CN107974951A - A kind of light-duty trackless Hanging Basket of bridge - Google Patents

A kind of light-duty trackless Hanging Basket of bridge Download PDF

Info

Publication number
CN107974951A
CN107974951A CN201711151452.XA CN201711151452A CN107974951A CN 107974951 A CN107974951 A CN 107974951A CN 201711151452 A CN201711151452 A CN 201711151452A CN 107974951 A CN107974951 A CN 107974951A
Authority
CN
China
Prior art keywords
girder
hanging basket
duty
light
mobile stent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711151452.XA
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Jing Hui Sports Facilities Engineering Co Ltd
Original Assignee
Shaanxi Jing Hui Sports Facilities Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Jing Hui Sports Facilities Engineering Co Ltd filed Critical Shaanxi Jing Hui Sports Facilities Engineering Co Ltd
Priority to CN201711151452.XA priority Critical patent/CN107974951A/en
Publication of CN107974951A publication Critical patent/CN107974951A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection

Abstract

The invention discloses a kind of light-duty trackless Hanging Basket of bridge, it is characterised in that:It includes the girder of triangle main couple, front wheel bearing, preceding bracket cushion beam, left-hand thread wheel system, mobile stent, anchor beam afterwards, anchor pole and steel sleeper afterwards, anchor hole after the rear end lower of the girder is provided with least three rows along girder length direction, the mobile stent is detachably arranged in the rear anchor hole of girder by left-hand thread wheel system, front wheel bearing sliding is arranged on the front lower portion of girder, preceding bracket cushion beam is fixed at the lower part of front wheel bearing, the rear anchor beam is detachably arranged in the rear end of girder and girder can be fixed on the face of pouring by rear anchor pole;The steel sleeper is separately positioned on the lower part of mobile stent and preceding bracket cushion beam.

Description

A kind of light-duty trackless Hanging Basket of bridge
Technical field
The present invention relates to the realm of building construction, and in particular to a kind of Hanging Basket.
Background technology
Since the rigidity of structure of gerber beam is big, deformation is small, expansion joint is few and drives a vehicle many advantages, such as steady comfortable, this Kind beam type structure is more and more extensive in the application of highway in China and railway bridge, and Hanging Basket is the capital equipment of cantilever construction.State at present The mainstream walking system of interior Hanging Basket in main couple bottom by setting walking rails to move ahead or retreat to realize Hanging Basket, Ci Zhongjie The Hanging Basket of configuration formula puts into the shortcomings of man-machine of high cost and walking guidance quality is poor from great, track, or even part beam type need to be pre-buried Track anchor rib, anchor rib material mainly use fining twisted steel, and finish rolling steel is high compared with common iron price, not only causes greatly Waste, pre-buried part finish rolling steel need to be stayed in permanently in beam body concrete, and the corrosion for undoubtedly having rolled up concrete structure is led to Road, causes bridge security greatly to endanger and influence the service life of bed rearrangement bridge in itself.
The content of the invention
In view of the above defects of the prior art and insufficient, the present invention provides a kind of master using triangle main couple Beam substitutes the walking rails of traditional Hanging Basket to realize the general Hanging Basket of the light-duty trackless of bridge of Hanging Basket walking.
The present invention is achieved by the following technical solution:A kind of light-duty trackless Hanging Basket of bridge, it is characterised in that:It is wrapped Include the girder of triangle main couple, front wheel bearing, preceding bracket cushion beam, left-hand thread wheel system, mobile stent, rear anchor beam, rear anchor pole and Steel sleeper, anchor hole after the rear end lower of the girder is provided with least three rows along girder length direction, the mobile stent lead to Left-hand thread wheel system to be crossed to be detachably arranged in the rear anchor hole of girder, front wheel bearing sliding is arranged on the front lower portion of girder, Preceding bracket cushion beam is fixed at the lower part of front wheel bearing, and the rear end that the rear anchor beam is detachably arranged in girder simultaneously may be used Girder is fixed on the face of pouring by rear anchor pole;
The steel sleeper is separately positioned on the lower part of mobile stent and preceding bracket cushion beam.
The lower part of the girder is additionally provided with jack jacking fulcrum.
Draw-gear is additionally provided with the front wheel bearing.
The center of the girder is additionally provided with montant.
Dismountable mobile stent anchoring temporarily muscle is additionally provided with the mobile stent.
Hanging Basket of the present invention is lighter:Due to eliminating walking track, such a Hanging Basket economizes on material 20% than traditional triangle Hanging Basket More than, the Diamond-Shape Form Traveler that compares economizes on material more than 30%, and dead weight is lighter, that is, has saved cost, also reduced Construction of continuous beam and bear Lotus;Construction less investment:Such a Hanging Basket need not carry out walking track anchoring, without in the pre-buried fining twisted steel of beam body, and it is mobile The anchor hole and anchor beam of stent can be shared with rear anchor system, on the one hand greatly reduce talent's machine caused by pre-buried track anchor rib Input wastes, on the other hand it also avoid because embedded bar can not take out increase the corrosion passage of concrete structure caused by safety Hidden danger, is more advantageous to ensureing the service life of bridge;Guidance quality of walking is good:Running gear is designed using such a trackless, can be avoided Traditional Hanging Basket is difficult to realize the disadvantage of curved path walking pouring the track that is run into plane curve beam type, and such a running gear is only The i.e. achievable Hanging Basket of front wheel support position need to be controlled accurately in place, it is with the obvious advantage;It is versatile:It is lighter due to conducting oneself with dignity, it is same Set Hanging Basket, which repeats, uses different size of beam type, embodies stronger versatility, adds the recycling rate of waterused of Hanging Basket, compared with Few construction cost.
Brief description of the drawings
Fig. 1 is the structure diagram of the present invention;
Fig. 2 is the sectional view along A-A of Fig. 1;
In figure, 1, girder, 2, rear anchor beam, 3, left-hand thread wheel system, 4, mobile stent, 5, steel sleeper, 6, rear anchor pole, 7, montant, 8, preceding Roller support, 9, preceding bracket cushion beam, 10, draw-gear, 11, jack jacking fulcrum, 12, rear anchor hole, 13, mobile stent it is interim Anchor rib.
Embodiment
Below by non-limiting embodiment and with reference to attached drawing to invention further instruction:
As shown in drawings, the light-duty trackless Hanging Basket of a kind of bridge, it is characterised in that:It includes girder 1, the front wheel of triangle main couple Bearing 8, preceding bracket cushion beam 9, left-hand thread wheel system 3, mobile stent 4, rear anchor beam 2, rear anchor pole 6 and steel sleeper 5, the girder 1 Anchor hole 12 after rear end lower is provided with least three rows along girder length direction, the mobile stent 4 can by left-hand thread wheel system 3 Dismounting installed in the rear anchor hole 12 of girder in, be additionally provided with the mobile stent 4 and removably move stent jury anchor Gu muscle 13..Front wheel bearing 8 is slidably arranged in the front lower portion of girder 1, and traction is additionally provided with the front wheel bearing 8 Device 10.Preceding bracket cushion beam 9 is fixed at the lower part of front wheel bearing 8.The rear anchor beam 2 is detachably arranged in girder Girder 1 can be simultaneously fixed on the face of pouring by 1 rear end by rear anchor pole 6;
The steel sleeper 5 is separately positioned on the lower part of mobile stent 4 and preceding bracket cushion beam 9.The lower part of the girder 1 is also set up There is jack to jack fulcrum 11.
The center of the girder 1 is additionally provided with montant 7.
Work step of the present invention is as follows:
1), after current casting complete with jack jacking Hanging Basket jack jacking fulcrum 11;
2), front wheel bearing 8, preceding bracket cushion beam 9 moved forward at next segment jack jacking fulcrum;
3), mobile left-hand thread wheel system 3 and mobile stent 4 to next segment rear anchor hole position(Can be using in anchor hole after three rows Arbitrary neighborhood two rows);
4), remove it is two rows of after anchor beam 3 and utilize the mobile stent of the anchoring of anchor hole 12 behind next segment;
5), from preceding roller support draw-gear 10 penetrate traction steel strand wires or fining twisted steel, rear end be anchored in jacking bearing;
6), remove anchor beam 2 after whole on Hanging Basket girder, make the lower part edge of a wing of 3 left-hand thread girder of left-hand thread wheel system, 1 I-steel, instead Sprocket wheel stress, completes the conversion of walking states stress system, and acting on traction Hanging Basket by hydraulic jack walks;
7), Hanging Basket walking it is in place after, first anchored with anchor beam 2 after a row, at this time after anchor beam stress inverse buckling wheel is departed from girder The edge of a wing, removes 4 anchoring temporarily of mobile stent, rear anchor beam 2 is all anchored in point after Hanging Basket, Hanging Basket stress system, which switches to, to be poured State;
8), such a walking system Hanging Basket can retreat, retreat walking with Hanging Basket advance flow.

Claims (5)

  1. A kind of 1. light-duty trackless Hanging Basket of bridge, it is characterised in that:It includes the girder of triangle main couple, front wheel bearing, preceding branch Seat cushion beam, left-hand thread wheel system, mobile stent, rear anchor beam, rear anchor pole and steel sleeper, the rear end lower of the girder is along girder length Direction is provided with anchor hole after at least three rows, and the mobile stent is detachably arranged in the rear anchor of girder by left-hand thread wheel system Kong Zhong, front wheel bearing sliding are arranged on the front lower portion of girder, and preceding bracket cushion beam is fixed at the lower part of front wheel bearing, The rear anchor beam is detachably arranged in the rear end of girder and girder can be fixed on the face of pouring by rear anchor pole;
    The steel sleeper is separately positioned on the lower part of mobile stent and preceding bracket cushion beam.
  2. A kind of 2. light-duty trackless Hanging Basket of bridge according to claim 1, it is characterised in that:The lower part of the girder is also set It is equipped with jack jacking fulcrum.
  3. A kind of 3. light-duty trackless Hanging Basket of bridge according to claim 1, it is characterised in that:On the front wheel bearing also It is provided with draw-gear.
  4. A kind of 4. light-duty trackless Hanging Basket of bridge according to claim 1 or 2, it is characterised in that:The center of the girder It is additionally provided with montant.
  5. A kind of 5. light-duty trackless Hanging Basket of bridge according to claim 1, it is characterised in that:Also set on the mobile stent It is equipped with dismountable mobile stent anchoring temporarily muscle.
CN201711151452.XA 2017-11-18 2017-11-18 A kind of light-duty trackless Hanging Basket of bridge Pending CN107974951A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711151452.XA CN107974951A (en) 2017-11-18 2017-11-18 A kind of light-duty trackless Hanging Basket of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711151452.XA CN107974951A (en) 2017-11-18 2017-11-18 A kind of light-duty trackless Hanging Basket of bridge

Publications (1)

Publication Number Publication Date
CN107974951A true CN107974951A (en) 2018-05-01

Family

ID=62010503

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711151452.XA Pending CN107974951A (en) 2017-11-18 2017-11-18 A kind of light-duty trackless Hanging Basket of bridge

Country Status (1)

Country Link
CN (1) CN107974951A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589554A (en) * 2018-07-05 2018-09-28 贵州路桥集团有限公司 Trackless triangle hanging basket
CN112523110A (en) * 2020-11-06 2021-03-19 江苏镇江路桥工程有限公司 Suspended casting construction hanging basket suspension system convenient to move
CN113529578A (en) * 2021-06-25 2021-10-22 浙江交通职业技术学院 Manufacturing process of automatic synchronous pushing hanging basket structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589554A (en) * 2018-07-05 2018-09-28 贵州路桥集团有限公司 Trackless triangle hanging basket
CN112523110A (en) * 2020-11-06 2021-03-19 江苏镇江路桥工程有限公司 Suspended casting construction hanging basket suspension system convenient to move
CN112523110B (en) * 2020-11-06 2022-07-12 江苏镇江路桥工程有限公司 Suspended casting construction hanging basket suspension system convenient to move
CN113529578A (en) * 2021-06-25 2021-10-22 浙江交通职业技术学院 Manufacturing process of automatic synchronous pushing hanging basket structure
CN113529578B (en) * 2021-06-25 2022-11-25 浙江交通职业技术学院 Manufacturing process of automatic synchronous pushing hanging basket structure

Similar Documents

Publication Publication Date Title
CN107905114B (en) A kind of construction method of large span Successive interference cancellation
CN102094392B (en) Lower supported hanging basket in bridge construction and application thereof
CN107974951A (en) A kind of light-duty trackless Hanging Basket of bridge
CN204174541U (en) Continuous girder bridge suspended casting suspended basket push unit
CN207608836U (en) A kind of Successive interference cancellation cantilever pouring construction Diamond-Shape Form Traveler
CN103669215B (en) Vertical-horizontal overall-sliding type side mold of fulcrum-few support
CN103938552B (en) Steel truss arched bridge self-balancing cantilever construction method and the spacing bearing of main pier
CN107747282B (en) On across both wired old bridge overall pulling down methods
CN102418534B (en) Split movable mould frame device for tunnel compartment wall, and construction method for split movable mould frame
CN202544854U (en) Lining trolley for subway station
CN109112974A (en) Bridge Erector and its process of setting a roof beam in place
CN101250854A (en) Large span double-linear-box beam bunching-frame method construction bridging machine
CN108316152A (en) A kind of high pier capping beam construction mobile formwork and its construction technology
CN105926464A (en) Inverted hanging type trapezoid inclined climbing form traveler
CN210561749U (en) Multi-frame juxtaposed double-cantilever bridge girder erection machine
CN207498835U (en) Needle beam combined steel plate beam bridge panel cast-in-place construction sliding form frame system
CN207512629U (en) The cast-in-place trolley of railway T-beam sound barrier beam slab
CN106192761B (en) A kind of method for disassembling mobile formwork in the narrow short transition time section of bridge tunnel
CN208618275U (en) Trackless triangle hanging basket
CN201972099U (en) Through type hanging basket in bridge construction
CN104179123A (en) Bridge fabrication machine capable of building and assembling two bridge segments
CN208803366U (en) A kind of rotor sections oblique pull steel truss girder bridge
CN207700074U (en) The double limb triangle hanging baskets of continuous rigid frame bridge cantilever beam section construction
CN107893377B (en) The on-site consolidation method of Cable-stayed Bridges loop wheel machine bottom basket system
CN203834366U (en) Energy-saving universal hanging basket for bridge construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180501