CN107905212B - A kind of construction method of water filling element earth pile composite foundation in situ - Google Patents

A kind of construction method of water filling element earth pile composite foundation in situ Download PDF

Info

Publication number
CN107905212B
CN107905212B CN201710888780.1A CN201710888780A CN107905212B CN 107905212 B CN107905212 B CN 107905212B CN 201710888780 A CN201710888780 A CN 201710888780A CN 107905212 B CN107905212 B CN 107905212B
Authority
CN
China
Prior art keywords
pile
water injection
injection pipe
pouch
immersed tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710888780.1A
Other languages
Chinese (zh)
Other versions
CN107905212A (en
Inventor
王志强
魏子龙
洪武
张云志
张红福
孙鹏德
刘国强
王存吉
谢壮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd, Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN201710888780.1A priority Critical patent/CN107905212B/en
Publication of CN107905212A publication Critical patent/CN107905212A/en
Application granted granted Critical
Publication of CN107905212B publication Critical patent/CN107905212B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • E02D3/123Consolidating by placing solidifying or pore-filling substances in the soil and compacting the soil

Abstract

The present invention relates to a kind of construction method of water filling element earth pile composite foundation in situ, mainly includes the steps that smooth site clearing, surveying setting-out, construction equipment assembling in place, pilot hole, water filling humidification, tube drawing secondary punching, bottom are rammed and fall soil, filler humidification after rise, layering filler in hole, compacted compacting pore-forming, loosening layer at the top of removing, spread out and put on compacting.Using construction method of the present invention, can form compound foundation, have and save construction machinery, reduce construction cost, improve working efficiency, reduce noise and mud pollution, the advantages of consumption dregs keeps environment.

Description

A kind of construction method of water filling element earth pile composite foundation in situ
Technical field
The present invention relates to a kind of field of foundation treatment of Canal in Loess Area, in particular to a kind of water filling element earth pile in situ is multiple Close the construction method of ground, the deep soft soil treatment suitable for engineerings such as highway, dykes and dams, building constructions.
Background technique
China has a vast territory, complex geologic conditions and various regions difference is larger, and loess foundation classification is more, distribution is wide;Especially There is deep loess foundation in northwest Gansu.With the further development of China's economy, northwest loess area is required necessarily to mention It rises, but also northwest loess engineering quantity and scale constantly expand.Seek that technologically advanced, economical rationality, easy for construction, quality is steady The ultra-deep Loess Subgrade mode fixed, bearing capacity is high, material saves, the feature of environmental protection is strong becomes that geotechnical engineering circle is urgently to be resolved to ask Topic.
Element earth pile is the pile-type that Canal in Loess Area is commonly used, and element earth pile is to utilize immersed tube, impact or explosive expansion etc. Then method soil compaction pore-forming in ground rams into hole and fills out plain native pile.When pile, made by the transverse shear stress in pore forming process With the soil in stake holes keeps inter-pile soil compacted around being pressed against, element native (cohesive soil) layering filling stake holes that then will be got ready It is interior, and tamping is layered to designed elevation.With the pile body of plain native compaction in layers, referred to as native compaction pile, the latter respectively with compacted stake Between local soil type at composite foundation, the common upper load for bearing basis.General driving depth control is between 10-12 meters, for ultra-deep Base processing does not use such pile-type.But with Loess Area of Northwest China economic development, general above 15 meters of structure foundation processing More than, according to current actual conditions and technical conditions, needs to invent a kind of water filling element earth pile composite foundation in situ and apply Work method, between duration, construction investment, construction quality can reasonable balance, the characteristics of abundant element earth pile.
Summary of the invention
It is an object of the invention to give full play to water filling element earth pile in situ, inadequate for foundation bearing capacity Problem is using specific water filling element earth pile composite foundation construction method in situ, to overcome the problems, such as that processing depth is limited.
In order to achieve the above purpose, the invention adopts the following technical scheme:
A kind of construction method of water filling element earth pile composite foundation in situ, it is characterised in that including following construction procedure:
(1) site clearing is smooth: according to design requirement site clearing;
(2) surveying setting-out: stake position is measured, and lays hidden pipe pile machine in designated position;
(3) construction equipment assembling is in place: assembling hidden pipe pile machine and its bracket, and assembling, which is rammed, expands equipment, completes pile foundation verticality Start to carry out pilot hole water filling pipe pile settling construction after control, water injection equipment debugging;
(4) pilot hole: start with hidden pipe pile machine after completing pile foundation degree control, water injection equipment debugging in low-water-content loess (1) hammering pilot hole is carried out on, the hidden pipe pile owner will include immersed tube (10), pouch (19), vertical water injection pipe (23), water injection pipe A(22), annular water injection pipe (24), pile top (15) and rear expanding unit;Pile top (15) is connected to the bottom of immersed tube (10), vertical to infuse Water pipe (23) is connected to annular water injection pipe (24), and annular water injection pipe (24) Gong She tri- is located at the upper of immersed tube (10) outer wall Portion, middle part and lower part, vertical water injection pipe (23) and water injection pipe A(22) it is fixed on immersed tube (10) inner wall;On the top of immersed tube (10) Pouch (19) are equipped with lower part, water injection pipe A(22) it is connected to pouch (19);Expanding unit is set under bottom pouch (19) afterwards On immersed tube (10) outer wall;The expanding unit afterwards is by fixed plate (11), rear expansion board (12), spring (13), limit plate (14), company Lug (18), connection steel wire (21) composition, fixed plate (11) one end and immersed tube (10) are fixed, the hinged expansion board of the other end (12), Hinged place is equipped with the limit plate (14) for expansion board (12) rotational angle after limiting, and engaging lug (18) is set to rear expansion board (12) the other end, connection steel wire (21) one end are connected on pouch (19), and the other end is connected on engaging lug (18);Spring (13) one end is fixed on immersed tube (10), expansion board (12) after other end connection;
(5) water filling humidification: section is divided according to pile body range soil layer moisture content during pilot hole and is contained according to Soil Parameters Water rate test coefficient, infiltration coefficient, single hole humidification range carry out quantitative timing water filling, by vertical water injection pipe (23), ring-shaped pouring Water pipe (24) water filling, while being filled the water from water injection pipe A(22) to pouch (19), expand pouch (19), with the compacted area of surrounding humidification (4) compacted formation water-stop sheet, pouch (19) expansion pull connection steel wire (21) and rear expansion board (12) outward, form monoblock type branch Support;
(6) tube drawing secondary punching: after downward pilot hole to designated position, start on pull out immersed tube (10), after be pulled out after the completion of pilot hole Pipe to half hole depth, hole wall falls soil after rise because impact is formed, and is humidified and is fallen after rise using vertical water injection pipe (23), annular water injection pipe (24) Soil, secondary punching squeeze compacting and fall soil after rise;
(7) falling soil is rammed at bottom: ramming expansion equipment and carries out Ramming operation, expands plate with the fixation pile top (26) on hammer ram (25), rammer (27) compacting falls soil after rise, is formed and falls native rammed bulb pile end (5) after rise;
(8) filler is humidified: being humidified by optimum moisture content shelving;
(9) it is layered filler in hole: single depth of packing being divided according to hammer ram parameter, ramming times, filler parameter and is divided Layer filler;
(10) compacted compacting pore-forming: combine compacted pore-forming using equilateral triangle arrangement, pore-forming using " interlacing, every row, jump Beat " method, compaction in layers pile survives for four times, while at the compacted formation element earth pile (6) of hole edge filling tamped;
(11) remove top and loosen layer: after pilot hole, ramming, surface soil layer loosens, and removes table according to condition of construction Face loosens layer, changes to fill out and rolls loading plate (7);
(12) spread out and put on compacting: surface loosens layer and with backfill carries out place Min layers and fill out to be densified to designed elevation.
Further, the pile top, which is equipped with to ram, expands plate (16), movable plate (17).
Expanding unit is by fixed plate (11), rear expansion board (12), spring (13), limit plate (14), engaging lug after described (18), connection steel wire (21) composition, connection steel wire (21) one end are connected on pouch (19), and one end is connected to engaging lug (18) On.
In above-mentioned construction method, it is compacted that long spire rotary drill machine, rotation control drilling machine, hammer hidden pipe also can be used in addition to hidden pipe pile machine Stake machine.According to pile body range soil layer moisture content sectional during pilot hole, according to Soil Parameters, moisture content test coefficient is seeped Saturating coefficient, single hole humidification range, carry out quantitative timing water filling by Con trolling index of most excellent moisture content, if using has pressure injection water And stand resolution time.Water proof is used as by vertical water injection pipe (23), annular water injection pipe (24) and pouch (19) if desired Plate water proof.Immersed tube tube drawing process mesoporous top uniformly fills the water humidification.
Using water filling element earth pile composite foundation construction method in situ of the invention, can form compound foundation, there is section Construction machinery is saved, construction cost is reduced, improves working efficiency, reduces noise and mud pollution, consumption dregs keeps the excellent of environment Point.
Detailed description of the invention
Fig. 1 is water filling element earth pile composite foundation diagrammatic cross-section in situ;
Fig. 2 is hidden pipe pile machine schematic diagram;
Fig. 3 is pile layout plan view;
Fig. 4 is hidden pipe pile machine sectional view;
Fig. 5 is to ram to expand construction schematic diagram;
Fig. 6 is fixed pile top front view;
Fig. 7 is fixed pile top top view;
Fig. 8 is hidden pipe pile machine tube drawing schematic diagram;
Fig. 9 is construction flow chart of the present invention.
1- low-water-content loess, the hard soil layer of 2-, 3- miscellaneous fill, the compacted area of 4- humidification, 5- fall native rammed bulb pile end, 6- element after rise Native compaction pile, 7- roll loading plate, 8- Soft Soil Layer, 9- with respect to hard stratum, 10-immersed tube, 11-fixed plates, 12-rear expansion board, 13-springs, 14-limit plates, 15-pile tops, 16-expansion board, 17-movable plates, 18-engaging lugs, 19-pouches, 20-notes Water hole, 21-connection steel wires, 22-water injection pipe A, 23-vertical water injection pipes, 24-annular water injection pipes, 25- hammer ram, 26- spud pile Point, 27-, which are rammed, expands plate.
Specific embodiment
Element earth pile design parameter and construction technical requirement, pouch design parameter and construction technical requirement connect steel wire Manufacture craft etc., be not repeated in present embodiment, emphasis illustrates that the present invention relates to the embodiments of structure.
Fig. 1 is water filling element earth pile composite foundation diagrammatic cross-section in situ of the invention.Referring to shown in Fig. 8 in situ The hidden pipe pile machine of element earth pile construction is filled the water, mainly includes immersed tube 10, pouch 19, vertical water injection pipe 23, water injection pipe A22, ring Shape water injection pipe 24, pile top 15 and rear expanding unit;Pile top 15 is connected to the bottom of immersed tube 10, and pile top, which is equipped with to ram, expands plate 16.Ring 24 Gong She tri- of shape water injection pipe is located at the upper, middle and lower of 10 outer wall of immersed tube, vertical water injection pipe 23 and water injection pipe A22 is fixed on 10 inner wall of immersed tube;The upper and lower part of immersed tube 10 be equipped with pouch 19, rear expanding unit be set to bottom pouch 19 it Under 10 outer wall of immersed tube on.Expanding unit is by fixed plate 11, rear expansion board 12, spring 13, limit plate 14, engaging lug 18, company afterwards The composition of steel wire 21 is connect, connection 21 one end of steel wire is connected in pouch 19, and one end is connected on engaging lug 18.
Element earth pile composite foundation is filled the water shown in Fig. 1 in situ to include element earth pile 6 and roll loading plate 7, element is native 6 bottom of compaction pile is to fall native rammed bulb pile end 5 after rise, and the compacted area 4 of humidification is formed with around element earth pile 6.Low-water-content loess 1 Miscellaneous fill 3, Soft Soil Layer 8, opposite hard stratum 9 and hard soil layer 2 are followed successively by under upper.
The construction method of water filling element earth pile in situ, including following construction procedure are set using above-mentioned hidden pipe pile machine:
(1) site clearing is smooth: according to design requirement site clearing;
(2) surveying setting-out: stake position is measured, and lays hidden pipe pile machine in designated position;
(3) construction equipment assembling is in place: assembling hidden pipe pile machine and its bracket, and assembling, which is rammed, expands equipment, completes pile foundation verticality Start to carry out pilot hole water filling pipe pile settling construction after control, water injection equipment debugging;
(4) pilot hole: start with hidden pipe pile machine after completing pile foundation degree control, water injection equipment debugging in low-water-content loess Hammering pilot hole is carried out on 1, the hidden pipe pile owner will include immersed tube 10, pouch 19, vertical water injection pipe 23, water injection pipe A22, annular Water injection pipe 24, pile top 15 and rear expanding unit;Pile top 15 is connected to the bottom of immersed tube 10, and annular 24 Gong She tri- of water injection pipe divides Not Wei Yu 10 outer wall of immersed tube upper, middle and lower, vertical water injection pipe 23 and water injection pipe A22 are fixed on 10 inner wall of immersed tube;? The upper and lower part of immersed tube 10 is equipped with pouch 19, and rear expanding unit is set on 10 outer wall of immersed tube under bottom pouch 19;
(5) water filling humidification: section is divided according to pile body range soil layer moisture content during pilot hole and is contained according to Soil Parameters Water rate test coefficient, infiltration coefficient, single hole humidification range carry out quantitative timing water filling, fill the water by vertical water injection pipe 23, annular Pipe 24 fills the water, while being filled the water from water injection pipe A22 to pouch 19, expands pouch 19, with surrounding be humidified compacted area 4 it is compacted formed every Water plate, the expansion of pouch 19 pull connection steel wire 21 and rear expansion board 12 outward, form integral support;
(6) tube drawing secondary punching: after downward pilot hole to designated position, start on pull out immersed tube 10, the tube drawing after the completion of pilot hole To half hole depth, hole wall falls soil after rise because impact is formed, and falls soil after rise using vertical water injection pipe 23, the annular humidification of water injection pipe 24, secondary Punching squeezes compacting and falls soil after rise;
(7) falling soil is rammed at bottom: ramming expansion equipment and carries out Ramming operation, expands plate 27 with the fixation pile top 26 on hammer ram 25, rammer and ram It is real to fall soil after rise, it is formed and falls native rammed bulb pile end 5 after rise;
(8) filler is humidified: being humidified by optimum moisture content shelving;
(9) it is layered filler in hole: single depth of packing being divided according to hammer ram parameter, ramming times, filler parameter and is divided Layer filler;
(10) compacted compacting pore-forming: combine compacted pore-forming using equilateral triangle arrangement, pore-forming using " interlacing, every row, jump Beat " method, compaction in layers pile survives for four times, while at the compacted formation element earth pile 6 of hole edge filling tamped;
(11) remove top and loosen layer: after pilot hole, ramming, surface soil layer loosens, and removes table according to condition of construction Face loosens layer, changes to fill out and rolls loading plate 7;
Spread out and put on compacting: surface loosens layer and with backfill carries out place Min layers and fill out to be densified to designed elevation.

Claims (1)

1. a kind of construction method of water filling element earth pile composite foundation in situ, it is characterised in that including following construction procedure:
(1) site clearing is smooth: according to design requirement site clearing;
(2) surveying setting-out: stake position is measured, and lays hidden pipe pile machine in designated position;
(3) construction equipment assembles in place: assembling hidden pipe pile machine and its bracket, assembling rammer expansion equipment, completion pile foundation degree control, Start to carry out pilot hole water filling pipe pile settling construction after water injection equipment debugging;
(4) pilot hole: start with hidden pipe pile machine after completing pile foundation degree control, water injection equipment debugging in low-water-content loess (1) On carry out hammering pilot hole, the hidden pipe pile owner will include immersed tube (10), pouch (19), vertical water injection pipe (23), water injection pipe A (22), annular water injection pipe (24), pile top (15) and rear expanding unit;Pile top (15) is connected to the bottom of immersed tube (10), vertical to infuse Water pipe (23) is connected to annular water injection pipe (24), and annular water injection pipe (24) Gong She tri- is located at the upper of immersed tube (10) outer wall Portion, middle part and lower part, vertical water injection pipe (23) and water injection pipe A(22) it is fixed on immersed tube (10) inner wall;On the top of immersed tube (10) Pouch (19) are equipped with lower part, water injection pipe A(22) it is connected to pouch (19);Expanding unit is set under bottom pouch (19) afterwards On immersed tube (10) outer wall;The expanding unit afterwards is by fixed plate (11), rear expansion board (12), spring (13), limit plate (14), company Lug (18), connection steel wire (21) composition, fixed plate (11) one end and immersed tube (10) are fixed, the hinged expansion board of the other end (12), Hinged place is equipped with the limit plate (14) for expansion board (12) rotational angle after limiting, and engaging lug (18) is set to rear expansion board (12) the other end, connection steel wire (21) one end are connected on pouch (19), and the other end is connected on engaging lug (18);Spring (13) one end is fixed on immersed tube (10), expansion board (12) after other end connection;
(5) water filling humidification: section is divided according to pile body range soil layer moisture content during pilot hole, according to Soil Parameters, moisture content Test coefficient, infiltration coefficient, single hole humidification range carry out quantitative timing water filling, by vertical water injection pipe (23), annular water injection pipe (24) it fills the water, while being filled the water from water injection pipe A(22) to pouch (19), expand pouch (19), squeezed with the compacted area (4) of surrounding humidification Close formation water-stop sheet, pouch (19) expansion pull connection steel wire (21) and rear expansion board (12) outward, form integral support;
(6) tube drawing secondary punching: after downward pilot hole to designated position, start on pull out immersed tube (10), tube drawing is extremely after the completion of pilot hole Half hole depth, hole wall fall soil after rise because impact is formed, and are humidified using vertical water injection pipe (23), annular water injection pipe (24) and fall soil after rise, and two Secondary punching squeezes compacting and falls soil after rise;
(7) falling soil is rammed at bottom: ramming expansion equipment and carries out Ramming operation, expands plate (27) with the fixation pile top (26) on hammer ram (25), rammer Compacting falls soil after rise, is formed and falls native rammed bulb pile end (5) after rise;
(8) filler is humidified: being humidified by optimum moisture content shelving;
(9) it is layered filler in hole: carrying out layering according to hammer ram parameter, ramming times, filler parameter division single depth of packing and fills out Material;
(10) compacted compacting pore-forming: compacted pore-forming is combined using equilateral triangle arrangement, pore-forming using " interlacing is beaten every row, jump " Method, compaction in layers pile survives for four times, while at the compacted formation element earth pile (6) of hole edge filling tamped;
(11) remove top and loosen layer: after pilot hole, ramming, surface soil layer loosens, and removes surface pine according to condition of construction Dynamic layer, changes to fill out and rolls loading plate (7);
Spread out and put on compacting: surface loosens layer and with backfill carries out place Min layers and fill out to be densified to designed elevation.
CN201710888780.1A 2017-09-27 2017-09-27 A kind of construction method of water filling element earth pile composite foundation in situ Active CN107905212B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710888780.1A CN107905212B (en) 2017-09-27 2017-09-27 A kind of construction method of water filling element earth pile composite foundation in situ

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710888780.1A CN107905212B (en) 2017-09-27 2017-09-27 A kind of construction method of water filling element earth pile composite foundation in situ

Publications (2)

Publication Number Publication Date
CN107905212A CN107905212A (en) 2018-04-13
CN107905212B true CN107905212B (en) 2019-08-27

Family

ID=61840394

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710888780.1A Active CN107905212B (en) 2017-09-27 2017-09-27 A kind of construction method of water filling element earth pile composite foundation in situ

Country Status (1)

Country Link
CN (1) CN107905212B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577312A (en) * 2018-11-22 2019-04-05 福建金东矿业股份有限公司 A kind of silt geology vibro-replacement stone compacting pile construction method
CN109706911B (en) * 2018-12-11 2020-09-04 天伟建设集团有限公司 Basement outer wall foundation groove regenerated material backfilling and compacting system and construction method
CN110820790B (en) * 2019-11-21 2022-07-05 太原理工大学 Synchronous water injection humidifying construction process for lime-soil compaction pile
CN110820789A (en) * 2019-11-21 2020-02-21 太原理工大学 Synchronous water injection humidifying device for lime-soil compaction pile
CN116201101A (en) * 2023-02-28 2023-06-02 中国十七冶集团有限公司 Construction method of ultra-long plain soil compaction pile in collapsible loess area with low water content

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5163972B1 (en) * 2012-06-13 2013-03-13 強化土株式会社 Injection pipe device and injection method
CN103835292B (en) * 2013-12-17 2015-09-02 建基建设集团有限公司 High frequency vibrating rushes the construction method of base-extending deposited pile tube
CN103835284B (en) * 2014-02-21 2015-10-07 安徽省公路桥梁工程有限公司 A kind of Pile In Drill In Karst Terrain structure and construction method
CN106381869A (en) * 2016-01-27 2017-02-08 浙江省东阳第三建筑工程有限公司 Double-protective barrel impact pile-forming method at silt rock soil layer
CN105970911B (en) * 2016-07-01 2018-12-28 王继忠 A kind of processing method of big thickness collapsible loess

Also Published As

Publication number Publication date
CN107905212A (en) 2018-04-13

Similar Documents

Publication Publication Date Title
CN107905212B (en) A kind of construction method of water filling element earth pile composite foundation in situ
CN103215960B (en) Grouting method for high polymer vertical support system
CN107859041B (en) The construction method of collapsible loess zanjon high roadbed structure
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN101544022B (en) Preparation method for preformed hole fender pile
CN104264655A (en) Preformed hole deep-layer underwater tamping method
CN103711114A (en) Foundation treatment method
CN105256790B (en) Prefabricated skirt type pipe pile used for drainage and added with pile body inclined support and construction method thereof
CN110761300A (en) Construction method for supporting impervious soft soil body on side slope of deep foundation pit of high-rise building through micro-expansion
CN104652411B (en) Composite foundation treatment method based on reinforcement, pretreatment and dynamic compaction of sandy soil
CN104652409A (en) Continuous forced drainage and compaction combined soft foundation treatment technical method
CN207314340U (en) Hidden pipe pile machine for water filling element earth pile Composite foundation construction in situ
CN106049413B (en) A kind of composite power drain consolidation system and construction method applied to deep layer foundation in saturated soft soil
CN106958239A (en) Precipitation union gently rams soft soil foundation reinforcing method
CN205276254U (en) Drainage is and add prefabricated skirt tubular pile of pile body bearing diagonal
CN102251514A (en) Multi-section type variable cross-section dynamic compaction method
CN207211176U (en) A kind of big open caisson of superelevation
CN212896322U (en) Side-root composite load-bearing pile
CN110144918A (en) Hypogee dewatering well antiseepage plugging construction method
CN209429054U (en) Seepage prevention of dam founda structure in ultra-deep thick-covering
CN207484447U (en) A kind of element earth pile equipment
CN113123301A (en) Partition structure of gravel soil core wall dam
CN208748638U (en) Underwater strong rammer subtraction unit
CN112813931A (en) Heightening mixed dam structure combined with built earth-rock dam and construction method thereof
CN109667260A (en) A kind of reinforcement system and its construction method based on soft foundation discharge fixing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant