CN107740418A - A kind of construction method excavated for rock vertical wall of deep foundation pit - Google Patents

A kind of construction method excavated for rock vertical wall of deep foundation pit Download PDF

Info

Publication number
CN107740418A
CN107740418A CN201710852319.0A CN201710852319A CN107740418A CN 107740418 A CN107740418 A CN 107740418A CN 201710852319 A CN201710852319 A CN 201710852319A CN 107740418 A CN107740418 A CN 107740418A
Authority
CN
China
Prior art keywords
excavated
excavating
foundation pit
scar
deep foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710852319.0A
Other languages
Chinese (zh)
Inventor
董浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Original Assignee
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd filed Critical Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Priority to CN201710852319.0A priority Critical patent/CN107740418A/en
Publication of CN107740418A publication Critical patent/CN107740418A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a kind of construction method excavated for rock vertical wall of deep foundation pit, this method carries out continuous vertical straight wall to excavation area scar using the outdoor Down-hole rolling rig of KT5 type integral types and excavated, the high excavating sideline error range control of precision controlling is in 50mm, facade vertical error is controlled within 5 °, cutting depth is between 1~10m, and the separation band for being mutually twisted and forming width 150mm is formed after excavating, realize the separation for excavating area and supporting region, broken clear is carried out to excavating area using broken excavator again, reduce it is broken excavate during disturbance to foundation, facade is finally excavated using the levelling circular arc of form of mesh plaster processing, form smooth waterproof construction basic unit.Therefore, present invention reduces overall excavated volume, foundation capability is ensure that, efficiency of construction is improved and shortens the construction period, construction is workable, reduces the various features such as dust and noise pollution, can obtain preferably economic and social benefit.

Description

A kind of construction method excavated for rock vertical wall of deep foundation pit
Technical field
The present invention relates to a kind of construction method excavated for rock vertical wall of deep foundation pit, belong to ground and base in architectural engineering Plinth technical field of construction.
Background technology
During construction of super highrise building, ground can often select the higher secondary hard stone of bearing capacity, general hard stone and special heavily fortified point Masonry is main carrying carrier, and it has, and bearing capacity is higher, the preferable physical characteristic of globality.During such foundation excavation Abolished more using power-equipment, such as large excavator, but powered excavation equipment is because of its hydraulic crushing device construction characteristic It is difficult to the construction precision of excavation line is controlled, more using 1:0.35 sloping coefficient is excavated, cause excavate region commonly greater than The excavation region of design, and need the supporting region retained to be produced by the disturbing influence of power-equipment excavating equipment in mining process Layer is loosened, this, which loosens layer, will influence basic holding force state, need to manually reject to compact substance area, not only wasting manpower and material resources, Er Qiejin One step increases excavation scope, and unnecessary excavation region is backfilled using concrete, adds backfill amount, cause construction cost to increase Add.Therefore, there is no preferable processing method in such work progress at present.
The content of the invention
For above-mentioned technical problem, the present invention provides a kind of excavation precision use that is high, easy for construction, can improving efficiency of construction In the construction method that rock vertical wall of deep foundation pit excavates, to overcome deficiency of the prior art.
Technical scheme:A kind of construction method excavated for rock vertical wall of deep foundation pit, comprises the following steps:
Step 1, it is sampled to excavating place, determines formation hardness scope, and then determines to excavate scope;
Step 2, leveling processing is carried out to region need to be excavated, control the scope of operation gradient;
Step 3, to needing excavating region and bearing area progress scope of operation division and carrying out excavation line for basic holding force rock stratum Put cloth;
Step 4, along excavation line continuous seaming straight wall is carried out to excavating area scar using the outdoor Down-hole rolling rig of KT5 type integral types Excavate, and control vertical precision, until excavating area's scar and supporting region scar is separated by required;
Step 5, using broken excavator to excavate area carry out it is broken clear, complete rock deep foundation pit construction.
In the above method, the formation hardness refers to according to the secondary hard stone in ground Pu Shi classification charts, general hard stone and special heavily fortified point Stone, its cutting depth are 1~10m.
In the above method, between the scope of operation gradient is 0~10 °.
In the above method, the bearing area refers to as the region for bearing built-loading.
In the above method, the excavation line mark refers to rig sideline away from design structure sideline distance controlling within 200mm, To reduce the distance between excavating sideline and design structure sideline, and then reduce excavated volume and reduce concrete backfill usage amount Purpose.
In the above method, opened using the outdoor Down-hole rolling rig of KT5 type integral types excavating area's continuous seaming straight wall of scar progress During digging, aperture is mutually twisted to form width 150mm separation bands, realizes the separation for excavating area's scar and supporting region scar.
In the above method, the centerline deviation in adjacent aperture is controlled within 50mm.
In the above method, when excavate the separation of area's scar and supporting region scar, removing equipment using static(al) will excavate Area is separated with supporting region, and block power-equipment abolish during disturbance to the influence of scar need to be retained.
In the above method, the circular arc interface to be formed is excavated to straight wall and is handled using mesh plaster, it is anti-water base to meet Layer requires.
Due to using above-mentioned technical proposal, the advantage of the invention is that:The present invention is excavated using straight wall and substitutes traditional put Slope hydraulic character, excavation amount and stemming operation amount are reduced, and separation band is first formed using static(al) rig, then using dynamic Power breaker is excavated, and eliminates disturbing influence of the digging process to carrying rock mass.Meanwhile the present invention first uses KT5 types one The outdoor Down-hole rolling rig of body formula carries out continuous vertical straight wall to excavation area scar and excavated, the high excavating sideline error range control of precision controlling System is controlled within 5 ° in 50mm, facade vertical error, and cutting depth forms after excavating between 1-10m and is mutually twisted shape Into φ 150mm separation band, the separation for excavating area and supporting region is realized, then to excavating area crush clearly using broken excavator Fortune, reduce it is broken excavate during disturbance to foundation.And the present invention passes through keyhole edge and design structure The distance in sideline within 150mm, with reach reduce breast wall concrete backfill usage amount purpose, finally using mesh plaster at The levelling circular arc of form of reason excavates facade, forms smooth waterproof construction basic unit.
Brief description of the drawings
Fig. 1 is the top view when present invention is implemented;
Fig. 2 is the elevation when present invention is implemented.
Description of reference numerals:The outdoor Down-hole rolling rig of 1-KT5 type integral types, 2- crush excavator, and 3- excavates area, 4- design knots Structure sideline, 5- separation bands, 6- supporting regions, 7- foundation excavation absolute altitudes, 8- basic engineering absolute altitudes.
Embodiment
In order that the object, technical solutions and advantages of the present invention are clearer, with reference to the accompanying drawings and examples to this hair It is bright to be described in further detail.
Embodiments of the invention:Referring to Fig. 1 and Fig. 2, a kind of construction party excavated for rock vertical wall of deep foundation pit of the present invention Method, comprise the following steps:
Step 1, be sampled to excavating place, determine formation hardness scope, according to time hard stone in ground Pu Shi classification charts, The construction method of the present invention can be used in the range of general hard stone and special hard stone, the cutting depth in each region is determined with reference to construction drawing And excavate scope;
Step 2, leveling processing is carried out to region need to be excavated, the control scope of operation gradient is within 1~10 °;
Step 3, the scar progress scope of operation division for excavating area 3 and supporting region 6 to needing basic holding force rock stratum are simultaneously opened Dig line and put cloth, and distance controlling of the rig sideline away from design structure sideline 4 is within 200mm;
Step 4, when excavate the separation of area's scar and supporting region scar, Qu Yucheng will be excavated by removing equipment using static(al) Area is carried to be separated, and block power-equipment abolish during disturbance to the influence of scar need to be retained;Used along excavation line The outdoor Down-hole rolling rig 1 of KT5 type integral types is continuously bored a diameter of φ 150mm hole to designed elevation 8 to excavating the scar of area 3, And adjacent hole is intersected, within 50mm, vertical precision forms a diameter of width within 5 ° for control aperture centerline deviation control 150mm separation band 5 is spent, area 3 will be excavated and the scar of supporting region 6 is separated;
Step 5, broken clear carried out to excavating area 3 using broken excavator 2;
Step 6, the circular arc to be formed occlusion facade is excavated to straight wall using mesh plaster processing.
The operation principle of the present invention:The present invention is first carried out using the outdoor Down-hole rolling rig 1 of KT5 type integral types to excavation area scar Continuous vertical straight wall is excavated, the high excavating sideline error range control of precision controlling in 50mm, the control of facade vertical error 5 ° with Interior, cutting depth forms the separation band 5 for being mutually twisted and forming width 150mm between 1~10m after excavating, area is excavated in realization 3 with the separation of supporting region 6, then using broken excavator 2 to excavate area 3 carry out it is broken clear, reduce it is broken excavate during Disturbance to foundation.And the present invention by the distance in keyhole edge and design structure sideline within 150mm, with Reaching reduces the purpose of breast wall concrete backfill usage amount, and the levelling circular arc of form finally handled using mesh plaster is excavated vertical Face, form smooth waterproof construction basic unit.Therefore, present invention reduces overall excavated volume, foundation capability is ensure that, is improved Efficiency of construction shortens the construction period, and construction is workable, reduces the various features such as dust and noise pollution, can obtain preferably Economy and social benefit.

Claims (9)

1. a kind of construction method excavated for rock vertical wall of deep foundation pit, it is characterised in that comprise the following steps:
Step 1, it is sampled to excavating place, determines formation hardness scope, and then determines to excavate scope;
Step 2, leveling processing is carried out to region need to be excavated, control the scope of operation gradient;
Step 3, to needing excavating region and bearing area progress scope of operation division and carry out excavation line and putting cloth for basic holding force rock stratum;
Step 4, continuous seaming straight wall is carried out to excavating area scar using the outdoor Down-hole rolling rig of KT5 type integral types along excavation line opened Dig, and control vertical precision, until excavating area's scar and supporting region scar is separated by required;
Step 5, using broken excavator to excavate area carry out it is broken clear, complete rock deep foundation pit construction.
2. the construction method according to claim 1 excavated for rock vertical wall of deep foundation pit, it is characterised in that:The rock Hardness refers to that its cutting depth is 1~10m according to the secondary hard stone in ground Pu Shi classification charts, general hard stone and special hard stone.
3. the construction method according to claim 1 excavated for rock vertical wall of deep foundation pit, it is characterised in that:The operation Between the face gradient is 0~10 °.
4. the construction method according to claim 1 excavated for rock vertical wall of deep foundation pit, it is characterised in that:The carrying Region refers to as the region for bearing built-loading.
5. the construction method according to claim 1 excavated for rock vertical wall of deep foundation pit, it is characterised in that:The excavation Line mark refers to rig sideline away from design structure sideline distance controlling within 200mm, to reduce excavating sideline and design structure side Distance between line, and then reduce excavated volume and reduce the purpose of concrete backfill usage amount.
6. the construction method according to claim 1 excavated for rock vertical wall of deep foundation pit, it is characterised in that:Using KT5 When the outdoor Down-hole rolling rig of type integral type carries out continuous seaming straight wall excavation to excavating area's scar, aperture is mutually twisted to form width 150mm separates band, realizes the separation for excavating area's scar and supporting region scar.
7. the construction method according to claim 6 excavated for rock vertical wall of deep foundation pit, it is characterised in that:Adjacent aperture Centerline deviation control within 50mm.
8. the construction method according to claim 1 excavated for rock vertical wall of deep foundation pit, it is characterised in that:Excavated During the separation of area's scar and supporting region scar, area will be excavated using static(al) dismounting equipment and separated with supporting region, and blocked dynamic Power equipment abolish during disturbance to the influence of scar need to be retained.
9. the construction method according to claim 1 excavated for rock vertical wall of deep foundation pit, it is characterised in that:Straight wall is opened Dig the circular arc interface formed to handle using mesh plaster, to meet waterproof matrix requirement.
CN201710852319.0A 2017-09-20 2017-09-20 A kind of construction method excavated for rock vertical wall of deep foundation pit Pending CN107740418A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710852319.0A CN107740418A (en) 2017-09-20 2017-09-20 A kind of construction method excavated for rock vertical wall of deep foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710852319.0A CN107740418A (en) 2017-09-20 2017-09-20 A kind of construction method excavated for rock vertical wall of deep foundation pit

Publications (1)

Publication Number Publication Date
CN107740418A true CN107740418A (en) 2018-02-27

Family

ID=61235204

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710852319.0A Pending CN107740418A (en) 2017-09-20 2017-09-20 A kind of construction method excavated for rock vertical wall of deep foundation pit

Country Status (1)

Country Link
CN (1) CN107740418A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113279422A (en) * 2021-06-10 2021-08-20 中庆建设有限责任公司 Excavation method suitable for hard rock stratum enlarged foundation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101806066A (en) * 2010-03-26 2010-08-18 重庆钢铁(集团)有限责任公司 Method for molding vertical wall of deep foundation pit
CN104775437A (en) * 2015-02-15 2015-07-15 福建省闽南建筑工程有限公司 Cutting type constructing method for excavating rock foundation pits in construction site
CN105952460A (en) * 2016-05-24 2016-09-21 中车建设工程有限公司 Non-blasting construction method of hard-rock tunnel in city
CN107084648A (en) * 2017-04-24 2017-08-22 哈密新智源水利水电工程建设监理有限公司 One kind uses pilot hole guide-localization and Smooth Blasting Construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101806066A (en) * 2010-03-26 2010-08-18 重庆钢铁(集团)有限责任公司 Method for molding vertical wall of deep foundation pit
CN104775437A (en) * 2015-02-15 2015-07-15 福建省闽南建筑工程有限公司 Cutting type constructing method for excavating rock foundation pits in construction site
CN105952460A (en) * 2016-05-24 2016-09-21 中车建设工程有限公司 Non-blasting construction method of hard-rock tunnel in city
CN107084648A (en) * 2017-04-24 2017-08-22 哈密新智源水利水电工程建设监理有限公司 One kind uses pilot hole guide-localization and Smooth Blasting Construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113279422A (en) * 2021-06-10 2021-08-20 中庆建设有限责任公司 Excavation method suitable for hard rock stratum enlarged foundation

Similar Documents

Publication Publication Date Title
CN103938617B (en) A kind of ultra-deep underground continuous wall and construction method thereof
CN108194088A (en) A kind of soft top coal layer cuts top release gob-side entry retaining method without explosion
CN102061923B (en) Tunnel construction method capable of protecting existing building
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN103046931B (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN110344400A (en) The hard rock pore-forming construction technology of churning driven opportunity
CN104947690A (en) Grooving construction method for embedding underground continuous wall into rock
CN105442532A (en) Construction method for pile-head-expanded bored pile
CN106837382B (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
CN103321233B (en) The preparation method of groundwater resources retracting device in landslide deep layer draining and sliding mass
CN106320403A (en) Inclination rectification and reinforcement method for existing building
CN103470263A (en) New-level development method for open-pit metal mine
CN110984132B (en) Construction method for grooving underground diaphragm wall under complex geological condition
CN109914395A (en) A kind of Big-Diameter Rock-Embedded Pile rapid constructing method and its structure
CN103939115A (en) Semi-subsurface excavation method construction shed tunnel method and structure
CN204825923U (en) Relay formula underground structure
CN106703059A (en) Construction method of cross-shaped pull trough of open caisson
CN102235010A (en) Treatment method for hanging sinking stop due to expansive soil in well sinking
CN108071110A (en) Rotary drilling rig Pile method under complex geological condition
CN105256819A (en) Improving method for open caisson sinking construction in geology of sludge layer
CN111561262A (en) Hole forming method of rotary drilling rig for large-size pile hole in karst area
CN113047844A (en) Sinking pipe sheet type vertical shaft construction method
CN107740418A (en) A kind of construction method excavated for rock vertical wall of deep foundation pit
CN114215066B (en) Collapse-prevention excavation construction method for side wall of open cut foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180227