CN107795055A - A kind of modular combination floor and construction method - Google Patents

A kind of modular combination floor and construction method Download PDF

Info

Publication number
CN107795055A
CN107795055A CN201710980281.5A CN201710980281A CN107795055A CN 107795055 A CN107795055 A CN 107795055A CN 201710980281 A CN201710980281 A CN 201710980281A CN 107795055 A CN107795055 A CN 107795055A
Authority
CN
China
Prior art keywords
floor
standard
slab
steel frame
concrete layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710980281.5A
Other languages
Chinese (zh)
Inventor
王小平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Technology WUT
Original Assignee
Wuhan University of Technology WUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Technology WUT filed Critical Wuhan University of Technology WUT
Priority to CN201710980281.5A priority Critical patent/CN107795055A/en
Publication of CN107795055A publication Critical patent/CN107795055A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种模块化组合楼板及施工方法,楼板整体由方(矩)形的模块化标准板在同一平面连续拼接而成,标准板下层为钢框架,钢框架的顶面铺设有混凝土层,混凝土层的侧面边缘相对钢框架的侧边内缩25~150mm;混凝土层和钢框架的上表面采用抗剪件连接,钢框架为四面槽钢围成中空的整体。将同样大小模块化标准板通过相邻的钢框架以螺栓固定连接,拼接成整体的组合楼板,组合楼板可从侧面或底面与建筑梁或柱连接固定,然后以混凝土抹平。本发明可以实现对不同形状大小的楼板通过预制模块化标准板在现场拼接完成楼板的安装,楼板重量轻,安装快速,施工方便,整体受力性能好。

A modular composite floor slab and its construction method. The floor slab is formed by continuous splicing of square (rectangular) modular standard slabs on the same plane. The lower layer of the standard slab is a steel frame, and the top surface of the steel frame is laid with a concrete layer. The concrete layer The side edge of the steel frame is retracted 25~150mm relative to the side of the steel frame; the concrete layer and the upper surface of the steel frame are connected by shear members, and the steel frame is surrounded by channel steel on all sides to form a hollow whole. Modular standard panels of the same size are fixed and connected by bolts through adjacent steel frames to form an integral composite floor. The composite floor can be connected and fixed with building beams or columns from the side or bottom surface, and then smoothed with concrete. The invention can realize the installation of floor slabs of different shapes and sizes by splicing prefabricated modularized standard slabs on site. The floor slabs are light in weight, fast in installation, convenient in construction, and good in overall force bearing performance.

Description

一种模块化组合楼板及施工方法A modular composite floor slab and its construction method

技术领域technical field

本发明涉及建筑工程技术,具体说是一种房屋建筑的模块化组合楼板及施工方法。The invention relates to construction engineering technology, in particular to a modular composite floor for building construction and a construction method.

背景技术Background technique

装配式混凝土结构是指采用工厂生产的预制混凝土构配件在工地装配而成的结构,具有安装速度快、对施工现场污染少、工程质量容易得到保证等优势,在我国具有广泛的应用前景。楼板是装配式混凝土结构中预制构配件的一部分,其做法包括预制(预应力)混凝土板、钢筋混凝土叠合楼板等。但这种两种做法均有缺陷:前者通过拼装而成的楼板整体性差,且仅能单向传力;而后者标准化程度不高,且现场存在大量湿作业。The prefabricated concrete structure refers to the structure assembled on the construction site using prefabricated concrete components produced by the factory. It has the advantages of fast installation speed, less pollution to the construction site, and easy guarantee of project quality. It has broad application prospects in our country. The floor slab is a part of the prefabricated components in the prefabricated concrete structure, and its methods include prefabricated (prestressed) concrete slabs, reinforced concrete laminated slabs, etc. However, both of these two methods have defects: the former has poor integrity of the assembled floor and can only transmit force in one direction; while the latter has a low degree of standardization and there are a lot of wet operations on site.

发明内容Contents of the invention

本发明所要解决的技术问题是提供一种模块化组合楼板及施工方法,这种组合楼板由工厂预制的模块化标准板拼接而成,整体性好,可以实现双向传力。The technical problem to be solved by the present invention is to provide a modular composite floor and its construction method. This composite floor is spliced by factory prefabricated modular standard panels, has good integrity and can realize two-way force transmission.

本发明提供一种模块化组合楼板,其特征在于:楼板整体由矩形模块化的标准板在同一平面连续拼接而成,标准板的边长为0.3~2.4m;The present invention provides a modular composite floor, which is characterized in that: the whole floor is formed by continuous splicing of rectangular modular standard panels on the same plane, and the side length of the standard panels is 0.3-2.4m;

所述标准板下层为钢框架,钢框架的顶面铺设有混凝土层,混凝土层的侧面边缘相对钢框架的侧边内缩25~150mm;The lower layer of the standard slab is a steel frame, the top surface of the steel frame is laid with a concrete layer, and the side edge of the concrete layer shrinks inward by 25 ~ 150mm relative to the side of the steel frame;

所述钢框架为四面槽钢围成中空的整体,槽钢的腹板与混凝土层垂直,槽口向内,槽钢顶面的翼板与混凝土层固定连接;The steel frame is a hollow whole surrounded by channel steel on all sides, the web of the channel steel is perpendicular to the concrete layer, the notch is inward, and the wing plate on the top surface of the channel steel is fixedly connected with the concrete layer;

在混凝土层内与混凝土层平行地埋设有钢筋网,钢筋网伸出混凝土层的侧边50~250mm。In the concrete layer and parallel to the concrete layer, a reinforcement mesh is buried, and the reinforcement mesh protrudes 50-250mm from the side of the concrete layer.

优选地,在钢筋网伸出混凝土层的侧边位置,混凝土层设有多个向内凹40~125mm的连接槽。Preferably, the concrete layer is provided with a plurality of connecting grooves concaved inward by 40-125mm at the side where the reinforcement mesh protrudes from the concrete layer.

优选地,在混凝土层覆盖的范围内设有与钢框架固定连接的栓钉。Preferably, studs fixedly connected to the steel frame are provided within the area covered by the concrete layer.

槽钢的腹板设有螺栓孔,用于楼板整体从侧面与建筑梁或柱连接安装或模块化标准板之间的拼接。The web of the channel steel is provided with bolt holes, which are used for the connection and installation of the whole floor slab to the building beam or column from the side, or the splicing between the modular standard slabs.

在槽钢底面的翼板设有螺栓孔,用于楼板整体从底面与建筑梁或柱连接安装。Bolt holes are provided on the wing plate on the bottom surface of the channel steel, which are used for connecting and installing the whole floor slab with the building beam or column from the bottom surface.

一种上述模块化组合楼板施工方法,其特征在于:按照下述步骤顺序进行:A construction method for the above-mentioned modularized composite floor, characterized in that it is carried out in accordance with the following sequence of steps:

第一步、在工厂批量预制标准板;The first step is to prefabricate standard panels in batches in the factory;

第二步、运输标准板到施工现场,在施工现场地面或空中按照楼板的设计形状和尺寸拼接出整体的楼板,在拼接过程中:The second step is to transport the standard slab to the construction site, and splice the whole floor slab according to the design shape and size of the floor slab on the ground or in the air at the construction site. During the splicing process:

首先将相邻的标准板水平对齐,钢框架的腹板对齐后,以连接螺栓穿过对齐的相邻腹板的螺栓孔并紧固,其次将相邻位置的钢筋网拧紧连接,形成楼板半成品;First, align the adjacent standard slabs horizontally. After the webs of the steel frame are aligned, use the connecting bolts to pass through the bolt holes of the aligned adjacent webs and fasten them. Secondly, tighten the reinforcement mesh at the adjacent positions to form a semi-finished floor slab. ;

第三步、将楼板半成品吊装到设计楼板位置,从侧面或底面与建筑梁或柱固定连接,然后在楼板表面的凹槽中填充混凝土浆料,并与混凝土层平齐,经过规定时间的养护并固化。The third step is to hoist the semi-finished floor slab to the design floor position, and fix it with the building beam or column from the side or bottom surface, then fill the groove on the surface of the floor slab with concrete slurry, and make it flush with the concrete layer, after a specified time of curing and solidified.

楼板从侧面与建筑梁或柱连接时,首先,从边缘标准板的钢框架腹板向连接建筑梁或柱侧面以螺钉或螺栓紧固,然后在边缘标准板的混凝土层外侧与连接建筑梁或柱的凹槽内填充混凝土浆料,并抹平,经过规定时间的养护固化。When the floor slab is connected to the building beam or column from the side, firstly, the steel frame web plate of the edge standard slab is fastened with screws or bolts to the side of the connecting building beam or column, and then the outer side of the concrete layer of the edge standard slab is connected to the building beam or The groove of the column is filled with concrete slurry, smoothed, and cured after a specified period of time.

楼板从底面与建筑梁或柱连接时,首先,在接触标准板底部的连接建筑梁或柱钢结构位置,从钢框架底部翼板内侧向连接建筑梁或柱以螺钉或螺栓紧固,然后在边缘标准板的混凝土层外侧与墙体的凹槽内填充混凝土浆料,并抹平,经过规定时间的养护固化。When the floor slab is connected to the building beam or column from the bottom surface, firstly, at the position of the connecting building beam or column steel structure that touches the bottom of the standard slab, connect the building beam or column laterally from the inside of the bottom flange of the steel frame with screws or bolts, and then fasten the The outside of the concrete layer of the edge standard slab and the groove of the wall are filled with concrete slurry, smoothed, and cured after a specified period of time.

所述楼板半成品在地面拼装而成时,所述楼板半成品为该位置需安装的整体楼板一部分,将楼板半成品从侧面或底面与连接建筑梁或柱连接后,在空缺位置扩展拼接新的标准板,并排从侧面将新的标准板钢框架与楼板半成品的标准板钢框架对齐,以螺栓连接紧固,逐个连接标准板到楼板搭接的建筑连接建筑梁或柱钢结构,并与连接建筑梁或柱螺栓连接,最后在顶面出现的凹槽内填充混凝土浆料并抹平,经过规定时间的养护固化。When the semi-finished floor slab is assembled on the ground, the semi-finished floor slab is a part of the overall floor to be installed at this position. After the semi-finished floor slab is connected to the connecting building beam or column from the side or bottom surface, a new standard slab is expanded and spliced at the vacant position , align the new standard slab steel frame with the standard slab steel frame of the semi-finished floor slab side by side, fasten it with bolts, connect the standard slab to the floor slab overlapped building connection building beam or column steel structure one by one, and connect with the building beam Or stud bolt connection, and finally fill the concrete slurry in the groove on the top surface and smooth it out, after a specified time of curing and curing.

第一步中,在工厂批量预制标准板的过程为:首先预制钢框架,然后在钢框架的混凝土层覆盖范围内焊接固定栓钉,之后安装对应形状的模板,浇注混凝土,在混凝土层内预埋纵横方向的钢筋网;等待固化。In the first step, the batch prefabrication process of standard slabs in the factory is as follows: first prefabricate the steel frame, then weld and fix the studs within the coverage of the concrete layer of the steel frame, then install the formwork of the corresponding shape, pour concrete, and prefabricate in the concrete layer Bury the reinforcement mesh in the vertical and horizontal directions; wait for curing.

本发明实现了楼板的工厂化预制和现场螺栓快速拼接,使楼板实现标准化预制,模块化的结构几乎不受现场实际形状大小的限制,可以现场根据具体情况快速安装。The invention realizes the factory prefabrication of the floor slab and fast splicing of bolts on site, so that the floor slab can be standardized and prefabricated. The modular structure is almost not limited by the actual shape and size on site, and can be quickly installed on site according to specific conditions.

本发明的组合楼板由方(矩)形的模块化标准预制板拼接而成。标准板下层为钢框架,钢框架的顶面铺设有混凝土层,混凝土层和钢框架之间通过抗剪件连接,每个钢框架的四角之间采用螺栓连接,每块标准板之间的预留缝采用混凝土现场浇实。The combined floor slab of the present invention is spliced by square (rectangular) modularized standard prefabricated panels. The lower layer of the standard slab is a steel frame, and the top surface of the steel frame is laid with a concrete layer. The concrete layer and the steel frame are connected by shear members, and the four corners of each steel frame are connected by bolts. The joints shall be poured concrete on site.

本发明针对不同平面尺寸的楼板实现模块化标准板的铺设,现场完成拼装,具有标准化程度高、楼板整体性好、承载力高且双向传力、现场湿作业少、安装快速等优点,应用前景良好。The present invention realizes the laying of modularized standard slabs for floor slabs of different plane sizes, and completes the assembly on site. It has the advantages of high standardization, good floor integrity, high bearing capacity, two-way force transmission, less wet work on site, and fast installation. good.

附图说明Description of drawings

图1 是模块化组合楼板的结构示意图,Figure 1 is a schematic diagram of the structure of the modular composite floor,

图2 是图1中的B-B剖面图,Fig. 2 is a B-B sectional view in Fig. 1,

图3 是图2中A-A剖面图,Fig. 3 is a sectional view of A-A in Fig. 2,

图4 是楼板侧面与钢制建筑梁或柱侧面连接示意图,Figure 4 is a schematic diagram of the connection between the side of the floor slab and the side of the steel building beam or column,

图5 是楼板底面与钢制建筑梁或柱连接示意图。Figure 5 is a schematic diagram of the connection between the bottom surface of the floor slab and the steel building beam or column.

图中:1—混凝土层,2—钢筋网,3—板间槽,4—栓钉,5—钢框架,6—腹板,7—螺栓,8—翼板,9—连接槽,10—螺栓孔。In the figure: 1—concrete layer, 2—reinforcing mesh, 3—slot between plates, 4—spindle, 5—steel frame, 6—web plate, 7—bolt, 8—flange, 9—connection groove, 10— Bolt hole.

具体实施方式Detailed ways

下面结合附图和实施例对本发明进一步说明:现有技术的楼板需要根据需要形状针对性地预制或只有单一的结构尺寸整体跨接在两侧的梁上,在房屋结构不能完整配合时,安装和施工都较为繁琐。本发明方案力图解决这一问题。The present invention will be further described below in conjunction with the accompanying drawings and embodiments: the floor slabs in the prior art need to be prefabricated according to the required shape or only have a single structural size to span the beams on both sides as a whole. When the building structure cannot be completely matched, install and construction are more complicated. The solution of the present invention seeks to solve this problem.

如图1、2中所示模块化组合楼板,楼板整体由矩形模块化的标准板在同一平面连续拼接而成,标准板的边长为0.3~2.4m,可设置不同规格的标准板,根据需要选用。As shown in Figures 1 and 2, the modular composite floor is composed of rectangular modular standard slabs spliced continuously on the same plane. The side length of the standard slab is 0.3~2.4m. Standard slabs of different specifications can be set according to Need to choose.

所述标准板下层为钢框架5,钢框架的顶面铺设有混凝土层1,混凝土层的侧面边缘相对钢框架的侧边内缩25~150mm。在混凝土层内与混凝土层平行地埋设有钢筋网2,钢筋网2伸出混凝土层的侧边50~250mm。以便于相邻模块化标准板之间的钢筋连接。The lower layer of the standard slab is a steel frame 5, and the top surface of the steel frame is laid with a concrete layer 1, and the side edges of the concrete layer are retracted 25-150mm relative to the sides of the steel frame. A reinforcement mesh 2 is buried parallel to the concrete layer in the concrete layer, and the reinforcement mesh 2 protrudes 50-250mm from the side of the concrete layer. In order to facilitate the reinforcement connection between adjacent modular standard slabs.

在钢筋网伸出混凝土层的侧边位置,混凝土层设有多个向内凹40~125mm的连接槽9。同样是便于为相邻标准板之间的钢筋连接提供较大的连接空间。At the side where the reinforcement mesh protrudes from the concrete layer, the concrete layer is provided with a plurality of connecting grooves 9 concaved inward by 40-125 mm. It is also convenient to provide a larger connection space for the reinforcement connection between adjacent standard plates.

所述钢框架5为四面槽钢围成中空的整体,槽钢的腹板6与混凝土层1垂直,槽口向内,槽钢顶面的翼板8与混凝土层固定连接;在混凝土层覆盖的范围内设有与钢框架固定连接的栓钉4。以增强钢框架与混凝土层之间的连接力。The steel frame 5 is a hollow whole surrounded by channel steel, the web 6 of the channel steel is perpendicular to the concrete layer 1, the notch is inward, and the wing plate 8 on the top surface of the channel steel is fixedly connected with the concrete layer; Be provided with the stud 4 that is fixedly connected with steel frame in the range. To enhance the connection between the steel frame and the concrete layer.

槽钢的腹板6设有螺栓孔10,用于楼板整体从侧面与建筑梁或柱连接安装或标准板之间的拼接。相邻标准板之间连接时,槽钢的腹板6直接接触,螺栓孔位置对齐,可以直接穿过螺栓7连接。标准板与建筑梁或柱从侧面连接时,将建筑梁或柱预埋的套筒或者连接件对齐,通过螺栓7连接。The web 6 of the channel steel is provided with a bolt hole 10, which is used for connecting and installing the whole floor slab to a building beam or column from the side or splicing between standard slabs. When the adjacent standard plates are connected, the web 6 of the channel steel is in direct contact, and the positions of the bolt holes are aligned, and the bolt 7 can be directly passed through for connection. When the standard plate is connected to the building beam or column from the side, align the embedded sleeve or connector of the building beam or column, and connect through the bolt 7.

在槽钢底面的翼板8设有螺栓孔10,用于楼板整体从底面与建筑梁或柱连接安装。标准板搭建于建筑梁或柱上方再连接时,将建筑梁或柱预埋的套筒或者连接件对齐,通过螺栓连接。The wing plate 8 on the bottom surface of the channel steel is provided with a bolt hole 10, which is used for connecting and installing the whole floor slab with the building beam or column from the bottom surface. When the standard plate is built on the top of the building beam or column and then connected, the sleeve or connector embedded in the building beam or column is aligned and connected by bolts.

一种上述模块化组合楼板施工方法,按照下述步骤顺序进行:A method for constructing the above-mentioned modular composite floor slabs is carried out in accordance with the following sequence of steps:

第一步、在工厂批量预制相应规格的标准板;The first step is to prefabricate standard panels of corresponding specifications in batches in the factory;

在工厂批量预制标准板的过程为:首先预制钢框架5,然后在钢框架的混凝土层覆盖范围内焊接固定栓钉4,安装对应形状的模板,浇注混凝土,在混凝土层内预埋纵横方向的钢筋网2;等待固化。The process of prefabricating standard slabs in batches in the factory is as follows: first prefabricate the steel frame 5, then weld and fix the studs 4 within the coverage of the concrete layer of the steel frame, install the formwork of the corresponding shape, pour concrete, and pre-embed vertical and horizontal slabs in the concrete layer. Mesh 2; waiting to cure.

第二步、运输标准板到施工现场,在施工现场地面或空中按照楼板的设计形状和尺寸拼接出整体的楼板,在拼接过程中:The second step is to transport the standard slab to the construction site, and splice the whole floor slab according to the design shape and size of the floor slab on the ground or in the air at the construction site. During the splicing process:

首先将相邻的标准板水平对齐,钢框架5的腹板6对齐后,以连接螺栓7穿过对齐的相邻腹板的螺栓孔10并紧固,其次将相邻位置的钢筋网2拧紧连接,形成楼板半成品;First, align the adjacent standard plates horizontally. After the webs 6 of the steel frame 5 are aligned, pass the connecting bolts 7 through the bolt holes 10 of the aligned adjacent webs and fasten them. Next, tighten the reinforcement mesh 2 at the adjacent position. connection to form a semi-finished floor slab;

第三步、将楼板半成品吊装到设计楼板位置,从侧面或底面与建筑梁或柱固定连接,然后在楼板表面的凹槽中填充混凝土浆料,并与混凝土层平齐,经过规定时间的养护并固化。The third step is to hoist the semi-finished floor slab to the design floor position, and fix it with the building beam or column from the side or bottom surface, then fill the groove on the surface of the floor slab with concrete slurry, and make it flush with the concrete layer, after a specified time of curing and solidified.

楼板从侧面与建筑梁或柱连接时,首先,从边缘标准板的钢框架腹板向连接建筑梁或柱侧面以螺钉或螺栓紧固,然后在边缘标准板的混凝土层外侧与连接建筑梁或柱的凹槽内填充混凝土浆料,并抹平,经过规定时间的养护固化。When the floor slab is connected to the building beam or column from the side, firstly, the steel frame web plate of the edge standard slab is fastened with screws or bolts to the side of the connecting building beam or column, and then the outer side of the concrete layer of the edge standard slab is connected to the building beam or The groove of the column is filled with concrete slurry, smoothed, and cured after a specified period of time.

楼板从底面与建筑梁或柱连接时,首先,在接触标准板底部的连接建筑梁或柱钢结构位置,从钢框架底部翼板内侧向连接建筑梁或柱以螺钉或螺栓紧固,连接建筑梁或柱可以预埋螺栓套筒或连接件,以供螺栓或螺钉连接。然后在边缘标准板的混凝土层外侧与墙体的凹槽内填充混凝土浆料,并抹平,经过规定时间的养护固化。When the floor slab is connected to the building beam or column from the bottom surface, firstly, at the steel structure position of the connecting building beam or column that touches the bottom of the standard slab, connect the building beam or column from the inner side of the bottom flange of the steel frame and fasten it with screws or bolts to connect the building Beams or columns can have embedded bolt sleeves or connectors for bolted or screwed connections. Then fill the concrete slurry outside the concrete layer of the edge standard plate and the groove of the wall, smooth it, and cure it after a specified period of time.

所述楼板半成品在地面拼装而成时,所述楼板半成品为该位置需安装的整体楼板一部分,将楼板半成品从侧面或底面与连接建筑梁或柱连接后,在空缺位置扩展拼接新的标准板,并排从侧面将新的标准板钢框架与楼板半成品的标准板钢框架对齐,以螺栓连接紧固,逐个连接标准板到楼板搭接的建筑连接建筑梁或柱钢结构,并与连接建筑梁或柱螺栓连接,最后在顶面出现的凹槽内填充混凝土浆料并抹平,经过规定时间的养护固化。When the semi-finished floor slab is assembled on the ground, the semi-finished floor slab is a part of the overall floor to be installed at this position. After the semi-finished floor slab is connected to the connecting building beam or column from the side or bottom surface, a new standard slab is expanded and spliced at the vacant position , align the new standard slab steel frame with the standard slab steel frame of the semi-finished floor slab side by side, fasten it with bolts, connect the standard slab to the floor slab overlapped building connection building beam or column steel structure one by one, and connect with the building beam Or stud bolt connection, and finally fill the concrete slurry in the groove on the top surface and smooth it out, after a specified time of curing and curing.

Claims (10)

1.一种模块化组合楼板,其特征在于:楼板整体由矩形模块化的标准板在同一平面连续拼接而成,标准板的边长为0.3~2.4m;1. A modular composite floor, characterized in that: the floor as a whole is formed by continuous splicing of rectangular modular standard panels on the same plane, and the side length of the standard panels is 0.3 to 2.4m; 所述标准板下层为钢框架(5),钢框架的顶面铺设有混凝土层(1),混凝土层的侧面边缘相对钢框架的侧边内缩25~150mm;The lower layer of the standard slab is a steel frame (5), the top surface of the steel frame is laid with a concrete layer (1), and the side edge of the concrete layer shrinks inwardly by 25-150 mm relative to the side edge of the steel frame; 所述钢框架(5)为四面槽钢围成中空的整体,槽钢的腹板(6)与混凝土层(1)垂直,槽口向内,槽钢顶面的翼板(8)与混凝土层固定连接;The steel frame (5) is a hollow whole surrounded by channel steel on all sides, the web (6) of the channel steel is perpendicular to the concrete layer (1), the notch is inward, and the wing plate (8) on the top surface of the channel steel is in contact with the concrete layer (1). layer fixed connection; 在混凝土层内与混凝土层平行地埋设有钢筋网(2),钢筋网(2)伸出混凝土层的侧边50~250mm。A reinforcement mesh (2) is buried parallel to the concrete layer in the concrete layer, and the reinforcement mesh (2) protrudes 50-250mm from the side of the concrete layer. 2.根据权利要求1所述的模块化组合楼板,其特征在于:在钢筋网伸出混凝土层的侧边位置,混凝土层设有多个向内凹40~125mm的连接槽(9)。2. The modular composite floor slab according to claim 1, characterized in that: at the side where the reinforcement mesh protrudes from the concrete layer, the concrete layer is provided with a plurality of connecting grooves (9) concave inward by 40-125mm. 3.根据权利要求1所述的模块化组合楼板,其特征在于:在混凝土层覆盖的范围内设有与钢框架固定连接的栓钉(4)。3. The modular composite floor slab according to claim 1, characterized in that: within the area covered by the concrete layer, there are pegs (4) fixedly connected with the steel frame. 4.根据权利要求1所述的模块化组合楼板,其特征在于:槽钢的腹板(6)设有螺栓孔(10),用于楼板整体从侧面与建筑梁或柱连接安装或模块化标准板之间的拼接。4. The modular composite floor slab according to claim 1, characterized in that: the web (6) of the channel steel is provided with bolt holes (10), which are used to connect and install the whole floor slab to the building beam or column from the side or to modularize it. Splicing between standard boards. 5.根据权利要求1所述的模块化组合楼板,其特征在于:在槽钢底面的翼板(8)设有螺栓孔(10),用于楼板整体从底面与建筑梁或柱连接安装。5. The modular composite floor according to claim 1, characterized in that: the flange (8) on the bottom of the channel steel is provided with bolt holes (10), which are used to connect and install the whole floor to the building beam or column from the bottom. 6.一种权利要求1~5之一所述的模块化组合楼板施工方法,其特征在于:按照下述步骤顺序进行:6. A construction method for modular composite floor slabs according to any one of claims 1 to 5, characterized in that: the following steps are carried out in sequence: 第一步、在工厂批量预制标准板;The first step is to prefabricate standard panels in batches in the factory; 第二步、运输标准板到施工现场,在施工现场地面或空中按照楼板的设计形状和尺寸拼接出整体的楼板,在拼接过程中:The second step is to transport the standard slab to the construction site, and splice the whole floor slab according to the design shape and size of the floor slab on the ground or in the air at the construction site. During the splicing process: 首先将相邻的标准板水平对齐,钢框架(5)的腹板(6)对齐后,以连接螺栓(7)穿过对齐的相邻腹板的螺栓孔(10)并紧固,其次将相邻位置的钢筋网(2)拧紧连接,形成楼板半成品;First align the adjacent standard plates horizontally, after the webs (6) of the steel frame (5) are aligned, pass the bolt holes (10) of the aligned adjacent webs with the connecting bolts (7) and fasten them, and then place the The steel mesh (2) at the adjacent position is tightened and connected to form a semi-finished floor slab; 第三步、将楼板半成品吊装到设计楼板位置,从侧面或底面与建筑梁或柱固定连接,然后在楼板表面的凹槽中填充混凝土浆料,并与混凝土层平齐,经过规定时间的养护并固化。The third step is to hoist the semi-finished floor slab to the design floor position, and fix it with the building beam or column from the side or bottom surface, then fill the groove on the surface of the floor slab with concrete slurry, and make it flush with the concrete layer, after a specified time of curing and solidified. 7.根据权利要求6所述的楼板施工方法,其特征在于:楼板从侧面与建筑梁或柱连接时,首先,从边缘标准板的钢框架腹板向连接建筑梁或柱侧面以螺钉或螺栓紧固,然后在边缘标准板的混凝土层外侧与连接建筑梁或柱的凹槽内填充混凝土浆料,并抹平,经过规定时间的养护固化。7. The floor construction method according to claim 6, characterized in that: when the floor is connected to the building beam or column from the side, at first, from the steel frame web of the edge standard plate to the side of the connecting building beam or column with screws or bolts Fasten, then fill the concrete slurry outside the concrete layer of the edge standard slab and the groove connecting the building beam or column, smooth it, and cure it after a specified period of time. 8.根据权利要求6所述的楼板施工方法,其特征在于:楼板从底面与建筑梁或柱连接时,首先,在接触标准板底部的连接建筑梁或柱钢结构位置,从钢框架底部翼板内侧向连接建筑梁或柱以螺钉或螺栓紧固,然后在边缘标准板的混凝土层外侧与墙体的凹槽内填充混凝土浆料,并抹平,经过规定时间的养护固化。8. The floor construction method according to claim 6, characterized in that: when the floor is connected to the building beam or column from the bottom surface, at first, at the position of the steel structure connecting the building beam or column contacting the bottom of the standard slab, from the bottom wing of the steel frame The inside of the slab is laterally connected to the building beams or columns and fastened with screws or bolts, and then the concrete slurry is filled in the outside of the concrete layer of the edge standard slab and the groove of the wall, smoothed, and cured after a specified period of time. 9.根据权利要求6所述的楼板施工方法,其特征在于:所述楼板半成品在地面拼装而成时,所述楼板半成品为该位置需安装的整体楼板一部分,将楼板半成品从侧面或底面与连接建筑梁或柱连接后,在空缺位置扩展拼接新的标准板,并排从侧面将新的标准板钢框架与楼板半成品的标准板钢框架对齐,以螺栓连接紧固,逐个连接标准板到楼板搭接的建筑连接建筑梁或柱钢结构,并与连接建筑梁或柱螺栓连接,最后在顶面出现的凹槽内填充混凝土浆料并抹平,经过规定时间的养护固化。9. The floor construction method according to claim 6, characterized in that: when the floor semi-finished product is assembled on the ground, the floor semi-finished product is a part of the overall floor to be installed at this position, and the floor semi-finished product is connected from the side or bottom surface After connecting the building beams or columns, expand and splice new standard slabs in the vacant position, align the new standard slab steel frame with the standard slab steel frame of the semi-finished floor slab side by side, fasten them with bolts, and connect the standard slabs to the floor slab one by one The lapped building is connected to the steel structure of the building beam or column, and is connected with the connecting building beam or column bolts. Finally, the grooves appearing on the top surface are filled with concrete slurry and smoothed, and cured after a specified period of time. 10.根据权利要求6所述的楼板施工方法,其特征在于:第一步中,在工厂批量预制标准板的过程为:首先预制钢框架(5),然后在钢框架的混凝土层覆盖范围内焊接固定栓钉(4),之后安装对应形状的模板,浇注混凝土,在混凝土层内预埋纵横方向的钢筋网(2);等待固化。10. The floor slab construction method according to claim 6, characterized in that: in the first step, the process of prefabricating standard slabs in batches in the factory is: first prefabricating the steel frame (5), and then within the coverage of the concrete layer of the steel frame The studs (4) are welded and fixed, and then the formwork of the corresponding shape is installed, the concrete is poured, and the reinforcement mesh (2) in the vertical and horizontal directions is pre-embedded in the concrete layer; wait for curing.
CN201710980281.5A 2017-10-19 2017-10-19 A kind of modular combination floor and construction method Pending CN107795055A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710980281.5A CN107795055A (en) 2017-10-19 2017-10-19 A kind of modular combination floor and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710980281.5A CN107795055A (en) 2017-10-19 2017-10-19 A kind of modular combination floor and construction method

Publications (1)

Publication Number Publication Date
CN107795055A true CN107795055A (en) 2018-03-13

Family

ID=61532559

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710980281.5A Pending CN107795055A (en) 2017-10-19 2017-10-19 A kind of modular combination floor and construction method

Country Status (1)

Country Link
CN (1) CN107795055A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339322A (en) * 2018-11-15 2019-02-15 武汉理工大学 A modular multidirectional beam and its installation method
CN114232783A (en) * 2021-12-16 2022-03-25 中南大学 A prefabricated beam-slab system of a fully assembled building and a beam-slab module prefabrication method thereof
CN114232843A (en) * 2021-12-16 2022-03-25 中建五局第三建设有限公司 A fully assembled building and its construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204238395U (en) * 2014-11-06 2015-04-01 安徽湖滨建设集团有限公司 A kind of prefabricated pair of thin plate cassette ceiling structure
CN106481007A (en) * 2016-11-11 2017-03-08 浙江绿筑建筑系统集成有限公司 Assembled flooring construction module and preparation method thereof
CN206053079U (en) * 2016-08-31 2017-03-29 青岛理工大学 Assembled beam slab integrated composite floor
CN207405843U (en) * 2017-10-19 2018-05-25 武汉理工大学 A kind of precast splice type floor

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204238395U (en) * 2014-11-06 2015-04-01 安徽湖滨建设集团有限公司 A kind of prefabricated pair of thin plate cassette ceiling structure
CN206053079U (en) * 2016-08-31 2017-03-29 青岛理工大学 Assembled beam slab integrated composite floor
CN106481007A (en) * 2016-11-11 2017-03-08 浙江绿筑建筑系统集成有限公司 Assembled flooring construction module and preparation method thereof
CN207405843U (en) * 2017-10-19 2018-05-25 武汉理工大学 A kind of precast splice type floor

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339322A (en) * 2018-11-15 2019-02-15 武汉理工大学 A modular multidirectional beam and its installation method
CN114232783A (en) * 2021-12-16 2022-03-25 中南大学 A prefabricated beam-slab system of a fully assembled building and a beam-slab module prefabrication method thereof
CN114232843A (en) * 2021-12-16 2022-03-25 中建五局第三建设有限公司 A fully assembled building and its construction method
CN114232843B (en) * 2021-12-16 2023-08-08 中建五局第三建设有限公司 A fully assembled building and construction method thereof

Similar Documents

Publication Publication Date Title
CN108360721B (en) Precast concrete ultra-thin two-way load-bearing prefabricated reinforced truss composite floor
CN105089178B (en) A kind of pre-splicing Standard formula building of prefabricated steel reinforced concrete shear walls
CN105839846A (en) Prefabricated reinforced concrete composite beam
CN108222347A (en) A kind of big module welding overlapping beam slab of the assembled with plane girder temporary support
CN204826308U (en) Structure assembly type structure is pieced together in advance to prefabricated shaped steel concrete shear force wall
CN108301545B (en) Assembled large-module superposed beam plate structure with three-dimensional truss temporary support
CN114562059A (en) Shear wall connector and assembled shear wall and assembly method
CN113585456B (en) Construction and Construction Method of Precast Concrete Beam-column Joints
CN110409617A (en) Z-shaped double plywood joint assembled H-shaped steel beam square steel pipe column steel structure system
CN108301546B (en) A prefabricated large modular composite beam-slab structure with temporary support of plane trusses
CN111424869A (en) Concrete floor secondary beam combined prefabricated part and manufacturing method
CN110670722A (en) Implementation method of beam-column connecting node of fabricated building
CN106193402B (en) Truss beam integrated floor module and installation method thereof
CN108360723B (en) Assembly type large module semi-welded superposed beam plate structure with stereo truss temporary support
CN107083853A (en) Modularization multi-storied garage and its installation method
CN107795055A (en) A kind of modular combination floor and construction method
CN113513041B (en) Assembled multi-layer flat-top large-span pillar-free underground structure and open excavation construction method thereof
CN207405843U (en) A kind of precast splice type floor
CN210066817U (en) Assembly integral vault is striden no post underground structure greatly
CN104032862B (en) Assembled girder steel seam line L shape mixing coupled wall and construction method thereof
CN112663788B (en) Assembled rapid construction method
CN110080291A (en) A kind of assembled flat-top is greatly across no column underground structure
CN210066818U (en) Assembled flat top has post underground structure
CN203834741U (en) Prefabricated steel beam joint L-shaped mixed coupled wall
CN104032863B (en) Assembled in-line mixing coupled wall and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180313

RJ01 Rejection of invention patent application after publication