CN107915159A - A kind of Crane Jib Structure - Google Patents

A kind of Crane Jib Structure Download PDF

Info

Publication number
CN107915159A
CN107915159A CN201711310069.4A CN201711310069A CN107915159A CN 107915159 A CN107915159 A CN 107915159A CN 201711310069 A CN201711310069 A CN 201711310069A CN 107915159 A CN107915159 A CN 107915159A
Authority
CN
China
Prior art keywords
arm
hinged
setting
tower arm
amplitude
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711310069.4A
Other languages
Chinese (zh)
Inventor
陈志灿
赵瑞学
贾体锋
谷思生
张平海
陈栋梁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Heavy Machinery Co Ltd
Original Assignee
Xuzhou Heavy Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou Heavy Machinery Co Ltd filed Critical Xuzhou Heavy Machinery Co Ltd
Priority to CN201711310069.4A priority Critical patent/CN107915159A/en
Publication of CN107915159A publication Critical patent/CN107915159A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/64Jibs
    • B66C23/70Jibs constructed of sections adapted to be assembled to form jibs or various lengths
    • B66C23/701Jibs constructed of sections adapted to be assembled to form jibs or various lengths telescopic
    • B66C23/705Jibs constructed of sections adapted to be assembled to form jibs or various lengths telescopic telescoped by hydraulic jacks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/64Jibs
    • B66C23/70Jibs constructed of sections adapted to be assembled to form jibs or various lengths
    • B66C23/701Jibs constructed of sections adapted to be assembled to form jibs or various lengths telescopic
    • B66C23/702Jibs constructed of sections adapted to be assembled to form jibs or various lengths telescopic with a jib extension boom
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/82Luffing gear
    • B66C23/821Bracing equipment for booms
    • B66C23/823Bracing equipment acting in vertical direction

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

The present invention announces a kind of Crane Jib Structure, belongs to crane technical field.Including car body and the flexible principal arm being hinged on rear side of car body;Amplitude oil cylinder I is hinged between the leading flank and car body of the flexible principal arm lower part first segment;The leading flank of flexible principal arm lower part first segment is also hinged with setting-up, and setting-up amplitude oil cylinder II is hinged between setting-up and flexible principal arm lower part first segment;The flexible principal arm upper end is hinged with tower arm;Tower arm stent is hinged with front side of the tower arm, tilting-preventing rod is connected between the tower arm stent and tower arm;Elevator is installed in the setting-up;Variable-amplitude steel wire rope is connected with the car body;After the variable-amplitude steel wire rope other end bypasses setting-up outer end, tower arm stent outer end successively, it is connected on elevator.Folding jib structure, dismounting variable-amplitude auxiliary arm, the variable-amplitude auxiliary arm that rises and falls are eliminated during transition, suspension hook is dismounted, connects steel wire rope and assistant conveyance vehicle, transition cost is greatly reduced, improves transition efficiency.

Description

A kind of Crane Jib Structure
Technical field
The present invention relates to crane technical field, is specifically a kind of Crane Jib Structure.
Background technology
With the intensified competition in crane hanging component market, super-tonnage crane is straight in general lifting marketing profit Line glides, and the main profit field of country's super-tonnage crane lifting work at present concentrates on wind-powered electricity generation installation and maintenance market.Wind Electric installation and maintenance market is no longer a wide range of, significantly field overall performance advantage for the demand of crane, but is concentrated The requirement of lift heavy amount when larger for lifting altitude, and more focus on convenience, the economy of transition and dismounting.
For at present, a Fans are after installation is complete, during crane transition, because crane is from great, brachium length, vehicle Center of gravity is uneven, it is necessary to variable-amplitude auxiliary arm combination in front is dismantled, and is re-assemblied again to next Fans lifting scene, during also Need to dismount suspension hook, connect steel wire rope and lift arm, whole disassembly process need 4 to 5 it is small when, undoubtedly consume time and people Power, while detaching structure needs to aid in vehicle to be transported, and adds transition cost.
The content of the invention
In order to improve the convenience that dismounting uses, transition cost is reduced, the present invention provides a kind of component when reducing transition Quantity is dismounted, easy to the Crane Jib Structure for assembling and transporting.
The present invention is achieved through the following technical solutions:A kind of Crane Jib Structure, including car body and after being hinged on car body The flexible principal arm of side;Amplitude oil cylinder I is hinged between the leading flank and car body of the flexible principal arm lower part first segment;Flexible principal arm The leading flank of lower part first segment is also hinged with setting-up, and setting-up luffing oil is hinged between setting-up and flexible principal arm lower part first segment Cylinder II;The flexible principal arm upper end is hinged with tower arm;Tower arm stent is hinged with front side of the tower arm, the tower arm stent with Tilting-preventing rod is connected between tower arm;Elevator is installed in the setting-up;Variable-amplitude steel wire rope is connected with the car body;The change After the width steel wire rope other end bypasses setting-up outer end, tower arm stent outer end successively, it is connected on elevator.
Preferably:The setting-up amplitude oil cylinder II is located at the upside of amplitude oil cylinder I.
Preferably:The tower arm stent outer end is connected with hanging wheel;The variable-amplitude steel wire rope is wound on hanging for tower arm stent outer end On wheel.
Preferably:Described tilting-preventing rod one end is detachably connected with tower arm stent, and the tilting-preventing rod other end is hinged with tower arm.
Compared with prior art, the beneficial effects of the invention are as follows:Folding jib structure, eliminates during transition Dismounting variable-amplitude auxiliary arm, the variable-amplitude auxiliary arm that rises and falls, dismount suspension hook, connect steel wire rope and assistant conveyance vehicle, greatly reduces transition Cost, improves transition efficiency.
Brief description of the drawings
Fig. 1 is job state structure diagram of the present invention;
Fig. 2 be flexible principal arm it is full reduced after structure diagram;
Fig. 3 is the structure diagram fallen after tower arm, tower arm stent;
Fig. 4 is the structure diagram after setting-up, setting-up amplitude oil cylinder II are packed up;
Fig. 5 is that amplitude oil cylinder I is packed up, flexible principal arm lie prone it is flat, in the structure diagram of transition state.
In figure:1st, car body;2nd, stretch principal arm;3rd, amplitude oil cylinder I;4th, tower arm;5th, setting-up;6th, setting-up amplitude oil cylinder II;7、 Tower arm stent;7-1, hanging wheel;8th, tilting-preventing rod;9th, elevator;10th, variable-amplitude steel wire rope.
Embodiment
It is the specific embodiment of the present invention below, in conjunction with attached drawing, the present invention will be further described.
With reference to shown in Fig. 1, a kind of Crane Jib Structure, including car body 1 and the flexible principal arm 2 for being hinged on the rear side of car body 1; Amplitude oil cylinder I 3 is hinged between the leading flank and car body 1 of 2 lower part first segment of flexible principal arm, is stretched by amplitude oil cylinder I 3 to control The rotation and positioning of contracting principal arm 2.Setting-up 5 is also hinged with the leading flank of flexible 2 lower part first segment of principal arm, in setting-up 5 with stretching Setting-up amplitude oil cylinder II 6 is hinged between 2 lower part first segment of principal arm, come the rotation of setting-up 5 and is determined by setting-up amplitude oil cylinder II 6 Position.Flexible 2 upper end of principal arm is hinged with tower arm 4;The front side of tower arm 4 is hinged with tower arm stent 7, tower arm stent 7 and setting-up phase about 5 It is right.Tilting-preventing rod 8 is connected between tower arm stent 7 and tower arm 4;Tower arm 4 is held in the end of tower arm stent 7 by steel wire rope, Coordinate tilting-preventing rod 8 again to realize the support of tower arm 4 and positioning;8 one end of tilting-preventing rod is detachably connected with tower arm stent 7, is prevented 8 other end of hypsokinesis bar is hinged with tower arm 4, facilitates the dismounting of tower arm 4.Elevator 9, the connection of 7 outer end of tower arm stent are installed in setting-up 5 There is hanging wheel 7-1;10 one end of variable-amplitude steel wire rope is connected on car body 1, and 10 other end of width steel wire rope is successively around 5 outer end of setting-up, tower After the hanging wheel 7-1 of 7 outer end of arm support, it is connected on elevator 9.
The course of work:
As shown in Figure 1, it is job state schematic diagram of the present invention;
As shown in Fig. 2, when starting to remove, flexible principal arm is slowly retracted, while elevator packs up variable-amplitude steel wire rope, keeps tower arm stent It is parallel with setting-up, maintain the stabilization of tower arm;Until flexible principal arm is full reduced;
As shown in figure 3, elevator slowly loosens variable-amplitude steel wire rope, tower arm slowly tilts, and falls;Remove one end of tilting-preventing rod 8;
As shown in figure 4, setting-up amplitude oil cylinder II is retracted, setting-up is transferred;
As shown in figure 5, amplitude oil cylinder I is retracted, flexible principal arm is placed on car body, flexible principal arm lie prone it is flat, in transition state;
The installation process of the present invention is opposite with above-mentioned demolishing process.

Claims (4)

  1. A kind of 1. Crane Jib Structure, it is characterised in that:Including car body(1)Be hinged on car body(1)The flexible principal arm of rear side (2);The flexible principal arm(2)The leading flank and car body of lower part first segment(1)Between be hinged with amplitude oil cylinder I(3);Flexible principal arm (2)The leading flank of lower part first segment is also hinged with setting-up(5), in setting-up(5)With flexible principal arm(2)It is hinged between the first segment of lower part There is setting-up amplitude oil cylinder II(6);The flexible principal arm(2)Upper end is hinged with tower arm(4);The tower arm(4)Front side be hinged with Tower arm stent(7), in the tower arm stent(7)With tower arm(4)Between be connected with tilting-preventing rod(8);The setting-up(5)Upper installation There is elevator(9);The car body(1)On be connected with variable-amplitude steel wire rope(10);The variable-amplitude steel wire rope(10)The other end bypasses successively Setting-up(5)Outer end, tower arm stent(7)Behind outer end, elevator is connected to(9)On.
  2. A kind of 2. Crane Jib Structure according to claim 1, it is characterised in that:The setting-up amplitude oil cylinder II(6) Positioned at amplitude oil cylinder I(3)Upside.
  3. A kind of 3. Crane Jib Structure according to claim 1, it is characterised in that:The tower arm stent(7)Outer end connects It is connected to hanging wheel(7-1);The variable-amplitude steel wire rope(10)It is wound on tower arm stent(7)The hanging wheel of outer end(7-1)On.
  4. A kind of 4. Crane Jib Structure according to claim 1, it is characterised in that:The tilting-preventing rod(8)One end with Tower arm stent(7)It is detachably connected, tilting-preventing rod(8)The other end and tower arm(4)It is hinged.
CN201711310069.4A 2017-12-11 2017-12-11 A kind of Crane Jib Structure Pending CN107915159A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711310069.4A CN107915159A (en) 2017-12-11 2017-12-11 A kind of Crane Jib Structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711310069.4A CN107915159A (en) 2017-12-11 2017-12-11 A kind of Crane Jib Structure

Publications (1)

Publication Number Publication Date
CN107915159A true CN107915159A (en) 2018-04-17

Family

ID=61893186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711310069.4A Pending CN107915159A (en) 2017-12-11 2017-12-11 A kind of Crane Jib Structure

Country Status (1)

Country Link
CN (1) CN107915159A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108946529A (en) * 2018-09-26 2018-12-07 太原科技大学 Anti-squat system is played after preceding spademan drag-line is anti-
CN109353946A (en) * 2018-11-30 2019-02-19 太原重工股份有限公司 Multilayer tension system and crane
EP3793930B1 (en) * 2018-07-09 2022-10-05 Tadano Demag GmbH Support for the rear anchoring line of a telescopic crane

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101670986A (en) * 2009-09-28 2010-03-17 三一汽车制造有限公司 Hoisting system and mobile crane
CN102381639A (en) * 2010-09-06 2012-03-21 利勃海尔-韦尔克爱茵根有限公司 Crane
CN102583178A (en) * 2012-03-26 2012-07-18 上海三一科技有限公司 Main amplitude mast of crawler crane and crane comprising mast
CN102795557A (en) * 2012-09-03 2012-11-28 徐州重型机械有限公司 Crane
CN103030074A (en) * 2011-10-08 2013-04-10 易肃 Hinge points-variable combined type multi-functional crawler crane
CN103145054A (en) * 2013-03-20 2013-06-12 中联重科股份有限公司 Jib tail bracket as well as jib and hoisting equipment comprising same
CN107117542A (en) * 2017-06-30 2017-09-01 徐州重型机械有限公司 Crane

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101670986A (en) * 2009-09-28 2010-03-17 三一汽车制造有限公司 Hoisting system and mobile crane
CN102381639A (en) * 2010-09-06 2012-03-21 利勃海尔-韦尔克爱茵根有限公司 Crane
CN103030074A (en) * 2011-10-08 2013-04-10 易肃 Hinge points-variable combined type multi-functional crawler crane
CN102583178A (en) * 2012-03-26 2012-07-18 上海三一科技有限公司 Main amplitude mast of crawler crane and crane comprising mast
CN102795557A (en) * 2012-09-03 2012-11-28 徐州重型机械有限公司 Crane
CN103145054A (en) * 2013-03-20 2013-06-12 中联重科股份有限公司 Jib tail bracket as well as jib and hoisting equipment comprising same
CN107117542A (en) * 2017-06-30 2017-09-01 徐州重型机械有限公司 Crane

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3793930B1 (en) * 2018-07-09 2022-10-05 Tadano Demag GmbH Support for the rear anchoring line of a telescopic crane
CN108946529A (en) * 2018-09-26 2018-12-07 太原科技大学 Anti-squat system is played after preceding spademan drag-line is anti-
CN109353946A (en) * 2018-11-30 2019-02-19 太原重工股份有限公司 Multilayer tension system and crane

Similar Documents

Publication Publication Date Title
CN106395645B (en) Wind-powered electricity generation arm method for turning and crane
CN107915159A (en) A kind of Crane Jib Structure
CN201176370Y (en) Electric generator stator combination sling
CN103663189B (en) Moving arm tower crane installation method
CN108792958A (en) A kind of wind power generating set sea integral hoisting device for rapid
CN106241663A (en) A kind of easy to operate power construction equipment
CN108821136B (en) A kind of hanging apparatus for large-scale wind driven generator fan blade set
CN202148134U (en) Dedicated hanging beam for hanging single blade of wind turbine
CN202265344U (en) Connection frame as well as boom system with same and hoisting machinery
CN108792964A (en) A kind of head mast device of wind power generating set lifting
CN202704895U (en) Articulated boom of crawler crane
CN209481045U (en) A kind of intelligent hanging apparatus of wind power hub
CN208292490U (en) A kind of turnover device for wind electricity blade
CN2763570Y (en) Integral standing type wind power generator
CN202449766U (en) Arm head hook assembly of truck-mounted crane as well as truck-mounted crane
CN201433037Y (en) Lifting hook for section of wind-power tower
CN204823892U (en) High stability hoist
CN211110747U (en) Collapsible integral type propeller strut suitable for swing arm tower crane
CN203568754U (en) Rapid combined lifting tool of power system
CN201291925Y (en) Leaf blade transportation isolated plant of wind-driven generator
CN201584868U (en) Stator frame turn-over device of through-flow generator
CN201713208U (en) Lifting device for cargoes in coil
CN206516988U (en) A kind of roller draw-gear of hydrogen fuel unmanned plane
CN201729604U (en) Aerogenerator set part-replacement hoisting structure
CN201703997U (en) Special wind power arm head device for caterpillar crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180417

RJ01 Rejection of invention patent application after publication