CN107859036A - A kind of in-situ deposited prefabricated combining structure stake and its construction method suitable for karst region - Google Patents
A kind of in-situ deposited prefabricated combining structure stake and its construction method suitable for karst region Download PDFInfo
- Publication number
- CN107859036A CN107859036A CN201711011239.9A CN201711011239A CN107859036A CN 107859036 A CN107859036 A CN 107859036A CN 201711011239 A CN201711011239 A CN 201711011239A CN 107859036 A CN107859036 A CN 107859036A
- Authority
- CN
- China
- Prior art keywords
- stake
- pile
- hypomere
- solution cavity
- cavity area
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 34
- 238000011065 in-situ storage Methods 0.000 title claims abstract description 22
- 239000004567 concrete Substances 0.000 claims abstract description 53
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 18
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 16
- 239000010959 steel Substances 0.000 claims abstract description 16
- 238000007789 sealing Methods 0.000 claims abstract description 15
- 238000000034 method Methods 0.000 claims abstract description 10
- 230000002787 reinforcement Effects 0.000 claims abstract description 10
- 238000005553 drilling Methods 0.000 claims abstract description 8
- 239000011435 rock Substances 0.000 claims abstract description 4
- 230000003014 reinforcing effect Effects 0.000 claims description 8
- 238000007796 conventional method Methods 0.000 abstract description 2
- 230000010354 integration Effects 0.000 abstract 1
- 230000008901 benefit Effects 0.000 description 3
- 238000005266 casting Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 210000003205 muscle Anatomy 0.000 description 2
- 230000034994 death Effects 0.000 description 1
- 231100000517 death Toxicity 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000002708 enhancing effect Effects 0.000 description 1
- 231100000241 scar Toxicity 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/52—Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
- E02D5/523—Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses a kind of in-situ deposited prefabricated combining structure pile foundation and its construction method suitable for karst region,Including epimere stake and hypomere stake,Epimere stake is cast-in-place deposited reinforced concrete pile,Hypomere stake is prefabricated concrete tubular pile,Hypomere stake passes through the solution cavity area in rock stratum,Epimere stake passes through non-solution cavity area,And it is supported in hypomere stake upper end,Pile foundation is together to form with hypomere stake,During construction,First with the conventional method construction non-solution cavity area stake holes in upper strata,Then manually borehole method or rotary drilling rig construction lower floor solution cavity area stake holes,Concrete tubular pile is lifted into solution cavity area stake holes afterwards,And sealing ring is set between non-solution cavity area stake holes at the top of concrete tubular pile,Then the steel reinforcement cage of deposited reinforced concrete pile is lifted to non-solution cavity area stake holes,Cast-in-place construction obtains the overall pile foundation of concrete tubular pile and deposited reinforced concrete pile integration,Epimere stake and hypomere stake of the present invention are combined into an overall common stress of pile body,It is easy for construction,Fast,It is cheap.
Description
Technical field
The invention belongs to the stake technical field in civil engineering, and in particular to a kind of in-situ deposited prefabricated group suitable for karst region
Close structure pile and its construction method.
Background technology
In karst area during construction building thing bored pile foundation, when drilling runs into larger solution cavity, often
The slurry coat method in drilling occurs to be lost in rapidly and cause the hole that collapses, causes any property loss and workmen's injures and deaths, while be also delayed
Duration.To prevent such accident from occurring, it is common practice to steel pipe casing is squeezed into as enclosed structure when drilling is to scar, it is this
Steel pile casting is working measure, and permanent structure stress can not also be taken out it is not intended that it after pile, costly.
The content of the invention
It is an object of the invention to provide a kind of safe and economical in-situ deposited prefabricated combining structure stake suitable for karst region.
To reach above-mentioned purpose, the technical solution adopted by the present invention is as follows:
A kind of in-situ deposited prefabricated combining structure stake suitable for karst region, including epimere stake and hypomere stake, it is characterised in that:On
Section stake is cast-in-place deposited reinforced concrete pile, and hypomere stake is prefabricated concrete tubular pile, and hypomere stake passes through the solution cavity in rock stratum
Area, epimere stake passes through non-solution cavity area, and is supported in hypomere stake upper end, and pile foundation is together to form with hypomere stake.
As an improvement, being provided with reserved joint reinforcing bar at the top of the prefabricated concrete tubular pile, epimere stake passes through joint steel
Muscle is cast as one structure with concrete tubular pile, forms in-situ deposited prefabricated combining structure stake.
As an improvement, the steel reinforcement cage lower end of the deposited reinforced concrete pile extend into hollow area in concrete tubular pile,
Strengthen cast-in-place rear epimere stake and hypomere stake bonding strength.
As an improvement, when epimere stake is cast-in-place, while fill out core to the hollow area of hypomere stake.
It is another object of the present invention to a kind of safe and economical in-situ deposited prefabricated combining structure stake suitable for karst region
Construction method.
In order to achieve the above object, technical scheme is as follows:
A kind of in-situ deposited prefabricated combining structure pile construction method suitable for karst region, it is characterised in that walked under this method bag
Suddenly:
A utilizes the conventional construction method construction non-solution cavity area stake holes in upper strata;
B utilizes manually digging hole method or rotary drilling rig construction lower floor solution cavity area stake holes;
C will be set with the inflation sealing of hole circle of unaerated as the concrete tubular pile top of hypomere stake, be lifted in the lump by crane
To lower floor's solution cavity area stake holes, it is cased with inflation sealing of hole circle upper end and stretches into the non-segment length of solution cavity area one;The inflation of sealing of hole circle is inflated, by stake
Space is closed between hole and concrete tubular pile top, and concrete leaks to lower floor's solution cavity area cavity during preventing epimere stake cast-in-place
It is interior;
D gives the circle inflation of inflation sealing of hole, and space between concrete tubular pile top and non-solution cavity area stake holes is closed, prevents epimere
Concrete is leaked in lower floor's solution cavity area cavity when stake is cast-in-place.
The steel reinforcement cage of F lifting deposited reinforced concrete piles enters stake holes, and placing concrete forms cast-in-place concrete pile, and makes to mix
Solidifying soil pours into hypomere stake hollow section and carries out filling out core, while by joint steel reserved at the top of the concrete tubular pile as hypomere stake
Muscle, concrete tubular pile and deposited reinforced concrete pile is set to be combined into an overall common stress of pile body.
As an improvement, the gas-flow closure circle replaces with flexible rubber seal.
Preferably, hypomere stake hollow section carries out filling out core and epimere stake is poured while carried out.
The present invention has following advantages and effect compared with prior art:The steel reinforcement cage and concrete of epimere stake stretch into down
Section pile tube suitable length, makes epimere stake and hypomere stake be combined into an overall common stress of pile body, easy for construction, quick.Hypomere
Pile body is concrete precast pipe pile, construction when without again in solution cavity throwing slabstone formed retaining wall or use steel pile casting retaining wall, saving
Solution cavity area steel pile casting expense or throwing slabstone long construction period shortcoming in current conventional method, have speed of application fast, make
The advantages such as valency is low.The present invention conventional stake in solution cavity area is replaced with concrete tubular pile, while the concrete tubular pile and can with below
The bored concrete pile of construction is combined into the common stress of permanent structure, therefore is a kind of economical and practical piling strtucture, and economic benefit will be non-
Chang Mingxian.
Brief description of the drawings
Fig. 1 is the in-situ deposited prefabricated combining structure pilework schematic diagram of the present invention.
Fig. 2 is the in-situ deposited prefabricated combining structure stake parts assembling figure of the present invention.
Fig. 3 to Fig. 7 is in-situ deposited prefabricated combining structure pile driving construction schematic flow sheet.
Wherein, Fig. 3 is to utilize the conventional construction method construction non-solution cavity area stake holes in upper strata;
Fig. 4 is to utilize manually digging hole method or rotary drilling rig construction lower floor solution cavity area stake holes;
Fig. 5 is that concrete tubular pile top is set with into inflation sealing of hole circle, and is lifted to schematic diagram in lower floor's solution cavity area stake holes;
Fig. 6 is the steel reinforcement cage Ru Fei solution cavities area stake holes of lifting deposited reinforced concrete pile, and is shown to the circle inflation of inflation sealing of hole
It is intended to;
Fig. 7 is that placing concrete forms cast-in-place concrete pile, and concrete tubular pile is carried out to fill out core schematic diagram.
1- epimere stakes, 2- hypomere stakes, 3- gas-flow closure circles, 11- deposited reinforced concrete piles, 12- steel reinforcement cages, 21- joints
Reinforcing bar, 22- concrete tubular piles, 1a- non-solution cavity area 2a, 2a- solution cavities area 2a, 3a- solution cavities area cavity.
Embodiment
The present invention is further described below in conjunction with the accompanying drawings, below a kind of only citing of technical solution of the present invention, and
Do not represent all technical scheme scopes of the present invention, in additional embodiment noun used have it is clearly defined be defined by its definition, do not have
There is clearly defined explained by industry universal to be defined, do not mentioned in following examples refer to structure or step part be it is existing into
Ripe technology.
As depicted in figs. 1 and 2, a kind of in-situ deposited prefabricated combining structure stake suitable for karst region, including epimere stake 1 and hypomere
Stake 2, epimere stake 1 is cast-in-place deposited reinforced concrete pile 11, and hypomere stake 2 is prefabricated concrete tubular pile 22, and hypomere stake 2 passes through
Solution cavity area 2a in rock stratum, epimere stake 1 passes through non-solution cavity area 2a, and is supported in the upper end of hypomere stake 2, with the common combination of hypomere stake 2
Into pile foundation.
The prefabricated top of concrete tubular pile 22 is provided with reserved joint reinforcing bar 21, and deposited reinforced concrete pile 11 passes through
Joint reinforcing bar 21 is cast as one structure with concrete tubular pile 22, forms in-situ deposited prefabricated combining structure stake.
The lower end of steel reinforcement cage 12 of the deposited reinforced concrete pile 11 extend into hollow area in concrete tubular pile 22, enhancing
Epimere stake 1 and the bonding strength of hypomere stake 2, when epimere stake 1 is cast-in-place, while fill out core to the hollow area of hypomere stake 2 after cast-in-place.
Present invention also offers a kind of construction of the safe and economical in-situ deposited prefabricated combining structure stake suitable for karst region
The embodiment of method, it is specially:
As shown in Fig. 3 to Fig. 7, a kind of in-situ deposited prefabricated combining structure pile construction method suitable for karst region, this method bag
Lower step:
A utilizes the conventional construction method construction non-solution cavity area 2a stake holes in upper strata;
B utilizes manually digging hole method or rotary drilling rig construction lower floor solution cavity area 2a stake holes;
C will be set with the inflation sealing of hole circle of unaerated as the top of concrete tubular pile 22 of hypomere stake 2, be hung in the lump by crane
It is filled in lower floor's solution cavity area 2a stake holes, is cased with inflation sealing of hole circle upper end and stretches into the non-segment length of solution cavity area 2a mono-;Inflation sealing of hole circle fills
Gas, space between stake holes and the top of concrete tubular pile 22 is closed, concrete leaks to lower floor during preventing epimere stake 1 cast-in-place
In solution cavity area cavity 3a;
D gives the circle inflation of inflation sealing of hole, and space between the top of concrete tubular pile 22 and non-solution cavity area 2a stake holes is closed, prevented
Concrete is leaked in lower floor solution cavity area cavity 3a when epimere stake 1 is cast-in-place.
The steel reinforcement cage 12 of F lifting deposited reinforced concrete piles 11 enters stake holes, and placing concrete forms cast-in-place concrete pile, and
Make concrete pour into the hollow section of hypomere stake 2 to carry out filling out core, while reserved by the top of concrete tubular pile 22 as hypomere stake 2
Joint reinforcing bar 21, concrete tubular pile 22 and deposited reinforced concrete pile 11 is set to be combined into an overall common stress of pile body.
The gas-flow closure circle 3 can be replaced flexible rubber seal or other sealing devices.
The hollow section of hypomere stake 2 carries out filling out core and epimere stake 1 is poured while carried out.
Claims (7)
1. a kind of in-situ deposited prefabricated combining structure stake suitable for karst region, including epimere stake and hypomere stake, it is characterised in that:Epimere
Stake is cast-in-place deposited reinforced concrete pile, and hypomere stake is prefabricated concrete tubular pile, and hypomere stake passes through the solution cavity area in rock stratum,
Epimere stake passes through non-solution cavity area, and is supported in hypomere stake upper end, and pile foundation is together to form with hypomere stake.
2. in-situ deposited prefabricated combining structure stake as claimed in claim 1, it is characterised in that:At the top of the prefabricated concrete tubular pile
Provided with reserved joint reinforcing bar, epimere stake is cast as one structure by joint reinforcing bar and concrete tubular pile, is formed in-situ deposited prefabricated
Combining structure stake.
3. combining structure stake as claimed in claim 1, it is characterised in that:The steel reinforcement cage lower end of the deposited reinforced concrete pile
Hollow area in concrete tubular pile is extend into, strengthens cast-in-place rear epimere stake and hypomere stake bonding strength.
4. combining structure stake as claimed in claim 1, it is characterised in that:When epimere stake is cast-in-place, while to the sky of hypomere stake
Core is filled out in heart district domain.
A kind of 5. in-situ deposited prefabricated combining structure pile construction method suitable for karst region, it is characterised in that step under this method bag:
A utilizes the conventional construction method construction non-solution cavity area stake holes in upper strata;
B utilizes manually digging hole method or rotary drilling rig construction lower floor solution cavity area stake holes;
C will be set with the inflation sealing of hole circle of unaerated as the concrete tubular pile top of hypomere stake, be lifted in the lump under by crane
In floor solution cavity area stake holes, it is cased with inflation sealing of hole circle upper end and stretches into the non-segment length of solution cavity area one;
D gives the circle inflation of inflation sealing of hole, and space between concrete tubular pile top and non-solution cavity area stake holes is closed, prevents epimere stake from showing
Concrete is leaked in lower floor's solution cavity area cavity when pouring;
The steel reinforcement cage of F lifting deposited reinforced concrete piles enters stake holes, and placing concrete forms cast-in-place concrete pile, and makes concrete
Pour into hypomere stake hollow section to carry out filling out core, while by joint reinforcing bar reserved at the top of the concrete tubular pile as hypomere stake, make
Concrete tubular pile and deposited reinforced concrete pile are combined into an overall common stress of pile body.
6. in-situ deposited prefabricated combining structure pile construction method as claimed in claim 5, it is characterised in that:The gas-flow closure circle replaces
It is changed to flexible rubber seal.
7. in-situ deposited prefabricated combining structure pile construction method as claimed in claim 5, it is characterised in that:Hypomere stake hollow section is carried out
Fill out core and epimere stake is poured while carried out.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711011239.9A CN107859036B (en) | 2017-10-26 | 2017-10-26 | A kind of in-situ deposited prefabricated composite structure stake and its construction method suitable for karst region |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711011239.9A CN107859036B (en) | 2017-10-26 | 2017-10-26 | A kind of in-situ deposited prefabricated composite structure stake and its construction method suitable for karst region |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107859036A true CN107859036A (en) | 2018-03-30 |
CN107859036B CN107859036B (en) | 2019-10-11 |
Family
ID=61696805
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711011239.9A Active CN107859036B (en) | 2017-10-26 | 2017-10-26 | A kind of in-situ deposited prefabricated composite structure stake and its construction method suitable for karst region |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107859036B (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109183831A (en) * | 2018-08-30 | 2019-01-11 | 广东省建筑设计研究院 | Become the multistage load stake of stake diameter string hole and its construction method |
CN109707322A (en) * | 2018-12-08 | 2019-05-03 | 深圳市勘察研究院有限公司 | A kind of solution cavity isolating device and the solution cavity partition method using the device |
CN110424437A (en) * | 2019-08-13 | 2019-11-08 | 中国电建集团山东电力建设有限公司 | Photo-voltaic power generation station installation foundation construction method |
CN110863488A (en) * | 2019-11-15 | 2020-03-06 | 广东地山基础工程有限公司 | Device for preventing concrete loss of perfusion pile and construction method |
CN111364449A (en) * | 2020-04-07 | 2020-07-03 | 中建四局第一建筑工程有限公司 | Construction method and structure for penetrating karst cave of precast tubular pile |
CN113047331A (en) * | 2021-03-19 | 2021-06-29 | 中交第二航务工程勘察设计院有限公司 | Modular breakwater dyke head navigation light stake foundation structure |
CN113417281A (en) * | 2021-06-29 | 2021-09-21 | 中冶南方城市建设工程技术有限公司 | Cast-in-place pile-prestressed pipe pile composite pile and construction method thereof |
CN113431490A (en) * | 2021-06-25 | 2021-09-24 | 广州市建筑科学研究院集团有限公司 | Large-diameter tubular pile construction equipment and method for karst area |
CN115324035A (en) * | 2022-09-01 | 2022-11-11 | 中国十七冶集团有限公司 | Prestressed pipe pile foundation and construction method thereof |
CN116537244A (en) * | 2023-07-06 | 2023-08-04 | 交通运输部公路科学研究所 | Combined underwater bridge Liang Zhuangji and construction method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN200955146Y (en) * | 2006-08-31 | 2007-10-03 | 郑新俊 | Multi-stage sink-pipe bored concrete pile |
CN104563147A (en) * | 2014-08-29 | 2015-04-29 | 上海市政工程设计研究总院(集团)有限公司 | Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation |
CN104612143A (en) * | 2014-12-31 | 2015-05-13 | 云南建工基础工程有限责任公司 | Bored composite pile structure under karst cave/soil cave geological condition |
CN206233232U (en) * | 2016-12-05 | 2017-06-09 | 周同和 | A kind of upper and lower part expansion type soil cement is combined pile tube |
-
2017
- 2017-10-26 CN CN201711011239.9A patent/CN107859036B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN200955146Y (en) * | 2006-08-31 | 2007-10-03 | 郑新俊 | Multi-stage sink-pipe bored concrete pile |
CN104563147A (en) * | 2014-08-29 | 2015-04-29 | 上海市政工程设计研究总院(集团)有限公司 | Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation |
CN104612143A (en) * | 2014-12-31 | 2015-05-13 | 云南建工基础工程有限责任公司 | Bored composite pile structure under karst cave/soil cave geological condition |
CN206233232U (en) * | 2016-12-05 | 2017-06-09 | 周同和 | A kind of upper and lower part expansion type soil cement is combined pile tube |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109183831A (en) * | 2018-08-30 | 2019-01-11 | 广东省建筑设计研究院 | Become the multistage load stake of stake diameter string hole and its construction method |
CN109707322A (en) * | 2018-12-08 | 2019-05-03 | 深圳市勘察研究院有限公司 | A kind of solution cavity isolating device and the solution cavity partition method using the device |
CN109707322B (en) * | 2018-12-08 | 2024-06-21 | 深圳市勘察研究院有限公司 | Karst cave isolation device and karst cave isolation method using same |
CN110424437A (en) * | 2019-08-13 | 2019-11-08 | 中国电建集团山东电力建设有限公司 | Photo-voltaic power generation station installation foundation construction method |
CN110863488A (en) * | 2019-11-15 | 2020-03-06 | 广东地山基础工程有限公司 | Device for preventing concrete loss of perfusion pile and construction method |
CN111364449A (en) * | 2020-04-07 | 2020-07-03 | 中建四局第一建筑工程有限公司 | Construction method and structure for penetrating karst cave of precast tubular pile |
CN113047331A (en) * | 2021-03-19 | 2021-06-29 | 中交第二航务工程勘察设计院有限公司 | Modular breakwater dyke head navigation light stake foundation structure |
CN113431490A (en) * | 2021-06-25 | 2021-09-24 | 广州市建筑科学研究院集团有限公司 | Large-diameter tubular pile construction equipment and method for karst area |
CN113417281A (en) * | 2021-06-29 | 2021-09-21 | 中冶南方城市建设工程技术有限公司 | Cast-in-place pile-prestressed pipe pile composite pile and construction method thereof |
CN115324035A (en) * | 2022-09-01 | 2022-11-11 | 中国十七冶集团有限公司 | Prestressed pipe pile foundation and construction method thereof |
CN115324035B (en) * | 2022-09-01 | 2024-05-17 | 中国十七冶集团有限公司 | Prestressed pipe pile foundation and construction method thereof |
CN116537244A (en) * | 2023-07-06 | 2023-08-04 | 交通运输部公路科学研究所 | Combined underwater bridge Liang Zhuangji and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN107859036B (en) | 2019-10-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107859036B (en) | A kind of in-situ deposited prefabricated composite structure stake and its construction method suitable for karst region | |
CN105908744B (en) | Pore pressure counter-force construction method | |
CN102086645B (en) | Socketed pile and construction method thereof | |
CN105275381B (en) | Impact drill drilling construction method in rich water pebble layer | |
CN107524142A (en) | A kind of holing with slurry wall protection cast-in-place pile construction method | |
CN103835284A (en) | Karst area drilling cast-in-place pile structure and construction method | |
CN108560541A (en) | A kind of full casing follow-up scar drilling construction method of churning driven | |
CN104612143A (en) | Bored composite pile structure under karst cave/soil cave geological condition | |
CN101614020A (en) | Flexible bladder type anti-corrosive apparatus and use the anticorrosion stake and the job practices of this device | |
CN104563147B (en) | Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation | |
CN106907157B (en) | A kind of shield machine normal pressure opens the cabin operation construction method | |
CN109667985A (en) | The method that push-bench is docked with received well steel sleeve in jacking construction | |
CN106049491B (en) | One kind is exempted to tear precast concrete pile protection template and construction method open | |
CN107587502A (en) | A kind of spiral-digging pore pressure pour water soil occlusion curtain pile construction method | |
CN107190776A (en) | Water discharge tunnel standpipe plants pipe construction device and method | |
DK2925934T3 (en) | Process for making a pile | |
CN110080779A (en) | Tunnel tunnel bottom karst cave treatment construction method | |
CN106638646A (en) | Secondary bottom sealing structure of open caisson and construction method | |
CN207109804U (en) | A kind of quick spreading structure configuration of soft soil foundation bored concrete pile | |
CN110144881A (en) | One kind is drowned oneself type precast hollow friction pile and its construction method | |
CN107975027A (en) | The construction method that shield launching is reinforced with reaching end soil body | |
CN107476293A (en) | A kind of quick spreading structure of soft soil foundation bored concrete pile configures and its spreading method | |
CN107059884A (en) | A kind of construction method of building foundation pit grouting support stake | |
CN209622195U (en) | Push-bench and received well steel sleeve docking structure in a kind of jacking construction | |
CN206233243U (en) | After-teeming sizing device after a kind of stake holes |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |