CN107942959A - Pipe gallery management system - Google Patents

Pipe gallery management system Download PDF

Info

Publication number
CN107942959A
CN107942959A CN201710965522.9A CN201710965522A CN107942959A CN 107942959 A CN107942959 A CN 107942959A CN 201710965522 A CN201710965522 A CN 201710965522A CN 107942959 A CN107942959 A CN 107942959A
Authority
CN
China
Prior art keywords
piping lane
pipe gallery
monitoring
management platform
layer subsystem
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710965522.9A
Other languages
Chinese (zh)
Inventor
孙成
李铭
许晓明
谢玉强
王义元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710965522.9A priority Critical patent/CN107942959A/en
Publication of CN107942959A publication Critical patent/CN107942959A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • G05B19/4183Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by data acquisition, e.g. workpiece identification
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Abstract

The present invention relates to city integrated piping lane field, a kind of pipe gallery management system is provided, the system is built management platform by way of live layer subsystem is combined, i.e. the system is combined using software with hardware, and live layer subsystem (hardware components) is used to gathering and transmitting different types of piping lane information;Management platform (software section) is used to receive piping lane information, and piping lane information is handled, and handling result is fed back to corresponding live layer subsystem;The result that live layer subsystem is handled according to management platform is operated accordingly.The pipe gallery management system, can realize the collection of a variety of piping lane information, feature-rich;By the real-time communication between management platform and each live layer subsystem, work efficiency is higher, has the ability of emergency processing;Unified management and control are realized using management platform so that the operation management of the system is simple, easy to operate.

Description

Pipe gallery management system
Technical field
The present invention relates to city integrated piping lane field, and in particular to a kind of pipe gallery management system.
Background technology
Urban underground space resource is very limited at present, and according to the requirement built a conservation-minded society, utilities pipeline needs to collect Reduction construction, is not take up or takes the underground space less as far as possible, or more functions are realized in the limited underground space, reaches To increase social resources and the purpose of economic benefit.
Pipe gallery is to be built in Urban Underground to be used to accommodate the structures of two classes and above municipal engineering pipeline and attached set Apply.A tunnel space is built in Urban Underground, the various engineering pipeline such as electric power, communication, water supply, combustion gas is concentrated on one Body, is the important infrastructure and " lifeline " for ensureing city operations equipped with special access hole, hoisting port and detecting system. " unified planning, unified construction, unified management " is carried out, accomplishes the comprehensive utilization of the underground space and sharing for resource.
Based on conventional monitoring systems, it is hand to be aided with substantial amounts of manual inspection for pipe gallery operation management of the prior art Section, system are limited only to the simple syndication to the function such as environmental monitoring, video monitoring, safety monitoring in piping lane.And the number obtained According to being only the expression to pipe gallery operating status merely, knot is built to piping lane involved in pipe gallery life cycle Structure, supplementing facility equipment, enter the unified description of the shortage such as corridor pipeline, the safe case of emergency during operation is lacked effective Response mechanism.The efficiency and service quality of piping lane operation management so can be not only reduced, but also piping lane operational management can be caused High expensive.
The content of the invention
The defects of the technical problem to be solved in the present invention is to overcome the efficiency of piping lane operation management of the prior art low.
In consideration of it, the present invention provides a kind of pipe gallery management system, including:
Various field layer subsystem, for gathering and transmitting different types of piping lane information;
Management platform, handles for receiving the piping lane information, and to the piping lane information, handling result is fed back To the corresponding live layer subsystem;The scene layer subsystem is operated accordingly according to the handling result.
Alternatively, the live layer subsystem includes:Automatic fire alarm system, environmental monitoring and equipment monitoring system, Video monitoring system, intrusion alarm system, access control system, patrol system and Energy Consumed Statistic System;
The automatic fire alarm system, for sending fire signal to the management platform;Join with the access control system It is dynamic, for the door when fire occurs near the access control system opening fire;
The environmental monitoring and equipment monitoring system, for environmental parameter in piping lane and equipment to be monitored and reported It is alert;Link with the video monitoring system, for when monitoring device fails in piping lane, the video monitoring system to be cut The equipment for changing to fault zone, and monitored picture is sent to the management platform;The environmental parameter include temperature, humidity, Oxygen content, hydrogen sulfide content and methane content;
The video monitoring system, for being monitored in real time to piping lane;
The intrusion alarm system, for alarming when unauthorized personnel invades piping lane;With the video monitoring System interlink, for when unauthorized personnel invade piping lane when, the video monitoring system be switched to intrusion region monitoring device, And monitored picture is sent to the management platform;
The access control system, the control for the piping lane that comes in and goes out;
The patrol system, is off-line type electronic patrol system;
The Energy Consumed Statistic System, the collection for piping lane gut line data are measured;The pipeline include water, electricity, gas with And heat.
Alternatively, the management platform is connected with exterior GIS-Geographic Information System, for receiving the exterior geography information system The piping lane geography information that system is sent.
Alternatively, the automatic fire alarm system determines fire location according to the piping lane GIS-Geographic Information System Position.
Alternatively, the environmental monitoring includes with equipment monitoring system:
At least 2 sets of sensors of piping lane fire compartment are arranged on, for measurement temperature, humidity or oxygen content;
First alarm unit, for sending alarm signal according to the measurement result of the sensor.
Alternatively, the environmental monitoring includes with equipment monitoring system:
At least two kinds of sensors of piping lane catch pit are arranged on, for measuring level value or water temperature value
Second alarm unit, for sending alarm signal according to the measurement result of the sensor.
Alternatively, the video monitoring system is included at least 1 set of monitoring device that each fire compartment of piping lane is set, institute Stating monitoring device includes being separately positioned on first video camera and the second video camera at the fire compartment both ends;The video monitoring System is used to be sent to the management platform to the monitored results of the monitoring device.
Alternatively, the pipe gallery management system further includes:
Convergence switch, for converging the data that IO stands in each live layer subsystem, and is sent to core exchange Machine;
The core switch, for converging the data of the convergence switch, and is sent to the management platform;
The video monitoring system includes the Power over Ethernet interchanger being connected with the core switch, and described first takes the photograph Camera is connected with the too net power supplying switch, and second video camera is connected with the convergence switch.
Alternatively, each live layer subsystem sets 2 convergence switches, the pipe gallery management system 2 core switch are set, and the convergence switch is connected using looped network form with the core switch.
Alternatively, the intrusion alarm system includes being arranged on the first detector at piping lane ventilating opening and escaping exit, The second detector being arranged at hoisting port;The intrusion alarm system is used to visit first detector and described second Survey device and result of detection is sent to the management platform.
Technical solution of the present invention, has the following advantages that:
1. pipe gallery management system provided in an embodiment of the present invention, is combined by management platform with live layer subsystem Mode build, i.e., the system is combined using software with hardware, live layer subsystem (hardware components) be used for gather and transmit Different types of piping lane information;Management platform (software section) is used to receive piping lane information, and piping lane information is handled, will Handling result feeds back to corresponding live layer subsystem;The result that live layer subsystem is handled according to management platform carries out corresponding Operation.The pipe gallery management system, can realize the collection of a variety of piping lane information, feature-rich;By management platform and respectively Real-time communication between live layer subsystem, work efficiency is higher, has the ability of emergency processing;Realized and united using management platform One management and control so that the operation management of the system is simple, easy to operate.
2. pipe gallery management system provided in an embodiment of the present invention, wherein, management platform and exterior GIS-Geographic Information System Connection, the piping lane geography information sent for receiving exterior GIS-Geographic Information System so that reach by management platform to piping lane into The pinpoint purpose of row, easy to which when emergency occurs, timely place can be made according to the piping lane geography information navigated to Reason.
3. pipe gallery management system provided in an embodiment of the present invention, wherein, environmental monitoring passes through with equipment monitoring system At least 2 sets of sensors of piping lane fire compartment are arranged on, for measuring the temperature, humidity or oxygen content of fire compartment;In temperature When degree, humidity or oxygen content exceed given threshold, alarm signal is sent by the first alarm unit of setting.By to prevent fires Subregion measures environmental parameter therein, so as to ensure that the stabilization of piping lane environment in real time as measuring unit.
4. pipe gallery management system provided in an embodiment of the present invention, environmental monitoring is with equipment monitoring system by being arranged on Two video cameras at the both ends of piping lane fire compartment are monitored fire compartment, wherein, two video cameras are formed to penetrating, can The monitoring of maximum magnitude is carried out to fire compartment, reduces monitoring blind area, improves monitoring accuracy.
5. pipe gallery management system provided in an embodiment of the present invention, passes through the level value to liquid in catch pit in piping lane And temperature value measures, when measurement result exceeds preset value, the second alarm unit sends alarm signal, easy to notify phase Pass personnel's timely processing, avoids influence of the liquid to other pipelines in catch pit.
6. pipe gallery management system provided in an embodiment of the present invention, wherein, the data of each scene layer subsystem are by converging Poly- interchanger carries out convergence, and each convergence switch is by core switch by the data sending of each live layer subsystem to pipe Platform, passes through the convergence switch and core switch for setting layering to set, it is possible to increase the transmission rate of data, and converge Poly- interchanger is provided with abundant interface, removable without changing data transfer mode easy to the extension of live layer subsystem Plant property is higher.
7. pipe gallery management system provided in an embodiment of the present invention, wherein, video monitoring system includes exchanging with core The Power over Ethernet interchanger of machine connection, the first video camera are powered using too net power supplying switch, the second video camera and other Equipment is without the Power over Ethernet power supply for exchange, cut-in convergent interchanger during use;Due to the first video camera be defined as it is close The video camera at the IO stations of video monitoring system, i.e. near end camera, by the way that near end camera is used Power over Ethernet interchanger Power supply, wiring distance is shorter, can save installation cost.
8. pipe gallery management system provided in an embodiment of the present invention, for connecting each live layer subsystem and management platform Network system use 2 layers of ring network framework, every road is as 1 sub-regions, and every road is according to the suitable IO of geographical location choice Stand and 2 convergence switches are set, be responsible for the convergent point at all IO stations in this road;According to above principle, the embodiment of the present invention is set altogether Several convergent points are put, each convergent point is equally connected using looped network form with monitoring center piping lane core switch, piping lane core Heart interchanger equally sets 2, and forming double-core dual link with above-mentioned convergence switch configures, and meets system stability requirement.
Brief description of the drawings
, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution of the prior art Embodiment or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, in describing below Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor Put, other attached drawings can also be obtained according to these attached drawings.
Fig. 1 is the structure diagram of pipe gallery in the embodiment of the present invention;
Fig. 2 is the structure diagram of pipe gallery management system in the embodiment of the present invention;
Fig. 3 is the structure diagram of live layer subsystem in the embodiment of the present invention.
Embodiment
Technical scheme is clearly and completely described below in conjunction with attached drawing, it is clear that described implementation Example is part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill Personnel's all other embodiments obtained without making creative work, belong to the scope of protection of the invention.
In the description of the present invention, it is necessary to which explanation, term " first ", " second ", " the 3rd " are only used for description purpose, And it is not intended that instruction or hint relative importance.
Fig. 1 shows a kind of schematical structure chart of the pipe gallery involved by the embodiment of the present invention, the pipe gallery Including combustion gas cabin, electric power cabin, plumbing and communication cabin, cabin containing sewage and catch pit.In addition, in pipe gallery One fire compartment is set at 200m, is separated between fire compartment with fire wall, wall is equipped with first class fireproof safety door.
As shown in Figure 1, the pipe gallery is when specifically setting pipeline, mutual glitch-free utilities pipeline --- supplying drainage Road and communication pipe are arranged in the same cabin of piping lane;Communication pipe is disposed on different cabins from power pipe Room;Feedwater piping is arranged on the same side in same cabin with drainage pipeline, wherein, drainage pipeline is arranged on the bottom in piping lane cabin Portion;Heat distribution pipeline, power pipe and gas pipeline are disposed on different cabins.The set-up mode of above-mentioned pipeline, not only Interfering with each other between different utilities pipelines is avoided, while ensure that the safety of pipeline.
As long as in addition, technical characteristic involved in invention described below different embodiments non-structure each other It can be combined with each other into conflict.
Embodiment
The embodiment of the present invention provides a kind of pipe gallery management system, as shown in Fig. 2, with 7 kinds of live layer subsystems in Fig. 2 Exemplified by be described, but protection scope of the present invention is not limited to this, and the quantity of live layer subsystem can be according to specific pipe The situation of corridor is specifically set.The system includes management platform 10, for receiving the piping lane letter of each live layer subsystem collection Breath, and piping lane information is handled, handling result is fed back into corresponding live layer subsystem;Live layer subsystem is according to pipe The result of platform processing is operated accordingly.In addition, management platform 10 is connected with exterior GIS-Geographic Information System 50, for obtaining The geography information of piping lane is taken, is easy to implement positioning.
Include as shown in figure 3, live layer subsystem includes the live layer subsystem:Automatic fire alarm system, environment Monitoring and equipment monitoring system, video monitoring system, intrusion alarm system, access control system, patrol system and energy measurement system System.
Automatic fire alarm system, for during generation fire, sending fire to management platform at the first time in pipe gallery Calamity signal, the emergency first-aid repair for taking next step easy to piping lane operation maintenance personnel work.
Fire alarm procedure is as follows in piping lane:By smog or temperature sensor in real time to the smokescope or ring in piping lane Border temperature measures, if the smokescope or environment temperature measured are more than given threshold value, fire detector action, hair Go out alarm signal;Alarm signal is sent to fire alarm control unit, sends sound, visual alarm;In addition, the automatic fire alarm System links with exterior GIS-Geographic Information System, and fire location is positioned, can show piping lane at the same time on display platform 10 The geographical location that interior fire occurs, easy to piping lane, administrative staff understand fire location in time, are accurately positioned, timely processing.
In addition, the automatic fire alarm system links with access control system, for the access control system opening fire when fire occurs Door near calamity, easy to evacuating personnel in piping lane.
Environmental monitoring and equipment monitoring system, for environmental parameter in piping lane and equipment to be monitored and alarmed.Its In, environmental parameter includes temperature, humidity, oxygen content, hydrogen sulfide gas and methane gas equal size;And work as the same of piping lane When containing two classes and above type of pipeline in cabin, the environmental monitoring to the cabin, according to the highest pipeline of environmental requirement, The environment of corresponding safe handling is monitored setting.Equipment in piping lane includes ventilation equipment, draining pump, all kinds of electrically sets Standby etc., the said equipment has multiple control modes:On the spot manually, automatic, remote manual and remote auto on the spot, specifically make Used time selects corresponding control mode according to different use environments.
Environmental monitoring and at least 2 set sensors of the equipment monitoring system including being arranged on each fire compartment, wherein, often cover Sensor includes Temperature Humidity Sensor, oxygen amount sensor, and the humiture in fire compartment and oxygen content are measured in real time, To ensure the Environmental security of fire compartment.Wherein, it using 2 sets and the sensor of the above, can ensure the accuracy of measurement, reduce Measurement error.
The alarm procedure for often covering sensor is as follows:By humiture and oxygen amount sensor in real time to the environment temperature in piping lane Humidity and oxygen content measure, if the ambient temperature and humidity and oxygen content measured are less than given threshold value, send report Alert signal;Alarm signal is sent to management platform, easy to piping lane administrative staff's timely processing.
Environmental monitoring further includes the liquid level sensor for being arranged on each catch pit of piping lane with equipment monitoring system, when the liquid level When the liquid level that sensor measures catch pit is higher than peak level, alarm signal is sent;Each catchment is arranged in addition, further including The temperature sensor in hole, when the fluid temperature that the temperature sensor measurement goes out catch pit is higher than preset temperature, sends alarm signal Number.
Fan valve executor of the system including setting at piping lane air outlet, exhaust outlet is, it can be achieved that real by management platform 10 Existing remote opening, close air-valve;Meanwhile air-valve open and-shut mode is fed back to management platform 10 by fan valve executor, in order to piping lane Administrative staff confirm the state of air-valve.
The pressure fan that the system includes the combustion gas cabin of piping lane, the air outlet in the cabin containing sewage is set, the row in all cabins Air port is respectively provided with exhaust blower, which can be realized by management platform 10 send, the remote opening of exhaust blower, close, while can be with Feedback is sent, the operating status of exhaust blower.
The methane that the system is included in the ventilating opening (including air outlet and exhaust outlet) in piping lane combustion gas cabin, escaping exit is set Sensor, realizes the monitoring to concentration of natural gas in cabin;Ventilating opening, escaping exit in cabin of the pipe gallery containing sewage conduct The hydrogen sulfide sensor of setting, realizes the monitoring to concentration of hydrogen sulfide in cabin;In the disengaging piping lane of pipe gallery pressure pipeline Place is provided with the valve with long-range opening and closing function, it can be achieved that monitoring to valve.
In addition, the environmental monitoring is connected with equipment monitoring system and video monitoring system, when pressure fan or exhaust blower are sent out During raw failure, environmental monitoring finds fault-signal with equipment monitoring system, and 10 automatic linkage video monitoring system of management platform, cuts The camera of respective regions is changed to, and picture is automatically switched on the display interface of management platform, so as to the of staff One time found, handles.
Video monitoring system, is pure digi-tal monitoring system, for being monitored in real time to piping lane, and passes through convergence switch And core switch network transfers data to management platform 10.The video monitoring system is included in each fire compartment of piping lane At least 1 set of monitoring device set, the monitoring device include being separately positioned on first video camera and second at fire compartment both ends Video camera.
Wherein, video monitoring system includes some IO stations, and each IO stations are used to connect different equipment, description herein In, by be correspondingly arranged two video cameras, the video camera close to IO stations is defined as near end camera, the video camera away from IO stations It is defined as Remote Camera;The first video camera is defined as near end camera, the second video camera is defined as Remote Camera.Take the photograph The type of camera can select wide infrared gun type camera, in use, be arranged on two of each fire compartment both ends Video camera is formed to penetrating, and the clipping room between video camera is away from can be according to actual pipe less than or equal to 100m, specific mounting distance The specific installation of corridor is accordingly set.
The video monitoring system further includes the Power over Ethernet interchanger being connected with core switch, and the first video camera uses Power over Ethernet power supply for exchange, the second video camera and other equipment are without the Power over Ethernet power supply for exchange, during use Cut-in convergent interchanger;Since the first video camera is defined as the video camera close to the IO stations of video monitoring system, i.e. near-end images Machine, by the way that near end camera is used Power over Ethernet power supply for exchange, wiring distance is shorter, can save installation cost.The Two video cameras, i.e. Remote Camera can select optical fiber interface, and electric signal, cut-in convergent are converted into after passing optical signal back IO stations Interchanger.
The use process of the video monitoring system:In the picture signal of all camera acquisitions of the system is stood by I/O Convergence switch network be collected to management platform;Wherein, management platform and core switch are arranged on monitoring center.Supervising Control center is respectively configured disk array and image is stored, and disk array is directly accessed the pipe of monitoring center by gigabit network interface Corridor core switch.Monitoring center is managed local image by management platform, is managed in addition, being set in monitoring center Platform, splice displaying system server, DLP mosaic screens carry out supervision to vision signal and show.Wherein, the storage time of video It can be configured according to the size of disk array;For example, in video monitoring system the storage time of video be arranged to according to Record a video 30 days when 720P image quality 24 is small.
Intrusion alarm system, for alarming when unauthorized personnel invades piping lane.The system is in piping lane total length model In enclosing, at ventilating opening, escaping exit, the first detector is set;As a kind of optional embodiment of the present embodiment, first spy Survey device is dual technology detector.Dual technology detector is measured using two kinds of different technical principles, and measurement accuracy is higher.Specifically make Used time, when exterior unauthorized personnel invades piping lane, dual technology detector sends alarm signal and sends to management platform;Meanwhile should System links with video monitoring system, for when unauthorized personnel invades piping lane, video monitoring system to be switched to intrusion region Monitoring device, and monitored picture is sent to management platform, recognized in time easy to the piping lane operating personnel in monitoring center Which invaded in region someone, to take corresponding measure.
The system sets the second detector at the hoisting port in piping lane length range.One kind as the present embodiment can Embodiment is selected, which is infrared palisade detector.The measurement range of infrared palisade detector is larger, suitable for opening The larger hoisting port of mouth bore.When exterior irrelevant personnel invades underground pipe gallery, infrared palisade detector sends a signal to management Platform.Administrative staff in monitoring center recognize in time to invade in which region someone, to take corresponding measure.
Intrusion alarm system, for alarming when unauthorized personnel invades piping lane;Link with video monitoring system, For when unauthorized personnel invades piping lane, video monitoring system to be switched to the monitoring device in intrusion region, and by monitored picture Send to management platform 10.
As a kind of optional embodiment of the present embodiment, the system monitoring center and IO exits using card reader, open Door button mode;To ensure safety at transregional fence, fire resistant doorsets both sides are disposed as card reader, it is necessary to enabling of swiping the card.At the same time There are personnel to authorize respectively gate inhibition's clamping during management, lack of competence card can not open the door.
Access control system, is arranged at monitoring center, IO exits and transregional fence, the control for the piping lane that comes in and goes out.Using During, access control system is connected with environmental monitoring and equipment monitoring system, at night, when thering are personnel to swipe the card in certain region or When person someone opens door lock by force, the linkage environmental monitoring of management platform 10 opens respective regions illumination with equipment monitoring system.
Wherein, access control system is connected with video monitoring system, when thering are personnel to swipe the card in certain region or someone by force When opening door lock, management platform automatic linkage video monitoring system, is switched to respective regions camera, and picture is automatically switched Onto the display interface of monitoring center, so as to time discovery, the processing of staff.
Patrol system, is arranged to off-line type electronic patrol system, sets patrol point along piping lane, patrolman passes through detector Each cabin of piping lane is pinpointed and is patrolled, is carried out after inspection by patrol system management software in monitoring center centralized Control platform Record, arrange and print.
Energy Consumed Statistic System, using fire compartment as collecting unit, the collection for piping lane gut line data is measured, pipeline Including water, electricity, gas and heat.Teletransmission multifunctional meter is set in each collecting unit, Energy Consumed Statistic System will by data collector The data of teletransmission multifunctional meter collection pass monitoring center back, there is provided Data Analysis Services.
Pipe gallery management system further includes:Convergence switch, for converging the number that IO stands in each live layer subsystem According to, and it is sent to core switch;Core switch, for being converged to the data of convergence switch, and is sent to management Platform 10.
It is used to connect each live layer subsystem in the pipe gallery management system and the network system of management platform uses 2 layers Ring network framework, every road set 2 convergences to exchange as 1 sub-regions, every road according to the suitable IO stations of geographical location choice Machine, is responsible for the convergent point at all IO stations in this road;According to above principle, the embodiment of the present invention sets several convergent points altogether, often A convergent point is equally connected using looped network form with monitoring center piping lane core switch, and piping lane core switch equally sets 2 Platform, forms double-core dual link with above-mentioned convergence switch and configures, meet system stability requirement.
The course of work of the pipe gallery management system is as follows:Each scene layer subsystem, carries out real time information to piping lane and adopts Collection and management;Each scene layer subsystem is stood including some IO, and the data at IO stations are converged by convergence switch;Each convergence The result of convergence is sent to core switch by interchanger, after core switch is converged all field layer subsystem datas It is sent to management platform 10;Management platform 10, for receiving the data of each live layer subsystem, feeds back after handling data To corresponding live layer subsystem;Live layer subsystem is operated accordingly according to handling result.
The data of each scene layer subsystem carry out convergence by convergence switch, and each convergence switch is handed over by core Change planes the data sending of each live layer subsystem to management platform, by the convergence switch and core that set layering setting Interchanger, it is possible to increase the transmission rate of data, and convergence switch is provided with abundant interface, easy to live layer subsystem Extension, it is portable higher without changing data transfer mode.
Pipe gallery management system has necessarily compatible and open, to realize the integrated of subsystems.This is The supported interface protocol of system should be including but not limited to following interface protocol:BACnet、OPC、Modbus、Lonworks、MBus、 OBix etc., meanwhile, the secondary development of supporting interface, supports the reference format of data to export, comprising OBix, BACnet, OPC, Modbus etc.;In view of the security of the system, 50 users, 50 kinds of authorities are at least supported;Support SSL, HTTPS, strong cipher Strategy, supports self-defined network encryption, supports data store encryption;Support a variety of relevant databases (MySQL SQLServer Oracle DB2), have embedded database to real time data;The system supports unlimited user, any mark at the same time The data of quasi- browser real time access system, and can check its historical data;With good opening, open interface is to the later stage Each operation management unit, to realize the real-time monitoring to pipe gallery internal environment.
As a kind of optional embodiment of the present embodiment, physical communication interface such as table used in each scene layer subsystem Shown in 1:
Each live layer subsystem physical communication interface of table 1
Pipe gallery management system provided by the invention, is taken management platform by way of live layer subsystem is combined Build, i.e., the system is combined using software with hardware, and live layer subsystem (hardware components) is used to gathering and transmitting variety classes Piping lane information;Management platform (software section) is used to receive piping lane information, and piping lane information is handled, by handling result Feed back to corresponding live layer subsystem;The result that live layer subsystem is handled according to management platform is operated accordingly.Should Pipe gallery management system, can realize the collection of a variety of piping lane information, feature-rich;Pass through management platform and each live straton Real-time communication between system, work efficiency is higher, has the ability of emergency processing;Using management platform realize unified management with Control so that the operation management of the system is simple, easy to operate.
Obviously, the above embodiments are merely examples for clarifying the description, and the restriction not to embodiment.It is right For those of ordinary skill in the art, can also make on the basis of the above description it is other it is various forms of change or Change.There is no necessity and possibility to exhaust all the enbodiments.And the obvious change thus extended out or Among changing still in the protection domain of the invention.

Claims (10)

  1. A kind of 1. pipe gallery management system, it is characterised in that including:
    Various field layer subsystem, for gathering and transmitting different types of piping lane information;
    Management platform, handles for receiving the piping lane information, and to the piping lane information, handling result is fed back to phase The live layer subsystem answered;The scene layer subsystem is operated accordingly according to the handling result.
  2. 2. pipe gallery management system according to claim 1, it is characterised in that the scene layer subsystem includes:Fire Calamity automatic alarm system, environmental monitoring and equipment monitoring system, video monitoring system, intrusion alarm system, access control system, night watching System and Energy Consumed Statistic System;
    The automatic fire alarm system, for sending fire signal to the management platform;Link, use with the access control system In the door when fire occurs near the access control system opening fire;
    The environmental monitoring and equipment monitoring system, for environmental parameter in piping lane and equipment to be monitored and alarmed;With The video monitoring system linkage, for when monitoring device fails in piping lane, the video monitoring system to be switched to The equipment of fault zone, and monitored picture is sent to the management platform;The environmental parameter includes temperature, humidity, oxygen Content, hydrogen sulfide content and methane content;
    The video monitoring system, for being monitored in real time to piping lane;
    The intrusion alarm system, for alarming when unauthorized personnel invades piping lane;With the video monitoring system Linkage, for when unauthorized personnel invades piping lane, the video monitoring system to be switched to the monitoring device in intrusion region, and will Monitored picture is sent to the management platform;
    The access control system, the control for the piping lane that comes in and goes out;
    The patrol system, is off-line type electronic patrol system;
    The Energy Consumed Statistic System, the collection for piping lane gut line data are measured;The pipeline includes water, electricity, gas and heat.
  3. 3. pipe gallery management system according to claim 2, it is characterised in that the management platform and exterior geographical letter Breath system connects, the piping lane geography information sent for receiving the exterior GIS-Geographic Information System.
  4. 4. pipe gallery management system according to claim 3, it is characterised in that the automatic fire alarm system according to The piping lane GIS-Geographic Information System positions fire location.
  5. 5. pipe gallery management system according to claim 2, it is characterised in that the environmental monitoring and monitoring of tools system System includes:
    At least 2 sets of sensors of piping lane fire compartment are arranged on, for measurement temperature, humidity or oxygen content;
    First alarm unit, for sending alarm signal according to the measurement result of the sensor.
  6. 6. pipe gallery management system according to claim 2, it is characterised in that the environmental monitoring and monitoring of tools system System includes:
    At least two kinds of sensors of piping lane catch pit are arranged on, for measuring level value or water temperature value;
    Second alarm unit, for sending alarm signal according to the measurement result of the sensor.
  7. 7. pipe gallery management system according to claim 2, it is characterised in that the video monitoring system is included in pipe At least 1 set of monitoring device that each fire compartment in corridor is set, the monitoring device include being separately positioned on the fire compartment two First video camera and the second video camera at end;The video monitoring system is used to be sent to the monitored results of the monitoring device The management platform.
  8. 8. pipe gallery management system according to claim 7, it is characterised in that the pipe gallery management system is also wrapped Include:
    Convergence switch, for converging the data that IO stands in each live layer subsystem, and is sent to core switch;
    The core switch, for converging the data of the convergence switch, and is sent to the management platform;
    The video monitoring system includes the Power over Ethernet interchanger being connected with the core switch, first video camera It is connected with the too net power supplying switch, second video camera is connected with the convergence switch.
  9. 9. pipe gallery management system according to claim 8, it is characterised in that each live layer subsystem is set 2 convergence switches, the pipe gallery management system set 2 core switch, and the convergence switch is adopted It is connected with looped network form with the core switch.
  10. 10. pipe gallery management system according to claim 2, it is characterised in that the intrusion alarm system includes setting The first detector at piping lane ventilating opening and escaping exit is put, the second detector being arranged at hoisting port;The invasion report Alert system is used to first detector and second detector result of detection is sent to the management platform.
CN201710965522.9A 2017-10-17 2017-10-17 Pipe gallery management system Pending CN107942959A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710965522.9A CN107942959A (en) 2017-10-17 2017-10-17 Pipe gallery management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710965522.9A CN107942959A (en) 2017-10-17 2017-10-17 Pipe gallery management system

Publications (1)

Publication Number Publication Date
CN107942959A true CN107942959A (en) 2018-04-20

Family

ID=61935396

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710965522.9A Pending CN107942959A (en) 2017-10-17 2017-10-17 Pipe gallery management system

Country Status (1)

Country Link
CN (1) CN107942959A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108985541A (en) * 2018-05-03 2018-12-11 安华智能股份公司 A kind of comprehensive wisdom operation management system of underground pipe gallery
CN109270878A (en) * 2018-12-11 2019-01-25 天水电气传动研究所有限责任公司 Underground pipe gallery environmental monitoring and draft fan control system
CN109283903A (en) * 2018-10-26 2019-01-29 中交第航务工程局有限公司 A kind of underground pipe gallery intelligence control system and its control method based on Internet of Things
CN109298740A (en) * 2018-10-25 2019-02-01 中冶京诚工程技术有限公司 Piping lane control cabinet and piping lane control system
CN109635380A (en) * 2018-11-27 2019-04-16 华南理工大学 A kind of piping lane electric compartment fire barriers and current-carrying capacity of cable quantitative relationship determine method
CN109706963A (en) * 2019-01-21 2019-05-03 海门市帕源路桥建设有限公司 The installation of piping lane box type telescopic internal model, unloading, conveying intelligent platform
CN110158648A (en) * 2019-05-29 2019-08-23 青岛市政空间开发集团有限责任公司 A kind of Urban Underground pipe gallery O&M monitoring management system
CN110187665A (en) * 2018-07-02 2019-08-30 青岛华高物联网科技有限公司 A kind of intelligent managing and control system of underground pipe gallery
CN110187666A (en) * 2018-07-02 2019-08-30 青岛华高物联网科技有限公司 A kind of underground pipe gallery environmental unit operation monitoring system
CN110188900A (en) * 2018-07-02 2019-08-30 青岛华高物联网科技有限公司 A kind of underground pipe gallery hand-portable information managing and control system
CN110673535A (en) * 2019-11-01 2020-01-10 杨国忠 Piping lane disaster prevention intelligent control system
CN111879355A (en) * 2020-07-01 2020-11-03 四川旷谷信息工程有限公司 Comprehensive pipe gallery health degree parameter measuring method
CN112437130A (en) * 2020-11-11 2021-03-02 上海电器科学研究所(集团)有限公司 City underground pipe gallery business function system based on little service
CN112907511A (en) * 2021-01-15 2021-06-04 广州市新誉工程咨询有限公司 Comprehensive pipe rack information management method and system under BIM technology
CN111314671B (en) * 2020-03-19 2021-11-02 哈工大(张家口)工业技术研究院 Underground pipe gallery personnel positioning method
CN114783126A (en) * 2022-04-22 2022-07-22 中煤科工集团重庆智慧城市科技研究院有限公司 Illegal intrusion control management system for tunnel pipe gallery

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110097143A (en) * 2010-02-24 2011-08-31 한국철도기술연구원 The intelligent surveillance system configuration plan in urban railroad environment
CN105762930A (en) * 2015-06-30 2016-07-13 巫立斌 Power management networking system
CN106097642A (en) * 2016-08-19 2016-11-09 徐州江煤科技有限公司 A kind of city integrated piping lane intelligent monitoring and alarm device
CN106094690A (en) * 2016-07-27 2016-11-09 浙江警安科技有限公司 City piping lane comprehensive monitoring system and monitoring method thereof
CN205875205U (en) * 2016-06-23 2017-01-11 史晓祎 Digit utility tunnel system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110097143A (en) * 2010-02-24 2011-08-31 한국철도기술연구원 The intelligent surveillance system configuration plan in urban railroad environment
CN105762930A (en) * 2015-06-30 2016-07-13 巫立斌 Power management networking system
CN205875205U (en) * 2016-06-23 2017-01-11 史晓祎 Digit utility tunnel system
CN106094690A (en) * 2016-07-27 2016-11-09 浙江警安科技有限公司 City piping lane comprehensive monitoring system and monitoring method thereof
CN106097642A (en) * 2016-08-19 2016-11-09 徐州江煤科技有限公司 A kind of city integrated piping lane intelligent monitoring and alarm device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《水利信息化新技术及应用》编委会: "《水利信息化新技术及应用》", 31 July 2013 *
陈林 等: "《互联网+智慧校园技术与工程实施》", 30 September 2017, 电子科技大学出版社 *

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108985541A (en) * 2018-05-03 2018-12-11 安华智能股份公司 A kind of comprehensive wisdom operation management system of underground pipe gallery
CN110187665A (en) * 2018-07-02 2019-08-30 青岛华高物联网科技有限公司 A kind of intelligent managing and control system of underground pipe gallery
CN110188900A (en) * 2018-07-02 2019-08-30 青岛华高物联网科技有限公司 A kind of underground pipe gallery hand-portable information managing and control system
CN110187666A (en) * 2018-07-02 2019-08-30 青岛华高物联网科技有限公司 A kind of underground pipe gallery environmental unit operation monitoring system
CN109298740A (en) * 2018-10-25 2019-02-01 中冶京诚工程技术有限公司 Piping lane control cabinet and piping lane control system
CN109283903A (en) * 2018-10-26 2019-01-29 中交第航务工程局有限公司 A kind of underground pipe gallery intelligence control system and its control method based on Internet of Things
CN109635380A (en) * 2018-11-27 2019-04-16 华南理工大学 A kind of piping lane electric compartment fire barriers and current-carrying capacity of cable quantitative relationship determine method
CN109635380B (en) * 2018-11-27 2021-03-30 华南理工大学 Method for determining quantitative relation between fireproof interval of pipe gallery power cabin and current-carrying capacity of cable
CN109270878A (en) * 2018-12-11 2019-01-25 天水电气传动研究所有限责任公司 Underground pipe gallery environmental monitoring and draft fan control system
CN109706963A (en) * 2019-01-21 2019-05-03 海门市帕源路桥建设有限公司 The installation of piping lane box type telescopic internal model, unloading, conveying intelligent platform
CN110158648A (en) * 2019-05-29 2019-08-23 青岛市政空间开发集团有限责任公司 A kind of Urban Underground pipe gallery O&M monitoring management system
CN110673535A (en) * 2019-11-01 2020-01-10 杨国忠 Piping lane disaster prevention intelligent control system
CN111314671B (en) * 2020-03-19 2021-11-02 哈工大(张家口)工业技术研究院 Underground pipe gallery personnel positioning method
CN111879355A (en) * 2020-07-01 2020-11-03 四川旷谷信息工程有限公司 Comprehensive pipe gallery health degree parameter measuring method
CN112437130A (en) * 2020-11-11 2021-03-02 上海电器科学研究所(集团)有限公司 City underground pipe gallery business function system based on little service
CN112907511A (en) * 2021-01-15 2021-06-04 广州市新誉工程咨询有限公司 Comprehensive pipe rack information management method and system under BIM technology
CN112907511B (en) * 2021-01-15 2024-01-23 广州市新誉工程咨询有限公司 Comprehensive pipe gallery information management method and system under BIM technology
CN114783126A (en) * 2022-04-22 2022-07-22 中煤科工集团重庆智慧城市科技研究院有限公司 Illegal intrusion control management system for tunnel pipe gallery
CN114783126B (en) * 2022-04-22 2024-04-12 中煤科工集团重庆智慧城市科技研究院有限公司 Illegal intrusion control management system for tunnel pipe gallery

Similar Documents

Publication Publication Date Title
CN107942959A (en) Pipe gallery management system
CN110707810B (en) Auxiliary comprehensive monitoring system for transformer substation
CN111107675B (en) Cable channel edge Internet of things terminal and method based on ubiquitous power Internet of things
CN106097642B (en) A kind of city integrated piping lane intelligent monitoring and warning device
CN107991999A (en) Power cable tunnel comprehensive monitoring system and method
CN104052151B (en) Intelligent substation aided synthesis is monitored and D5000 cooler interlock platforms
CN108508831A (en) A kind of intelligent managing and control system of underground pipe gallery
CN110187666A (en) A kind of underground pipe gallery environmental unit operation monitoring system
CN107632581A (en) A kind of monitoring management system of underground pipe gallery
CN107333113A (en) A kind of pipe gallery wireless supervisory control system
CN109841044A (en) A kind of wisdom fire-fighting remote monitoring system
CN106200526A (en) Pipe gallery online monitoring system and monitoring method thereof
CN209218140U (en) A kind of city fire-fighting remote monitoring management system based on Internet of Things
CN102566519A (en) Setting method for power tunnel monitoring system
CN106208395A (en) Unattended substation is met an urgent need monitoring system
CN107015548A (en) Archive office's intelligent environment detecting and controlling system
CN213690892U (en) Utility tunnel intelligent monitoring and operation and maintenance system
CN205920375U (en) City piping lane automatic fire extinguishing system
CN106525138A (en) Electric power tunnel monitoring management method and management system thereof
CN111145482A (en) Fire control command control system
CN108375962A (en) Offshore boosting station patrols control system
CN110197567A (en) A kind of inspection well cover monitoring system
CN211015113U (en) Intelligent type pipe control system for underground comprehensive pipe gallery
CN205920360U (en) Online monitored control system of utility tunnel
CN207182049U (en) A kind of heat exchange station intelligent measurement and control system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: Shinan District 266003 Shandong city of Qingdao province Liujiaxia Road No. 17

Applicant after: Qingdao Power Supply Company, State Grid Shandong Electric Power Company

Applicant after: State Grid Co., Ltd.

Address before: Shinan District 266003 Shandong city of Qingdao province Liujiaxia Road No. 17

Applicant before: Qingdao Power Supply Company, State Grid Shandong Electric Power Company

Applicant before: State Grid Corporation

CB02 Change of applicant information
RJ01 Rejection of invention patent application after publication

Application publication date: 20180420

RJ01 Rejection of invention patent application after publication