CN107747498B - A kind of mould bag filled type anchor bolt grouting device and method - Google Patents

A kind of mould bag filled type anchor bolt grouting device and method Download PDF

Info

Publication number
CN107747498B
CN107747498B CN201710796824.8A CN201710796824A CN107747498B CN 107747498 B CN107747498 B CN 107747498B CN 201710796824 A CN201710796824 A CN 201710796824A CN 107747498 B CN107747498 B CN 107747498B
Authority
CN
China
Prior art keywords
hole
steel pipe
slip casting
mould bag
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710796824.8A
Other languages
Chinese (zh)
Other versions
CN107747498A (en
Inventor
程鹏达
李世海
冯春
杨田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Institute of Mechanics of CAS
Original Assignee
Institute of Mechanics of CAS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Institute of Mechanics of CAS filed Critical Institute of Mechanics of CAS
Priority to CN201710796824.8A priority Critical patent/CN107747498B/en
Publication of CN107747498A publication Critical patent/CN107747498A/en
Application granted granted Critical
Publication of CN107747498B publication Critical patent/CN107747498B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/028Devices or accesories for injecting a grouting liquid in a bore-hole

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of mould bag filled type anchor bolt grouting devices, comprising: aperture sealing of hole steel pipe (1), wall surface presbyopia (2), level pressure disabler A, aperture sealing of hole mould bag (4), slip casting steel pipe (5), level pressure disabler B, reinforcing rib (6), bottom hole anchoring steel pipe (7), bottom hole anchoring mould bag (8).The present invention anchors steel pipe three parts by the way that anchor pole is divided into aperture sealing of hole steel pipe, slip casting steel pipe, bottom hole, and mould bag, reinforcing rib, wall surface presbyopia is arranged, swell in conjunction with mould bag slip casting, unsuitable spillage the features such as, realize the low anchoring in hole and the filling in aperture closing;By wall surface presbyopia, what realization cement slurry, solidification were starched is efficiently injected into loose wall rock;To effectively increase grouting pressure, Fast Filling crushed zone loose wall rock avoids injection slurry by underground water erosion, ultimately forms firm mould bag filled type anchor pole, improve construction quality and technical level comprehensively.

Description

A kind of mould bag filled type anchor bolt grouting device and method
Technical field
The invention belongs to engineering reinforcement slurry injection technique field, in particular to a kind of mould bag filled type anchor bolt grouting device and side Method.
Background technique
Currently, rich water crushed zone area tunnel surrounding intensity is lower, easily there is surrounding rock collapse, mud-rock flow, tunnel gushing water etc. Security risk.Bolt grouting reinforce country rock be through frequently with one of reinforcement measure, but conventional anchor pole injection slurry is light water Cement mortar is largely lost under the conditions of underground water erosion, anchoring quality is caused to decline to a great extent.Additionally due to the high stream of cement mortar Dynamic property, grouting pressure are usually less than 0.4MPa, cannot effectively fill and densification crushed zone country rock.
Summary of the invention
The object of the present invention is to provide a kind of mould bag filled type anchor bolt grouting device and method, effectively improve grouting pressure, Fast Filling crushed zone loose wall rock avoids injection slurry by underground water erosion, ultimately forms firm mould bag filled type anchor pole, entirely Improve construction quality and technical level in face.
The technical scheme is that a kind of mould bag filled type anchor bolt grouting device, comprising: aperture sealing of hole steel pipe, wall surface Presbyopia, level pressure disabler A, aperture sealing of hole mould bag, slip casting steel pipe, level pressure disabler B, reinforcing rib, bottom hole anchor steel pipe, bottom hole anchor Solid model bag;
The aperture sealing of hole steel pipe, the slip casting steel pipe, bottom hole anchoring steel pipe are seamless steel pipe, are fixedly connected, The junction of the aperture sealing of hole steel pipe (1) and the slip casting steel pipe (5) is placed in level pressure disabler A, in the slip casting steel pipe (5) Level pressure disabler B is placed in the junction of bottom hole anchoring steel pipe (7);
The aperture sealing of hole length of steel pipe is consistent with aperture sealing of hole area depth, for by the wall surface presbyopia by striaght cement Slurry injects the aperture sealing of hole mould bag;
The wall surface presbyopia is arranged the neat slurry in the aperture sealing of hole steel pipe surrounding, for that will fill and injects the hole Mouth sealing of hole mould bag;The wall surface presbyopia is arranged in the slip casting steel pipe surrounding, neat slurry and accelerated cement for that will fill Slurry injection crushed zone stratum;
The level pressure disabler A is crushed after aperture sealing of hole mould bag filling finishes and reaches design grouting pressure, makes to add The neat slurry of note injects the slip casting steel pipe;
The aperture sealing of hole mould bag is fixed on the aperture sealing of hole steel pipe, after injecting the neat slurry of certain pressure, institute It states aperture sealing of hole mould bag to swell, realizes orifice closing;
The slip casting length of steel pipe is consistent with crushed zone depth of stratum, for by the wall surface presbyopia 2 by neat slurry Crushed zone stratum is injected with Fast Setting Cement Slurry;
The Fast Setting Cement Slurry on the crushed zone stratum to be implanted level pressure disabler B is crushed after reaching scheduled pressure, makes to add The neat slurry of note injects the bottom hole and anchors steel pipe;
The reinforcing rib 7 is reinforcing bar or pastes glass mat, is welded on around the slip casting steel pipe, described for improving The shearing resistance of slip casting steel pipe, tensile strength;
The bottom hole anchoring steel pipe, which is used to neat slurry injecting the bottom hole according to scheduled pressure, anchors mould bag;
The bottom hole anchoring mould bag is fixed on the bottom hole anchoring steel pipe, after injecting the neat slurry of certain pressure, institute It states bottom hole anchoring mould bag to swell, realizes the filling of device to hole base space.
A kind of mould bag filled type anchor bolt grouting method, using a kind of above-mentioned mould bag filled type anchor bolt grouting device, including under Column step:
A. data and surrounding rock consolidation design objective are reconnoitred according to crushed zone loose wall rock, calculates and reaches design value to stabilization zone Required aperture sealing of hole mould bag size, anchor bolt grouting drilling depth, bottom hole anchoring mould bag size, Grouting Pipe reinforcing rib size, Drilling hole amount and the spacing of wells;
B. according to design anchoring hole location drilling, select bit diameter for Φ 70mm to Φ 200mm drill hole of drilling machine, drilling is primary It is drilled into design anchorage depth;
C. anchor bolt grouting pipe is assembled;Aperture sealing of hole steel pipe, slip casting steel pipe and bottom hole anchoring steel pipe are connected first, Each connecting portion is placed in level pressure disabler, realizes aperture sealing of hole area, middle part broken formation stabilization zone and bottom hole anchorage zone Subregion slip casting;Then reinforcing rib and slip casting steel pipe are fixed as one, finally by aperture sealing of hole mould bag and bottom hole anchoring mould bag point It does not cover on aperture sealing of hole steel pipe and bottom hole anchoring steel pipe and fixed;
D. after the assembling of anchor bolt grouting pipe, connection grouting pump starts slip casting, while recording injection pressure curve and flow; Grouting sequence is from aperture to bottom hole;
First by the striaght cement slurries injection hole mouth sealing of hole mould bag of ratio of mud 0.6:1~0.8:1, design pressure is reached Afterwards, it maintains grouting pressure 5 to 10 minutes, terminates the bag slip casting of aperture sealing of hole mould;
Then hole flushing and grouting pressure is improved to level pressure stopper design pressure, slip casting disabler failure, injection slurry passes through Grouting Pipe wall surface presbyopia enters crushed zone stratum, and accelerator is added in aperture at this time, forms accelerated cement slurries, accelerated cement slurries Setting time can be by adjusting rapid hardening agent content, 30 seconds to several minutes are controllable, and the cement slurry of quick solidification can effectively avoid brokenly The broken erosion with underground water in stratum improves the slip casting filling rate on crushed zone stratum, and when crushed zone stratum, grouting pressure, which reaches, sets After evaluation, grouting pressure stopping slip casting in 5 to 10 minutes is maintained, and with high pressure water cleaning grouting pipe;
Last hole flushing simultaneously improves grouting pressure to level pressure stopper design pressure, and the failure of slip casting disabler uses water again The striaght cement slurries filling bottom hole of gray scale 0.6:1~0.8:1 anchors mould bag, after reaching design pressure, maintains grouting pressure 5 to 10 Minute, terminate the bag slip casting of hole bed die;
E. after solidifying a few hours, prefabricated anchor plate is installed in aperture, terminates the casement bag filled type anchor bolt grouting.
The present invention anchors steel pipe three parts, and mould is arranged by the way that anchor pole is divided into aperture sealing of hole steel pipe, slip casting steel pipe, bottom hole Bag, reinforcing rib, wall surface presbyopia, swell in conjunction with mould bag slip casting, unsuitable spillage the features such as, realize filling out for the low anchoring in hole and aperture Fill closing;By wall surface presbyopia, what realization cement slurry, solidification were starched is efficiently injected into loose wall rock;To effectively increase slip casting pressure Power, Fast Filling crushed zone loose wall rock, avoids injection slurry by underground water erosion, ultimately forms firm mould bag filled type Anchor pole improves construction quality and technical level comprehensively.
Detailed description of the invention
Fig. 1 is structure of the invention composition schematic diagram.
Fig. 2 is the method for the present invention flow chart.
The aperture 1-- sealing of hole steel pipe, 2-- wall surface presbyopia, 3-- level pressure disabler, the aperture 4-- sealing of hole mould bag, 5-- slip casting steel Pipe, 6-- reinforcing rib, 7-- bottom hole anchoring steel pipe, 8-- bottom hole anchor mould bag
Specific embodiment
Embodiment 1: referring to Fig. 1, a kind of mould bag filled type anchor bolt grouting device, comprising: aperture sealing of hole steel pipe 1, wall surface flower Eye 2, level pressure disabler A, aperture sealing of hole mould bag 4, slip casting steel pipe 5, level pressure disabler B, reinforcing rib 6, bottom hole anchor steel pipe 7, hole Bottom anchors mould bag 8;
The aperture sealing of hole steel pipe 1, the slip casting steel pipe 5, bottom hole anchoring steel pipe 7 are seamless steel pipe, are fixedly connected, It is placed in level pressure disabler A in the junction of the aperture sealing of hole steel pipe (1) and the slip casting steel pipe (5), in the slip casting steel pipe (5) level pressure disabler B is placed in the junction of bottom hole anchoring steel pipe (7);
1 length of aperture sealing of hole steel pipe is consistent with aperture sealing of hole area depth, for by the wall surface presbyopia 2 by pure water Mud injects the aperture sealing of hole mould bag 4;
The wall surface presbyopia 2 is arranged described in the neat slurry injection in 1 surrounding of aperture sealing of hole steel pipe, for that will fill Aperture sealing of hole mould bag 4;Neat slurry and rapid hardening in 5 surrounding of slip casting steel pipe, for that will fill is arranged in the wall surface presbyopia 2 Cement slurry injects crushed zone stratum;
The level pressure disabler A is crushed after the aperture sealing of hole mould bag 4 filling finishes and reaches design grouting pressure, makes to add The neat slurry of note injects the slip casting steel pipe 5;
The aperture sealing of hole mould bag 4 is fixed on the aperture sealing of hole steel pipe 1, after injecting the neat slurry of certain pressure, The aperture sealing of hole mould bag 4 swells, and realizes orifice closing;
5 length of slip casting steel pipe is consistent with crushed zone depth of stratum, for by the wall surface presbyopia 2 by neat slurry Crushed zone stratum is injected with Fast Setting Cement Slurry;
The Fast Setting Cement Slurry on injection crushed zone stratum is crushed after reaching scheduled pressure in the level pressure disabler B, makes to add The neat slurry of note injects the bottom hole and anchors steel pipe 7;
The reinforcing rib 6 is reinforcing bar or pastes glass mat, is welded on around the slip casting steel pipe 5, for improving State 5 shearing resistance of slip casting steel pipe, tensile strength;
The bottom hole anchoring steel pipe 7, which is used to neat slurry injecting the bottom hole according to scheduled pressure, anchors mould bag 8;
The bottom hole anchoring mould bag 8 is fixed on the bottom hole anchoring steel pipe 7, after injecting the neat slurry of certain pressure, The bottom hole anchoring mould bag 8 swells, and realizes the filling of device to hole base space.
Embodiment 2: referring to fig. 2, a kind of 2. mould bag filled type anchor bolt grouting methods use a kind of mould described in embodiment 1 Bag filled type anchor bolt grouting device, including the following steps:
A. data and surrounding rock consolidation design objective are reconnoitred according to crushed zone loose wall rock, calculates and reaches design value to stabilization zone Required aperture sealing of hole mould bag size, anchor bolt grouting drilling depth, bottom hole anchoring mould bag size, Grouting Pipe reinforcing rib size, Drilling hole amount and the spacing of wells;
B. according to design anchoring hole location drilling, select bit diameter for Φ 70mm to Φ 200mm drill hole of drilling machine, drilling is primary It is drilled into design anchorage depth;
C. anchor bolt grouting pipe is assembled;Aperture sealing of hole steel pipe, slip casting steel pipe and bottom hole anchoring steel pipe are connected first, Each connecting portion is placed in level pressure disabler, realizes aperture sealing of hole area, middle part broken formation stabilization zone and bottom hole anchorage zone Subregion slip casting;Then reinforcing rib and slip casting steel pipe are fixed as one, finally by aperture sealing of hole mould bag and bottom hole anchoring mould bag point It does not cover on aperture sealing of hole steel pipe and bottom hole anchoring steel pipe and fixed;
D. after the assembling of anchor bolt grouting pipe, connection grouting pump starts slip casting, while recording injection pressure curve and flow; Grouting sequence is from aperture to bottom hole;
First by the striaght cement slurries injection hole mouth sealing of hole mould bag of ratio of mud 0.6:1~0.8:1, design pressure is reached Afterwards, it maintains grouting pressure 5 to 10 minutes, terminates the bag slip casting of aperture sealing of hole mould;
Then hole flushing and grouting pressure is improved to level pressure stopper design pressure, slip casting disabler failure, injection slurry passes through Grouting Pipe wall surface presbyopia enters crushed zone stratum, and accelerator is added in aperture at this time, forms accelerated cement slurries, accelerated cement slurries Setting time can be by adjusting rapid hardening agent content, 30 seconds to several minutes are controllable, and the cement slurry of quick solidification can effectively avoid brokenly The broken erosion with underground water in stratum improves the slip casting filling rate on crushed zone stratum, and when crushed zone stratum, grouting pressure, which reaches, sets After evaluation, grouting pressure stopping slip casting in 5 to 10 minutes is maintained, and with high pressure water cleaning grouting pipe;
Last hole flushing simultaneously improves grouting pressure to level pressure stopper design pressure, and the failure of slip casting disabler uses water again The striaght cement slurries filling bottom hole of gray scale 0.6:1~0.8:1 anchors mould bag, after reaching design pressure, maintains grouting pressure 5 to 10 Minute, terminate the bag slip casting of hole bed die;
E. after solidifying a few hours, prefabricated anchor plate is installed in aperture, terminates the casement bag filled type anchor bolt grouting.

Claims (2)

1. a kind of mould bag filled type anchor bolt grouting device characterized by comprising aperture sealing of hole steel pipe (1), wall surface presbyopia (2), Level pressure disabler A, aperture sealing of hole mould bag (4), slip casting steel pipe (5), level pressure disabler B, reinforcing rib (6), bottom hole anchor steel pipe (7), bottom hole anchoring mould bag (8);
The aperture sealing of hole steel pipe (1), the slip casting steel pipe (5), bottom hole anchoring steel pipe (7) are seamless steel pipe, fixed to connect It connects and is placed in level pressure disabler A in the junction of the aperture sealing of hole steel pipe (1) and the slip casting steel pipe (5), in the slip casting steel The junction for managing (5) and bottom hole anchoring steel pipe (7) is placed in level pressure disabler B;
Aperture sealing of hole steel pipe (1) length is consistent with aperture sealing of hole area depth, for by the wall surface presbyopia (2) by pure water Mud injects the aperture sealing of hole mould bag (4);
The wall surface presbyopia (2) is arranged described in the neat slurry injection in aperture sealing of hole steel pipe (1) surrounding, for that will fill Aperture sealing of hole mould bag (4);The neat slurry in slip casting steel pipe (5) surrounding, for will fill is arranged in the wall surface presbyopia (2) Crushed zone stratum is injected with Fast Setting Cement Slurry;
The level pressure disabler A is crushed after the aperture sealing of hole mould bag (4) filling finishes and reaches design grouting pressure, makes to fill Neat slurry inject the slip casting steel pipe (5);
The aperture sealing of hole mould bag (4) is fixed on the aperture sealing of hole steel pipe (1), after injecting the neat slurry of certain pressure, The aperture sealing of hole mould bag (4) swells, and realizes orifice closing;
Slip casting steel pipe (5) length is consistent with crushed zone depth of stratum, for by the wall surface presbyopia (2) by neat slurry Crushed zone stratum is injected with Fast Setting Cement Slurry;
The Fast Setting Cement Slurry on the crushed zone stratum to be implanted level pressure disabler B is crushed after reaching scheduled pressure, makes filling Neat slurry injects bottom hole anchoring steel pipe (7);
The reinforcing rib (6) is reinforcing bar or pastes glass mat, is welded on around the slip casting steel pipe (5), for improving State slip casting steel pipe (5) shearing resistance, tensile strength;
Bottom hole anchoring steel pipe (7) is used to neat slurry injecting bottom hole anchoring mould bag (8) according to scheduled pressure;
Bottom hole anchoring mould bag (8) is fixed on bottom hole anchoring steel pipe (7), after injecting the neat slurry of certain pressure, Bottom hole anchoring mould bag (8) swells, and realizes the filling of device to hole base space.
2. a kind of mould bag filled type anchor bolt grouting method is filled using a kind of mould bag filled type anchor bolt grouting described in claim 1 It sets, it is characterised in that: include the following steps:
A. data and surrounding rock consolidation design objective are reconnoitred according to crushed zone loose wall rock, calculating reaches needed for design value to stabilization zone Aperture sealing of hole mould bag size, anchor bolt grouting drilling depth, the bottom hole anchoring mould bag size, Grouting Pipe reinforcing rib size, drilling wanted Quantity and the spacing of wells;
B. according to design anchoring hole location drilling, select bit diameter for Φ 70mm to Φ 200mm drill hole of drilling machine, drilling is once drilled into Design anchorage depth;
C. anchor bolt grouting pipe is assembled;Aperture sealing of hole steel pipe, slip casting steel pipe and bottom hole anchoring steel pipe are connected first, each Connecting portion is all placed in level pressure disabler, realizes the subregion of aperture sealing of hole area, middle part broken formation stabilization zone and bottom hole anchorage zone Slip casting;Then reinforcing rib and slip casting steel pipe are fixed as one, finally cover aperture sealing of hole mould bag and bottom hole anchoring mould bag respectively It is on aperture sealing of hole steel pipe and bottom hole anchoring steel pipe and fixed;
D. after the assembling of anchor bolt grouting pipe, connection grouting pump starts slip casting, while recording injection pressure curve and flow;Slip casting Sequence is from aperture to bottom hole;
First by the striaght cement slurries injection hole mouth sealing of hole mould bag of ratio of mud 0.6:1~0.8:1, after reaching design pressure, tie up It holds grouting pressure 5 to 10 minutes, terminates the bag slip casting of aperture sealing of hole mould;
Then hole flushing and grouting pressure is improved to level pressure stopper design pressure, slip casting disabler failure, injection slurry passes through slip casting Tube wall face presbyopia enters crushed zone stratum, and accelerator is added in aperture at this time, forms accelerated cement slurries, and accelerated cement slurries coagulate Gu the time can be by adjusting rapid hardening agent content, 30 seconds to several minutes controllable, and the cement slurry of quick solidification can effectively avoid crushed zone The erosion of underground water in stratum improves the slip casting filling rate on crushed zone stratum, and when crushed zone stratum, grouting pressure reaches design value Afterwards, grouting pressure stopping slip casting in 5 to 10 minutes is maintained, and with high pressure water cleaning grouting pipe;
Last hole flushing simultaneously improves grouting pressure to level pressure stopper design pressure, and the failure of slip casting disabler uses the ratio of mud again The striaght cement slurries filling bottom hole of 0.6:1~0.8:1 anchors mould bag, after reaching design pressure, maintains 5 to 10 points of grouting pressure Clock terminates the bag slip casting of hole bed die;
E. after solidifying a few hours, prefabricated anchor plate is installed in aperture, terminates the casement bag filled type anchor bolt grouting.
CN201710796824.8A 2017-09-06 2017-09-06 A kind of mould bag filled type anchor bolt grouting device and method Active CN107747498B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710796824.8A CN107747498B (en) 2017-09-06 2017-09-06 A kind of mould bag filled type anchor bolt grouting device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710796824.8A CN107747498B (en) 2017-09-06 2017-09-06 A kind of mould bag filled type anchor bolt grouting device and method

Publications (2)

Publication Number Publication Date
CN107747498A CN107747498A (en) 2018-03-02
CN107747498B true CN107747498B (en) 2019-03-22

Family

ID=61255684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710796824.8A Active CN107747498B (en) 2017-09-06 2017-09-06 A kind of mould bag filled type anchor bolt grouting device and method

Country Status (1)

Country Link
CN (1) CN107747498B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109798140B (en) * 2019-02-21 2020-12-18 平顶山天安煤业股份有限公司 Splitting grouting reinforcement support method for kilometer deep well soft rock

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202380463U (en) * 2011-12-19 2012-08-15 中铁第四勘察设计院集团有限公司 Grouting capsule type recyclable anchor cable
CN103603683A (en) * 2013-12-03 2014-02-26 河南理工大学 Bag type grouting anchoring device and anchoring method
CN204475326U (en) * 2015-03-01 2015-07-15 宁波鸿晨建设有限公司 The construction equipment of anti-slub type anti-float anchor rod
CN105888673A (en) * 2016-05-09 2016-08-24 山东大学 Deep-hole plastic pipe high-pressure grouting anti-explosion device in soft water-rich surrounding rock and operation method
CN105909257A (en) * 2016-05-31 2016-08-31 山东大学 Separated grouting device in drilled hole and sectional grouting operation process

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202380463U (en) * 2011-12-19 2012-08-15 中铁第四勘察设计院集团有限公司 Grouting capsule type recyclable anchor cable
CN103603683A (en) * 2013-12-03 2014-02-26 河南理工大学 Bag type grouting anchoring device and anchoring method
CN204475326U (en) * 2015-03-01 2015-07-15 宁波鸿晨建设有限公司 The construction equipment of anti-slub type anti-float anchor rod
CN105888673A (en) * 2016-05-09 2016-08-24 山东大学 Deep-hole plastic pipe high-pressure grouting anti-explosion device in soft water-rich surrounding rock and operation method
CN105909257A (en) * 2016-05-31 2016-08-31 山东大学 Separated grouting device in drilled hole and sectional grouting operation process

Also Published As

Publication number Publication date
CN107747498A (en) 2018-03-02

Similar Documents

Publication Publication Date Title
CN104453913B (en) A kind of Shaft Stopes front pre-grouting method
CN108301857B (en) Rock anchor
CN104674809B (en) Anti-floating anchor rod structure and its construction method
CN104453946B (en) Advanced reinforcing construction method for building tunnel in soft surrounding rock
CN101748728B (en) Soil cement expanding uplift pile
CN107417182B (en) Expansion type high polymer cement slurry, grouting reinforcement device and grouting reinforcement method
CN101570970A (en) Construction method of cement soil anchor and anchor plate combined member thereof
CN105350988B (en) Tunnel Base reinforcement means
CN109538216A (en) Pass through mined out and subsidence area constructing tunnel technique
CN104196014A (en) Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof
CN110130936A (en) It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack
CN109680675A (en) A kind of Stabilizing Grout method that can dynamically control grouting amount and harden opportunity
CN103556554B (en) Reinforce the construction method of the drilled pile composite foundation structure of the soft base of embankment
CN102877470A (en) Combined soil nailing construction method
CN103410144B (en) Prestressed reinforcement piles set into rock and construction method
CN105019427A (en) Bolting-grouting integrated treatment method for railway tunnel base disease
CN208201874U (en) A kind of open-cell cloth bag grouting structure
CN107747498B (en) A kind of mould bag filled type anchor bolt grouting device and method
CN104196488B (en) Underwater exploration hole hole-sealing technology
CN105178966A (en) Grouting process for water blocking by wall breaking for mine vertical shafts
CN109505641A (en) A kind of soft-rock tunnel bottom plate anchor pouring reinforcement method
CN108952765B (en) Construction method for advanced support of super-large pipe shed on water-rich sand layer
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
JP6733892B1 (en) Proportional pouring grout monitor and proportional pouring method for hardened grout using the same
CN102979087B (en) Construction method for rotary excavation pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant