CN107816366A - 一种多层采空区充填井成井工法 - Google Patents

一种多层采空区充填井成井工法 Download PDF

Info

Publication number
CN107816366A
CN107816366A CN201711008500.XA CN201711008500A CN107816366A CN 107816366 A CN107816366 A CN 107816366A CN 201711008500 A CN201711008500 A CN 201711008500A CN 107816366 A CN107816366 A CN 107816366A
Authority
CN
China
Prior art keywords
goaf
drilling
filling
rubble
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711008500.XA
Other languages
English (en)
Other versions
CN107816366B (zh
Inventor
王茂森
博坤
廉墨客
苏向荣
彭枧明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin University
Original Assignee
Jilin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin University filed Critical Jilin University
Priority to CN201711008500.XA priority Critical patent/CN107816366B/zh
Publication of CN107816366A publication Critical patent/CN107816366A/zh
Application granted granted Critical
Publication of CN107816366B publication Critical patent/CN107816366B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/08Filling-up hydraulically or pneumatically

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Earth Drilling (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种多层采空区充填井成井工法,该工法采用如下步骤:用小口径勘探孔探明多层采空区的位置;根据勘探情况,选择扩孔钻具,进行扩孔;穿越第一层采空区后,用碎石充填第一采空区;用带有注浆喷嘴的小口径钻具,钻进至采空区底板,然后进行旋喷注浆,在碎石内形成由碎石和注浆材料组成的碎石桩;用扩孔钻具钻穿已形成的碎石桩,在碎石层中形成充填井;用跟管钻具把选择好的钢管下入充填井内,形成充填通道;重复以上步骤可穿越两层以上的空区。本发明解决了穿越多层采空区进行充填井施工的钻井技术问题。

Description

一种多层采空区充填井成井工法
技术领域
本发明涉及矿山勘探开采领域,尤其涉及一种多层采空区充填井的施工方法。
背景技术
地下矿产开采必然形成采空区,采空区的形成使周边一定范围内的岩体应力重新分布,导致岩石变形、移动和破坏,成为露天开采生产的安全隐患。为了减少岩石和地表移动幅度,减慢其移动的发生和发展,防止大面积的地压活动,避免采空区坍塌或塌陷,必须对采空区进行处理。矿山地下遗留的采空区的处理方法通常有封闭、崩落、充填和支撑等方法。但由于各个矿山的具体条件不同,采空区的位置、形态特征及大小不同,对采空区的处理方法也不尽相同。如何针对地层采空区的条件和特点,综合考虑影响其多层采空区处理方法决策的多种因素,采用先进高效的钻井和充填技术,从多种方案中选择安全可靠、高效经济、技术先进等方面总体效果最佳的施工技术,是确保矿区安全生产的重要环节。
栾川钼矿最早采用地下开采,产生了大量的单层或多次采空区,采空区的高度从几米到几十米不等,多层采空区最多可达五层,采空区埋藏较浅,实际生产过程中,重型设备要在采空区上部工作,给实际生产带来了安全隐患。因此,对工作面以下的采空区要进行处理,以确保安全生产。
目前处理采空区的方法有以下几种:(1)强制崩落围岩;(2)围岩自然崩落充填采空区;(3)用矿石垫层将作业区段和采空区隔开;(4)用废石、选矿尾砂或尾砂加其它胶结材料充填采空区;(5)预留永久矿柱支撑采空区;(6)矿柱支撑和充填联合处理采空区;(7)密闭采空区;(8)以上几种方法联合处理采空区。
以上现有的几种采空区处理技术均有其局限性,均不能解决多层采空区充填的技术问题。
发明内容
本发明的目的在于针对现有采空区处理的局限性和不足,提供一种能够解决多层采空区充填的采空区成井方法;
一种多层采空区充填井成井工法,包括以下步骤:
步骤一、小口径钻进:从地表向采空区内钻孔,形成钻孔;由于矿区地层坚硬破碎,要采用潜孔锤钻进技术进行钻孔;
步骤二、钻到采空区的底板,获得采空区高度;下入采空区探测仪,探测第一采空区的范围;
步骤三、穿过第一层采空区继续钻进,钻进第二层采空区,钻穿后把钻具从孔中提出,下入探测仪器,探测第二层采空区的范围;
步骤四、继续步骤二和步骤三,可继续探明下部采空区;
步骤五、大口径钻进:采用大直径潜孔锤钻进方法把小口径钻孔扩大到所需直径(Φ450mm);
步骤六、把直径5-10mm的碎石充填至第一层采空区,充填到顶部时下入钻具回转,扩大顶部碎石面积,再填满顶部;
步骤七、用带有注浆喷嘴的钻头钻进至第一层采空区底板,然后用注浆泵通过注浆钻杆向喷嘴注入水泥浆,边旋转钻头边缓慢向上移动钻头,确保水泥浆充满钻头周围的碎石空隙,以形成由碎石和水泥浆组成具有一定强度的水泥碎石桩;
步骤八、下入大直径钻头在形成的水泥碎石桩内钻孔,形成大直径钻孔;形成充填碎石的通道;
步骤九、大直径钻头穿过第一层采空区后,继续向下钻进,钻至第二层采空区的顶板;
步骤十、将大直径钻具从孔中提出,然后用跟管钻头把已选好的套管带入孔内,作为充填碎石的通道;
步骤十一、重复步骤一至步骤十,可穿越二层以上采空区。
附图说明
图1勘探多层采空区的钻孔图。
图2大直径扩孔钻进示意图示意图。
图3 采空区充填碎石支护示意图。
图4 碎石内旋喷注浆形成碎石桩示意图。
图5 碎石桩内大直径扩孔钻进示意图。
图6 跟管钻进下入套管示意图。
1—钻杆,2—潜孔锤,3—潜孔锤钻头,4—大直径潜孔锤,5—大直径钻头,6—碎石,7—注浆钻杆,8—注浆管,9—喷嘴,10—导向钻头,11—水泥碎石桩,12—潜孔锤跟管钻头,13—套管靴,14—套管,15—孔口板,Ⅰ—第一层采空区,Ⅱ—第二层采空区,Ⅲ—第三层采空区。
具体实施方式
一种多层采空区充填井成井工法,包括以下步骤:
步骤一、参见图1所示,小口径钻进:从地表向地下钻孔,用钻杆1、潜孔锤2和潜孔锤钻头3的钻具组合,钻进直径Φ140钻孔到第一层采空区Ⅰ底板;
步骤二、从孔中下入井下电视,观察底板表面的平整程度,以确定在采空区底板的钻进工艺;
步骤三、根据采空区底板情况,选择穿越采空区的特殊钻进方法,垂直在底板上开孔;
步骤四、继续钻进至第二层采空区Ⅱ的底板,探明第二层采空区Ⅱ位置,将钻具提出孔外;下入井下电视;重复步骤四,钻穿第三层采空区Ⅲ和下一采空区;
步骤五、大口径钻进:参见图2,选择钻杆直径Φ200mm、潜孔锤直径Φ300mm、钻头直径Φ450mm的大口径钻具组合,将步骤一中的小孔扩大为至设计口径;
步骤六、参见图3,从已钻成的大口径钻孔中注入直径5-10mm的碎石6,注入到第一层采空区Ⅰ顶板;
步骤七、下入大口径钻头,在碎石堆顶端回转,使锥体碎石的顶部面积扩大,提钻再灌注碎石,直到第一层采空区顶板;
步骤八、参见图4,采用小口径钻进方法,在锥形碎石堆中形成钻孔,下入注浆钻杆7、注浆管8、带有喷嘴9的导向钻头10,在碎石中钻进,钻进至第一层采空区Ⅰ底板后,开动注浆泵,使水泥浆液从喷嘴高速喷出,进入碎石6中;
步骤九、边旋转钻头边缓慢向上移动钻具钻头,使水泥浆液尽可能地向周围高速喷射,与碎石胶结形成较大直径的水泥碎石桩11;
步骤十、待水泥浆液与碎石固结后,如图5所示,重复大口径钻进过程,在碎石桩11中钻出大直径孔;这就完成了第一层采空区Ⅰ大直径钻孔。
步骤十一、重复步骤十,可在二层以上采空区钻成大直径钻孔;
步骤十二、参见图6,形成大直径钻孔后,为防止充填碎石过程中卡堵,要在大直径钻孔中再下入无缝钢管(套管);
步骤十三、用潜孔锤跟管钻头12带动套管靴13,套管靴13带动套管14,使套管底端进入充填采空区的顶板处,在地面把孔口板15和套管14顶端焊接在一起,防止套管14滑落入孔内,即可进行碎石充填工作。

Claims (1)

1.一种多层采空区充填井成井工法,其特征在于:包括以下步骤:
步骤一、小口径钻进:从地表向采空区内钻孔,形成钻孔;由于矿区地层坚硬破碎,要采用潜孔锤钻进技术进行钻孔;
步骤二、钻到采空区的底板,获得采空区高度;下入采空区探测仪,探测第一采空区的范围;
步骤三、穿过第一层采空区继续钻进,钻进第二层采空区,钻穿后把钻具从孔中提出,下入探测仪器,探测第二层采空区的范围;
步骤四、继续步骤二和步骤三,可继续探明下部采空区;
步骤五、大口径钻进:采用大直径潜孔锤钻进方法把小口径钻孔扩大到设计直径;
步骤六、把直径5-10mm的碎石充填至第一层采空区,充填到顶部时下入钻具回转,扩大顶部碎石面积,再填满顶部;
步骤七、用带有注浆喷嘴的钻头钻进至第一层采空区底板,然后用注浆泵通过注浆钻杆向喷嘴注入水泥浆,边旋转钻头边缓慢向上移动钻头,确保水泥浆充满钻头周围的碎石空隙,以形成由碎石和水泥浆组成的水泥碎石桩;
步骤八、下入大直径钻头在形成的水泥碎石桩内钻孔,形成大直径钻孔;形成充填碎石的通道;
步骤九、大直径钻头穿过第一层采空区后,继续向下钻进,钻至第二层采空区的顶板;
步骤十、将大直径钻具从孔中提出,然后用跟管钻头把已选好的套管带入孔内,作为充填碎石的通道;
步骤十一、重复步骤一至步骤十,可穿越二层以上采空区。
CN201711008500.XA 2017-10-25 2017-10-25 一种多层采空区充填井成井工法 Expired - Fee Related CN107816366B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711008500.XA CN107816366B (zh) 2017-10-25 2017-10-25 一种多层采空区充填井成井工法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711008500.XA CN107816366B (zh) 2017-10-25 2017-10-25 一种多层采空区充填井成井工法

Publications (2)

Publication Number Publication Date
CN107816366A true CN107816366A (zh) 2018-03-20
CN107816366B CN107816366B (zh) 2019-06-07

Family

ID=61603006

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711008500.XA Expired - Fee Related CN107816366B (zh) 2017-10-25 2017-10-25 一种多层采空区充填井成井工法

Country Status (1)

Country Link
CN (1) CN107816366B (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110017120A (zh) * 2019-04-02 2019-07-16 中国地质科学院勘探技术研究所 一种垂直井井底高强度腔室的建造方法
CN111365066A (zh) * 2020-03-10 2020-07-03 中国平煤神马能源化工集团有限责任公司 一种分阶式充水采空区充填方法
CN110043190B (zh) * 2019-04-02 2020-08-18 中国地质科学院勘探技术研究所 一种垂直井大直径腔室的建造方法
CN112855029A (zh) * 2021-04-26 2021-05-28 中铁九局集团第七工程有限公司 一种采空区钻孔外扩管施工方法
CN113202552A (zh) * 2021-05-28 2021-08-03 鞍钢集团矿业有限公司 一种充填与人工支柱相结合的地下空区处理方法
CN113339057A (zh) * 2021-06-24 2021-09-03 中国矿业大学 一种流态化矸石穿层嗣后充填采煤系统及方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2573475A1 (fr) * 1984-11-16 1986-05-23 Soletanche Nouveau procede pour l'exploitation de gisements de minerais
CN101906991A (zh) * 2010-07-19 2010-12-08 刘清洁 一种治理地下采空区或空洞的施工方法
CN102071940A (zh) * 2010-12-31 2011-05-25 大同煤矿集团有限责任公司 煤矿井筒穿越多层采空区的施工方法
CN102561950A (zh) * 2012-01-20 2012-07-11 山东大学 一种对地层空洞内填充的骨料进行注浆固结的工艺及喷射钻头
CN104929567A (zh) * 2015-04-30 2015-09-23 山西蓝焰煤层气集团有限责任公司 一种低成本穿越采空区施工工艺
CN104989390A (zh) * 2015-06-12 2015-10-21 太原钢铁(集团)有限公司 多层采空区一次性探测不提钻同步扫描方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2573475A1 (fr) * 1984-11-16 1986-05-23 Soletanche Nouveau procede pour l'exploitation de gisements de minerais
CN101906991A (zh) * 2010-07-19 2010-12-08 刘清洁 一种治理地下采空区或空洞的施工方法
CN102071940A (zh) * 2010-12-31 2011-05-25 大同煤矿集团有限责任公司 煤矿井筒穿越多层采空区的施工方法
CN102561950A (zh) * 2012-01-20 2012-07-11 山东大学 一种对地层空洞内填充的骨料进行注浆固结的工艺及喷射钻头
CN104929567A (zh) * 2015-04-30 2015-09-23 山西蓝焰煤层气集团有限责任公司 一种低成本穿越采空区施工工艺
CN104989390A (zh) * 2015-06-12 2015-10-21 太原钢铁(集团)有限公司 多层采空区一次性探测不提钻同步扫描方法

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110017120A (zh) * 2019-04-02 2019-07-16 中国地质科学院勘探技术研究所 一种垂直井井底高强度腔室的建造方法
CN110043190B (zh) * 2019-04-02 2020-08-18 中国地质科学院勘探技术研究所 一种垂直井大直径腔室的建造方法
CN110017120B (zh) * 2019-04-02 2021-08-17 中国地质科学院勘探技术研究所 一种垂直井井底高强度腔室的建造方法
CN111365066A (zh) * 2020-03-10 2020-07-03 中国平煤神马能源化工集团有限责任公司 一种分阶式充水采空区充填方法
CN111365066B (zh) * 2020-03-10 2021-08-03 中国平煤神马能源化工集团有限责任公司 一种分阶式充水采空区充填方法
CN112855029A (zh) * 2021-04-26 2021-05-28 中铁九局集团第七工程有限公司 一种采空区钻孔外扩管施工方法
WO2022117124A1 (zh) * 2021-04-26 2022-06-09 中铁九局集团第七工程有限公司 一种采空区钻孔外扩管施工方法
CN113202552A (zh) * 2021-05-28 2021-08-03 鞍钢集团矿业有限公司 一种充填与人工支柱相结合的地下空区处理方法
CN113202552B (zh) * 2021-05-28 2023-08-11 鞍钢集团矿业有限公司 一种充填与人工支柱相结合的地下空区处理方法
CN113339057A (zh) * 2021-06-24 2021-09-03 中国矿业大学 一种流态化矸石穿层嗣后充填采煤系统及方法

Also Published As

Publication number Publication date
CN107816366B (zh) 2019-06-07

Similar Documents

Publication Publication Date Title
CN107816366B (zh) 一种多层采空区充填井成井工法
WO2023029617A1 (zh) 煤矸石井下减排的覆岩隔离注浆充填方法
WO2017096674A1 (zh) 特大采场空间远近场井上下协同顶板控制方法
CN110374600B (zh) 一种极近距离煤层群回采巷道无错距式布置方法
CN111535791B (zh) 碎软低渗煤层井上下联合压裂区域瓦斯高效抽采方法
CN104863629A (zh) 一种利用复合钻孔抽覆岩下离层瓦斯及排水注浆的方法
CN107387082A (zh) 一种弱化煤层坚硬顶板的方法
CN106014419B (zh) 多分支孔地面预注浆堵水施工方法
CN107044280A (zh) 一种采动覆岩离层分布特征的钻孔注浆探测方法
AU2021106168A4 (en) High-gas Coal Seam Group Pressure Relief Mining Method Based on Gob-side Entry Retaining in the First Mining Whole Rock Pressure Relief Working Face
CN109519149A (zh) 一种煤层气穿越采空区井全井固井方法
CN109162731A (zh) 铁矿区深部开采突水注浆治理方法
CN111608726A (zh) 一种间隔式覆岩碎胀充填钢筋笼囊袋注浆减损方法
CN109611146B (zh) 一种离层水疏放注浆方法
CN103899351A (zh) 一种处理复杂采空区的充填加固方法
WO2023197573A1 (zh) 冲击地压煤层巷道防冲卸压掘进方法
CN114215530B (zh) 一种坚硬顶板定向水压致裂沿空巷道快速掘巷方法
CN102912791A (zh) 一种钻孔灌注桩的施工方法
CN107339122B (zh) 一种钢管柱处理采空区工法
CN106837382A (zh) 一种地铁隧道围岩地面预注浆加固工艺
CN106761750A (zh) 急倾斜煤层纵向长壁刨铣建槽式开采方法
CN105804752A (zh) 一种煤矿条带开采中覆岩离层注浆减沉工艺
CN113700016B (zh) 一种矿山地下极强动水过水通道地面封堵水方法
CN115539039A (zh) 一种基于井上下联合作业的区域化提高放顶煤回采率方法
CN113027467A (zh) 一种综采工作面过构造破碎带超前注浆加固治理方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190607

Termination date: 20191025