CN107900140A - The construction method of correction steel bridge beam and face buckling deformation is completed using gantry cutting machine - Google Patents

The construction method of correction steel bridge beam and face buckling deformation is completed using gantry cutting machine Download PDF

Info

Publication number
CN107900140A
CN107900140A CN201711089378.3A CN201711089378A CN107900140A CN 107900140 A CN107900140 A CN 107900140A CN 201711089378 A CN201711089378 A CN 201711089378A CN 107900140 A CN107900140 A CN 107900140A
Authority
CN
China
Prior art keywords
cutting machine
gantry cutting
floorings
completed
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711089378.3A
Other languages
Chinese (zh)
Inventor
张宝平
薛日飞
张丙东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Second Metallurgy Group Co Ltd
Original Assignee
China Second Metallurgy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Second Metallurgy Group Co Ltd filed Critical China Second Metallurgy Group Co Ltd
Priority to CN201711089378.3A priority Critical patent/CN107900140A/en
Publication of CN107900140A publication Critical patent/CN107900140A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21DWORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21D1/00Straightening, restoring form or removing local distortions of sheet metal or specific articles made therefrom; Stretching sheet metal combined with rolling

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of construction method that correction steel bridge beam and face buckling deformation is completed using gantry cutting machine, it is characterized in that:More mouth grilled guns are installed on gantry cutting machine crossbeam, the floorings for welding completion are placed on gantry cutting machine platform, the spacing of each grilled gun is adjusted according to the spacing of every piece of ribbed stiffener on floorings, every welding bead on floorings is aligned with each grilled gun respectively, light a fire after aligning, start gantry cutting machine to be moved forward or rearward, that is, complete the correction work of floorings.

Description

The construction method of correction steel bridge beam and face buckling deformation is completed using gantry cutting machine
Technical field
Patent of the present invention is related to a kind of construction party that correction steel bridge beam and face buckling deformation is completed using gantry cutting machine Method, mainly applies to structure steel fabrication field.
Background technology
Top, bottom in Steel Bridge, web are referred to as floorings, since the area of floorings is larger, in order to increase its intensity And rigidity, welding ribbed stiffener, and the gap ratio comparatively dense of ribbed stiffener are required on floorings, after the completion of welding, floorings because Warping phenomenon occurs for welding contraction, occurs such situation in the past, typically using artificial flame straightening, i.e., is baked and robbed with one Toasted on a welding bead, such construction method, that is, lost labor, and shorten efficiency, cost increase.
The content of the invention
The purpose of patent of the present invention is low in order to solve artificial flame straightening efficiency, and a kind of operation that is of high cost and inventing is simple Construction method single, efficient, cost is low.
The purpose of the present invention is what is realized in the following ways:
Multiple grilled guns are installed on gantry cutting machine crossbeam, the floorings for welding completion are placed on gantry cutting machine puts down On platform, the spacing of each grilled gun is adjusted according to the spacing of every piece of ribbed stiffener on floorings, every welding bead on floorings is distinguished Align with each grilled gun, light a fire after aligning, start gantry cutting machine and be moved forward or rearward, that is, complete rectifying for floorings Positive work.
It is an advantage of the invention that:Labor strength can effectively be reduced using this construction method, improve production efficiency, reduced Cost.
Brief description of the drawings
This figure is the usage state diagram of patent of the present invention.
With reference to this figure, patent of the present invention includes gantry cutting machine 1, bakes and rob 2, platform 3, workpiece 4.
Embodiment
The workpiece 4 completed will be welded to be put on platform 3, adjust it is each roasting rob 2 distance, make it is each it is roasting rob 2 distance with The per pass ribbed stiffener of workpiece 4 apart from equal, to it is each adjust it is roasting rob 2 and light a fire, start gantry cutting machine 1 forward or Walk backward, that is, complete the correction work of workpiece 4.

Claims (1)

1. the construction method of correction steel bridge beam and face buckling deformation is completed using gantry cutting machine, it is characterized in that:Using gantry Formula cuts machine frame, and multiple bake is installed on the crossbeam of gantry cutting machine frame and is robbed, and sets Cutting platform, adjusts each roasting The position robbed is equal with the position of floorings ribbed stiffener.
CN201711089378.3A 2017-11-07 2017-11-07 The construction method of correction steel bridge beam and face buckling deformation is completed using gantry cutting machine Pending CN107900140A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711089378.3A CN107900140A (en) 2017-11-07 2017-11-07 The construction method of correction steel bridge beam and face buckling deformation is completed using gantry cutting machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711089378.3A CN107900140A (en) 2017-11-07 2017-11-07 The construction method of correction steel bridge beam and face buckling deformation is completed using gantry cutting machine

Publications (1)

Publication Number Publication Date
CN107900140A true CN107900140A (en) 2018-04-13

Family

ID=61842757

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711089378.3A Pending CN107900140A (en) 2017-11-07 2017-11-07 The construction method of correction steel bridge beam and face buckling deformation is completed using gantry cutting machine

Country Status (1)

Country Link
CN (1) CN107900140A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DD252774A1 (en) * 1986-09-19 1987-12-30 Bautzen Waggonbau Veb DEVICE AND METHOD FOR ALIGNING HARDENED PANELS
JPH0671486A (en) * 1992-08-26 1994-03-15 Ishikawajima Harima Heavy Ind Co Ltd Device for straightening block steel plate
JPH10156436A (en) * 1996-11-21 1998-06-16 Nippon Seiko Kk Method for straightening deformation of long size member
EP1935524A1 (en) * 2006-12-21 2008-06-25 Linde Aktiengesellschaft Device for flame straightening
CN204412817U (en) * 2015-01-09 2015-06-24 湖北龙星钢构有限公司 A kind of gag press with point-like heater

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DD252774A1 (en) * 1986-09-19 1987-12-30 Bautzen Waggonbau Veb DEVICE AND METHOD FOR ALIGNING HARDENED PANELS
JPH0671486A (en) * 1992-08-26 1994-03-15 Ishikawajima Harima Heavy Ind Co Ltd Device for straightening block steel plate
JPH10156436A (en) * 1996-11-21 1998-06-16 Nippon Seiko Kk Method for straightening deformation of long size member
EP1935524A1 (en) * 2006-12-21 2008-06-25 Linde Aktiengesellschaft Device for flame straightening
CN204412817U (en) * 2015-01-09 2015-06-24 湖北龙星钢构有限公司 A kind of gag press with point-like heater

Similar Documents

Publication Publication Date Title
CN102848087B (en) A kind of groove tank makes welding method
CN102861972B (en) Welding method for vertically spliced super-thick steel plate
CN105057856A (en) Extra-thick sheet submerged-arc welding technique
CN102632344A (en) Welding deformation control process for ship superstructure
CN110524129B (en) Welding deformation control method for large-size super-thick bridge steel tower bearing plate
CN214133393U (en) Steel box girder bridge face steel plate flame straightening equipment
CN102500660A (en) Integral correction device for long and thin beam structure and correction method
CN108465904A (en) A kind of spelling welding shaping method of H profile steel
CN105728886A (en) Flame cutting technology
CN104942410A (en) Ultra-narrow gap TIG (tungsten inert gas) hot wire welding method
CN107570874A (en) Laser-arc hybrid welding process
CN112570861A (en) Control method for welding deformation of sheet sectional construction
CN104057189A (en) Novel U-shaped cross section component, special jig frame and processing and setting method
CN105710497A (en) Splicing technology of H-shaped steel
CN106736262A (en) H profile steel production technology
CN107900140A (en) The construction method of correction steel bridge beam and face buckling deformation is completed using gantry cutting machine
CN106270953B (en) Large-scale I-shaped crane beam field assembly, welding method
CN104057176A (en) I-shaped full-penetration steel member seam welding method without grooving or back chipping
CN104028875B (en) Aluminum electrolytic cell manufacturing method
CN203992775U (en) The synchronous bilateral welding tractor of trackless
CN103028891B (en) The welding and restoring process of mounting edge endoporus after rear overcoat
CN104275558B (en) Control welding deformation and improve the welding method of weldquality
CN104057256B (en) A kind of manufacture method of down-hole big bucket capacity scraper lifting large arm
CN104439775B (en) A kind of welding method of diaphragm plate unit
CN104772551B (en) Rubber film sealing coal gas cabinet bottom plate or top plate welding method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180413

WD01 Invention patent application deemed withdrawn after publication