CN107856809A - A kind of ultra-large type liquid pump installation and locating method peculiar to vessel - Google Patents

A kind of ultra-large type liquid pump installation and locating method peculiar to vessel Download PDF

Info

Publication number
CN107856809A
CN107856809A CN201710546780.3A CN201710546780A CN107856809A CN 107856809 A CN107856809 A CN 107856809A CN 201710546780 A CN201710546780 A CN 201710546780A CN 107856809 A CN107856809 A CN 107856809A
Authority
CN
China
Prior art keywords
liquid pump
laser
template
roof plate
ultra
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710546780.3A
Other languages
Chinese (zh)
Inventor
张治军
颜俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hudong Zhonghua Shipbuilding Group Co Ltd
Original Assignee
Hudong Zhonghua Shipbuilding Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hudong Zhonghua Shipbuilding Group Co Ltd filed Critical Hudong Zhonghua Shipbuilding Group Co Ltd
Priority to CN201710546780.3A priority Critical patent/CN107856809A/en
Publication of CN107856809A publication Critical patent/CN107856809A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B71/00Designing vessels; Predicting their performance

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Structures Of Non-Positive Displacement Pumps (AREA)

Abstract

The present invention relates to a kind of ultra-large type liquid pump installation and locating method peculiar to vessel, this method comprises the following steps:Step 1, deck plane perforate;Step 2, liquid pump pedestal(1)Assembling;Step 3, liquid pump pedestal(1)Tack welding;Step 4, liquid pump pedestal(1)It is welded and fixed;Step 5, bottom support installation;Step 6, midfoot support installation.Present invention ultra-large type liquid pump installation and locating method peculiar to vessel has the advantages of installation accuracy is high, improves efficiency and be cost-effective.

Description

A kind of ultra-large type liquid pump installation and locating method peculiar to vessel
Technical field
The present invention relates to field of shipbuilding, more particularly, to a kind of ultra-large type liquid pump installation and locating method peculiar to vessel.
Background technology
Stainless steel chemical tanker compares less novel ship as country's construction, and it is at a relatively high to build difficulty, at present I The oil carrier for the 38000T chemical tankers construction different from the past that company builds, the ship type is using a current cabin state-of-the-art in the world The a set of independent liquid pump system of the design pattern of one pump system, i.e. an independent liquid cargo tank, full ship amount to 43 cargo tanks, also In the presence of 43 sets of independent liquid pump systems, so the core technology as ship cargo tank construction is that the peace of liquid pump in cabin Dress, the accuracy of installation directly determine the whole liquefied cargo system success or not of the ship, because the ship cargo tank material selection is double Phase stainless steel material, perforate are very prudent.
In original constructing operation, polishing groove, and the positioning at perforate center are coordinated using manual plasma cut Using the location dimension in design drawing, there is following defect in such construction:
First, due to being manual perforate, the center of circle degree in hole is in the presence of very big error, and the shaping very irregular of groove, this is directly resulted in The installation gap of last liquid pump pedestal crossing cabin part can not ensure, so as to cause the penetration weld of liquid pump and deck plane complete Full penetration.
Second, on the determination at deck perforate center, original adoption is design drawing size, but liquid pump center is necessary When liquid pump pedestal center and the bilge inhale well center and keep certain perpendicularity, but in actual building course, due to deck Segmentation and bottom section precision are not to ensure to install without surplus, so certain error be present with design drawing, cause liquid pump Pedestal center and oil suction well central perpendicularity deviation are excessive, beyond design requirement.
The content of the invention
In order to solve above-mentioned the deficiencies in the prior art, it is fixed that the present invention provides a kind of ultra-large type liquid pump installation peculiar to vessel Position method, can effectively ensure that the accuracy of liquid pump installation, avoids doing over again because error is excessive, so as to improve efficiency and section About cost.
In order to realize foregoing invention purpose, technical scheme provided by the invention is as follows:
A kind of ultra-large type liquid pump installation and locating method peculiar to vessel, this method comprise the following steps:
Step 1, deck plane perforate:The perforate center of deck plane is determined simultaneously with the actual size of bilge oil suction well centre-to-centre spacing bulkhead Sample punching is struck, the actual size includes lateral dimension and longitudinal size, carries out vertical open pores using CUT, vertically opens Along the oblique bevel of perforate top edge after the completion of hole, and root is stayed in the lower end of perforate, the surface of perforate and groove is polished smooth;
Step 2, the assembling of liquid pump pedestal:Liquid pump pedestal is put into perforate, between being left between liquid pump pedestal surrounding and perforate Gap and gap length is consistent, it is 25-50mm that distance in perforate is goed deep into liquid pump pedestal bottom, and is pushed up and liquid pump platform deck is counter Roof plate template, is fixed on the flange face of liquid pump pedestal, from oil suction well by the gap location patch triangle pad of seat by bolt The heart draws measuring scale to make the spacing of pedestal and oil suction well theoretical higher than on measuring scale to roof plate template, adjustment template surrounding regulating bolt Data 3-5mm, now measuring scale data are recorded, laser are located at the center of roof plate template, and the light beam of laser is hung down Straight polishing is fixed liquid pump pedestal with iron bell-shaped percussion instrument, used in ancient time by troops on march to suction well center;
Step 3, liquid pump pedestal tack welding:Gap between deck plane and liquid pump pedestal chooses anchor point and makees tack welding, The anchor point at least four;
Step 4, liquid pump pedestal are welded and fixed:Liquid pump pedestal is passed through along the gap between deck plane and liquid pump pedestal The method of single face welding and double face shaping is welded and fixed above deck, and the mode of the welding includes backing welding, filling weldering and cosmetic welding;
Step 5, bottom support installation:Open the laser alignment on roof plate template and inhale well center polishing, the support of adjustment bottom Template makes bottom support shuttering central point be matched with laser polishing point, while is stayed in bottom support shuttering and oil suction bottom There is space, fix bottom support shuttering in six adjustment studs of the gap spot welding, and examine bottom support shuttering and top plate mould Perpendicularity between plate;
Step 6, midfoot support installation:Measuring scale is pulled out from oil suction bottom, middle prop up is determined according to the mark on measuring scale Well center polishing is inhaled in the setting height(from bottom) of support, the laser alignment opened on roof plate template, and middle prop up is adjusted by chain block Hold mode Ban Shi intermediate supports template center's point matches with laser polishing point, examines between intermediate supports template and roof plate template Perpendicularity, intermediate supports are weldingly fixed on bulkhead.
In a kind of above-mentioned ultra-large type liquid pump installation and locating method peculiar to vessel of the invention, the angle of the groove in step 1 Spend for 45 °, it is 2mm that groove, which stays the length of root,.
In a kind of above-mentioned ultra-large type liquid pump installation and locating method peculiar to vessel of the invention, liquid pump pedestal surrounding and perforate Between gap width be 8mm.
In a kind of above-mentioned ultra-large type liquid pump installation and locating method peculiar to vessel of the invention, the weldering of the tack welding is a length of 10-15mm。
Further, in step 3, after tack welding terminates, the both ends of the weld seam after cooling is polished and tilted.
In a kind of above-mentioned ultra-large type liquid pump installation and locating method peculiar to vessel of the invention, when using laser every time, Laser calibration operation is carried out, the operation comprises the following steps:Laser is opened, polishing point of the laser beam on oil suction well is done Lower mark;Rotary laser, mark now polishing point of the laser beam on oil suction well is often rotated by 90 °, until laser rotates 360 ° of end;Examine it is above-mentioned mark whether using inhale well center as the center of circle, diameter 10mm circle in, if it is all mark all fall within In the circle, calibration terminates, if at least one mark be present exceeds the circle, adjusts laser, then repeats the above steps until institute There is mark to all fall within the circle, calibration terminates.
In a kind of above-mentioned ultra-large type liquid pump installation and locating method peculiar to vessel of the invention, in step 4, in liquid pump During pedestal is welded and fixed, operation is carried out using the welding sequence being symmetrically welded, and ensure laser during weld job The polishing point of instrument fall using inhale well center as the center of circle, diameter 10mm circle in, will corresponding one when polishing point offsets out the bowlder The weld seam of side is excluded to be welded again, until welding finishes.
Further, after welding, using measuring scale verify inhale well center to liquid pump pedestal flange face distance, Ensure the precision of follow-up bottom support and intermediate supports installation.
In a kind of above-mentioned ultra-large type liquid pump installation and locating method peculiar to vessel of the invention, in step 5, bottom is examined Perpendicularity between support shuttering and roof plate template comprises the following steps:One piece of plane is placed at the center of bottom support shuttering Mirror;The laser that verification finishes is opened, if the light beam of level crossing reflection falls on roof plate template, perpendicularity is qualified, if institute The light beam for stating level crossing reflection falls outside roof plate template, and adjustment bottom support shuttering makes level crossing the reflected beams fall in roof plate template On.
In a kind of above-mentioned ultra-large type liquid pump installation and locating method peculiar to vessel of the invention, in step 6, examine middle Perpendicularity between support shuttering and roof plate template comprises the following steps:One piece of plane is placed at the center of intermediate supports template Mirror;The laser that verification finishes is opened, if the light beam of level crossing reflection falls on roof plate template, perpendicularity is qualified, if institute The light beam for stating level crossing reflection falls outside roof plate template, and adjustment intermediate supports template makes level crossing the reflected beams fall in roof plate template On.
Based on above-mentioned technical proposal, there is advantages below compared to prior art:
First, the present invention obviates manual perforate in the perforate stage, on the one hand ensure that the precision and smoothness of perforate, on the other hand Also so that operating efficiency improves, while human cost is not only saved, also shortens shipbuilding period, saved production cost.
2nd, the present invention chose at least four anchor point tack welding stage, one week, ensure that the steadiness and safety of positioning Property, while the weld seam of tack welding is ground to the efficiency and quality that tiltedly, ensure that next step backing welding and filling weldering.
3rd, the present invention is calibrated before laser use every time, the precision of the polishing of laser is ensure that, so as to protect The accuracy of liquid pump installation is demonstrate,proved.
4th, the present invention is vertical between verification measurement and roof plate template after bottom support and intermediate supports install Straight degree, ensure that the precision of liquid pump installation.
Brief description of the drawings
Fig. 1 is the assembling schematic diagram of liquid pump pedestal in the present invention.
Fig. 2 is the liquid pump installation structural representation of the present invention.
Embodiment
Come below in conjunction with the accompanying drawings with specific embodiment to a kind of ultra-large type liquid pump installation and locating method peculiar to vessel of the present invention Do and further elaborate, in the hope of providing a clearer understanding of its course of work and occupation mode, but can not be limited with this The protection domain of fixed patent of the present invention.
As depicted in figs. 1 and 2, by taking the SD125 type liquid pump pedestals of H1707A chemical tankers as an example, a kind of ultra-large type peculiar to vessel Liquid pump installation and locating method, this method comprise the following steps:
Step 1, the perforate of deck plane 2:The perforate center of deck plane 2 is determined with the actual size of bilge oil suction well centre-to-centre spacing bulkhead And sample punching is struck, the actual size includes lateral dimension and longitudinal size, and vertical open pores, perforate are carried out using CUT A diameter of 490mm, along 45 ° of the oblique bevel of perforate top edge after the completion of vertical open pores, and root is stayed in the lower end of perforate, stays root long Spend for 2mm, the surface of perforate and groove is polished smooth;
Step 2, liquid pump pedestal 1 assemble:Liquid pump pedestal 1 is put into perforate, stayed between the surrounding of liquid pump pedestal 1 and perforate There is gap and gap length is consistent, the width in the gap is 8mm, and it is 25- that distance in perforate is goed deep into the bottom of liquid pump pedestal 1 50mm, and 3 are padded with the gap location of liquid pump pedestal 1 patch triangle in counter push up in deck, roof plate template is fixed on by liquid by bolt On the flange face of goods pump pedestal 1, measuring scale is drawn to make pedestal to roof plate template, adjustment template surrounding regulating bolt from well center is inhaled Spacing with oil suction well records now measuring scale data, laser is located at into top plate mould higher than gross data 3-5mm on measuring scale At the center of plate, and the beam orthogonal polishing of laser is set then to choose four iron bell-shaped percussion instrument, used in ancient time by troops on march, the iron bell-shaped percussion instrument, used in ancient time by troops on march is wedge to well center is inhaled Shape structure, the tip portion of wedge structure is inserted in the gap between the surrounding of liquid pump pedestal 1 and perforate and by iron bell-shaped percussion instrument, used in ancient time by troops on march ramming, So as to which liquid pump pedestal 1 be fixed;
Step 3, the tack welding of liquid pump pedestal 1:Choose anchor point and position in gap between deck plane 2 and liquid pump pedestal 1 Weldering, a length of 10-15mm of weldering of the tack welding, the anchor point at least four, after tack welding terminates, by the weld seam after cooling Both ends polishing tilt, to ensure in follow-up welding process with backing welding and filling weldering transition;
Step 4, liquid pump pedestal 1 are welded and fixed:Along the gap between deck plane 2 and liquid pump pedestal 1 by liquid pump pedestal 1 It is welded and fixed above deck by the method for single face welding and double face shaping, the mode of the welding includes backing welding, filling weldering and lid Face is welded, and carries out weld job using the welding sequence being symmetrically welded, and ensure the polishing point of laser during weld job Fall using inhale well center as the center of circle, diameter 10mm circle in, when polishing point offsets out the bowlder, will corresponding side weld seam plane Except welding again, until welding finishes, then verified using measuring scale inhale well center to the flange face of liquid pump pedestal 1 away from From ensureing the precision of the support of follow-up bottom and intermediate supports installation;
Step 5, bottom support installation:Open the laser alignment on roof plate template and inhale well center polishing, the support of adjustment bottom Template 4 makes the central point of bottom support shuttering 4 be matched with laser polishing point, while in bottom support shuttering 4 and oil suction shaft bottom Portion leaves space, and bottom support shutterings 4 are fixed in the adjustment studs of the gap spot welding six, and examine bottom support shuttering 4 with Perpendicularity between roof plate template;
Step 6, midfoot support installation:Measuring scale is pulled out from oil suction bottom, middle prop up is determined according to the mark on measuring scale Well center polishing is inhaled in the setting height(from bottom) of support, the laser alignment opened on roof plate template, and middle prop up is adjusted by chain block Hold mode plate 5 makes the central point of intermediate supports template 5 be matched with laser polishing point, examines intermediate supports template 5 and roof plate template Between perpendicularity, intermediate supports are weldingly fixed on bulkhead.
In step 1, the actual size of first survey room bottom oil suction well centre-to-centre spacing bulkhead measures and distance on deck plane 2 The perforate center of the point, as deck plane 2 of deck waling size correspondent equal.
When using laser every time, laser calibration operation is carried out, the operation comprises the following steps:Open laser, Polishing point of the laser beam on oil suction well is done into lower mark;Rotary laser, be often rotated by 90 ° mark now laser beam in oil suction well On polishing point, until laser is rotated by 360 ° end;Examine above-mentioned mark whether to inhale well center as the center of circle, diameter In 10mm circle, if all marks are all fallen within the circle, calibration terminates, if at least one mark be present exceeds the circle, regulation swashs Light instrument, then repeat the above steps until all marks are all fallen within the circle, calibration terminates.
In step 5, the perpendicularity between bottom support shuttering 4 and roof plate template is examined to comprise the following steps:In bottom One piece of level crossing is placed at the center of support shuttering 4;The laser that verification finishes is opened, if the light beam of level crossing reflection falls On roof plate template, perpendicularity is qualified, if the light beam of level crossing reflection falls outside roof plate template, adjusts bottom support shuttering 4 make level crossing the reflected beams fall on roof plate template.
In step 6, the perpendicularity between intermediate supports template 5 and roof plate template is examined to comprise the following steps:In centre One piece of level crossing is placed at the center of support shuttering 5;The laser that verification finishes is opened, if the light beam of level crossing reflection falls On roof plate template, perpendicularity is qualified, if the light beam of level crossing reflection falls outside roof plate template, adjusts intermediate supports template 5 make level crossing the reflected beams fall on roof plate template.
Certainly, a kind of present invention ultra-large type liquid pump installation and locating method peculiar to vessel in above-described embodiment except telling about Beyond type and mode, in addition to other similar structure composition modes be fixedly connected with mode.Sum it up, the present invention is a kind of Ultra-large type liquid pump installation and locating method peculiar to vessel also includes conversion and the replacement that other will be apparent to those skilled in the art.

Claims (10)

1. a kind of ultra-large type liquid pump installation and locating method peculiar to vessel, it is characterised in that this method comprises the following steps:
Step 1, deck plane(2)Perforate:Deck plane is determined with the actual size of bilge oil suction well centre-to-centre spacing bulkhead(2)Perforate Sample punching is simultaneously struck in center, and the actual size includes lateral dimension and longitudinal size, and vertical open pores are carried out using CUT, Along the oblique bevel of perforate top edge after the completion of vertical open pores, and root is stayed in the lower end of perforate, the surface of perforate and groove is polished It is smooth;
Step 2, liquid pump pedestal(1)Assembling:By liquid pump pedestal(1)It is put into perforate, liquid pump pedestal(1)Surrounding is with opening Gap is left between hole and gap length is consistent, liquid pump pedestal(1)It is 25-50mm that distance in perforate is goed deep into bottom, and on deck Anti- top and liquid pump pedestal(1)Gap location patch triangle pad(3), roof plate template is fixed on by liquid pump pedestal by bolt (1)Flange face on, draw measuring scale to roof plate template from well center is inhaled, adjustment template surrounding regulating bolt makes pedestal and oil suction The spacing of well records now measuring scale data, laser is located in roof plate template higher than gross data 3-5mm on measuring scale At the heart, and make the beam orthogonal polishing of laser to inhaling well center, and with iron bell-shaped percussion instrument, used in ancient time by troops on march by liquid pump pedestal(1)It is fixed;
Step 3, liquid pump pedestal(1)Tack welding:In deck plane(2)With liquid pump pedestal(1)Between gap choose anchor point Do tack welding, the anchor point at least four;
Step 4, liquid pump pedestal(1)It is welded and fixed:Along deck plane(2)With liquid pump pedestal(1)Between gap by liquid pump Pedestal(1)It is welded and fixed above deck by the method for single face welding and double face shaping, the mode of the welding includes backing welding, filling Weldering and cosmetic welding;
Step 5, bottom support installation:Open the laser alignment on roof plate template and inhale well center polishing, the support of adjustment bottom Template(4)Make bottom support shuttering(4)Central point matches with laser polishing point, while in bottom support shuttering(4)With suction Space is left in oil well bottom, and bottom support shuttering is fixed in six adjustment studs of the gap spot welding(4), and examine bottom to support Template(4)Perpendicularity between roof plate template;
Step 6, midfoot support installation:Measuring scale is pulled out from oil suction bottom, middle prop up is determined according to the mark on measuring scale Well center polishing is inhaled in the setting height(from bottom) of support, the laser alignment opened on roof plate template, and middle prop up is adjusted by chain block Hold mode plate(5)Make intermediate supports template(5)Central point matches with laser polishing point, examines intermediate supports template(5)With top Perpendicularity between template die plate, intermediate supports are weldingly fixed on bulkhead.
2. a kind of ultra-large type liquid pump installation and locating method peculiar to vessel according to claim 1, it is characterised in that in step 1 In groove angle be 45 °, it is 2mm that groove, which stays the length of root,.
A kind of 3. ultra-large type liquid pump installation and locating method peculiar to vessel according to claim 1, it is characterised in that liquid pump platform Seat(1)Gap width between surrounding and perforate is 8mm.
A kind of 4. ultra-large type liquid pump installation and locating method peculiar to vessel according to claim 1, it is characterised in that the positioning The a length of 10-15mm of weldering of weldering.
5. a kind of ultra-large type liquid pump installation and locating method peculiar to vessel according to claim 1 or 4, it is characterised in that in step In rapid three, after tack welding terminates, the both ends of the weld seam after cooling are polished and tilted.
6. a kind of ultra-large type liquid pump installation and locating method peculiar to vessel according to claim 1, it is characterised in that make every time During with laser, laser calibration operation is carried out, the operation comprises the following steps:Laser is opened, by laser beam in oil suction well On polishing point do lower mark;Rotary laser, mark now polishing point of the laser beam on oil suction well is often rotated by 90 °, until Laser is rotated by 360 ° end;Examine it is above-mentioned mark whether using inhale well center as the center of circle, diameter 10mm circle in, if all Mark is all fallen within the circle, and calibration terminates, if at least one mark be present exceeds the circle, is adjusted laser, is then repeated above-mentioned Until all marks are all fallen within the circle, calibration terminates step.
7. a kind of ultra-large type liquid pump installation and locating method peculiar to vessel according to claim 1, it is characterised in that in step 4 In, in liquid pump pedestal(1)During being welded and fixed, operation is carried out using the welding sequence being symmetrically welded, and in weld job During ensure laser polishing point fall using inhale well center as the center of circle, diameter 10mm circle in, when polishing point is offset out The bowlder, the weld seam of corresponding side is excluded and welded again, until welding finishes.
A kind of 8. ultra-large type liquid pump installation and locating method peculiar to vessel according to claim 1 or 7, it is characterised in that welding After, verified using measuring scale and inhale well center to liquid pump pedestal(1)The distance of flange face, ensure the support of follow-up bottom and The precision of intermediate supports installation.
9. a kind of ultra-large type liquid pump installation and locating method peculiar to vessel according to claim 1, it is characterised in that in step 5 In, examine bottom support shuttering(4)Perpendicularity between roof plate template comprises the following steps:In bottom support shuttering(4)'s One piece of level crossing is placed at center;The laser that verification finishes is opened, if the light beam of level crossing reflection falls in roof plate template On, perpendicularity is qualified, if the light beam of level crossing reflection falls outside roof plate template, adjusts bottom support shuttering(4)Make plane Mirror the reflected beams fall on roof plate template.
10. a kind of ultra-large type liquid pump installation and locating method peculiar to vessel according to claim 1, it is characterised in that in step In six, intermediate supports template is examined(5)Perpendicularity between roof plate template comprises the following steps:In intermediate supports template(5) Center at place one piece of level crossing;The laser that verification finishes is opened, if the light beam of level crossing reflection falls in top plate mould On plate, perpendicularity is qualified, if the light beam of level crossing reflection falls outside roof plate template, adjusts intermediate supports template(5)Make to put down Face mirror the reflected beams fall on roof plate template.
CN201710546780.3A 2017-07-06 2017-07-06 A kind of ultra-large type liquid pump installation and locating method peculiar to vessel Pending CN107856809A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710546780.3A CN107856809A (en) 2017-07-06 2017-07-06 A kind of ultra-large type liquid pump installation and locating method peculiar to vessel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710546780.3A CN107856809A (en) 2017-07-06 2017-07-06 A kind of ultra-large type liquid pump installation and locating method peculiar to vessel

Publications (1)

Publication Number Publication Date
CN107856809A true CN107856809A (en) 2018-03-30

Family

ID=61699111

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710546780.3A Pending CN107856809A (en) 2017-07-06 2017-07-06 A kind of ultra-large type liquid pump installation and locating method peculiar to vessel

Country Status (1)

Country Link
CN (1) CN107856809A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109131733A (en) * 2018-09-17 2019-01-04 中船澄西船舶修造有限公司 A kind of mounting process of chemical tanker liquid pump
CN109500521A (en) * 2018-10-23 2019-03-22 沪东中华造船(集团)有限公司 A kind of washing of tanks machine support localization method
CN109606563A (en) * 2018-09-21 2019-04-12 沪东中华造船(集团)有限公司 A kind of installation method of two phase stainless steel chemical tanker liquid pump pedestal
CN110342387A (en) * 2019-05-31 2019-10-18 武汉船用机械有限责任公司 The hoisting fixture and hanging method of hydraulic immersed pump
CN110732747A (en) * 2019-09-16 2020-01-31 广州文冲船厂有限责任公司 Welding method
CN113581410A (en) * 2021-07-21 2021-11-02 上海外高桥造船有限公司 Method for mounting cargo oil pump
CN114044108A (en) * 2021-12-14 2022-02-15 武昌船舶重工集团有限公司 Marine ballast pump positioning and mounting method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1371841A (en) * 2001-02-28 2002-10-02 曾民先 Multi-function environment protection type oil-collecting mud-digging boat
CN103673813A (en) * 2013-12-04 2014-03-26 渤海造船厂集团有限公司 Cargo oil pump and turbine mounting and aligning method
CN104986295A (en) * 2015-04-08 2015-10-21 江苏宏强船舶重工有限公司 Installation method for cargo oil pump of cargo oil tank of oil tanker

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1371841A (en) * 2001-02-28 2002-10-02 曾民先 Multi-function environment protection type oil-collecting mud-digging boat
CN103673813A (en) * 2013-12-04 2014-03-26 渤海造船厂集团有限公司 Cargo oil pump and turbine mounting and aligning method
CN104986295A (en) * 2015-04-08 2015-10-21 江苏宏强船舶重工有限公司 Installation method for cargo oil pump of cargo oil tank of oil tanker

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
188331: "FRAMO液压深井泵安装工艺", 《豆丁网,HTTP://WWW.DOCIN.COM/P-1115119699.HTML》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109131733A (en) * 2018-09-17 2019-01-04 中船澄西船舶修造有限公司 A kind of mounting process of chemical tanker liquid pump
CN109606563A (en) * 2018-09-21 2019-04-12 沪东中华造船(集团)有限公司 A kind of installation method of two phase stainless steel chemical tanker liquid pump pedestal
CN109606563B (en) * 2018-09-21 2021-03-19 沪东中华造船(集团)有限公司 Installation method of base of liquid cargo pump of duplex stainless steel chemical tanker
CN109500521A (en) * 2018-10-23 2019-03-22 沪东中华造船(集团)有限公司 A kind of washing of tanks machine support localization method
CN109500521B (en) * 2018-10-23 2021-04-23 沪东中华造船(集团)有限公司 Cabin washing machine support positioning method
CN110342387A (en) * 2019-05-31 2019-10-18 武汉船用机械有限责任公司 The hoisting fixture and hanging method of hydraulic immersed pump
CN110342387B (en) * 2019-05-31 2021-07-27 武汉船用机械有限责任公司 Hoisting tool and hoisting method of hydraulic immersed pump
CN110732747A (en) * 2019-09-16 2020-01-31 广州文冲船厂有限责任公司 Welding method
CN113581410A (en) * 2021-07-21 2021-11-02 上海外高桥造船有限公司 Method for mounting cargo oil pump
CN114044108A (en) * 2021-12-14 2022-02-15 武昌船舶重工集团有限公司 Marine ballast pump positioning and mounting method
CN114044108B (en) * 2021-12-14 2022-08-23 武昌船舶重工集团有限公司 Marine ballast pump positioning and mounting method

Similar Documents

Publication Publication Date Title
CN107856809A (en) A kind of ultra-large type liquid pump installation and locating method peculiar to vessel
CN104986295B (en) A kind of oil ship goods tank Cargo Oil Pump installation method
CN109606542A (en) A method of location and installation precision of the control special equipment pedestal on block
EP2427299B1 (en) Method for manufacturing a door frame, welding arrangement and structure of a door frame
CN108146578A (en) A kind of manufacturing method of two phase stainless steel chemical tanker topside segmentation
CN109079437A (en) Large size liquefied gas storage multilayer limb end socket arrangement and method for construction peculiar to vessel
CN105057855B (en) Erecting welding technological method for single-upper-ring type large segmented stand ring with sole plates
CN107323610A (en) Main engine bed, the installation method in gear block block stage
CN106002008B (en) A kind of ultralow temperature high-power wind turbine tower door frame welding method
CN109900181A (en) Arc frame is to arc method in a kind of fan-shaped section
CN104895082A (en) Precise large-diameter steel casing deviation rectifying device and method
CN101381200B (en) Tin pot base production method of float glass production line
CN109623262A (en) A kind of on-site assembly method of Bellows expansion joint
CN105905261A (en) Vertical general assembly jig frame for container ship lashing bridge
CN107289917A (en) A kind of taper pile method for rapidly positioning waterborne is with examining measuring method
CN110295620A (en) The fast accurate installation method of large-scale space division device overall skid-mounted formula ice chest
US3780903A (en) Corner construction for reinforcing rib on tank made from thin sheet metal
CN115383407B (en) Machining and manufacturing method of wall-mounted cross crane beam
WO2023124244A1 (en) Positioning device and use method therefor
CN205742129U (en) A kind of vertical ship lift balance weight track Fast Installation adjusting apparatus
CN106584233B (en) A kind of circumferential weld weld root cleaning device, back chipping mechanism and back chipping method
CN110144828A (en) The linear control method of the location structure of steel box girder assembling, support construction and bridge
CN111843108B (en) End socket inner wall surfacing method and end socket inner wall scribing device applied in method
CN109396610A (en) A kind of welding procedure of bellows
CN108381128B (en) Manufacturing method of I-shaped weather-resistant steel edge girder with lifting point penetrating out

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180330