CN107818371A - Operation management APP method - Google Patents

Operation management APP method Download PDF

Info

Publication number
CN107818371A
CN107818371A CN201711021769.1A CN201711021769A CN107818371A CN 107818371 A CN107818371 A CN 107818371A CN 201711021769 A CN201711021769 A CN 201711021769A CN 107818371 A CN107818371 A CN 107818371A
Authority
CN
China
Prior art keywords
work order
cabinet
server
operating personnel
electrical form
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711021769.1A
Other languages
Chinese (zh)
Inventor
曹辉
邵凡
薛海涛
施沩
黄伟刚
张驰
鲁燕
何斌
施辉
黄家伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
Nantong Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Power Supply Co of State Grid Jiangsu Electric Power Co Ltd filed Critical Nantong Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority to CN201711021769.1A priority Critical patent/CN107818371A/en
Publication of CN107818371A publication Critical patent/CN107818371A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F1/00Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
    • G06F1/16Constructional details or arrangements
    • G06F1/18Packaging or power distribution
    • G06F1/181Enclosures
    • G06F1/182Enclosures with special features, e.g. for use in industrial environments; grounding or shielding against radio frequency interference [RFI] or electromagnetical interference [EMI]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F1/00Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
    • G06F1/16Constructional details or arrangements
    • G06F1/20Cooling means
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063112Skill-based matching of a person or a group to a task
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2200/00Indexing scheme relating to G06F1/04 - G06F1/32
    • G06F2200/20Indexing scheme relating to G06F1/20
    • G06F2200/201Cooling arrangements using cooling fluid
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02DCLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
    • Y02D10/00Energy efficient computing, e.g. low power processors, power management or thermal management

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • General Engineering & Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Human Computer Interaction (AREA)
  • Public Health (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Electromagnetism (AREA)
  • Computer Hardware Design (AREA)
  • Power Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A kind of operation management APP method, when sending worker person to need to arrange for operating personnel to detect the equipment of power network, the second electrical form is just opened on background server, the input of work order state is 0;Background server is arranged in server cabinet, the server cabinet is rectangular parallelepiped structure, the roof of the server cabinet is provided with the liquid storage cabinet for accommodating refrigerating fluid, the two for the cavity that the bottom wall of the liquid storage cabinet for accommodating refrigerating fluid penetrates with two communicates, and the cavity of two insertion is on the edge surface in server cabinet;Effectively prevent wastes time and energy that cumbersome, refrigeration performance is bad, the performance of background server is damaged, the defects of microwave damages to staff's body in the prior art.

Description

运维管理APP的方法Operation and maintenance management APP method

技术领域technical field

本发明涉及运维管理技术领域,具体涉及一种运维管理APP的方法。The present invention relates to the technical field of operation and maintenance management, in particular to a method for operation and maintenance management APP.

背景技术Background technique

随着智能电网建设的不断发展和持续深入,营销计量业务、工程项目逐渐增多,操作员在施工作业现场呈现点多面广的特点。同时,客户对于供电服务透明化,智能互动深入化的要求也不断提高。与之相矛盾的是,派工人员结构性缺员愈发严重,难以满足作业现场管控要求,计量施工作业现场安全、质量、进度、服务等问题日益凸显。因此,如何强化现场管控能力,提高作业安全和质量,提升服务品质,同时有效降低管理成本,成为专业管理当务之急。With the continuous development and continuous deepening of smart grid construction, marketing measurement business and engineering projects are gradually increasing, and operators present a wide range of points at the construction site. At the same time, customers' requirements for transparent power supply services and in-depth intelligent interaction are also increasing. Contradictory to this is that the structural shortage of dispatched workers is becoming more and more serious, making it difficult to meet the requirements of job site management and control, and the problems of metering construction site safety, quality, progress, and service have become increasingly prominent. Therefore, how to strengthen on-site management and control capabilities, improve operation safety and quality, improve service quality, and effectively reduce management costs has become a top priority for professional management.

具体而言,派工人员把检测电网设备的任务人工派发给操作员,操作员必须从现场赶到派工人员处领取任务,然后返回现场检测,而检测完毕后还要回返用纸档的形式把检测结果交给派工人员,这样费时费力操作繁琐。Specifically, the dispatcher manually assigns the task of testing the grid equipment to the operator, and the operator must rush from the site to the dispatcher to pick up the task, and then return to the site for inspection, and return to the form of a paper file after the inspection is completed. It is time-consuming, laborious and cumbersome to hand over the test results to the dispatcher.

现在的所述后台服务器设置在服务器机柜中,服务器机柜为长方体结构,现在服务器机柜通常都伴着制冷效果不佳的缺陷,往往经由气流制冷,制冷性能不佳,对后台服务器的性能有损。后台服务器工作时会发射出微波,对工作人员身体有损。The present background server is arranged in the server cabinet, and the server cabinet is a cuboid structure. Now the server cabinet is usually accompanied by the defect of poor cooling effect, which is often cooled by air flow, and the cooling performance is not good, which is detrimental to the performance of the background server. When the background server is working, it will emit microwaves, which will damage the health of the staff.

这样就须研制服务器机柜,经由在服务器机柜上安装储存有制冷液的柜体且于所述柜体的底壁架设两头贯通的腔体,该腔体的下部经由电机与翅片使得制冷液往复运动,改善制冷性能。经由于柜体顶壁沟路位置设有的带有贯通腔的挡片与肾蕨,对后台服务器的微波有吸取的性能,防止工作人员在微波环境下身体受损,结构简单而性能佳。In this way, it is necessary to develop a server cabinet. By installing a cabinet with refrigerant liquid on the server cabinet and erecting a cavity through the bottom wall of the cabinet, the lower part of the cavity makes the refrigerant reciprocate through the motor and the fins. Exercise to improve cooling performance. Due to the baffle plate and kidney fern with a through cavity at the position of the top wall of the cabinet, it has the performance of absorbing the microwave of the background server and prevents the staff from being damaged in the microwave environment. The structure is simple and the performance is good.

发明内容Contents of the invention

为解决上述问题,本发明提供了一种运维管理APP的方法,有效避免了现有技术中费时费力操作繁琐、制冷性能不佳、对后台服务器的性能有损、微波对工作人员身体有损的缺陷。In order to solve the above problems, the present invention provides a method of operation and maintenance management APP, which effectively avoids the time-consuming and laborious operation in the prior art, poor refrigeration performance, damage to the performance of the background server, and damage to the health of the staff by microwaves. Defects.

为了克服现有技术中的不足,本发明提供了一种运维管理APP的方法的解决方案,具体如下:In order to overcome the deficiencies in the prior art, the present invention provides a solution to the method of operation and maintenance management APP, specifically as follows:

一种运维管理APP的方法,包括如下步骤:A method for operating and maintaining an APP, comprising the following steps:

步骤1:首先,构建运维管理系统,所述运维管理系统包括配发给操作员的智能手机,所述智能手机中包括运维管理APP和第一电子表格;还包括配发给派工人员的后台服务器,所述后台服务器中包括派工模块和第二电子表格,所述智能手机与所述后台服务器相通信连接;Step 1: First, build an operation and maintenance management system, the operation and maintenance management system includes a smart phone distributed to the operator, the smart phone includes the operation and maintenance management APP and the first electronic form; The background server of the personnel, the background server includes a labor dispatching module and a second electronic form, and the smart phone is connected to the background server by communication;

步骤2:派工人员需要安排操作人员对电网的设备进行检测时,就在后台服务器上打开第二电子表格,在第二电子表格的工单号、工单状态、派工人员号、操作人员号、终端资产号、安装位置以及终端类型这样的表格标题下的单元格中分别输入工单号、工单状态、派工人员号、操作人员号、终端资产号、安装位置以及终端类型,其中工单状态的输入为0;Step 2: When the dispatcher needs to arrange for the operator to detect the equipment of the power grid, he will open the second electronic form on the background server, and enter the work order number, work order status, dispatcher number, and operator in the second electronic form. Enter the work order number, work order status, dispatcher number, operator number, terminal asset number, installation location, and terminal type in the cells under the table headings such as number, terminal asset number, installation location, and terminal type. The input of the work order status is 0;

步骤3:输入结束后,所述派工模块把所述第二电子表格发送到与输入的操作人员号对应的操作人员的智能手机中;Step 3: After the input is completed, the dispatching module sends the second electronic form to the smart phone of the operator corresponding to the input operator number;

步骤4:然后智能手机中的运维管理APP打开所述第二电子表格,操作人员就根据终端资产号、安装位置以及终端类型的内容来对该内容里的电网中的设备进行检测;Step 4: Then the operation and maintenance management APP in the smart phone opens the second electronic form, and the operator detects the equipment in the power grid in the content according to the content of the terminal asset number, installation location and terminal type;

步骤5:检测完毕后,运维管理APP就打开所述第一电子表格,在第一电子表格的工单号、派工人员号、操作人员号、终端资产号、安装位置以及终端类型这样的表格标题下的单元格中分别输入第二电子表格中输入的输入工单号、派工人员号、操作人员号、终端资产号、安装位置以及终端类型的信息,另外还把第一电子表格的工单状态这个表格标题下的单元格中输入1,以及把第一电子表格的提交时间这个表格标题下的单元格中输入此时的时间、把第一电子表格的故障原因这个表格标题下的单元格中输入检测设备时的该设备的故障原因和把第一电子表格的处理措施这个表格标题下的单元格中输入处理该设备故障的措施;Step 5: After the detection is completed, the operation and maintenance management APP will open the first electronic form, and in the first electronic form, such as work order number, dispatcher number, operator number, terminal asset number, installation location and terminal type Enter the input work order number, dispatcher number, operator number, terminal asset number, installation location, and terminal type information entered in the second electronic form in the cells under the table title. In addition, the information in the first electronic form Enter 1 in the cell under the table title of work order status, and enter the time at this time in the cell under the table title of the submission time of the first electronic form, and enter the failure reason of the first electronic form under the table title Input the cause of failure of the equipment when testing the equipment in the cell and input the measures to deal with the equipment failure in the cell under the table title of the treatment measures of the first electronic form;

步骤6:然后运维管理APP把所述第一电子表格发送给后台服务器中进行保存;Step 6: Then the operation and maintenance management APP sends the first electronic form to the background server for saving;

所述后台服务器设置在服务器机柜中,所述服务器机柜为长方体结构,所述服务器机柜F1的顶壁设有容纳有制冷液的储液柜F2,所述容纳有制冷液的储液柜F2的底壁与两头贯通的腔体F3的两头相通,所述两头贯通的腔体F3设于服务器机柜内的边部表面上,所述两头贯通的腔体F3的下部里面设有翅片F5,所述翅片F5设在电机F6的电机旋转杆的外壁,所述电机F6设在服务器机柜里面的下壁面上;The background server is arranged in a server cabinet, the server cabinet is a cuboid structure, the top wall of the server cabinet F1 is provided with a liquid storage cabinet F2 containing refrigerant liquid, and the liquid storage cabinet F2 containing refrigerant liquid is The bottom wall communicates with both ends of the cavity F3 that penetrates at both ends. The cavity F3 that penetrates both ends is arranged on the side surface of the server cabinet, and the lower part of the cavity F3 that penetrates both ends is provided with fins F5. The fins F5 are arranged on the outer wall of the motor rotating rod of the motor F6, and the motor F6 is arranged on the lower wall surface inside the server cabinet;

所述容纳有制冷液的储液柜F2的顶壁上开有槽道,所述槽道内卡入有带有从顶壁到底壁的贯通腔的撑持板F8,所述撑持板F8的贯通腔的底端周边设有阻隔片F9,所述阻隔片F9设在所述撑持板F8的底壁上,所述带有从顶壁到底壁的贯通腔的撑持板F8上设有肾蕨A0,所述服务器机柜F1的底壁设有底座F7。There is a channel on the top wall of the liquid storage cabinet F2 containing the refrigerant liquid, and a support plate F8 with a through cavity from the top wall to the bottom wall is snapped into the channel, and the through cavity of the support plate F8 The periphery of the bottom end is provided with a barrier sheet F9, and the barrier sheet F9 is arranged on the bottom wall of the support plate F8, and the support plate F8 with a through cavity from the top wall to the bottom wall is provided with a kidney fern A0, The bottom wall of the server cabinet F1 is provided with a base F7.

所述第一电子表格的表格标题包括工单号、工单状态、派工人员号、操作人员号、提交时间、终端资产号、安装位置、终端类型、故障原因以及处理措施;The form title of the first electronic form includes work order number, work order status, dispatcher number, operator number, submission time, terminal asset number, installation location, terminal type, failure cause and treatment measures;

所述第二电子表格的表格标题包括工单号、工单状态、派工人员号、操作人员号、终端资产号、安装位置以及终端类型。The table title of the second electronic form includes work order number, work order status, dispatcher number, operator number, terminal asset number, installation location and terminal type.

所述工单号为派工人员需要安排给操作人员的检测任务的编号,该编号为所述检测任务的标识符;The work order number is the number of the detection task that the dispatcher needs to arrange for the operator, and the number is the identifier of the detection task;

所述工单状态为0或1表示,为0表示所述检测任务没完成,为1表示所述检测任务已完成;The status of the work order is 0 or 1, 0 means that the detection task has not been completed, and 1 means that the detection task has been completed;

所述派工人员号为分配给派工人员的编号,该编号为所述派工人员的标识符;The dispatcher number is the number assigned to the dispatcher, which is the identifier of the dispatcher;

所述操作人员号为分配给操作人员的编号,该编号为所述操作人员的标识符;The operator number is the number assigned to the operator, and the number is the identifier of the operator;

所述提交时间为所述操作人员检测完成后把第一电子表格传输给后台服务器时的时间;The submission time is the time when the operator transmits the first electronic form to the background server after the detection is completed;

所述终端资产号为待检测的电网中的设备的编号,该编号为所述设备的标识符;The terminal asset number is the number of the equipment in the power grid to be detected, and the number is the identifier of the equipment;

所述安装位置为待检测的电网中的设备的所在地址;The installation location is the address of the equipment in the grid to be detected;

所述终端类型为待检测的电网中的设备的名称;The terminal type is the name of the equipment in the grid to be detected;

所述故障原因为待检测的电网中的设备的故障类别;The fault cause is the fault category of the equipment in the power grid to be detected;

所述处理措施为处理待检测的电网中的设备的故障的措施。The processing measure is a measure for dealing with the fault of the equipment in the power grid to be detected.

所述容纳有制冷液的储液柜F2设在服务器机柜F1的顶壁,容纳有制冷液的储液柜F2的底壁把所述服务器机柜的顶壁完整覆盖。The liquid storage cabinet F2 containing the refrigerant liquid is arranged on the top wall of the server cabinet F1, and the bottom wall of the liquid storage cabinet F2 containing the refrigerant liquid completely covers the top wall of the server cabinet.

所述两头贯通的腔体F3是盘旋结构。The cavity F3 connected at both ends is a spiral structure.

所述服务器机柜F1里面的一头的边部表面上设有移动硬盘F4,移动硬盘F4同所述后台服务器的USB端口相连。A side surface of one end of the server cabinet F1 is provided with a mobile hard disk F4, and the mobile hard disk F4 is connected to the USB port of the background server.

所述肾蕨A0的底部透过撑持板F8的贯通腔伸进槽道中的营养液里。The bottom of the kidney fern A0 extends into the nutrient solution in the channel through the through cavity of the support plate F8.

本发明的有益效果为:The beneficial effects of the present invention are:

这样就能通过操作人员在服务器上进行排出任务,让操作人员执行并通过运维管理APP的运行来把处理结果返回服务器,省时省力,节省了操作人员来回时间和精力,提高了运维管理的效率。运用该服务器机柜之际,把后台服务器设于服务器机柜里就能运用,经由在主服务器机柜上设有容纳有制冷液的储液柜且在容纳有制冷液的储液柜的底部设有两头贯通的腔体,两头贯通的腔体的下部经由电机和翅片使得制冷液往复运动,改善制冷性能。经由在容纳有制冷液的储液柜的槽道位置构建带有从顶壁到底壁的贯通腔的撑持板和肾蕨,对后台服务器的微波有吸取的性能,防止工作人员在微波环境下身体受损,结构简单而性能佳。In this way, the operator can discharge tasks on the server, let the operator execute and return the processing results to the server through the operation of the operation and maintenance management APP, saving time and effort, saving the time and energy of the operator to go back and forth, and improving the operation and maintenance management s efficiency. When using the server cabinet, it can be used by setting the background server in the server cabinet. By setting the liquid storage cabinet containing the refrigerant liquid on the main server cabinet and setting two ends at the bottom of the liquid storage cabinet containing the refrigerant liquid Through the cavity, the lower part of the cavity through the two ends makes the refrigerant liquid reciprocate through the motor and the fins, improving the cooling performance. By constructing a support plate and a kidney fern with a through cavity from the top wall to the bottom wall at the channel position of the liquid storage cabinet containing the refrigerant liquid, it has the ability to absorb the microwave of the background server and prevent the staff from being physically injured in the microwave environment. damage, simple structure and good performance.

附图说明Description of drawings

图1为本发明的运维管理系统结构示意图;Fig. 1 is a schematic structural diagram of the operation and maintenance management system of the present invention;

图2为本发明的一种第二电子表格的示意图;Fig. 2 is a schematic diagram of a second electronic form of the present invention;

图3为本发明的一种第一电子表格的示意图;Fig. 3 is a schematic diagram of a first electronic form of the present invention;

图4为本发明的服务器机柜的示意图。Fig. 4 is a schematic diagram of the server cabinet of the present invention.

图5为本发明的服务器机柜的外部轮廓示意图。Fig. 5 is a schematic diagram of the external outline of the server cabinet of the present invention.

具体实施方式Detailed ways

下面将结合实施例对本发明做进一步地说明。The present invention will be further described below in conjunction with examples.

为了克服现有技术中的不足,本发明提供了一种运维管理APP的方法的解决方案,具体如下:In order to overcome the deficiencies in the prior art, the present invention provides a solution to the method of operation and maintenance management APP, specifically as follows:

如图1-图5所示,运维管理APP的方法,包括如下步骤:As shown in Figure 1-Figure 5, the method of operation and maintenance management APP includes the following steps:

步骤1:首先,构建运维管理系统,所述运维管理系统包括配发给操作员的智能手机,所述智能手机中包括运维管理APP和第一电子表格;还包括配发给派工人员的后台服务器,所述后台服务器中包括派工模块和第二电子表格,所述智能手机与所述后台服务器相通信连接;Step 1: First, build an operation and maintenance management system, the operation and maintenance management system includes a smart phone distributed to the operator, the smart phone includes the operation and maintenance management APP and the first electronic form; The background server of the personnel, the background server includes a labor dispatching module and a second electronic form, and the smart phone is connected to the background server by communication;

步骤2:派工人员需要安排操作人员对电网的设备进行检测时,就在后台服务器上打开如图2所示的第二电子表格,在第二电子表格的工单号、工单状态、派工人员号、操作人员号、终端资产号、安装位置以及终端类型这样的表格标题下的单元格中分别输入工单号、工单状态、派工人员号、操作人员号、终端资产号、安装位置以及终端类型,其中工单状态的输入为0;Step 2: When the dispatcher needs to arrange for the operator to detect the equipment of the power grid, he will open the second electronic form shown in Figure 2 on the background server, and enter the work order number, work order status, dispatch Enter work order number, work order status, dispatcher number, operator number, terminal asset number, installation Location and terminal type, where the input of work order status is 0;

步骤3:输入结束后,所述派工模块把所述第二电子表格发送到与输入的操作人员号对应的操作人员的智能手机中;Step 3: After the input is completed, the dispatching module sends the second electronic form to the smart phone of the operator corresponding to the input operator number;

步骤4:然后智能手机中的运维管理APP打开所述第二电子表格,操作人员就根据终端资产号、安装位置以及终端类型的内容来对该内容里的电网中的设备进行检测;Step 4: Then the operation and maintenance management APP in the smart phone opens the second electronic form, and the operator detects the equipment in the power grid in the content according to the content of the terminal asset number, installation location and terminal type;

步骤5:检测完毕后,运维管理APP就打开如图3所示的所述第一电子表格,在第一电子表格的工单号、派工人员号、操作人员号、终端资产号、安装位置以及终端类型这样的表格标题下的单元格中分别输入第二电子表格中输入的输入工单号、派工人员号、操作人员号、终端资产号、安装位置以及终端类型的信息,另外还把第一电子表格的工单状态这个表格标题下的单元格中输入1,以及把第一电子表格的提交时间这个表格标题下的单元格中输入此时的时间、把第一电子表格的故障原因这个表格标题下的单元格中输入检测设备时的该设备的故障原因和把第一电子表格的处理措施这个表格标题下的单元格中输入处理该设备故障的措施;Step 5: After the detection is completed, the operation and maintenance management APP will open the first electronic form as shown in Figure 3. In the first electronic form, the work order number, dispatcher number, operator number, terminal asset number, installation Enter the input work order number, dispatcher number, operator number, terminal asset number, installation location and terminal type information entered in the second electronic form in the cells under the table headings such as location and terminal type. Enter 1 in the cell under the table title of the work order status of the first spreadsheet, and enter the time at this time in the cell under the table title of the submission time of the first spreadsheet, and enter the fault of the first spreadsheet Input the cause of failure of the equipment when testing the equipment in the cell under the table title of reason and input the measures to deal with the equipment failure in the cell under the table title of the processing measures of the first electronic form;

步骤6:然后运维管理APP把所述第一电子表格发送给后台服务器中进行保存;Step 6: Then the operation and maintenance management APP sends the first electronic form to the background server for saving;

所述后台服务器设置在服务器机柜中,所述服务器机柜为长方体结构,所述服务器机柜F1的顶壁设有容纳有制冷液的储液柜F2,所述容纳有制冷液的储液柜F2的底壁与两头贯通的腔体F3的两头相通,所述两头贯通的腔体F3设于服务器机柜内的边部表面上,所述两头贯通的腔体F3的下部里面设有翅片F5,所述翅片F5设在电机F6的电机旋转杆的外壁,所述电机F6设在服务器机柜里面的下壁面上;The background server is arranged in a server cabinet, the server cabinet is a cuboid structure, the top wall of the server cabinet F1 is provided with a liquid storage cabinet F2 containing refrigerant liquid, and the liquid storage cabinet F2 containing refrigerant liquid is The bottom wall communicates with both ends of the cavity F3 that penetrates at both ends. The cavity F3 that penetrates both ends is arranged on the side surface of the server cabinet, and the lower part of the cavity F3 that penetrates both ends is provided with fins F5. The fins F5 are arranged on the outer wall of the motor rotating rod of the motor F6, and the motor F6 is arranged on the lower wall surface inside the server cabinet;

所述容纳有制冷液的储液柜F2的顶壁上开有槽道,所述槽道内卡入有带有从顶壁到底壁的贯通腔的撑持板F8,所述撑持板F8的贯通腔的底端周边设有阻隔片F9,所述阻隔片F9设在所述撑持板F8的底壁上,所述带有从顶壁到底壁的贯通腔的撑持板F8上设有肾蕨A0,所述服务器机柜F1的底壁设有底座F7。There is a channel on the top wall of the liquid storage cabinet F2 containing the refrigerant liquid, and a support plate F8 with a through cavity from the top wall to the bottom wall is snapped into the channel, and the through cavity of the support plate F8 The periphery of the bottom end is provided with a barrier sheet F9, and the barrier sheet F9 is arranged on the bottom wall of the support plate F8, and the support plate F8 with a through cavity from the top wall to the bottom wall is provided with a kidney fern A0, The bottom wall of the server cabinet F1 is provided with a base F7.

所述第一电子表格的表格标题包括工单号、工单状态、派工人员号、操作人员号、提交时间、终端资产号、安装位置、终端类型、故障原因以及处理措施;The form title of the first electronic form includes work order number, work order status, dispatcher number, operator number, submission time, terminal asset number, installation location, terminal type, failure cause and treatment measures;

所述第二电子表格的表格标题包括工单号、工单状态、派工人员号、操作人员号、终端资产号、安装位置以及终端类型。The table title of the second electronic form includes work order number, work order status, dispatcher number, operator number, terminal asset number, installation location and terminal type.

所述工单号为派工人员需要安排给操作人员的检测任务的编号,该编号为所述检测任务的标识符;The work order number is the number of the detection task that the dispatcher needs to arrange for the operator, and the number is the identifier of the detection task;

所述工单状态为0或1表示,为0表示所述检测任务没完成,为1表示所述检测任务已完成;The status of the work order is 0 or 1, 0 means that the detection task has not been completed, and 1 means that the detection task has been completed;

所述派工人员号为分配给派工人员的编号,该编号为所述派工人员的标识符;The dispatcher number is the number assigned to the dispatcher, which is the identifier of the dispatcher;

所述操作人员号为分配给操作人员的编号,该编号为所述操作人员的标识符;The operator number is the number assigned to the operator, and the number is the identifier of the operator;

所述提交时间为所述操作人员检测完成后把第一电子表格传输给后台服务器时的时间;The submission time is the time when the operator transmits the first electronic form to the background server after the detection is completed;

所述终端资产号为待检测的电网中的设备的编号,该编号为所述设备的标识符;The terminal asset number is the number of the equipment in the power grid to be detected, and the number is the identifier of the equipment;

所述安装位置为待检测的电网中的设备的所在地址;The installation location is the address of the equipment in the grid to be detected;

所述终端类型为待检测的电网中的设备的名称;The terminal type is the name of the equipment in the grid to be detected;

所述故障原因为待检测的电网中的设备的故障类别;The fault cause is the fault category of the equipment in the power grid to be detected;

所述处理措施为处理待检测的电网中的设备的故障的措施。The processing measure is a measure for dealing with the fault of the equipment in the power grid to be detected.

所述容纳有制冷液的储液柜F2设在服务器机柜F1的顶壁,容纳有制冷液的储液柜F2的底壁把所述服务器机柜的顶壁完整覆盖,可以改善制冷性能。The liquid storage cabinet F2 containing the refrigerant liquid is arranged on the top wall of the server cabinet F1, and the bottom wall of the liquid storage cabinet F2 containing the refrigerant liquid completely covers the top wall of the server cabinet, which can improve cooling performance.

所述两头贯通的腔体F3是盘旋结构,增大两头贯通的腔体F3和服务器机柜内部的接触面积,提高散热效果。The two-ended cavity F3 is a spiral structure, which increases the contact area between the two-ended cavity F3 and the inside of the server cabinet, and improves the heat dissipation effect.

所述服务器机柜F1里面的一头的边部表面上设有移动硬盘F4,移动硬盘F4同所述后台服务器的USB端口相连。A side surface of one end of the server cabinet F1 is provided with a mobile hard disk F4, and the mobile hard disk F4 is connected to the USB port of the background server.

所述肾蕨A0的底部透过撑持板F8的贯通腔伸进槽道中的营养液里。The bottom of the kidney fern A0 extends into the nutrient solution in the channel through the through cavity of the support plate F8.

这样就能通过操作人员在服务器上进行排出任务,让操作人员执行并通过运维管理APP的运行来把处理结果返回服务器,省时省力,节省了操作人员来回时间和精力,提高了运维管理的效率。运用该服务器机柜之际,把后台服务器设于服务器机柜里就能运用,经由在主服务器机柜上设有容纳有制冷液的储液柜且在容纳有制冷液的储液柜的底部设有两头贯通的腔体,两头贯通的腔体的下部经由电机和翅片使得制冷液往复运动,改善制冷性能。经由于柜体顶壁沟路位置设有的带有贯通腔的挡片与肾蕨,对后台服务器的微波有吸取的性能,防止工作人员在微波环境下身体受损,结构简单而性能佳。In this way, the operator can discharge tasks on the server, let the operator execute and return the processing results to the server through the operation of the operation and maintenance management APP, saving time and effort, saving the time and energy of the operator to go back and forth, and improving the operation and maintenance management s efficiency. When using the server cabinet, it can be used by setting the background server in the server cabinet. By setting the liquid storage cabinet containing the refrigerant liquid on the main server cabinet and setting two ends at the bottom of the liquid storage cabinet containing the refrigerant liquid Through the cavity, the lower part of the cavity through the two ends makes the refrigerant liquid reciprocate through the motor and the fins, improving the cooling performance. Due to the baffle plate and kidney fern with a through cavity at the position of the top wall of the cabinet, it has the performance of absorbing the microwave of the background server and prevents the staff from being damaged in the microwave environment. The structure is simple and the performance is good.

以上以实施例的方式对本发明作了描述,本领域的技术人员应当理解,本公开不限于以上描述的实施例,在不偏离本发明的范围的情况下,可以做出各种变化、改变和替换。The present invention has been described above in the form of embodiments, and those skilled in the art should understand that the present disclosure is not limited to the embodiments described above, and various changes, changes and modifications can be made without departing from the scope of the present invention. replace.

Claims (4)

  1. A kind of 1. operation management APP method, it is characterised in that comprise the following steps:
    Step 1:First, operation management system is built, the operation management system is included with the smart mobile phone for issuing operator, institute Stating smart mobile phone includes operation management APP and the first electrical form;Also include matching somebody with somebody the background server issued and send worker person, institute Stating background server includes sending work module and the second electrical form, and the smart mobile phone communicates company with the background server Connect;
    Step 2:When sending worker person to need to arrange for operating personnel to detect the equipment of power network, just opened on background server Second electrical form, work order number, work order state in the second electrical form, send worker person number, operating personnel number, terminal wealth Number, input work order number, work order state respectively in the cell under form caption as installation site and terminal type, send work Personnel number, operating personnel number, terminal wealth number, installation site and terminal type, the wherein input of work order state are 0;
    Step 3:After end of input, it is described send work module second electrical form be sent to input operating personnel number it is right In the smart mobile phone of the operating personnel answered;
    Step 4:Then the operation management APP in smart mobile phone opens second electrical form, and operating personnel are just according to terminal The content of asset number, installation site and terminal type detects to the equipment in the power network in the content;
    Step 5:After detection, operation management APP turns on first electrical form, in the work order of the first electrical form Number, send list under worker person number, operating personnel number, terminal wealth number, installation site and form caption as terminal type The input work order number inputted is inputted in the second electrical form in first lattice respectively, sends worker person number, operating personnel number, terminal wealth Number, the information of installation site and terminal type, in addition also under the work order state of the first electrical form this form caption Input 1 in cell, and being inputted now in the cell under the submission time of the first electrical form this form caption Time, equipment when inputting detection device in the cell under the failure cause of the first electrical form this form caption Failure cause and input processing equipment fault in the cell under the treatment measures of the first electrical form this form captions Measure;
    Step 6:Then operation management APP is sent to first electrical form in background server and preserved;
    The background server is arranged in server cabinet, and the server cabinet is rectangular parallelepiped structure, the server machine The roof of cabinet is provided with the liquid storage cabinet for accommodating refrigerating fluid, the bottom wall and the chamber of two insertion of the liquid storage cabinet for accommodating refrigerating fluid Two of body communicates, and the cavity of two insertion is on the edge surface in server cabinet, the chamber of two insertion The inside lower portions of body are provided with fin, and the fin is located at the outer wall of the motor swingle of motor, and the motor is located at server machine On lower wall surface inside cabinet;Conduit is provided with the roof of the liquid storage cabinet for accommodating refrigerating fluid, band has been caught in the conduit There is the plate that props up of the lumen therethrough from roof to bottom wall, the bottom periphery of the lumen therethrough for propping up plate is provided with barrier flaps, the resistance Partition is propped up on the bottom wall of plate described in being located at, and the plate that props up of the lumen therethrough with from roof to bottom wall is provided with tuber fern, institute The bottom wall for stating server cabinet is provided with base.
  2. 2. operation management APP according to claim 1 method, it is characterised in that the form of first electrical form Title includes work order number, work order state, sends worker person number, operating personnel number, submission time, terminal wealth number, installation site, end Hold type, failure cause and treatment measures;
    The form caption of second electrical form includes work order number, work order state, sends worker person number, operating personnel number, terminal Asset number, installation site and terminal type.
  3. 3. operation management APP according to claim 2 method, it is characterised in that the work order number is to send worker person to need Will be arranged to the numbering of the Detection task of operating personnel, the numbering is the identifier of the Detection task;
    The work order state is 0 or 1 expression, is that the 0 expression Detection task is not completed, is that the 1 expression Detection task is complete Into;
    Described to send worker person number to distribute to the numbering for sending worker person, the numbering is the identifier for sending worker person;
    The operating personnel number are the numbering for distributing to operating personnel, and the numbering is the identifier of the operating personnel;
    The submission time be when the first electrical form being transferred to background server after the completion of operating personnel detection when Between;
    The terminal wealth number is the numbering of the equipment in power network to be detected, and the numbering is the identifier of the equipment;
    The installation site is the address of the equipment in power network to be detected;
    The terminal type is the title of the equipment in power network to be detected;
    The failure cause is the fault category of the equipment in power network to be detected;
    The treatment measures are the measure for the failure for handling the equipment in power network to be detected.
  4. 4. operation management APP according to claim 3 method, it is characterised in that the liquid storage for accommodating refrigerating fluid Cabinet is located at the roof of server cabinet, and the bottom wall for accommodating the liquid storage cabinet of refrigerating fluid completely covers the roof of the server cabinet Lid;
    The cavity of two insertion is spiral structure;
    The edge surface of one inside the server cabinet is provided with mobile hard disk, and mobile hard disk is the same as the background server USB port be connected;
    The bottom of the tuber fern is put in the nutrient solution in conduit through the lumen therethrough for propping up plate;
    The wall of the rectangular-shape base is provided with holding tank;The sleeve pipe of two insertion is movably arranged in appearance with plenum fan Receive in groove.
CN201711021769.1A 2017-10-27 2017-10-27 Operation management APP method Pending CN107818371A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711021769.1A CN107818371A (en) 2017-10-27 2017-10-27 Operation management APP method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711021769.1A CN107818371A (en) 2017-10-27 2017-10-27 Operation management APP method

Publications (1)

Publication Number Publication Date
CN107818371A true CN107818371A (en) 2018-03-20

Family

ID=61604341

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711021769.1A Pending CN107818371A (en) 2017-10-27 2017-10-27 Operation management APP method

Country Status (1)

Country Link
CN (1) CN107818371A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108520306A (en) * 2018-03-23 2018-09-11 华翔翔能(湖南)能源科技有限公司 Energy management method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104460885A (en) * 2014-11-27 2015-03-25 华为技术有限公司 Case and storage device
CN105321051A (en) * 2015-11-26 2016-02-10 国网安徽省电力公司检修公司 Extra-high voltage substation intelligent operation and maintenance management and method for generating report thereof
CN105976092A (en) * 2016-04-28 2016-09-28 广东鹰视能效科技有限公司 Method of generating power distribution room patrol project based on power distribution equipment structure and system thereof
CN107246812A (en) * 2017-06-22 2017-10-13 东莞市联洲知识产权运营管理有限公司 A kind of energy-efficient radiating heat exchange mechanisms

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104460885A (en) * 2014-11-27 2015-03-25 华为技术有限公司 Case and storage device
CN105321051A (en) * 2015-11-26 2016-02-10 国网安徽省电力公司检修公司 Extra-high voltage substation intelligent operation and maintenance management and method for generating report thereof
CN105976092A (en) * 2016-04-28 2016-09-28 广东鹰视能效科技有限公司 Method of generating power distribution room patrol project based on power distribution equipment structure and system thereof
CN107246812A (en) * 2017-06-22 2017-10-13 东莞市联洲知识产权运营管理有限公司 A kind of energy-efficient radiating heat exchange mechanisms

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108520306A (en) * 2018-03-23 2018-09-11 华翔翔能(湖南)能源科技有限公司 Energy management method

Similar Documents

Publication Publication Date Title
CN113543595B (en) Mobile immersed servers, workstations and work systems
CN103987233B (en) A kind of intelligent pipeline adding pressure type network cabinet and server cooling system
CN107818371A (en) Operation management APP method
CN208077071U (en) A kind of machine box for server easy to repair
CN209515389U (en) A kind of oil-immersed transformer
CN204461685U (en) A kind of device detecting heating radiator leakproofness
CN107179811A (en) A kind of high computer cabinet of heat dispersion
CN205864907U (en) A kind of Novel Communication cabinet heat dissipation device
CN209165701U (en) A kind of machine room humiture monitoring regulating device
CN106550582A (en) A kind of heat abstractor for high-power electric switch board
CN107832856A (en) Operation management APP method
CN105431004B (en) A kind of cooling system and control method for data center machine room
CN207200116U (en) Combined power traffic control platform
CN207183893U (en) A kind of power distribution cabinet with automatic dissipating heat function
CN210015136U (en) An integrated test device for power distribution automation
CN202668564U (en) Maintaining device for butterfly valve of radiating pipe of transformer
CN207989438U (en) A kind of hydraulic oil container heat sink
CN208071034U (en) A kind of Internet of Things wiring storage device for preventing wiring from winding
CN216289786U (en) Distribution automation terminal equipment
CN112003133A (en) Distribution network low-voltage power distribution cabinet for monitoring device
CN207457750U (en) A kind of current conversion station spare unit storehouse in-out-storehouse management platform based on RFID technique
CN221793955U (en) Metal mold with cooling function
CN212786384U (en) IDC computer lab heat abstractor
CN221630100U (en) A ventilation and cooling equipment for logistics warehouse
CN219535333U (en) Integrated box of intelligent power grid system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180320

RJ01 Rejection of invention patent application after publication