CN107974943A - A kind of road and bridge pavement construction method - Google Patents

A kind of road and bridge pavement construction method Download PDF

Info

Publication number
CN107974943A
CN107974943A CN201711243442.9A CN201711243442A CN107974943A CN 107974943 A CN107974943 A CN 107974943A CN 201711243442 A CN201711243442 A CN 201711243442A CN 107974943 A CN107974943 A CN 107974943A
Authority
CN
China
Prior art keywords
box beam
road
concrete
construction method
pavement construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711243442.9A
Other languages
Chinese (zh)
Inventor
曹端阳
黄成锐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Hua Xia Technical College
Original Assignee
Guangzhou Hua Xia Technical College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Hua Xia Technical College filed Critical Guangzhou Hua Xia Technical College
Priority to CN201711243442.9A priority Critical patent/CN107974943A/en
Publication of CN107974943A publication Critical patent/CN107974943A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Abstract

The invention discloses a kind of road and bridge pavement construction method, including bent cap frame, it is characterised in that:The prefabricated bent cap lower portion embedded bar frame, then pass through concreting bent cap, while in the reinforcing bar of the pre-buried installation pinner in the top of bent cap, pinner is poured by pre-buried reinforcing bar, pinner bearing is installed in pinner upper surface middle part, and ensures that its installation is close during secondary;By being laid with first layer bitumen layer in concrete layer upper surface, and it is laid with second layer bitumen layer, so that the layering laying between the bitumen layer on upper strata and the bitumen layer of next time causes it when in use, the bitumen layer more consolidation of lower floor, so that its water resistance is stronger.

Description

A kind of road and bridge pavement construction method
Technical field
The present invention relates to bridge pavement technical field of construction, is specially a kind of road and bridge pavement construction method.
Background technology
Highway alignment passes through the waters such as rivers, bay, lake, reservoir, feed ditch, or across the big deep valley area of height difference, or Across other traffic routes, in order to keep the traffic moving, needs build a bridge.Bustling urban district needs to set to be made of overpass sometimes Viaduct.Other hill path line is great because digging subgrade engineering, or because geological structure is unstable, or because protecting landscape, sometimes Overpass is built, without constructing roadbed.It is general that the high water level that can lead expected maximum flood off safely is set across the bridge of rivers Bridge.In the river small stream of seasonal current, as the volume of traffic is small, low water level bridge (also known as overflow bridge) is set sometimes or crosses water to reduce investment outlay Road surface.The river surface of bridge construction is not easy in the lake surface of the broad depth of water and a period of time can set up pontoon bridge.Build bridge on navigable river, as two sides are put down It is smooth, when bridge floor is not easy to raise, frequently with can move or elevated movable bridge.When highway and railway or highway intersect When, in order to avoid level-crossing can build cloverleaf intersection.Viaduct can be upper straddle type when primary highway passes through secondary road Or underpass type.When acrossing highway, the highway of heavy traffic and street, for the safe passing of pedestrian, it can repair Pedway is built, across highway above highway
Bridges in highway engineering includes bridge main body (i.e. bridge superstructure and bridge substructure) engineering and bridge location is overall In attached job facilities.Attached job facilities are very much, such as in order to which the shore protection, the trraning pole that keep river at bridge location to stablize are adjusted Harness the river the structure of stream, what end of the bridge was connected with highway lead the way access bridge, the railing that anti-wheel collides on bridge floor, ensures pedestrains safety Navigation marker and bridge floor lighting apparatus etc. under livery, bridge on pedestrian guardrail, and bridge.In addition, positioned at earthquake territory bridge also Equipped with vibration abatement, cable-stayed bridge hoist cable guy rope is equipped with the attachment device of windproof dynamic resonance, and movable bridge is equipped with mechanical device, floating ice Bridge on river is equipped with icebreaking device etc..Therefore the same Structural Engineering of science of bridge building, foundation engineering, hydraulic engineering and traffic engineering have Close, and it is related with subjects such as meteorology, the hydrology, engineering geology, construction material, measuring technology, engineering machinery, aesthetics, environmental protections, It is a comprehensive very strong engineering technology.And still have much in the occupation mode for bridge pavement in the prior art Defect is for example:
1. the water resistance on bridge pavement of the prior art road surface in construction is very poor, for a long time in use, its pitch So that pit easily occurs in its road surface after layer inside is permeable, so can not meet needed for the prior art.
2. during bridge pavement of the prior art construction often due to it is long in time limit in its work progress and in construction its It is excessively numerous and diverse during the construction of bent cap, and when constructing to pinner, that the deviation of position is excessive is empty between box beam when causing subsequent construction Gap is difficult to control, causes the slight of its pontic to cross bottom, so can not meet needed for the prior art.
The content of the invention
It is an object of the invention to provide a kind of road and bridge pavement construction method, to solve to propose in above-mentioned background technology The problem of.
To achieve the above object, the present invention provides following technical solution:A kind of road and bridge pavement construction method, including lid Beam frame, box beam and put and to survey an elevation, it is characterised in that:The prefabricated bent cap lower portion embedded bar frame, then passes through Concreting bent cap, at the same the top of bent cap it is pre-buried installation pinner reinforcing bar, pour pinner by pre-buried reinforcing bar, padding Stone upper surface middle part installs pinner bearing, and ensures that its installation is close during secondary;The box beam carries out being lifted on pinner On bearing, gap is left between box beam side, box beam leaves gap between both ends, passes through reinforcing bar to the gap between box beam side The splicing of wet seam is carried out with concrete, and is spliced in the gap at box beam both ends by middle cross beam with concrete, then The box beam of two flanks is mutually installed into guardrail from side upper surface;First in box beam upper surface comparison diagram during the pavement construction Paper carries out putting a survey elevation, and 5m spacing is kept between each point, and reinforcing bar is stamped on the point put, and reinforcing bar is highly high to survey The height that journey is surveyed, places reinforced mesh on reinforcing bar, stringent when pouring to box beam upper surface casting concrete after the completion of placement Poured according to surveyed elevation, wait and be laid with first layer pitch in concrete upper surface after concrete coagulation, to the after laying One layer of pitch is compacted using road roller, ensures pavement compaction in process of deployment and smooth while first layer pitch thickness is 8cm, is then cooled down first layer pitch with weather by environment temperature, then smears waterproof in first layer pitch upper face Coating, re-lays second layer pitch and carries out compaction treatment using road roller again, ensures that it is laid with uniform outer surface and puts down in process of deployment 6cm after whole while second layer pitch thickness, finally carries out cooling treatment according to environment to second layer pitch.
Preferably, the box beam be lifted on pinner bearing, leaves gap between box beam side, between box beam both ends Gap is left, carries out the splicing of wet seam with concrete by reinforcing bar to the gap between box beam side, and at box beam both ends Gap spliced by middle cross beam with concrete, the box beams of two flanks is mutually then installed into guardrail from side upper surface.
Preferably, first in box beam upper surface, contrast drawing carries out putting a survey elevation during the pavement construction, and 5m spacing is kept between each point, reinforcing bar is stamped on the point put, reinforcing bar is highly to survey the height that elevation is surveyed, on reinforcing bar Reinforced mesh is placed, to box beam upper surface casting concrete after the completion of placement, is poured when pouring in strict accordance with surveyed elevation, First layer pitch is laid with concrete upper surface after wait concrete coagulation, first layer pitch is carried out using road roller after laying It is compacted, ensures pavement compaction in process of deployment and smooth while first layer pitch thickness is 8cm, then by environment temperature and gas Time is cooled down first layer pitch, is then smeared water-repellent paint in first layer pitch upper face, is re-layed second layer pitch again Compaction treatment is carried out using road roller, ensures that it is laid with that uniform outer surface is smooth while after second layer pitch thickness in process of deployment 6cm, finally carries out cooling treatment according to environment to second layer pitch.
Preferably, between the gap holding 30-20cm between the box beam side and both ends.
Preferably, the intensity for pouring concrete used in pinner it is identical with concrete strength used in bent cap be C30 and Its concrete mix is:0.38:1:1.11:2.72.
Preferably, the water-repellent paint is SBS modified-high polymer Emulsificated asphalt water-proof painting materials.
Preferably, the reinforced mesh smears cement to keep it from getting rusty using preceding with putting reinforcing bar a little used to it Slurry.
Preferably, it is described to prevent to ensure that box beam upper surface is cleaned before bar-mat reinforcement after-pouring concrete, while pouring The situation of concrete feed supplement is avoided to occur during concrete.
Preferably, it must ensure that concrete upper surface is cleaned before the laying first layer pitch.
Preferably, box beam upper surface is polished before casting concrete in the box beam upper surface.
Preferably, need to carry out wharf's pavement quality to concrete after the concreting of the box beam upper surface.
Preferably, the box beam side needs to carry out tensioning processing to box beam before wet seam is carried out.
Compared with prior art, the beneficial effects of the invention are as follows:
1st, the present invention is by being laid with first layer bitumen layer in concrete layer upper surface, and is laid with second layer bitumen layer, makes The layering between the bitumen layer on upper strata when in use and the bitumen layer of next time is obtained to be laid with so that it, the bitumen layer of lower floor is more stepped up It is real, so that its water resistance is stronger.
2nd, the present invention passes through the embedded bar when pouring bent cap so that when the pinner to bent cap upper surface is pouring Position is more accurate, so as to avoid using when there is pinner position offset subsequent construction had an impact.
Brief description of the drawings
Fig. 1 is the Coping Construction flow of the present invention;
Fig. 2 is the box girder construction flow of the present invention;
Fig. 3 is the pavement construction flow of the present invention.
Embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other without making creative work Embodiment, belongs to the scope of protection of the invention.
Refering to Figure 1, the present invention provides a kind of technical solution:A kind of road and bridge pavement construction method, including lid Beam frame, it is characterised in that:The prefabricated bent cap lower portion embedded bar frame, then by concreting bent cap, together When the top of bent cap it is pre-buried installation pinner reinforcing bar, pour pinner by pre-buried reinforcing bar, pinner upper surface middle part install Pinner bearing, and ensure that its installation is close during secondary, used in the intensity for pouring concrete used in pinner and bent cap Concrete strength is identical to be C30 and its concrete mix is:0.38:1:1.11:2.72.
As shown in Fig. 2, the box beam be lifted on pinner bearing, gap, box beam both ends are left between box beam side Between leave gap, the splicing of wet seam is carried out by reinforcing bar and concrete to the gap between box beam side, and in box beam The gap at both ends is spliced by middle cross beam with concrete, and then the box beam of two flanks is mutually installed from side upper surface and is protected Column, the box beam side needs to carry out tensioning processing to box beam before wet seam is carried out, between the box beam side and both ends Gap is kept between 30-20cm.
As shown in figure 3, first in box beam upper surface, contrast drawing carries out putting a survey elevation during the pavement construction, and And 5m spacing is kept between each point, reinforcing bar is stamped on the point put, reinforcing bar is highly to survey the height that elevation is surveyed, in reinforcing bar Upper placement reinforced mesh, to box beam upper surface casting concrete after the completion of placement, is poured when pouring in strict accordance with surveyed elevation Build, be laid with first layer pitch in concrete upper surface after wait concrete coagulation, road roller is used to first layer pitch after laying It is compacted, ensures pavement compaction in process of deployment and smooth while first layer pitch thickness is 8cm, then by environment temperature First layer pitch is cooled down with weather, then smears water-repellent paint in first layer pitch upper face, re-lays second layer drip It is blue or green that compaction treatment is carried out using road roller again, ensure that it is laid with that uniform outer surface is smooth while second layer pitch thickness in process of deployment 6cm afterwards, finally carries out the second layer pitch cooling treatment according to environment, and the water-repellent paint is the emulsification drip of SBS modified-high polymers Blue or green water-repellent paint, the reinforced mesh smear cement mortar to keep it from getting rusty using preceding with putting reinforcing bar a little used to it, institute Stating must ensure that box beam upper surface is cleaned before preventing bar-mat reinforcement after-pouring concrete, while avoid concrete in casting concrete The situation of feed supplement occurs, and must ensure that concrete upper surface is cleaned before the laying first layer pitch, the box beam upper surface exists Box beam upper surface polish before casting concrete the box beam upper surface concreting after need to carry out concrete Wharf's pavement quality, and spacing is maintained between 5-20cm between its plucking.
Operation principle:When in use,.
It should be noted that herein, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any this actual relation or order.Moreover, term " comprising ", "comprising" or its any other variant are intended to Non-exclusive inclusion, so that process, method, article or equipment including a series of elements not only will including those Element, but also including other elements that are not explicitly listed, or further include as this process, method, article or equipment Intrinsic key element.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with Understanding without departing from the principles and spirit of the present invention can carry out these embodiments a variety of changes, modification, replace And modification, the scope of the present invention is defined by the appended.

Claims (12)

1. a kind of road and bridge pavement construction method, including bent cap frame, it is characterised in that:The prefabricated bent cap lower portion is pre- Steel bar framework is buried, then by concreting bent cap, and meanwhile it is pre-buried in the reinforcing bar of the pre-buried installation pinner in the top of bent cap, process Reinforcing bar pour pinner, pinner bearing is installed in pinner upper surface middle part, and ensure that during secondary its installation is close.
A kind of 2. road and bridge pavement construction method according to claim 1, it is characterised in that:The box beam is lifted On pinner bearing, gap is left between box beam side, box beam leaves gap between both ends, and the gap between box beam side is passed through Cross reinforcing bar and the splicing of wet seam is carried out with concrete, and spelled in the gap at box beam both ends by middle cross beam with concrete Connect, the box beam of two flanks is mutually then installed into guardrail from side upper surface.
A kind of 3. road and bridge pavement construction method according to claim 2, it is characterised in that:The pavement construction process In first in box beam upper surface, contrast drawing put and to survey an elevation, and 5m spacing is kept between each point, in the point put On stamp reinforcing bar, reinforcing bar highly to survey the height that elevation is surveyed, places reinforced mesh, in box beam after the completion of placement on reinforcing bar Surface casting concrete, is poured when pouring in strict accordance with surveyed elevation, in concrete upper surface after wait concrete coagulation Be laid with first layer pitch, first layer pitch is compacted using road roller after laying, in process of deployment guarantee pavement compaction and Smooth while first layer pitch thickness is 8cm, then cools down first layer pitch with weather by environment temperature, then exists First layer pitch upper face smears water-repellent paint, re-lays second layer pitch and carries out compaction treatment using road roller again, was laid with Ensure that it is laid with that uniform outer surface is smooth while 6cm after second layer pitch thickness in journey, finally according to environment to second layer pitch into Row cooling treatment.
A kind of 4. road and bridge pavement construction method according to claim 2, it is characterised in that:The box beam side and two Gap between end is kept between 30-20cm.
A kind of 5. road and bridge pavement construction method according to claim 1, it is characterised in that:It is described to pour used in pinner The intensity of concrete is identical with concrete strength used in bent cap to be C30 and its concrete mix is:0.38:1:1.11: 2.72。
A kind of 6. road and bridge pavement construction method according to claim 3, it is characterised in that:The water-repellent paint is SBS modified-high polymer Emulsificated asphalt water-proof painting materials.
A kind of 7. road and bridge pavement construction method according to claim 3, it is characterised in that:The reinforced mesh is with putting Point reinforcing bar used smears cement mortar to keep it from getting rusty using preceding to it.
A kind of 8. road and bridge pavement construction method according to claim 3, it is characterised in that:It is described prevent bar-mat reinforcement after It must ensure that box beam upper surface is cleaned before casting concrete, while avoid the situation of concrete feed supplement from sending out in casting concrete It is raw.
A kind of 9. road and bridge pavement construction method according to claim 3, it is characterised in that:The laying first layer drip It must ensure that concrete upper surface is cleaned before green grass or young crops.
A kind of 10. road and bridge pavement construction method according to claim 3, it is characterised in that:The box beam upper surface Polish before casting concrete box beam upper surface.
A kind of 11. road and bridge pavement construction method according to claim 3, it is characterised in that:The box beam upper surface Concreting after need to concrete carry out wharf's pavement quality.
A kind of 12. road and bridge pavement construction method according to claim 2, it is characterised in that:The box beam side exists Need to carry out tensioning processing to box beam before carrying out wet seam.
CN201711243442.9A 2017-11-30 2017-11-30 A kind of road and bridge pavement construction method Pending CN107974943A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711243442.9A CN107974943A (en) 2017-11-30 2017-11-30 A kind of road and bridge pavement construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711243442.9A CN107974943A (en) 2017-11-30 2017-11-30 A kind of road and bridge pavement construction method

Publications (1)

Publication Number Publication Date
CN107974943A true CN107974943A (en) 2018-05-01

Family

ID=62008822

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711243442.9A Pending CN107974943A (en) 2017-11-30 2017-11-30 A kind of road and bridge pavement construction method

Country Status (1)

Country Link
CN (1) CN107974943A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110344316A (en) * 2019-07-16 2019-10-18 中铁建设集团有限公司 A kind of ramp bridge bar construction and its construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817325A (en) * 2012-09-13 2012-12-12 永升建设集团有限公司 Construction method of simply supported-continuous switching system of negative moment beam prestressed precast box beam
CN203034353U (en) * 2013-01-31 2013-07-03 江苏淮安交通勘察设计研究院有限公司 Connection structure of bridge support padstone and abutment
KR20130111902A (en) * 2012-04-02 2013-10-11 한국건설기술연구원 Walking bridge construction method using psc girder with connecting anchor block
CN105297620A (en) * 2015-11-07 2016-02-03 西安公路研究院 Steel plate spherical crown polymer mortar structure support and construction method thereof
CN106958186A (en) * 2017-05-31 2017-07-18 浙江省交通规划设计研究院 The construction method of bridge floor body, bridge and bridge

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20130111902A (en) * 2012-04-02 2013-10-11 한국건설기술연구원 Walking bridge construction method using psc girder with connecting anchor block
CN102817325A (en) * 2012-09-13 2012-12-12 永升建设集团有限公司 Construction method of simply supported-continuous switching system of negative moment beam prestressed precast box beam
CN203034353U (en) * 2013-01-31 2013-07-03 江苏淮安交通勘察设计研究院有限公司 Connection structure of bridge support padstone and abutment
CN105297620A (en) * 2015-11-07 2016-02-03 西安公路研究院 Steel plate spherical crown polymer mortar structure support and construction method thereof
CN106958186A (en) * 2017-05-31 2017-07-18 浙江省交通规划设计研究院 The construction method of bridge floor body, bridge and bridge

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
佚名: "大桥盖梁施工技术方案", 《HTTPS://WENKU.BAIDU.COM/VIEW/489CF656A26925C52CC5BF4B.HTML?FROM=SEARCH》 *
佚名: "桥面铺装施工技术交底", 《HTTPS://WENKU.BAIDU.COM/VIEW/A898737224C52CC58BD63186BCEB19E8B9F6EC50.HTML?FROM=SEARCH》 *
冯旭: "装配式箱梁安装及桥面铺装施工实例探讨", 《交通建设与管理》 *
无: "桥梁盖梁、挡块、支座垫石施工方案", 《HTTPS://WENKU.BAIDU.COM/VIEW/EF42E725C850AD02DF804156.HTML?FROM=SEARCH》 *
许海涛等: "预制梁先简支后连续的优化施工", 《科学之友(学术版)》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110344316A (en) * 2019-07-16 2019-10-18 中铁建设集团有限公司 A kind of ramp bridge bar construction and its construction method
CN110344316B (en) * 2019-07-16 2024-03-26 中铁建设集团有限公司 Ramp bridge steel bar structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN108678000B (en) U-shaped retaining structure for roadbed underpass highway and construction method thereof
CN110438914B (en) Water passing box culvert on soft soil foundation and construction method thereof
CN107700299A (en) A kind of elevated bridge lower floor road structure and its construction method
CN109505213A (en) A kind of the seif-citing rate reinforced concrete pavement structure and its construction method of both sides draining
CN107974943A (en) A kind of road and bridge pavement construction method
CN110359366A (en) It is a kind of using the bridge drainage structure of pervious concrete and the calculation method of pervious concrete permeability rate
CN107700301B (en) A kind of ruggedized construction on express highway roadbed
Ali Manual RC box culvert analysis and designing
CN110904756B (en) Construction method of three-layer bridge
CN111501459B (en) Roadbed structure of mountain road and construction method thereof
RU2589138C2 (en) Automobile road
RU2453650C1 (en) Complex for construction of motor road on piles
CN218345845U (en) Novel half assembled L type escape canal
JP2014009472A (en) Concrete overhang sidewalk structure, and method for constructing drive way with overhang sidewalk using the structure
CN209602905U (en) A kind of seif-citing rate reinforced concrete pavement structure of both sides draining
Kerensky et al. THE FOUR LEVEL INTERCHANGE BETWEEN M4 AND M5 MOTORWAYS AT ALMONDSBURY.(INCLUDES APPENDIX)
JP7129567B2 (en) System for the construction of double U and single U steel concrete composite structures for bridges
Prakash Analysis and Design of RE Wall and Retaining Wall
Figi Rehabilitation of the Salginatobel Bridge
CN117166303A (en) U-shaped groove device for repairing and reforming highway-railway underpass overpass and manufacturing method
Veera et al. Design Development of 9.759 km Long Six Lane Extradosed Bridge Project Crossing River Ganga in the State of Bihar, INDIA
RU89124U1 (en) DEVICE FOR ESTABLISHING A TUNNEL OF A SMALL LOCATION UNDER THE ROAD SECTION
RU2122615C1 (en) Method of pavement formation
Hall et al. Preserving a Landmark
RU2122058C1 (en) Method of pavement formation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180501

RJ01 Rejection of invention patent application after publication