A kind of power distribution automation adjustment method on the spot based on simulation main website
Technical field
The present invention relates to telecontrol information in distribution automation system to gather field, be international standard IEC61850 distribution from
A kind of application in dynamicization field.
Background technology
With the digitizing of power distribution network, information-based, automation, interactive and intelligentized development, to the distant of distribution terminal
The requirement for the efficiency that control, remote measurement, the standardization of remote signalling " three is distant " information, distribution terminal are debugged is higher and higher.Terminal and reality at present
The laying of communication equipment takes a long time between the operation main website of border, and the debugging to distribution terminal brings very big unfavorable.At present
When carrying out power distribution automation and debugging on the spot, it is necessary to keep communicating with main website, need, by terminal commissioning staff, also to need one at the scene
People is coordinated in actual motion main website, in communications facility when breaking down, be able to not will be got in touch with main website, is caused existing
Field debugging can not be normally carried out, and cause the significant wastage of personnel and time.
(1) data sent on distribution terminal will have clear and definite implication, and different terminal equipment manufacturer formulates a unified mark
Table masterplate and automatic generation method on schedule;
(2) distribution terminal equipment needs to have self-described function and unified interface specification;
(3) effectively power distribution automation quickly access with joint debugging, acceptance method, ensure the practical of distribution system;
(4) the terminal device field adjustable flow of standard, automatically generates terminal debugging report, can promptly and accurately exclude existing
Field failure;
(5) security, reliability, the requirement of stability are reached.
In traditional power distribution automation is debugged on the spot, distribution terminal (ring main unit DTU, on-pole switch FTU etc.) information
Specification access distribution main website needs end side personnel manually to carry out the examination and submission of three distant table signals, then is safeguarded by main website
Personnel with the information that terminal commissioning staff provides point by point check examination.Transmission test between distribution terminal and distribution main website
By be accomplished manually, terminal and the remote debugging efforts efficiency of main website it is low, field basic debugging to communication dependence it is big, be unfavorable for
The Large scale construction of electrical power distribution automatization system and popularization and application.Remote signalling, remote measurement, remote controlled point table are transmitted by manual type, then
By the mode of information point table input database, there are relevance between the indefinite and various data of data implication is not strong manually for main website
The problem of.The joint debugging of distribution end access at present external environment restriction, joint debugging heavy workload, the scene such as communicated needs power off time to grow
Etc. problem.
The present invention is carried with easy to commissioning staff by designing a kind of simulation main website for depositing in laptop,
When carrying out power distribution automation and debugging on the spot, it is complete to be not required to the communication equipment laying of terminal and actual motion main website, can carry out
Full process automatization is debugged, and multiple terminals that current actual motion main website faces while the coordination difficulty of access is reduced, according to existing
Field debugging situation, debugging report can be read by automatically generating, and improve debugging efficiency.
The content of the invention
Goal of the invention:The meaning that simulation main website can be carried is to solve live distribution power automation terminal and does not possess and main website
The contradiction that can not be debugged during communication, is not required to keep communicating freely with terminal commissioning staff's moment when main website maintenance personnel debugs at the scene
It is logical, improve commissioning staff's efficiency.Meanwhile simulation main website can solve distribution power automation terminal operation and maintenance information point table before putting into operation and advise
Generalized and the difficulty issued automatically, in debugging at the scene, establish the debugging of standard and check and accept system, can be in time by simulating main website
The debugging report of generation finds field failure, such as order of connection problem, crosses flow problem etc..Simulation main station system possesses specified
The inputting interface of overcurrent value so that the adaptability of field adjustable is stronger.Debugging, which is carried out, using simulation main website avoids multiple terminals
The problem of accessing at the same time.
Technical solution:In order to solve the above technical problems, the technical solution adopted by the present invention is:Invention is a kind of based on simulation master
Stand and debug the distribution terminal information method that quick joint debugging is automatically accessed with overall process on the spot of subsystem, carry out power distribution automation
Debug on the spot.
(1) mold sync and the figure for simulating main website are synchronous.The model of actual motion main website and graphic file are synchronized to
Simulate in main website, synchronizing content includes distribution terminal information, passage and stipulations etc.;In debugging at the scene, simulation main website receives
After data message, compare the information such as channel number, IP address, the network port, the state that puts into operation, if the letter synchronous with actual motion main website
Manner of breathing is consistent, then returns to confirmation message, if inconsistent with synchronizing information, in the instant debugging report of simulation main website generation into
Row feedback.
(2) terminal commissioning staff can learn the accuracy of " three is distant " data by way of secure accessing platform;
(3) debugging on the spot for distribution terminal is realized by way of debugging process standardization, including different interval data
On send order, telemetry and overcurrent overload alarm signal;
Hardware layer explanation:The domestic mainstream server of D5200 (power distribution network train operation control and management system) is installed, for scene
The wireless module or cable that commissioning staff uses.Operating system layer:(SuSE) Linux OS, up to dream database.D5200 systems can
Directly apply to the quick of power distribution automation to debug on the spot, realize automatic decision wiring line sequence, protection remote measurement matching, it is final automatic
Generation debugging report.
Brief description of the drawings
Fig. 1 carries out power distribution automation using simulation main website and debugs schematic diagram on the spot;
Fig. 2 simulations main website mold sync flow chart.
Embodiment
The present invention is further described with reference to specific embodiment.
(1) on the premise of distribution terminal is installed in place at the scene, carrying out scene using simulation main website, debugging can be put on the spot
The de- dependence to communication, realize terminal on the spot quickly with main website joint debugging.Simulation main website debugging system is debugged using subsystem is debugged
States model, automatic point table generation technique, with actual motion main website simultaneous techniques, realize that power distribution automation simulation main station system is preposition
Collection and real time data processing.The debugging enironment completely the same with operation main website, verification " three are realized at the scene by simulating main website
It is distant ", terminal configuration parameters, the correctness of stipulations configuration etc., ensure it is consistent with main website end acceptance criteria, flow, realize distribution oneself
Dynamicization is quickly debugged on the spot;
(2) deployment simulation main station system debugging system, distribution terminal information full mistake of the deployment based on power distribution automation main station
Process automation access function module, actual motion main website is according to each self-generating model of result of the information exchange sent in terminal producer
Configuration file, then actual motion main website is according to the database of distribution terminal self-described fileinfo renewal main station system, formulation
Based on " it is three distant " standard point table, and then mold sync carried out by distribution main website management tool exp_man, passes through Graph texts
Part figure is synchronized to simulation main website.When debugging on the spot at the scene, distribution terminal commissioning staff can lead according to field condition with simulation
Information in standing is checked;
(3) required standard power distribution automation debugs flow on the spot, and the order of data is sent in unified field adjustable wiring, from
And ensure the correctness of field connection line sequence.According to field condition, the rated value of input overcurrent overload in simulation main website, from
It is dynamic to judge whether overcurrent Overload, CT (current transformer) equipment work normally and overcurrent overload announcement
Whether alert signal can normally send;
(4) method by automating generation terminal debugging report, debugs reporting requirements with reference to on-site terminal, automatically generates
Terminal debugging result is reported, all failures that distribution terminal is likely to occur in debugging process on the spot, such as wiring are shown in report
Sequence error, alarm signal can not generate, current transformer accuracy is sub-standard, switch changed position and remote signals be not immediately right
The problems such as answering.Reiterate to standardize herein and debug the importance of flow, sent in debugging process in remote signals and telemetry
The deviation for sequentially and on defined sending order to produce, can displaying scene wiring error in the debugging report of generation;
Each one of use site main flow terminal any producer's distribution terminal such as FTU, DTU, foundation meet project distribution end
Hold joint debugging, acceptance criteria system, for the overall process with regard to the quick joint debugging test of system of simulation main website and power distribution automation main station
Quickly access.During inspection, semaphore, change debugging dosage order, conversion terminal protection definite value etc. are sent by changing on FTU, DTU
Disturbing factor verification simulation main website carries out the reliability of power distribution automation adjustment method on the spot.