CN107844873A - One introduces a collection net coordinates performance whole-life cycle fee system and its management method - Google Patents

One introduces a collection net coordinates performance whole-life cycle fee system and its management method Download PDF

Info

Publication number
CN107844873A
CN107844873A CN201610730804.6A CN201610730804A CN107844873A CN 107844873 A CN107844873 A CN 107844873A CN 201610730804 A CN201610730804 A CN 201610730804A CN 107844873 A CN107844873 A CN 107844873A
Authority
CN
China
Prior art keywords
unit
management
equipment
life cycle
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610730804.6A
Other languages
Chinese (zh)
Inventor
汤伟
杨铖
陈真
施秀萍
黄远超
江世杰
唐耀华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Anhui Electric Power Co Ltd
State Grid Henan Electric Power Co Ltd
Nanjing NARI Group Corp
Original Assignee
State Grid Corp of China SGCC
State Grid Anhui Electric Power Co Ltd
State Grid Henan Electric Power Co Ltd
Nanjing NARI Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Anhui Electric Power Co Ltd, State Grid Henan Electric Power Co Ltd, Nanjing NARI Group Corp filed Critical State Grid Corp of China SGCC
Priority to CN201610730804.6A priority Critical patent/CN107844873A/en
Publication of CN107844873A publication Critical patent/CN107844873A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention, which provides introduces a collection net coordination performance whole-life cycle fee system and its management method, the system, to be included:System configuration module, life cycle management module, on-line monitoring module and the statistical analysis module being sequentially connected.Its method includes:The prophase management of equipment, equipment operation management, the dynamic monitoring management of equipment, equipment rotation and scrap management.Technical scheme provided by the invention improves source net coordinated management level, realizes comprehensive, real-time, dynamic and grasps unit source net coordination performance.

Description

One introduces a collection net coordinates performance whole-life cycle fee system and its management method
Technical field
The present invention relates to a kind of whole-life cycle fee system, an in particular to introduces a collection net coordinates performance life cycle management Management system and its management method.
Background technology
Whole-life cycle fee refer to a system or equipment from early stage, go into operation, to run to the life cycle such as retired each Individual link carries out the management of overall process, and to be better understood by the system or equipment, targetedly the system or equipment has been carried out It is kind.
The quality that generating set source net coordinates performance has vital influence on electricity net safety stable.Source net is coordinated at present Performance management is mainly verified and verified by field test of new machine when grid-connected, is then passed through after unit commitment commercial operation Artificial report carries out management with offline verification mode.As extra-high voltage alternating current-direct current power network is fast-developing, and distributed and concentration The new energy large-scale grid connection such as wind-powered electricity generation and photovoltaic of formula, power network dynamic characteristic is increasingly sophisticated, simultaneously because unit generates electricity after putting into operation Enterprise from improving performance angle considers that light maintenance, overhaul can be carried out, partly or wholly transformed, and repairs every time and improved unit is joined For number all by that may readjust, other part source net coordinates performance can not bring direct generation of electricity benefit, power plant to power plant in itself Side is for number one considers possible adjustment control system parameter, therefore field test and artificial pattern verification are difficult in time comprehensively Grasp generating set source net and coordinate performance.
For this reason, it may be necessary to providing a kind of generating set source net coordinates performance whole-life cycle fee system and method, with lifting Source net coordinated management is horizontal, and comprehensive, real-time, dynamic grasps unit source net coordination performance.
The content of the invention
In order to solve the above-mentioned deficiency in the presence of prior art, the present invention provides a kind of generating set source net and coordinates performance Whole-life cycle fee system and method.
Technical scheme provided by the invention is:A kind of generating set source net coordinate performance whole-life cycle fee system and its Method, the system include:System configuration module, life cycle management module, on-line monitoring module and the statistics being sequentially connected Analysis module.
Preferably, the system configuration module includes:
(1) submodule of acquisition system configuring maintenance information;
(2) submodule of the relation database table structure of system configuration is established;
(3) typing generating set information and it is stored in the submodule of relational database;
(4) submodule safeguarded to system.
Preferably, the life cycle management module includes:Relation database table construction unit, the thermoelectricity hydroelectric machine of parallel connection Group archives and information management unit, wind-powered electricity generation photovoltaic unit archives and information management unit, test report information management unit, definite value change Information management unit, operation maintenance information management unit, unit increase-volume information management unit, unit equipment change information management list Member, unit change of title information management unit, equipment deficiency information management unit, on-line monitoring assay administrative unit, report Useless record information administrative unit, equipment state change management unit and running status management function.
Preferably, the on-line monitoring module includes:Source net coordinates performance on-line monitoring unit and definite value changes online prison Survey unit.
Preferably, the statistical analysis module includes:Test report statistical report form submodule, equipment deficiency statistical report form Module, unit source net coordinate performance state Real-Time Evaluation statistical report form submodule, unit source net coordinates whole-life cycle fee system Count form submodule, subregion statistical report form submodule and divide electricity power group's statistical report form submodule.
One introduces a collection net coordinates performance whole-life cycle fee method, and methods described includes:
1) prophase management of equipment;
2) operational management of equipment;
3) dynamic monitoring management of equipment;
4) rotation of equipment and management is scrapped.
Preferably, the prophase management of the step 1) equipment includes:Establish life cycle management archives, acquisition system configuration dimension Information, opening relationships database table structure are protected, typing generating set information is simultaneously stored in relational database, system is safeguarded.
Preferably, the operational management of the step 2) equipment includes:Grid-connected examination, the filing and management of test report;
The grid-connected examination includes:Grid-connected examination to unit, and the suggestion feedback of examination is proposed whole to electricity power enterprise Change opinion and regulation rectification time limit;
The filing and management of the test report include:To grid-connected conditions identification, grid-connected examination opinion, written rectification situation Report, grid connection test report and unit relate to net experiment correlation report and are filed and managed.
Preferably, the dynamic monitoring management of the step 3) equipment includes:Unit definite value is become by monitoring module on-line Dynamic information, On-Line Dynamic Monitoring index and evaluation result carry out filing management.
Preferably, the rotation of the step 4) equipment and scrap management and include:Unit technological transformation overhaul maintenance, equipment rotation, Equipment operation maintenance, tissue test and hidden troubles removing improvement and equipment scrapping.
With immediate prior art ratio, count protocol provided by the invention has following excellent effect:
1st, technical scheme provided by the invention reaches comprehensive, real-time, dynamic is slapped by the information system management to generating set Hold unit source net and coordinate performance, it is horizontal effectively to improve source net coordinated management;
2nd, technical scheme provided by the invention promotes the up to standard of power plant unit performance by monitoring, examining and manage, Avoid in time and power grid risk occur because unit performance is not up to standard.Technical scheme provided by the invention is formulated and has issued a system Row specialized management system, it is ensured that source net dynamic characteristic on-line monitoring and management is implemented;To promoting power network and power supply to coordinate to transport Row, power system controllability and reliability are enhanced, improves power system comprehensive energy efficiency, ensure that power system security is stable Quality and economy is run.
3rd, technical scheme provided by the invention according to " one grade of a machine " principle, to each unit and its control system Source net coordinates performance and establishes life cycle management archives, and complete documentation design early stage review comment, new set grid-connection check and accept meaning See and rectify and improve situation, new set grid-connection test report, performance test report and assess record, operation hidden danger after unit technological transformation overhaul Special project investigation improvement situation and online dynamic evaluation result etc., realize the key of unit source net coordination information one have access to, related system Count the generation of the key of information one.
Brief description of the drawings
The generating set source net that Fig. 1 is the present invention coordinates performance whole-life cycle fee system schematic diagram;
The generating set source net that Fig. 2 is the present invention coordinates performance whole-life cycle fee system flow chart;
The generating set source net that Fig. 3 is the present invention coordinates performance whole-life cycle fee system structure diagram.
Embodiment
For a better understanding of the present invention, present disclosure is done further with reference to Figure of description and example Explanation.
The present invention provides a kind of generating set source net and coordinates performance whole-life cycle fee system and method, the system Including:System configuration module, life cycle management module, on-line monitoring module and the statistical analysis module being sequentially connected;
The system configuration module includes:
(1) acquisition system configuring maintenance information:
Including with possessory lien unit, affiliated electricity power group, affiliated area, producer's unit, device type, test type, dimension Shield type, value type, scrap type, fault type, voltage class, the title of machine set type.
(2) the relation database table structure of system configuration is established:
Establishing is included with possessory lien unit, affiliated electricity power group, affiliated area, producer's unit, device type, experiment class Type, safeguard type, value type, scrap type, fault type, voltage class, the relation database table of the title of machine set type Structure.
(3) typing generating set information and it is stored in relational database:
Typing is included with possessory lien unit, affiliated electricity power group, affiliated area, producer's unit, device type, experiment class Type, type, value type are safeguarded, the information such as type, fault type, voltage class, the title of machine set type, code is scrapped and deposits Enter in relational database.
(4) system is safeguarded:
System maintenance is mainly to manage, create and adjust role, user and its authority of system, and carries out system operatio power Limit distribution;Set and the real time information of adjustment system is fed back;Operation Log, data backup and data recovery operation are completed, is ensured System well operates.
The life cycle management module includes:The relation database table construction unit that is connected in parallel, thermoelectricity Hydropower Unit Archives and information management unit, wind-powered electricity generation photovoltaic unit archives and information management unit, test report information management unit, definite value change letter Cease administrative unit, operation maintenance information management unit, unit increase-volume information management unit, unit equipment and change information management list Member, unit change of title information management unit, equipment deficiency information management unit, on-line monitoring assay administrative unit, report Useless record information administrative unit, equipment state change management unit and running status management function;
Relation database table construction unit includes thermoelectricity Hydropower Unit archives and information management table, wind-powered electricity generation photovoltaic unit archives are believed Breath management table, test report information management table, definite value change information management table, operation maintenance information management table, unit increase-volume letter Breath management table, unit equipment change information management table, equipment deficiency information management table, scrap the relation numbers such as record information management table According to database table structure.
Thermoelectricity Hydropower Unit archives and information management unit, there is provided human-computer interaction interface, realize the hair to thermoelectricity Hydropower Unit Group of motors Chinese name, voltage class, unit model, the time of putting into operation, property right unit, electricity power group, affiliated area, producer's unit, The increase of the information such as machine set type, modification, deletion action, and in real time guest operation record renewal into database.
Wind-powered electricity generation photovoltaic unit archives and information management unit, there is provided human-computer interaction interface, realize the factory to wind-powered electricity generation photovoltaic unit Station name, voltage class, the wiring map title, wind energy turbine set installed capacity, wind power plant installation number of units, Reactive Compensation in Wind Farm capacity, wind Electric field geography information longitude, wind power plant geography information latitude, wind power plant abbreviation, wind power plant address, the time of putting into operation, property right unit, The increase of the information such as electricity power group, affiliated area, producer's unit, grid connection capacity, machine set type, modification, deletion action, and in real time Guest operation record renewal into database.
Test report information management unit, there is provided human-computer interaction interface, realize that the grid connection test report to unit carries out pipe Reason.Every record include generating set Chinese name, test period, whether qualified, pdf forms test report document, test in The information fields such as appearance, device type, test type, and record can be increased, change, delete, preserving operation.
Definite value change information management unit, there is provided human-computer interaction interface, realize that changing record to the definite value of unit carries out pipe Reason.Every record includes generating set Chinese name, changes the time, changes the information fields such as record, record sign, value type, and Record can be increased, change, delete, preserving operation.
Operation maintenance information management unit, there is provided human-computer interaction interface, realize that the record of the operation maintenance to unit carries out pipe Reason.Every record, which includes generating set Chinese name, maintenance time, maintenance record, record, to be indicated, safeguards the information fields such as type, and Record can be increased, change, delete, preserving operation.
Unit increase-volume information management unit, there is provided human-computer interaction interface, realize that the record of the unit increase-volume to unit carries out pipe Reason.Every record include generating set Chinese name, the increase-volume time, increase-volume record, record indicate etc. information field, and can to record into Row increase, modification, delete, preserve operation.
Unit equipment change information management unit, there is provided human-computer interaction interface, realize the equipment replacement to unit record into Row management.Every record includes generating set Chinese name, replacing construction, changes the information such as record, record sign, device type Domain, and record can be increased, change, delete, preserving operation.
Unit change of title information management unit, there is provided human-computer interaction interface, realize the change of title to unit record into Row management.Every record includes generating set Chinese name, change time, originates in the letters such as power affiliated unit, existing property right affiliated unit Domain is ceased, and record can be increased, be changed, delete, preserving operation.
Equipment deficiency information management unit, there is provided human-computer interaction interface, realize and pipe is carried out to the equipment deficiency record of unit Reason.Every record includes the information fields such as generating set Chinese name, fault time, defect content, fault type, device type, and Record can be increased, change, delete, preserving operation.
Monitor assay administrative unit on-line, there is provided human-computer interaction interface, to definite value transition information, On-Line Dynamic Monitoring Index and evaluation result carry out filing management, netted according to unit source coordinate performance state Real-Time Evaluation result, Optimizing Suggestions and The information such as the recessive defect of set speed adjustment system, excitation system and PSS, and record can be increased, change, delete, preserving Operation.
Scrap record information administrative unit, there is provided human-computer interaction interface, realize and the record of scrapping of unit is managed.Often Bar record include generating set Chinese name, failure time, scrap record, scrap the information fields such as type, remarks, and can to record into Row increase, modification, delete, preserve operation.
Equipment state change management unit, there is provided human-computer interaction interface, recording equipment are enabled, disabled, leaving unused, rent into, Lease, be transferred to, produce, failure, accident, the management scrapped etc., quickly and accurately provide equipment current state for administrative decision layer, And record can be increased, change, delete, preserving operation.
Running status management function, there is provided human-computer interaction interface, recording equipment day-to-day operation man-hour information, the energy disappear Information, operator message etc. are consumed, and record can be increased, be changed, delete, preserving operation.
The on-line monitoring module includes:Source net coordinates performance on-line monitoring unit and definite value changes on-line monitoring unit. Realize that the generator sets in power plant based on WAMS information relates to network parameters model configuration feature, including:Parameter name, parameter type, The functions such as parameter value, protection type, protection title, protection definite value, remarks, establish generating set motor excitation system, PSS parameter Model, transformer unit voltage protection, frequency protection, field loss protection, loss of synchronism protection etc. relate to net and protect important definite value model.
Power plant field performance statistical appraisal advanced application function of the realization based on WAMS information, including generating set are effective Excitation output response lag time, excitation system transient state multiplication factor, dynamic multiplication factor and stable state amplification under voltage disturbance The indexs such as multiple;Frequency of oscillation, oscillation damping ratio, PSS dynamics multiplication factor, PSS dynamical output phases under system oscillation etc. Function, the active power of generator loading step response evaluation and the evaluation of excitation system nominal response etc..
Realize the advanced application function of generating set primary frequency regulation performance evaluation based on WAMS information, including generating set ginseng Frequency modulation contributing electricity, primary frequency modulation effectiveness indicator, primary frequency modulation performance indicator-specific statistics, primary frequency modulation action with primary frequency modulation are just The function such as true rate and devoting rate statistics.
The statistical analysis module includes:Test report statistical report form, equipment deficiency statistical report form, unit source net are coordinated Performance state Real-Time Evaluation statistical report form, unit source net coordinate whole-life cycle fee statistical report form, subregion statistical report form and Electricity power group's statistical report form is divided to carry out comprehensive statistics analysis.
Test report statistical report form is to look into according to test period, whether qualified, content of the test, device type, test type Inquiry condition, statistical separates out the unit test data sheet in the period from relational database.
Equipment deficiency statistical report form is querying condition according to fault time, defect content, fault type, device type, from Analysis shows the unit equipment defect record in the period in relational database.
Unit source net coordinates performance state Real-Time Evaluation statistical report form, on-line computer group excitation actuating accuracy and once Frequency modulation acts accuracy, netted according to unit source coordinate performance state Real-Time Evaluation result, Optimizing Suggestions and set speed adjustment system, The information such as excitation system and PSS recessive defect.
Unit source net coordinates whole-life cycle fee statistical report form, including unit experiment, definite value variation, system maintenance, machine The generating sets such as group increase-volume, equipment replacement, equipment changing, system defect, unit are scrapped, excitation event and primary frequency modulation event are complete The Information Statistics of life cycle closed loop management are analyzed.
Subregion statistical report form and divide electricity power group's statistical report form, according to area belonging to unit, to unit in the region Comprehensive condition carries out statistical analysis and counted according to the affiliated electricity power group of unit, the comprehensive condition to electricity power group's unit Analysis.
Count equipment items technical-economic index and comprehensive state, there is provided defeated for the form of different management leveled demands Go out.By various statistics and index, manager comprehensively, is fast and accurately understood current enterprise generator set device makes With situation, auxiliary leader carries out enterprise management decision making.
A kind of generating set source net coordinates performance whole-life cycle fee method, and methods described includes:
1) plan diagram;
2) equipment operation management;
3) dynamic monitoring management of equipment;
4) equipment rotation and management is scrapped.
The step 1) includes:Establish life cycle management archives, acquisition system configuring maintenance information, opening relationships database Table structure, typing generating set information are simultaneously stored in relational database, system are safeguarded.
Principle of the life cycle management archives according to " one grade of a machine " is established, to each unit and its net source of control system Coordinate performance and establish life cycle management archives, including the affiliated plant stand of every unit, affiliated voltage class, affiliated property right unit, institute Belong to the Back ground Informations such as electricity power group, affiliated area, unit model and time of putting into operation.
Before filing management, including project being carried out to new-built unit project's earlier stage, engineering early stage and Construction Phase data Phase tissue establishment, feasibility study evaluation and approval data, the evaluation of engineering preliminary stage preliminary design and construction bid data, Construction Phase Go into operation with asbuilt documentation etc..
The prophase management of generator set device:Including programmed decision-making, plan, investigation, purchase, stock, until installation and debugging, Grid connection test, all processes of trial operation.According to unit archive information unique mark, improving includes thermoelectricity, water power, wind-powered electricity generation and light Lie prostrate buying early stage of unit engineering, stock control, installation construction period and operation phase data and carry out filing management.
The step 2) includes:The filing management of grid-connected receipt control and test report;
The grid-connected receipt control includes:Grid-connected work is responsible for by saving to adjust, and participating department is sales department of provincial electric power company, section Letter portion and DianKeYuan, the grid-connected examination to unit, and suggestion feedback will be checked and accepted to electricity power enterprise, specify every reform advice and whole Change the date limit, after completing rectifying and improving, rectification situation report is submitted to saving to adjust;
The filing management of the test report includes:To grid-connected conditions identification, grid-connected examination opinion, written rectification situation report Accuse, grid connection test report and unit relate to net experiment correlation report and carry out filing management.
Unit relate to net experiment correlation report relates to net pilot project etc. including fired power generating unit, wind power plant relates to net pilot project etc., Photovoltaic plant relates to net pilot project etc..
The step 3) includes:By monitor on-line module to unit definite value transition information, On-Line Dynamic Monitoring index and Evaluation result carries out filing management.
Monitor assay management on-line:Definite value transition information, On-Line Dynamic Monitoring index and evaluation result are returned Shelves management, nets according to unit source and coordinates performance state Real-Time Evaluation result, Optimizing Suggestions and set speed adjustment system, excitation system And the information such as PSS recessive defect.
The step 4) includes:Unit technological transformation overhaul maintenance management, equipment rotation management, equipment operation maintenance management, group Knit experiment and management and equipment scrapping management are administered in hidden troubles removing.
Unit technological transformation overhaul maintenance management:Including excitation system reconstruction, governing system replacing, unit capacity-increasing transformation, unit The data such as equipment replacement, unit change of title, equipment deficiency information carry out filing management.
Equipment rotation management:For part repairable queue, equipment periodically carries out rotation and offline repair is maintained, Ran Houji Continuous change is on active service.Rotation management is purchased for reduction and maintenance cost, and recycling equipment has certain meaning.
Equipment operation maintenance management:Including the daily maintenance for preventing inferior equipment function and carrying out, check, monitoring, Diagnosis and the management such as repairing, renewal, the purpose is to ensure equipment in the process of running often in good technique state, and have Effect ground reduces maintenance cost.
Management is administered in tissue test and hidden troubles removing:Including being recorded to performance test report, assessment after unit technological transformation overhaul Situation is administered in report, special hidden troubles removing and unit scraps record information and carries out filing management.
Equipment scrapping management:Equipment has integrally arrived service life, Frequent Troubles, has influence on the reliability of equipment group, it is tieed up Accomplish this exceeds equipment purchase cost, it is necessary to equipment is changed, the asset of equipments after replacing sold off or transferred the possession of or Disposal, Erecting and improving scrap flow.Scrap management and represent that equipment life formally terminates, so that equipment full life cycle management Form closed loop.
Embodiments of the invention are these are only, are not intended to limit the invention, it is all in the spirit and principles in the present invention Within, any modification, equivalent substitution and improvements done etc., be all contained in apply pending scope of the presently claimed invention it It is interior.

Claims (10)

1. an introduces a collection net coordinates performance whole-life cycle fee system, the system includes:The system configuration module that is sequentially connected, Life cycle management module, on-line monitoring module and statistical analysis module.
2. source net as claimed in claim 1 coordinates performance whole-life cycle fee system, it is characterised in that the system configuration Module includes:
(1) submodule of acquisition system configuring maintenance information;
(2) submodule of the relation database table structure of system configuration is established;
(3) typing generating set information and it is stored in the submodule of relational database;
(4) submodule safeguarded to system.
3. source net as claimed in claim 1 coordinates performance whole-life cycle fee system, it is characterised in that the life cycle Management module includes:Relation database table construction unit, thermoelectricity Hydropower Unit archives and information management unit, the wind-powered electricity generation photovoltaic of parallel connection Unit archives and information management unit, test report information management unit, definite value change information management unit, operation maintenance message tube Manage unit, unit increase-volume information management unit, unit equipment and change information management unit, unit change of title information management list Member, equipment deficiency information management unit, monitor assay administrative unit on-line, scrap record information administrative unit, equipment shape State change management unit and running status management function.
4. source net as claimed in claim 1 coordinates performance whole-life cycle fee system, it is characterised in that the on-line monitoring Module includes:Source net coordinates performance on-line monitoring unit and definite value changes on-line monitoring unit.
5. source net as claimed in claim 1 coordinates performance whole-life cycle fee system, it is characterised in that the statistical analysis Module includes:Test report statistical report form submodule, equipment deficiency statistical report form submodule, the unit source net of parallel connection coordinate performance State Real-Time Evaluation statistical report form submodule, unit source net coordinate whole-life cycle fee statistical report form submodule, subregion system Count form submodule and divide electricity power group's statistical report form submodule.
6. an introduces a collection net coordinates performance whole-life cycle fee method, it is characterised in that methods described includes:
1) prophase management of equipment;
2) operational management of equipment;
3) dynamic monitoring management of equipment;
4) rotation of equipment and management is scrapped.
7. generating set source net as claimed in claim 6 coordinates performance whole-life cycle fee method, it is characterised in that described The prophase management of step 1) equipment includes:Life cycle management archives are established, acquisition system configuring maintenance information, establish system configuration Relation database table structure, typing generating set information are simultaneously stored in relational database, system are safeguarded.
8. generating set source net as claimed in claim 6 coordinates performance whole-life cycle fee method, it is characterised in that described The operational management of step 2) equipment includes:Grid-connected examination, the filing and management of test report;
The grid-connected examination includes:Grid-connected examination to unit, and the suggestion feedback of examination is proposed into rectification meaning to electricity power enterprise See and regulation rectifies and improves the time limit;
The filing and management of the test report include:To grid-connected conditions identification, grid-connected examination opinion, written rectification situation report Accuse, grid connection test report and unit relate to net experiment correlation report and filed and managed.
9. generating set source net as claimed in claim 6 coordinates performance whole-life cycle fee method, it is characterised in that described The dynamic monitoring management of step 3) equipment includes:By monitoring module on-line to unit definite value transition information, On-Line Dynamic Monitoring Index and evaluation result carry out filing management.
10. generating set source net as claimed in claim 6 coordinates performance whole-life cycle fee method, it is characterised in that institute Stating the rotation of step 4) equipment and scrapping management includes:Unit technological transformation overhaul maintenance, equipment rotation, equipment operation maintenance, tissue Experiment and hidden troubles removing improvement and equipment scrapping.
CN201610730804.6A 2016-08-26 2016-08-26 One introduces a collection net coordinates performance whole-life cycle fee system and its management method Pending CN107844873A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610730804.6A CN107844873A (en) 2016-08-26 2016-08-26 One introduces a collection net coordinates performance whole-life cycle fee system and its management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610730804.6A CN107844873A (en) 2016-08-26 2016-08-26 One introduces a collection net coordinates performance whole-life cycle fee system and its management method

Publications (1)

Publication Number Publication Date
CN107844873A true CN107844873A (en) 2018-03-27

Family

ID=61656389

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610730804.6A Pending CN107844873A (en) 2016-08-26 2016-08-26 One introduces a collection net coordinates performance whole-life cycle fee system and its management method

Country Status (1)

Country Link
CN (1) CN107844873A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112365173A (en) * 2020-11-16 2021-02-12 云南电网有限责任公司昆明供电局 Method for standardizing field acceptance test of power transformation equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101320259A (en) * 2007-12-14 2008-12-10 上海发电设备成套设计研究院 Important component service life management method and system for unit generator set main unit
CN104200245A (en) * 2014-08-10 2014-12-10 国家电网公司 Quick checking method for life cycle asset of power asset
CN104361419A (en) * 2014-09-10 2015-02-18 国家电网公司 Electric transmission and transformation equipment state monitoring defect management system and method based on regulation and control integration
CN104503399A (en) * 2014-12-09 2015-04-08 华电电力科学研究院 Group stage wind power generator set state monitoring and fault diagnosis platform
CN105741053A (en) * 2016-03-07 2016-07-06 特瑞斯能源装备股份有限公司 Whole life-cycle management model for intelligent gas device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101320259A (en) * 2007-12-14 2008-12-10 上海发电设备成套设计研究院 Important component service life management method and system for unit generator set main unit
CN104200245A (en) * 2014-08-10 2014-12-10 国家电网公司 Quick checking method for life cycle asset of power asset
CN104361419A (en) * 2014-09-10 2015-02-18 国家电网公司 Electric transmission and transformation equipment state monitoring defect management system and method based on regulation and control integration
CN104503399A (en) * 2014-12-09 2015-04-08 华电电力科学研究院 Group stage wind power generator set state monitoring and fault diagnosis platform
CN105741053A (en) * 2016-03-07 2016-07-06 特瑞斯能源装备股份有限公司 Whole life-cycle management model for intelligent gas device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112365173A (en) * 2020-11-16 2021-02-12 云南电网有限责任公司昆明供电局 Method for standardizing field acceptance test of power transformation equipment

Similar Documents

Publication Publication Date Title
Denholm et al. The challenges of achieving a 100% renewable electricity system in the United States
Feng et al. Power system operation risk assessment using credibility theory
CN104361419B (en) Power transmission and transformation equipment state monitoring fault management system and method based on regulation and control unification
Varela et al. The IGREENGrid project: Increasing hosting capacity in distribution grids
Wu et al. GENCO's risk-based maintenance outage scheduling
Ding et al. Multi-period active distribution network planning using multi-stage stochastic programming and nested decomposition by SDDIP
CN107766457A (en) A kind of thermal power plant's operation management system and its task executing method
CN104657824B (en) Modern power distribution net power supply plan automatic creation system
CN107169617A (en) A kind of controller switching equipment state evaluation system
CN104182902A (en) Monitoring method based on centralized operation and maintenance system of dispatching data network
CN106228300A (en) A kind of distributed power source operation management system
CN103093303A (en) Outage schedule management apparatus and method in ems
CN108460467A (en) A kind of photovoltaic operation management system
Boardman The role of integrated distribution management systems in smart grid implementations
Raza et al. Towards improving technical performance of a 747 MW thermal power plant
CN107844873A (en) One introduces a collection net coordinates performance whole-life cycle fee system and its management method
Judson et al. Application of a resilience framework to military installations: A methodology for energy resilience business case decisions
Parzen et al. Reducing energy system model distortions from unintended storage cycling through variable costs
CN101409396A (en) Power usage management system for electric power system
CN114372594A (en) Distributed power supply comprehensive analysis and safety management and control system
Payyala et al. Sizing of distributed generation plant through techno-economic feasibility assessment
Armanda et al. Plans for upgrading existing conventional 150 kv substations into digital substations in Sulawesi-Indonesia, accompanied by Financial Studies
JP4597076B2 (en) Power system blackout work plan setting method and system
He et al. Maintenance risk management in Daya Bay nuclear power plant: PSA model, tools and applications
CN107317393A (en) Intelligent distribution network application management system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180327