulic grooving by hydraulic grab handling system Machine fluid power system driving rope saw cut anchor cable, after cutting off anchor cable, by hydraulic grooving machine fluid power system and rope saw driving System disconnects, and removes rope saw frame, and hydraulic grooving machine continues grooving operation;
The rope saw is installed by saw frame of restricting to hydraulic grooving machine grab bucket;The rope saw frame is fixed on for the saw that will restrict The upper structure of hydraulic grooving machine grab bucket.
Before encountering anchor cable, using the normal grooving operation of hydraulic grooving machine, after encountering anchor cable, for during reducing anchor cable processing Rope saw is quick mounting in chute forming machine grab bucket in the form of saw frame of restricting, utilizes hydraulic grooving machine hydraulic-driven by the collapsing of cell wall System drive rope saw cut anchor cable, to realize the purpose to anchor cable fly-cutting;After cutting off anchor cable, rope saw frame is removed, it is hydraulic Chute forming machine continues grooving operation, avoids chute forming machine shift position and causes to relocate, accelerates construction speed, simultaneously Also the safety and quality of construction of diaphragm wall are effectively guaranteed.
Further, rope saw includes that rope saw chain item (3), rope saw driving wheel (4), rope saw directive wheel (5), rope saw are hydraulic Drive motor (6);The rope saw frame and rope saw driving wheel (4) and the rope saw nonrotational position of directive wheel (5), the rope saw frame and Rope saw hydraulic drive motor (6) is removably secured by dismounting facility B.
Further, the dismounting facility A is bolt and nut connector, and the rope saw frame is rope saw Steel plate frame (1);It is restricting Bolt hole, rope saw Steel plate frame (1) and hydraulic grooving machine grab bucket are respectively set on saw Steel plate frame (1) and hydraulic grooving machine grab bucket (7) (7) it is bolted by bolt hole.
Further, it is described be set to rope saw Steel plate frame (1) on bolt hole be slotted eye, it is described be set to it is hydraulic The bolt hole that chute forming machine is grabbed bucket on (7) is round hole.
Further, the dismounting facility B is bolt and nut connector, the rope saw frame and rope saw driving wheel (4) and restricts It saws and is provided on nonrotational position, the rope saw frame and rope saw hydraulic drive motor (6) of directive wheel (5) for the dismounting facility The structure of B work.
Further, the rope saw is that hydraulic diamond rope is sawed.
Further, carry out grooving is grabbed in the hydraulic grooving machine grooving operation point three, after verifying first of anchor cable position, Framing is carried out to diaphram wall again according to design requirement, chute forming machine is positioned according to framing line position.
Further, it is that chute forming machine grab bucket cannot be closed during taking soil that above-mentioned hydraulic grooving machine, which encounters the mark of anchor cable, Can tentatively verify has anchor cable at this.
Further, after tentatively verifying anchor cable position, anchor cable specific location is further verified using magnet, it then will rope Saw frame is detachably mounted in hydraulic grooving machine grab bucket by dismounting facility, and connection chute forming machine grab bucket hydraulic tube and rope saw are hydraulic Oil pipe.
Further, above-mentioned hydraulic grooving machine is equipped with random monitoring deviation correcting device.
Optionally, compared with the prior art, the invention has the following beneficial effects:
(1) anchor cable processing method disclosed by the invention improves the safety in anchor cable treatment process: before encountering anchor cable, Using the normal grooving operation of hydraulic grooving machine, after encountering anchor cable, rope saw is quick mounting to chute forming machine in the form of saw frame of restricting and is grabbed On bucket, rope saw cut anchor cable is driven using hydraulic grooving machine fluid power system, the purpose to anchor cable fly-cutting is realized, subtracts The collapsing of cell wall during small anchor cable processing.
(2) anchor cable processing method disclosed by the invention shortens the construction period of anchor cable processing: after cutting anchor cable, removing rope Saw frame, hydraulic grooving machine continue grooving operation, avoid chute forming machine shift position and cause to relocate, accelerate construction Progress, while being also effectively guaranteed the safety and quality of construction of diaphragm wall.
(3) anchor cable processing method disclosed by the invention saves cost: totality arrangement and method for construction economy disclosed by the invention.
(4) anchor cable processing method strong operability disclosed by the invention: rope saw frame structure disclosed by the invention, so that Rope saw is convenient to assemble and disassemble, and environmental suitability increases;Rope saw frame can be removed after cutting off anchor cable, it is convenient and efficient.
(5) anchor cable processing method disclosed by the invention cuts anchor cable while grooving to achieve the purpose that processing: utilizing Chute forming machine gravity itself and probe strop saw position, and grooving is combined with processing anchor cable.
Detailed description of the invention
Fig. 1 is the hydraulic grab front view after hydraulic grab handling system of the invention-installing rope saw;
Fig. 2 is the hydraulic grab side view after hydraulic grab handling system of the invention-installing rope saw;
Fig. 3 is chute forming machine grab bucket schematic diagram of the invention;
Fig. 4 is that rope of the invention saws system schematic-front view;
Fig. 5 is that rope of the invention saws system schematic-side view;
Fig. 6 is rope saw chain bar schematic diagram of the invention;
Fig. 7 is the connection sheet schematic diagram with cavernous structure.
Wherein:
1, rope saw Steel plate frame;2, oval bolt hole in rope saw Steel plate frame;3, rope saw chain item;4, rope saw driving wheel;5, it restricts Saw directive wheel;6, rope saw hydraulic drive motor;7, hydraulic grooving machine is grabbed bucket;8, rope saw position.
Specific embodiment
The present invention will be further described combined with specific embodiments below.It should be understood that within the scope of the present invention, it is of the invention It can be combined with each other between above-mentioned each technical characteristic and specifically described in below (e.g. embodiment) each technical characteristic, thus Constitute new or preferred technical solution.Due to space limitations, I will not repeat them here.It is all to be realized based on above content of the present invention Technology all belong to the scope of the present invention.
Lead wall
A kind of working measure mode that wall is unit in charge of construction is led, first to be constructed before continuous wall trench underground and lead wall, leading wall is Guarantee that diaphram wall position accurately leads wall and often bear steel reinforcement cage, pour concrete use with the key of grooving quality in construction period The static and dynamic loadings such as conduit, drilling machine effect, thus conscientiously must design and construct, just can be carried out the formal of diaphram wall Construction.
Diaphram wall, which should all be arranged, leads wall, lead wall form have it is prefabricated and two kinds cast-in-place, it is cast-in-place lead wall shape have " L " type or Inverted "L" shape can be selected according to different soil properties.When soil layer property is preferable, inverted "L" shape can be selected or even pre-manufactured steel leads wall, use " L " type leads wall, and what Ying Jiaqiang led wall behind is backfilling and compacted work.Ground good location in surface layer is led using simple form reinforced concrete Wall;Wall is led using cast-in-place L shape reinforced concrete in the area of topsoil weakness.
Construction of guide wall is to ensure that the axial location of subterranean wall and grooving quality have critical process.In order to keep ground surface soil body Stablize, attaches interim wood support and stull between wall every 1~3 meter leading;The construction precision for leading wall is directly related to underground company The precision of continuous wall, thus construct lead wall when, it has to be noted that lead the headroom size, vertical and horizontal precision and plane position of side within the walls It sets.The horizontal reinforcement for leading wall must connect, and make to lead wall as an entirety, prevent due to intensity is insufficient or construction is not good at Generation accident.For the construction precision for guaranteeing subterranean wall, be convenient for grooving machine operation, lead side clearway within the walls should compared with subterranean wall thickness slightly It is larger (5cm bigger than design value), wall top mouth is led than ground and is higher by 5cm, and the depth for leading wall is 1.5m.Lead the construction error mark of wall Standard is: centerline error is ± 10mm;Absolute altitude error is ± 10mm in the length range of top surface.
Wall effect is led in diaphram wall: 1, providing guiding to chute forming machine grooving;2, it stores mud and prevents notch from collapsing; 3, the benchmark of level and vertical measurement when as construction;4, it is placed for steel reinforcement cage, tremie disposes, chute forming machine provides mark It is fixed.
Rope saw
Rope saw is a kind of saw that a kind of pair of crisp and hard material designed using the principle that a rope can cut through a log is cut, and is needle To mine, quarry stone, arc panel, big flag material, thick concrete, irregular concrete reinforcement, work is cut and disassembled in bridge road etc. Tool.Rope saw is easy for installation, and application method is flexible, crosscutting to cut, and erects cutting.Rope saw generally comprises rope saw driving, flywheel, guiding Wheel, rope saw chain item, wherein rope saw chain item is made by diamond.
Rope saw of the present invention includes at least the driving of rope saw, flywheel, directive wheel, rope saw chain item.
A kind of specific saw of restricting of the present invention saws driving wheel including rope saw chain item, rope, rope saws directive wheel, rope saw is hydraulic Drive motor.
In the present invention, " rope saw system " and " rope saw " in case of no particular description, can be equal and use.
Rope saw frame
" rope saw frame " of the present invention is the structure being fixed in hydraulic grooving machine grab bucket for the saw that will restrict.
" rope saw frame " of the present invention is it is optionally possible to be a kind of frame structure, for example rope saws Steel plate frame, is also possible to Plate structure, such as rectangle rope saw steel plate or trapezoidal rope saw steel plate, are also possible to its in addition to rope saw Steel plate frame, rope saw steel plate He is able to achieve the structure type of the purpose of fixed rope saw.
Shape and the chute forming machine grab bucket of " rope saw frame " of the present invention are adapted, can also be with it is optionally possible to be rectangle It is polygon, is also possible to other irregular shapes.
The shape of " rope saw frame " of the present invention can be with size is able to satisfy rope saw frame and hydraulic grooving machine grab bucket is removable The arbitrary shape and size installed with unloading, and its mechanical strength should be able to realize that rope saw frame is grabbed bucket with rope saw, hydraulic grooving machine, torn open The function of the cutting anchor cable of the hydraulic grab handling system of A composition is applied in installing.
Other modes other than rope saw frame of the present invention can be bolted with hydraulic grooving machine grab bucket are detachable Ground assembling, optionally, is also possible to other thread connecting modes, is also possible to anchor bolts.Threaded connection refers to will with screw thread Two plates link together, including bolt and nut connection, bolt welding helical connect, screw snaps connection and tapping screw connects It connects.
In a specific embodiment, rope saw frame is rope saw Steel plate frame, and rope is sawed in Steel plate frame and hydraulic grooving machine grab bucket Bolt hole is respectively set, the two is bolted by bolt hole.
In the present invention, rope saw is quick mounting in chute forming machine grab bucket by saw frame of restricting.
In the present invention, the rope saw and rope saw frame are detachably connected by dismounting facility.
Dismount facility
" dismounting facility " of the present invention is the device that can reach fast quick-detach purpose.
A kind of form realized of " dismounting facility " of the present invention is bolt and nut connector.It is optionally possible to be Heavy hex bolts, screw connector and/or lifting bolt, screw connector and/or T hook bolt, screw connector.
Preferably, " dismounting facility " of the present invention is heavy hex bolts, screw connector.
It is corresponding, the knot for " dismounting facility A " work of the present invention has been reserved in restrict saw frame and hydraulic grooving machine grab bucket Structure.Optionally, it can be cavernous structure for the structure of " dismounting facility A " work of the present invention.Specific work structuring can be with It is: bolt hole is respectively set in rope saw frame and hydraulic grooving machine grab bucket, and/or by welding by the company with cavernous structure Contact pin (as shown in Figure 7) be fixed on rope saw frame and hydraulic grooving machine grab bucket on, rope saw Steel plate frame and hydraulic grooving machine grab bucket to It is bolted.
It is corresponding, rope saw frame and rope saw driving wheel, the nonrotational position of rope saw directive wheel and rope saw hydraulic drive motor On reserved structure for " dismounting facility B " of the present invention work.Optionally, for " dismounting facility B " work of the present invention Structure can be cavernous structure.Specific work structuring may is that the nonrotational position of rope saw frame and rope saw driving wheel, rope are sawed Setting bolt hole (explanation is respectively corresponded on the nonrotational position of frame and rope saw directive wheel, rope saw frame and rope saw hydraulic drive motor Book attached drawing does not provide), rope saw frame and rope saw driving wheel nonrotational position, rope saw frame and rope saw directive wheel nonrotational position, Rope saw frame and rope saw hydraulic drive motor are bolted by bolt hole.Bolt hole can be directly in rope saw frame, hydraulic grooving machine Aperture on grab bucket, the nonrotational position of rope saw driving wheel, the nonrotational position of rope saw directive wheel and rope saw hydraulic drive motor, And/or the connection sheet (as shown in Figure 7) with cavernous structure is fixed on restrict saw frame, hydraulic grooving machine by welding and is grabbed In the structures such as bucket, the nonrotational position of rope saw driving wheel, the nonrotational position of rope saw directive wheel and rope saw hydraulic drive motor, with Realization is bolted.
Hydraulic grab handling system
" hydraulic grab handling system " of the present invention is mainly grabbed by the rope saw frame and hydraulic grooving machine with rope saw connection Bucket composition, wherein rope saw frame and hydraulic grooving machine grab bucket are removably installed combination by dismounting facility.
After the hydraulic grooving machine grab bucket installing rope saw of " hydraulic grab handling system " of the present invention, it is connected to the dynamic of the two Force system is, it can be achieved that the function of hydraulic grooving machine fluid power system driving rope saw system work and then cutting anchor cable.
Chute forming machine
Chute forming machine of the present invention is also known as groover.It is filled when construction diaphram wall by the machinery of the downward milling slot of earth's surface It is standby.Late 1950s start to apply in construction project.When operation, according to formation condition and engineering design in soil layer or rock Body is excavated into the flute profile of one fixed width and depth sky, is placed steel reinforcement cage and concrete perfusion and is formed diaphram wall body.Grooving Machine has multi-head spiral to bore, rushes grab bucket, impact drill, Multi-drill bit and wheel milling formula, disk mill formula, pincers slot type and slicing formula etc..At wall thickness Degree can be 400~1500 millimeters, and being once constructed into wall length can be 2500~2700 millimeters.
Chute forming machine random monitoring deviation correcting device
In order to guarantee the verticality of grooving, chute forming machine is equipped with random monitoring deviation correcting device.
Optionally, in the actual construction process, the present invention can also realize that anchor cable position is accurately positioned, and concrete operations are as follows: Field technician's whole process is stuck to post during grooving, is grabbed according to hydraulic during the observation grooving of the basic data moment of collection Parameters in the drift condition and construction of bucket, scene are accurately located out the position of anchor cable.
The present invention improve anchor cable treatment process in safety be also embodied in: orient the strict control grooving of anchor cable position into Ruler, using rope saw cut anchor cable, avoid in the prior art because to anchor cable pull handle caused by landslip of the sides of the trench.
The present invention is further illustrated below in conjunction with specific embodiment.
1 hydraulic grab handling system of embodiment
As shown in Figure of description 1~6, hydraulic grab handling system includes: rope saw Steel plate frame 1, hydraulic grooving machine grab bucket 7, rope saw.Rope saw includes: rope saw chain item 3, rope saw driving wheel 4, rope saw directive wheel 5, rope saw hydraulic drive motor 6.
Bolt hole is directly set in rope saw Steel plate frame 1 and hydraulic grooving machine grab bucket 7 respectively, is set to rope saw Steel plate frame 1 On bolt hole be slotted eye, be set to hydraulic grooving machine grab bucket 7 on bolt hole be round hole.Rope saw Steel plate frame 1 and liquid Scouring machine grab bucket 7 is pressed by bolt hole, is connected with heavy hex bolts, nut.Rope saw Steel plate frame 1 and hydraulic grooving machine grab bucket 7 It is bolted to realize that fast assembling-disassembling is fixed.
The installing rope saw at rope saw position 8 of hydraulic grooving machine grab bucket 7.
Rope saws the connection type of each building block and rope saw frame: the nonrotational portion of rope saw Steel plate frame 1 and rope saw driving wheel 4 On position, the nonrotational position of rope saw Steel plate frame 1 and rope saw directive wheel 5, rope saw Steel plate frame 1 and rope saw hydraulic drive motor 6 respectively It is corresponding that bolt hole is directly set, then with heavy hex bolts, nut connection.
2 hydraulic grab handling system of embodiment
As shown in Figure of description 1~6, hydraulic grab handling system includes: rope saw Steel plate frame 1, hydraulic grooving machine grab bucket 7, rope saw.Rope saw includes: rope saw chain item 3, rope saw driving wheel 4, rope saw directive wheel 5, rope saw hydraulic drive motor 6.
Bolt hole is directly set in rope saw Steel plate frame 1 and hydraulic grooving machine grab bucket 7 respectively, is set to rope saw Steel plate frame 1 On bolt hole be slotted eye, be set to hydraulic grooving machine grab bucket 7 on bolt hole be round hole.Rope saw Steel plate frame 1 and liquid Scouring machine grab bucket 7 is pressed by bolt hole, is connected with lifting bolt, nut.
The installing rope saw at rope saw position 8 of hydraulic grooving machine grab bucket 7.
Rope saws the connection type of each building block and rope saw frame: the nonrotational portion of rope saw Steel plate frame 1 and rope saw driving wheel 4 On position, the nonrotational position of rope saw Steel plate frame 1 and rope saw directive wheel 5, rope saw Steel plate frame 1 and rope saw hydraulic drive motor 6 respectively Connection sheet with holes is welded, then with heavy hex bolts, nut connection.
3 hydraulic grab handling system of embodiment
As shown in Figure of description 1~6, hydraulic grab handling system includes: rope saw Steel plate frame 1, hydraulic grooving machine grab bucket 7, rope saw.Rope saw includes: rope saw chain item 3, rope saw driving wheel 4, rope saw directive wheel 5, rope saw hydraulic drive motor 6, rope saw steel plate Frame 1 is bolted achievable fast assembling-disassembling with hydraulic grooving machine grab bucket 7 and fixes.Hydraulic grooving machine grab bucket 7 saws position 8 in rope Locate installing rope saw.
Connection sheet with holes is welded in rope saw Steel plate frame 1, bolt hole is directly set in hydraulic grooving machine grab bucket 7.Connection The hole of on piece is slotted eye, and the bolt hole being directly arranged in hydraulic grooving machine grab bucket 7 is round hole.Rope saw Steel plate frame 1 and liquid Scouring machine grab bucket 7 is pressed by connection sheet with holes and bolt hole, is connected with T hook bolt, nut.
The connection type of saw system of restricting and saw frame of restricting: the nonrotational position of rope saw Steel plate frame 1 and rope saw driving wheel 4, rope are sawed The position that the nonrotational position of Steel plate frame 1 and rope saw directive wheel 5, rope saw Steel plate frame 1 and rope saw hydraulic drive motor 6 are correspondingly connected with Bolt hole is directly set.The nonrotational position of rope saw driving wheel 4, the nonrotational position of rope saw directive wheel 5, rope saw hydraulic-driven horse Connection sheet with holes is respectively welded on up to 6, is then connected with T hook bolt, nut.
The construction process and concrete operation step that anchor cable is handled within the scope of 4 foundation pit enclosure structure of embodiment
Construction process: construction of guide wall --- chute forming machine positioning --- grooving operation --- encountering anchor cable --- grab bucket installing rope Saw, hydraulic tube connection --- excision anchor cable --- remove rope saw, hydraulic tube disconnects.
Specific steps:
1) it positions
Construction of guide wall is according to geological condition, using different form.
2) chute forming machine positions
Grooving process point three grabs carry out grooving, after verifying first of anchor cable position, according to design requirement again to underground Diaphragm wall carries out framing, and chute forming machine is positioned according to framing line position, it is ensured that grooving verticality and position are accurate.
3) grooving operation
It is 2.8m that native width is grabbed in chute forming machine grab bucket (as shown in Figure 3) every time, and in order to guarantee the verticality of grooving, chute forming machine is set There is random monitoring deviation correcting device.
4) anchor cable is encountered
Since anchor cable intensity is higher, chute forming machine is difficult to directly grab disconnected, pulls the generation that will lead to the hole that collapses by force, chute forming machine is grabbed Bucket, which cannot be closed verify during taking soil, has anchor cable at this.
5) grab bucket installing rope saw, hydraulic tube connection
After tentatively verifying anchor cable position, anchor cable specific location is further verified using magnet, by saw frame Fast Installation of restricting Onto chute forming machine grab bucket, the hydraulic oil pipe and rope saw driving hydraulic oil pipe reserved in connection chute forming machine grab bucket.
6) anchor cable is cut off
Using rope sawing except the feature that face is stable, anchor cable anti-shear ability is weak, rope sawing is driven using fluid power system Anchor cable is cut, and applies the pressure to anchor cable using chute forming machine grab bucket self weight.
7) rope saw is removed, hydraulic tube disconnects
After cutting off anchor cable, chute forming machine grab bucket is lifted, rapid removal rope saw frame, disconnects chute forming machine grab bucket hydraulic tube and rope is sawed Hydraulic oil pipe, chute forming machine grab bucket continue to take native construction.
The present invention carries out that native machine anchor cable is taken to position using diaphram wall, chute forming machine, sets on chute forming machine grab bucket, rope saw frame Dismounting facility is set, encounters anchor cable during grooving, lifts chute forming machine grab bucket immediately, is installed in advance using dismounting facility Fast Installation The rope saw frame (being detailed in Fig. 1, Fig. 2, Fig. 3) for thering is rope to saw.
As preferably technical solution, the threaded hole in hydraulic grooving machine grab bucket uses round hole, corresponding rope saw Steel plate frame On threaded hole use slotted eye, facilitate adjusting rope saw height, more adapt to the angle of anchor cable, reach cell wall two sides and synchronize and cut The purpose cut.
On chute forming machine after installing rope saw, grooving machine hydraulic system is connect with rope saw drive system (such as connection grooving The hydraulic oil pipe reserved in machine grab bucket and rope saw driving hydraulic oil pipe), it can fast driving rope saw progress cutting operation.
By chute forming machine grooving operation, anchor cable position can be quickly positioned.After cutting off anchor cable, by rope saw frame disassembly, chute forming machine It can proceed with grooving operation, avoid chute forming machine shift position and cause to relocate, accelerate construction progress.In grooving process Middle field technician's whole process is stuck to post, and the offset feelings of hydraulic grab during grooving are observed according to the basic data moment of collection The position of anchor cable is accurately oriented at parameters in condition and construction, scene.Orient the strict control grooving of anchor cable position into Ruler avoids pullling anchor cable and leading to landslip of the sides of the trench using rope saw cut anchor cable.
Anchor cable processing method disclosed by the invention is for the specific location in anchor cable in foundation pit wall, in combination in wall construction Equipment hydraulic grab install additional shear rope saw, using grab bucket be accurately positioned and hydraulic grooving machine hydraulic system driving rope saw cut Disconnected anchor cable cuts anchor cable while grooving to achieve the purpose that processing to reach processing intent, safety is good, short time limit, Strong operability.
The above content is only presently preferred embodiments of the present invention, for those of ordinary skill in the art, according to the present invention Thinking, place can be changed in specific embodiment mode and its application range, the content of the present specification should not be construed as Limitation of the present invention.

Claims (7)

1. anchor cable processing method within the scope of a kind of foundation pit enclosure structure, which is characterized in that saw of being grabbed bucket plus restricted using hydraulic grooving machine Before encountering anchor cable, using hydraulic grooving machine grooving operation, after encountering anchor cable, rope saw frame is passed through for the arrangement and method for construction for cutting off anchor cable Dismounting facility A is detachably mounted in hydraulic grooving machine grab bucket, and hydraulic grooving machine grab bucket (7) is set with rope saw frame, rope saw, dismounting It applies A and hydraulic grab handling system is collectively formed, then connect hydraulic grooving machine fluid power system with rope saw drive system, benefit Rope saw cut anchor cable is driven with hydraulic grooving machine fluid power system, after cutting off anchor cable, by hydraulic grooving machine fluid power system It is disconnected with rope saw drive system, removes rope saw frame, hydraulic grooving machine continues grooving operation;
The dismounting facility A is bolt and nut connector, and the rope saw frame is rope saw Steel plate frame (1);Rope saw Steel plate frame (1) and Bolt hole is respectively set in hydraulic grooving machine grab bucket (7), rope saw Steel plate frame (1) and hydraulic grooving machine grab bucket (7) pass through bolt hole It is bolted;
The rope saw is installed by saw frame of restricting to hydraulic grooving machine grab bucket;The rope saw frame be for will restrict saw be fixed on it is hydraulic The upper structure of chute forming machine grab bucket;Rope saw includes that rope saw chain item (3), rope saw driving wheel (4), rope saw directive wheel (5), rope saw are hydraulic Drive motor (6);
The mark that the hydraulic grooving machine encounters anchor cable is that chute forming machine grab bucket cannot be closed during taking soil and can tentatively verify There is anchor cable at this.
2. anchor cable processing method within the scope of foundation pit enclosure structure according to claim 1, which is characterized in that tentatively verify anchor Rope position postpones, and anchor cable specific location is further verified using magnet, is then removably installed rope saw frame by dismounting facility To hydraulic grooving machine grab bucket, connection chute forming machine grab bucket hydraulic tube and rope saw hydraulic oil pipe.
3. anchor cable processing method within the scope of foundation pit enclosure structure according to claim 1, which is characterized in that the rope saw frame It is logical with the nonrotational position of rope saw driving wheel (4) and rope saw directive wheel (5), the rope saw frame and rope saw hydraulic drive motor (6) It crosses dismounting facility B to be removably secured, the dismounting facility B is bolt and nut connector, the rope saw frame and rope saw driving wheel (4) and on the nonrotational position of rope saw directive wheel (5), the rope saw frame and rope saw hydraulic drive motor (6) it is provided with described in confession Dismount the structure of facility B work.
4. anchor cable processing method within the scope of foundation pit enclosure structure according to claim 1, which is characterized in that described to be set to Bolt hole on rope saw Steel plate frame (1) is slotted eye, and the bolt hole being set in hydraulic grooving machine grab bucket (7) is circle Hole.
5. anchor cable processing method within the scope of foundation pit enclosure structure according to claim 1, which is characterized in that the rope, which is sawed, is Hydraulic diamond rope saw.
6. anchor cable processing method within the scope of foundation pit enclosure structure described in any one, feature exist according to claim 1~5 In carry out grooving is grabbed in the hydraulic grooving machine grooving operation point three, after verifying first of anchor cable position, according to design requirement weight Framing newly is carried out to diaphram wall, chute forming machine is positioned according to framing line position.
7. anchor cable processing method within the scope of foundation pit enclosure structure described in any one, feature exist according to claim 1~5 In the hydraulic grooving machine is equipped with random monitoring deviation correcting device.
CN201711136658.5A 2017-11-16 2017-11-16 Anchor cable processing method within the scope of a kind of foundation pit enclosure structure Active CN108005083B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711136658.5A CN108005083B (en) 2017-11-16 2017-11-16 Anchor cable processing method within the scope of a kind of foundation pit enclosure structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711136658.5A CN108005083B (en) 2017-11-16 2017-11-16 Anchor cable processing method within the scope of a kind of foundation pit enclosure structure

Publications (2)

Publication Number Publication Date
CN108005083A CN108005083A (en) 2018-05-08
CN108005083B true CN108005083B (en) 2019-11-19

Family

ID=62052452

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711136658.5A Active CN108005083B (en) 2017-11-16 2017-11-16 Anchor cable processing method within the scope of a kind of foundation pit enclosure structure

Country Status (1)

Country Link
CN (1) CN108005083B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110630196B (en) * 2019-10-12 2022-12-06 中国建筑第四工程局有限公司 Anchor cable sleeving and taking machine for construction of tunnel crossing anchor cable by shield method
CN115045355B (en) * 2022-05-30 2023-06-06 中交二公局铁路建设有限公司 Grab bucket assembly device of grooving machine for grabbing and breaking anchor cable and application method of grab bucket assembly device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02171422A (en) * 1988-12-26 1990-07-03 Mitsui Constr Co Ltd Underground continuous wall construction process
CN201411728Y (en) * 2009-05-08 2010-02-24 山东交通学院 Gripping apparatus of mechanical digging machine
CN201738362U (en) * 2010-08-03 2011-02-09 中天建设集团有限公司 Hydraulic grab bucket of shearable underground anchor rod slotting machine
CN102086653A (en) * 2010-12-30 2011-06-08 北京市三一重机有限公司 Continuous wall grab
CN102974721A (en) * 2012-10-24 2013-03-20 北京发研工程技术有限公司 Underground anchor cable cutting construction method and cutting device thereof
CN104763438A (en) * 2015-04-23 2015-07-08 张清林 Rope sawing type heading machine
CN204738332U (en) * 2015-03-17 2015-11-04 中铁十六局集团有限公司 Hydraulic pressure grooving machine
CN106088099A (en) * 2016-07-15 2016-11-09 南昌轨道交通集团有限公司 A kind of subway foundation pit anchor cable processing method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02171422A (en) * 1988-12-26 1990-07-03 Mitsui Constr Co Ltd Underground continuous wall construction process
CN201411728Y (en) * 2009-05-08 2010-02-24 山东交通学院 Gripping apparatus of mechanical digging machine
CN201738362U (en) * 2010-08-03 2011-02-09 中天建设集团有限公司 Hydraulic grab bucket of shearable underground anchor rod slotting machine
CN102086653A (en) * 2010-12-30 2011-06-08 北京市三一重机有限公司 Continuous wall grab
CN102974721A (en) * 2012-10-24 2013-03-20 北京发研工程技术有限公司 Underground anchor cable cutting construction method and cutting device thereof
CN204738332U (en) * 2015-03-17 2015-11-04 中铁十六局集团有限公司 Hydraulic pressure grooving machine
CN104763438A (en) * 2015-04-23 2015-07-08 张清林 Rope sawing type heading machine
CN106088099A (en) * 2016-07-15 2016-11-09 南昌轨道交通集团有限公司 A kind of subway foundation pit anchor cable processing method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
金刚石绳索切割技术在某地下既有锚索拆除中的应用;杨光值,潘鸿宝;《施工技术》;20131130;71-73 *

Also Published As

Publication number Publication date
CN108005083A (en) 2018-05-08

Similar Documents

Publication Publication Date Title
CN110206493B (en) Construction process of full-sleeve full-rotation bored pile
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN106320333B (en) Combined drainage type water filling pile device and construction method
CN105780763A (en) Construction method of medium-hole vibrating casing wall protection type long spiral cast-in-situ bored pile
CN106978807A (en) Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area
CN103290840A (en) Prestressed pipe pile construction method under boulder group geological conditions
CN104775437A (en) Cutting type constructing method for excavating rock foundation pits in construction site
CN104532842A (en) Sleeve rotating friction type breaking pile-extracting construction method
JP2023501743A (en) Foundation pit support method in geological conditions where stones are mixed in the soil layer
CN108005083B (en) Anchor cable processing method within the scope of a kind of foundation pit enclosure structure
CN112942399A (en) Open caisson mechanical construction device and method for penetrating rock stratum
JP2012031680A (en) Device for foundation construction
CN109056709A (en) A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation
CN203658036U (en) Shield hob test bench
CN103866787B (en) A kind of spacious reverse masonry method concrete cut that digs builds construction technology
CN102926382A (en) Construction method of soil mixing wall (SMW) engineering method
CN113106965A (en) Construction device and method for undisturbed breaking of steel strand diaphragm wall of temporary subway structure
CN115478543B (en) Artificial hole digging pile foundation pit supporting structure and construction method
CN218060412U (en) Utility tunnel enclosure wall construction structures
CN206570811U (en) Existing bridge pile pulling device is passed through in weak soil shield driving area
CN214886883U (en) Manual hole digging mechanical auxiliary device
CN105888595B (en) Rotary drilling rig fishes for drill bit special purpose device and method in the case of bit freezing
CN115075249A (en) Pile foundation clearing device and pile foundation clearing process
CN114837209A (en) Construction method of deep sand layer large-diameter pile foundation in karst development area
CN102505724B (en) Hole guiding device and hole guiding method for bad ground

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant