CN107906253A - Pipe installation method and system - Google Patents

Pipe installation method and system Download PDF

Info

Publication number
CN107906253A
CN107906253A CN201711017598.5A CN201711017598A CN107906253A CN 107906253 A CN107906253 A CN 107906253A CN 201711017598 A CN201711017598 A CN 201711017598A CN 107906253 A CN107906253 A CN 107906253A
Authority
CN
China
Prior art keywords
pipeline
mathematical models
adjustment
pipe
component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711017598.5A
Other languages
Chinese (zh)
Inventor
王孙骏
李琰
王泊宁
潘峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN201711017598.5A priority Critical patent/CN107906253A/en
Publication of CN107906253A publication Critical patent/CN107906253A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/17Mechanical parametric or variational design
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/14Pipes

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Geometry (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Computer Graphics (AREA)
  • Software Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of pipe installation method and system, pass through the sign of the mount message in the 3D mathematical models of pipeline, and the setting-out instrument for passing through erecting bed, 3D mathematical models after the corresponding mount message of the sign pipeline are adjusted, splice for later stage pipeline, and unknown in work progress carries out place mat, staff is eliminated when the individual character in face of 2D drawings judges by the expression directly perceived of 3D mathematical models, it is more easy to reach common understanding to optimal solution, make installation more accurate, also there are 3D mathematical models as reference during examination, it can realize during pipeline construction, material is made full use of, lifting construction precision and efficiency.

Description

Pipe installation method and system
Technical field
The present invention relates to a kind of pipe installation method and system.
Background technology
(referring to PVC pipeline) in present electromechanics work progress more, pipeline is mostly the on-site cutting after field lofting, It is laborious that this is time consuming, inefficiency, and the use to material is not planned well, and material exposes in atmosphere, quality It is easy to give a discount.In addition, the leftover pieces arbitrarily stacked, some is in order to be continuing with, it is necessary to stack for a long time, so not only accounting for With space, quality of materials declines, and adds many security risks.
The content of the invention
It is an object of the invention to provide a kind of pipe installation method and system, can solve Pipe installing inefficiency Problem.
To solve the above problems, the present invention provides a kind of pipe installation method, including:
Based on pipeline mounting construction drawing, the 3D mathematical models of pipeline are established by software;
The corresponding mount message of the pipeline is indicated on the 3D mathematical models;
By the setting-out instrument of erecting bed, the 3D mathematical models after the corresponding mount message of the sign pipeline are made Adjustment;
The Pipe installing of erecting bed is completed based on the 3D mathematical models after the adjustment.
Further, in the above-mentioned methods, the corresponding mount message of the pipeline includes:The parameter of conduit assembly, connection Technique and numbering.
Further, in the above-mentioned methods, indicated on the 3D mathematical models the corresponding mount message of the pipeline it Afterwards, further include:
Export the work sheet of the parameter for indicating the corresponding conduit assembly of the pipeline, Joining Technology and numbering;
The cutting of PVC pipeline component in the conduit assembly is completed in processing factory according to the work sheet.
Further, in the above-mentioned methods, the pipeline peace of erecting bed is completed based on the 3D mathematical models after the adjustment Dress, including:
The cutting of iron pipe component in the conduit assembly is completed according to the 3D mathematical models after the adjustment;
The PVC pipeline component and iron pipe component are combined by installation according to the 3D mathematical models after the adjustment.
Further, in the above-mentioned methods, the pipeline peace of erecting bed is completed based on the 3D mathematical models after the adjustment After dress, further include:
Two dimensional pipeline construction drawing according to the 3D mathematical models generation after the adjustment.
Another side according to the present invention, there is provided a kind of pipeline installation system, including:
Model building module, for based on pipeline mounting construction drawing, establishing the 3D mathematical models of pipeline by software;
Module is indicated, for indicating the corresponding mount message of the pipeline on the 3D mathematical models;
Module is adjusted, for the setting-out instrument by erecting bed, after indicating the corresponding mount message of the pipeline 3D mathematical models adjust;
Module is installed, for completing the Pipe installing of erecting bed based on the 3D mathematical models after the adjustment.
Further, in said system, the corresponding mount message of the pipeline includes:The parameter of conduit assembly, connection Technique and numbering.
Further, in said system, cutting module is further included, the corresponding pipeline group of the pipeline is indicated for exporting The work sheet of the parameter of part, Joining Technology and numbering;According to the work sheet in processing factory completes the conduit assembly PVC The cutting of conduit assembly.
Further, in said system, the installation module, for being completed according to the 3D mathematical models after the adjustment The cutting of iron pipe component in the conduit assembly;According to the 3D mathematical models after the adjustment by the PVC pipeline component and iron Tube assembly is combined installation.
Further, in said system, two-dimentional construction drawing generation module is further included, for according to the 3D after the adjustment The two dimensional pipeline construction drawing of mathematical model generation.
Compared with prior art, the sign of the invention by the mount message in the 3D mathematical models of pipeline, and pass through peace The setting-out instrument at scene is filled, the 3D mathematical models after the corresponding mount message of the sign pipeline are adjusted, are managed for the later stage Road splices, and unknown in work progress carries out place mat, and eliminating staff by the expression directly perceived of 3D mathematical models works as Individual character in face of 2D drawings judges, is more easy to reach common understanding to optimal solution, makes installation more accurate, and also there is 3D mathematical models work in when examination For reference, it can realize during pipeline construction, material is made full use of, lifting construction precision and efficiency.
Brief description of the drawings
Fig. 1 is the flow chart of the pipe installation method of one embodiment of the invention.
Embodiment
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, it is below in conjunction with the accompanying drawings and specific real Applying mode, the present invention is described in further detail.
As shown in Figure 1, the present invention provides a kind of pipe installation method, including:
Step S1, based on pipeline mounting construction drawing, the 3D mathematical models of pipeline are established by software;
Step S2, indicates the corresponding mount message of the pipeline on the 3D mathematical models;
Step S3, by the setting-out instrument of erecting bed, to the 3D numerals after the corresponding mount message of the sign pipeline Model adjusts;
Step S4, the Pipe installing of erecting bed is completed based on the 3D mathematical models after the adjustment.
Here, sign of the present invention by the mount message in the 3D mathematical models of pipeline, and putting by erecting bed Sampling instrument, adjusts the 3D mathematical models after the corresponding mount message of the sign pipeline, splices for later stage pipeline, and Unknown in work progress carries out place mat, and staff is eliminated when in face of 2D drawings by the expression directly perceived of 3D mathematical models Individual character judges, is more easy to reach common understanding to optimal solution, makes installation more accurate, and also there are 3D mathematical models in when examination as reference, can Realize during pipeline construction, material is made full use of, lifting construction precision and efficiency.
In one embodiment of pipe installation method of the present invention, the corresponding mount message of the pipeline includes:Conduit assembly Parameter, Joining Technology and numbering.
Here, by the mount message of the parameter of conduit assembly, Joining Technology and numbering, make pipeline, connector and company Connect technique and have and accurately express, various components are numbered according to sequence of construction, it is possible to achieve the accurate installation of pipeline. Realize that material cost reduces with time cost.High machining accuracy, pre-designed Joining Technology, to pipe fitting and connector Numbering the utilization rate of material is reached maximum, greatly promote the efficiency of construction stage.
In one embodiment of pipe installation method of the present invention, step S2, the pipeline is indicated on the 3D mathematical models After corresponding mount message, further include:
Export the work sheet of the parameter for indicating the corresponding conduit assembly of the pipeline, Joining Technology and numbering;
The cutting of PVC pipeline component in the conduit assembly is completed in processing factory according to the work sheet.
, can be with here, by indicating the parameter of the corresponding conduit assembly of the pipeline, Joining Technology and the work sheet of numbering Ensure the accurate cutting of PVC pipeline component in the conduit assembly.With assembled architecture close to pipeline also using at assembled Reason, after processing factory's preprocessing, is shipped in batches, ensures stock utilization highest.
In one embodiment of pipe installation method of the present invention, step S4, is completed based on the 3D mathematical models after the adjustment The Pipe installing of erecting bed, including:
The cutting of iron pipe component in the conduit assembly is completed according to the 3D mathematical models after the adjustment;
The PVC pipeline component and iron pipe component are combined by installation according to the 3D mathematical models after the adjustment.
Here, pass through the 3D mathematical models after the adjustment, it is ensured that iron pipe component is accurate in the conduit assembly Cutting, and the installation of the efficient combination of the PVC pipeline component and iron pipe component.
As shown in Figure 1, in one embodiment of pipe installation method of the present invention, step S4, based on the 3D numbers after the adjustment After word model completes the Pipe installing of erecting bed, further include:
Step S5, according to the two dimensional pipeline construction drawing of the 3D mathematical models generation after the adjustment, during for onsite acceptance Use.
The present invention also provides a kind of another pipeline installation system, including:
Model building module, for based on pipeline mounting construction drawing, establishing the 3D mathematical models of pipeline by software;
Module is indicated, for indicating the corresponding mount message of the pipeline on the 3D mathematical models;
Module is adjusted, for the setting-out instrument by erecting bed, after indicating the corresponding mount message of the pipeline 3D mathematical models adjust;
Module is installed, for completing the Pipe installing of erecting bed based on the 3D mathematical models after the adjustment.
Here, sign of the present invention by the mount message in the 3D mathematical models of pipeline, and putting by erecting bed Sampling instrument, adjusts the 3D mathematical models after the corresponding mount message of the sign pipeline, splices for later stage pipeline, and Unknown in work progress carries out place mat, and staff is eliminated when in face of 2D drawings by the expression directly perceived of 3D mathematical models Individual character judges, is more easy to reach common understanding to optimal solution, makes installation more accurate, and also there are 3D mathematical models in when examination as reference, can Realize during pipeline construction, material is made full use of, lifting construction precision and efficiency.
In one embodiment of pipeline installation system of the present invention, the corresponding mount message of the pipeline includes:Conduit assembly Parameter, Joining Technology and numbering.
Here, by the mount message of the parameter of conduit assembly, Joining Technology and numbering, make pipeline, connector and company Connect technique and have and accurately express, various components are numbered according to sequence of construction, it is possible to achieve the accurate installation of pipeline. Realize that material cost reduces with time cost.High machining accuracy, pre-designed Joining Technology, to pipe fitting and connector Numbering the utilization rate of material is reached maximum, greatly promote the efficiency of construction stage.
In one embodiment of pipeline installation system of the present invention, cutting module is further included, the pipeline pair is indicated for exporting The work sheet of the parameter of the conduit assembly answered, Joining Technology and numbering;The pipe is completed in processing factory according to the work sheet The cutting of PVC pipeline component in road component.
, can be with here, by indicating the parameter of the corresponding conduit assembly of the pipeline, Joining Technology and the work sheet of numbering Ensure the accurate cutting of PVC pipeline component in the conduit assembly.With assembled architecture close to pipeline also using at assembled Reason, after processing factory's preprocessing, is shipped in batches, ensures stock utilization highest.
In one embodiment of pipeline installation system of the present invention, the installation module, for according to the 3D numbers after the adjustment Word model completes the cutting of iron pipe component in the conduit assembly;According to the 3D mathematical models after the adjustment by the pvc pipe Road component and iron pipe component are combined installation.
Here, pass through the 3D mathematical models after the adjustment, it is ensured that iron pipe component is accurate in the conduit assembly Cutting, and the installation of the efficient combination of the PVC pipeline component and iron pipe component.
In one embodiment of pipeline installation system of the present invention, further include:
Two-dimentional construction drawing generation module, for the two dimensional pipeline construction according to the 3D mathematical models generation after the adjustment Figure, for being used during onsite acceptance.
Each embodiment is described by the way of progressive in this specification, what each embodiment stressed be and other The difference of embodiment, between each embodiment identical similar portion mutually referring to.
Obviously, those skilled in the art can carry out invention spirit of the various modification and variations without departing from the present invention And scope.If in this way, these modifications and changes of the present invention belong to the claims in the present invention and its equivalent technologies scope it Interior, then the present invention is also intended to including these modification and variations.

Claims (10)

  1. A kind of 1. pipe installation method, it is characterised in that including:
    Based on pipeline mounting construction drawing, the 3D mathematical models of pipeline are established by software;
    The corresponding mount message of the pipeline is indicated on the 3D mathematical models;
    By the setting-out instrument of erecting bed, tune is made to the 3D mathematical models after the corresponding mount message of the sign pipeline It is whole;
    The Pipe installing of erecting bed is completed based on the 3D mathematical models after the adjustment.
  2. 2. pipe installation method as claimed in claim 1, it is characterised in that the corresponding mount message of the pipeline includes:Pipe Parameter, Joining Technology and the numbering of road component.
  3. 3. pipe installation method as claimed in claim 2, it is characterised in that indicate the pipeline on the 3D mathematical models After corresponding mount message, further include:
    Export the work sheet of the parameter for indicating the corresponding conduit assembly of the pipeline, Joining Technology and numbering;
    The cutting of PVC pipeline component in the conduit assembly is completed in processing factory according to the work sheet.
  4. 4. pipe installation method as claimed in claim 3, it is characterised in that completed based on the 3D mathematical models after the adjustment The Pipe installing of erecting bed, including:
    The cutting of iron pipe component in the conduit assembly is completed according to the 3D mathematical models after the adjustment;
    The PVC pipeline component and iron pipe component are combined by installation according to the 3D mathematical models after the adjustment.
  5. 5. such as Claims 1-4 any one of them pipe installation method, it is characterised in that based on the 3D numbers after the adjustment After word model completes the Pipe installing of erecting bed, further include:
    Two dimensional pipeline construction drawing according to the 3D mathematical models generation after the adjustment.
  6. A kind of 6. pipeline installation system, it is characterised in that including:
    Model building module, for based on pipeline mounting construction drawing, establishing the 3D mathematical models of pipeline by software;
    Module is indicated, for indicating the corresponding mount message of the pipeline on the 3D mathematical models;
    Module is adjusted, for the setting-out instrument by erecting bed, to the 3D numbers after the corresponding mount message of the sign pipeline Word model adjusts;
    Module is installed, for completing the Pipe installing of erecting bed based on the 3D mathematical models after the adjustment.
  7. 7. pipeline installation system as claimed in claim 6, it is characterised in that the corresponding mount message of the pipeline includes:Pipe Parameter, Joining Technology and the numbering of road component.
  8. 8. pipeline installation system as claimed in claim 7, it is characterised in that further include cutting module, institute is indicated for exporting State the work sheet of the parameter of the corresponding conduit assembly of pipeline, Joining Technology and numbering;It is complete in processing factory according to the work sheet The cutting of PVC pipeline component into the conduit assembly.
  9. 9. pipeline installation system as claimed in claim 8, it is characterised in that the installation module, for according to the adjustment 3D mathematical models afterwards complete the cutting of iron pipe component in the conduit assembly;According to the 3D mathematical models after the adjustment by institute State PVC pipeline component and iron pipe component is combined installation.
  10. 10. such as claim 6 to 9 any one of them pipeline installation system, it is characterised in that further include two-dimentional construction drawing generation Module, for the two dimensional pipeline construction drawing according to the 3D mathematical models generation after the adjustment.
CN201711017598.5A 2017-10-26 2017-10-26 Pipe installation method and system Pending CN107906253A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711017598.5A CN107906253A (en) 2017-10-26 2017-10-26 Pipe installation method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711017598.5A CN107906253A (en) 2017-10-26 2017-10-26 Pipe installation method and system

Publications (1)

Publication Number Publication Date
CN107906253A true CN107906253A (en) 2018-04-13

Family

ID=61841793

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711017598.5A Pending CN107906253A (en) 2017-10-26 2017-10-26 Pipe installation method and system

Country Status (1)

Country Link
CN (1) CN107906253A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108674927A (en) * 2018-05-22 2018-10-19 江苏赛麟汽车科技有限公司 A kind of pipeline parts divide packing method
CN108941990A (en) * 2018-07-28 2018-12-07 上海二十冶建设有限公司 A kind of cooling-bed hydraulic pipeline modular installation method
CN109296048A (en) * 2018-09-07 2019-02-01 中天建设集团有限公司 A kind of water supply and sewerage pipeline virtual assembling, batch production processing construction method
CN111457157A (en) * 2020-04-20 2020-07-28 中国十七冶集团有限公司 Production and installation method of outdoor multi-professional prefabricated pressure pipeline set

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103793553A (en) * 2013-12-17 2014-05-14 西安航天动力试验技术研究所 Pipeline arrangement method
CN105046359A (en) * 2015-07-19 2015-11-11 南宁市政工程集团有限公司 BIM (Building Information Modelling) technology based municipal pipeline factory prefabrication and installation method
CN106481880A (en) * 2016-11-16 2017-03-08 中铁上海工程局集团有限公司 One kind is based on BIM and aluminum alloy mould plate correct embedment water supply and drainage sleeve pipe and construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103793553A (en) * 2013-12-17 2014-05-14 西安航天动力试验技术研究所 Pipeline arrangement method
CN105046359A (en) * 2015-07-19 2015-11-11 南宁市政工程集团有限公司 BIM (Building Information Modelling) technology based municipal pipeline factory prefabrication and installation method
CN106481880A (en) * 2016-11-16 2017-03-08 中铁上海工程局集团有限公司 One kind is based on BIM and aluminum alloy mould plate correct embedment water supply and drainage sleeve pipe and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108674927A (en) * 2018-05-22 2018-10-19 江苏赛麟汽车科技有限公司 A kind of pipeline parts divide packing method
CN108941990A (en) * 2018-07-28 2018-12-07 上海二十冶建设有限公司 A kind of cooling-bed hydraulic pipeline modular installation method
CN109296048A (en) * 2018-09-07 2019-02-01 中天建设集团有限公司 A kind of water supply and sewerage pipeline virtual assembling, batch production processing construction method
CN111457157A (en) * 2020-04-20 2020-07-28 中国十七冶集团有限公司 Production and installation method of outdoor multi-professional prefabricated pressure pipeline set

Similar Documents

Publication Publication Date Title
CN107906253A (en) Pipe installation method and system
CN111627099B (en) Steel structure non-contact actual measurement real quantity method and system based on three-dimensional scanning technology
CN104499714A (en) Mechanical and electrical installation engineering construction method based on BIM platform and measuring robot
CN105888248A (en) Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology
CN102768026B (en) The equipment of the full-scale quick detection of a kind of blade
CN110717212B (en) BIM (building information modeling) model checking method
CN103336856A (en) Virtual steel structure pre-assembly method based on visual model
US10614179B2 (en) Method for automating full-scale templates for positioning audio/video components
CN102518204B (en) Buddha ceremonial canopy and manufacturing method thereof
CN111797451B (en) BIM-based overhead line model construction method
CN108563860A (en) A kind of virtual pre-assembly method of steel construction
CN104778488A (en) Steel-structure building positioning paster based on BIM
CN106840014A (en) A kind of method for monitoring face along tunnel axial deformation
CN110414136B (en) BIM-based bridge rapid modeling method and system
CN111432197A (en) Construction monitoring method and system
CN105043347A (en) Wall inclination measuring system and method
CN107103170A (en) Support of pipelines design method based on BIM technology
CN111309945A (en) Method and system for accurately classifying inspection pictures of unmanned aerial vehicle
CN111691691A (en) Method for installing, measuring and positioning box body bending and twisting component and drum node
CN105382491A (en) Machining, manufacturing and inspection method of arc-shaped steel pipe column
CN104217065B (en) BIM technology-based drawing reviewing system and method
CN204189034U (en) A kind of engine pedestal centralising device
CN110864625A (en) Method and system for installing, positioning and detecting construction site equipment
CN109376989B (en) BiM-based bid management method
CN112884896B (en) BIM technology-based special-shaped ramp three-dimensional model rapid generation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180413