CN107729707A - Engineering construction setting out method based on mobile augmented reality technology and BIM - Google Patents

Engineering construction setting out method based on mobile augmented reality technology and BIM Download PDF

Info

Publication number
CN107729707A
CN107729707A CN201711275425.3A CN201711275425A CN107729707A CN 107729707 A CN107729707 A CN 107729707A CN 201711275425 A CN201711275425 A CN 201711275425A CN 107729707 A CN107729707 A CN 107729707A
Authority
CN
China
Prior art keywords
coordinate
job site
terminal device
mobile terminal
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711275425.3A
Other languages
Chinese (zh)
Other versions
CN107729707B (en
Inventor
屈志刚
高英
马山玉
白勇
侯燕
李政鹏
曲晓宁
葛均建
尚银磊
刘建龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Water and Power Engineering Consulting Co Ltd
Original Assignee
Henan Water and Power Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Water and Power Engineering Consulting Co Ltd filed Critical Henan Water and Power Engineering Consulting Co Ltd
Priority to CN201711275425.3A priority Critical patent/CN107729707B/en
Publication of CN107729707A publication Critical patent/CN107729707A/en
Application granted granted Critical
Publication of CN107729707B publication Critical patent/CN107729707B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a kind of engineering construction setting out method based on mobile augmented reality technology and BIM, including the preparation of dummy model and platform, the job site virtually with the conversion of job site coordinate and matching, job site coordinate elevation real-time exhibition and information placements, the job site positioning of dummy model, the distance measuring of job site, Virtual Construction boost line are drawn, the storage of dummy model positional information and shared.The invention has the advantages that mobile augmented reality technology is applied in engineering site construction, realize and dummy model is accurately placed at job site by former design size, show the image after Practical Completion in advance, the each side such as unwrapping wire, coordinate and elevation inquiry, accurate distance measurement are excavated in engineering construction, play auxiliary Contraction in Site, accelerate understanding of each side to engineering, reach accelerating construction progress, save engineering construction investment purpose.

Description

Engineering construction setting out method based on mobile augmented reality technology and BIM
Technical field
The present invention relates to augmented reality field, more particularly, to the engineering based on mobile augmented reality technology and BIM Construction lofting method.
Background technology
Augmented reality (English:Augmented Reality, abbreviation AR), it is that one kind is superimposed virtually in reality scene Word, image, the visualization technique of threedimensional model.With smart mobile phone, Ipad(Notebook computer, tablet personal computer)Deng mobile whole The lifting of end equipment performance, and correlation space cognition technology are perfect, and augmented reality progressively moves towards mobile terminal from PC ends, Move towards to perceive reality three-dimensional from the two-dimentional augmented reality of the simple picture of superposition, word, and can be accurate on realistic space Place the three-dimensional enhanced reality of three dimensional virtual models.At present, mobile augmented reality technology is only applied public auxiliary with some in game Help in service, and be the application of two-dimentional augmented reality mostly, be attempted to mobile augmented reality technology and architecture information mould Type (English:Building Information Modeling, abbreviation:BIM) it is combined and is constructed applied to engineering site, but mesh It is preceding to be not yet seen in the report about engineering site construction application moving three dimension augmented reality.
The content of the invention
Present invention aims at a kind of engineering construction setting out method based on mobile augmented reality technology and BIM is provided, in fact Now aid in site operation, accelerating construction progress, reduce investment outlay.
To achieve the above object, the present invention takes following technical proposals:
Engineering construction setting out method of the present invention based on mobile augmented reality technology and BIM, including dummy model and platform Preparation, virtually the conversion and matching with job site coordinate, job site coordinate elevation real-time exhibition and information are placed, are virtual The job site positioning of model, the job site of the distance measuring of job site, Virtual Construction boost line are drawn, dummy model position The storage of confidence breath is with sharing;
The preparation method of the dummy model and platform is:By the way that Three-dimensional Design Software will be used as Microstation is built Complete engineering Three Dimensional Design Model, is exported in the Scenekit d engines of Mac systems, and use with DAE forms The developing instrument of more than Xcode9.0 versions is based on Arkit interface exploitation systems, and installs on the mobile terminal device, completes empty The preparation of analog model and scene are placed;
The virtually conversion with job site coordinate and the matching process, are carried out as steps described below:
Step 1, the application system based on Arkit interface exploitations is established, i.e.,:When mobile terminal device is built automatically when application starts A virtual coordinate system is found, original is in the camera position of the mobile terminal device when virtual coordinate system is opened using application Point, using mobile terminal device left and right directions as X-axis, using vertical direction as Y-axis, using fore-and-aft direction as Z axis;
Step 2, by the way that the Quick Response Code with the live coordinate information of stake point is attached on the stake point of job site two;
Step 3, mobile terminal device is placed in and scanned thereon as low coverage directly over first of the origin of coordinates stake point Quick Response Code, the live coordinate of the site coordinate system of this point is obtained, and synchronously obtain mobile terminal device now in virtual coordinates Virtual coordinates in system;By contrasting the live coordinate and the virtual coordinates, the origin of coordinates position of virtual coordinate system is corrected;
Step 4, in terms of adjustment in direction, pass through scan second stake point on Quick Response Code, obtain second stake point institute The live coordinate of site coordinate system, and now virtual coordinates of the mobile terminal device in virtual coordinate system are stated, then by several What, which is calculated, obtains the angle that virtual coordinates X-axis sensing East and West direction needs to rotate, and carries out respective angles to the virtual coordinates X-axis Rotation, by virtual coordinates Z axis invert 180 degree, so as to be finally completed the matching of virtual coordinates and live coordinate;
The job site coordinate elevation real-time exhibition is with information laying method:By ARKit interfaces with the frequency of 30 times per second Rate obtains the real-time virtual coordinates of the mobile terminal device, after Coordinate Conversion, is accordingly obtained with the frequency of 30 times per second The live coordinate of mobile terminal device at the construction field (site) is obtained, then by building live coordinate described in label control real-time displays Information;It is by the method that live coordinate information is placed at the construction field (site):By SceneKit interfaces one is built in specified location Spherical model and a verbal model, and in placement at the construction field (site), the content of word is mobile terminal device real-time coordinates X, Y, Z value;
The job site localization method of the dummy model is:Dummy model size is set by full-size(d), mobile terminal is set Purchase and place dummy model after the basic point scene coordinate position of the dummy model, and by mobile terminal device screen Gesture rotation process, i.e. double-contact rotation process, dummy model is carried out along Z-direction be vertical direction rotation, make void Analog model is navigated in the construction scene of job site;
The distance measuring method of the job site is:Including being measured with mobile terminal device screen contact position, and with movement Terminal device screen contact ray measures two methods with job site plane point of intersection position;
When measuring job site size with mobile terminal device screen contact position, mobile terminal device is obtained in real time and is measured Stop screen contact position coordinate information, then obtains measurement result by range formula;
When measuring job site size with mobile terminal device screen contact ray and job site plane point of intersection position, in real time Mobile terminal device measurement terminal screen contact position is obtained, and with the screen contact position vertical screen divergent-ray with moving The job site plane that dynamic terminal device detects intersects, with intersecting point coordinate amount of calculation ranging twice from;
The job site method for drafting of the Virtual Construction boost line is:Point coordinates is controlled to be adopted as foundation using boost line of constructing Virtual Construction boost line is drawn in two ways, is respectively:First, drawn in a manner of mobile terminal device screen contact position outstanding Empty three-dimensional construction boost line;2nd, drawn in a manner of mobile terminal device screen contact ray and job site plane point of intersection Paste the construction boost line on ground;The basic model structure that the drafting of above two Virtual Construction boost line is provided using Scenekit Formation function line model, and be placed on corresponding job site position;
The storage of the dummy model positional information is with sharing method:By preserve place at the construction field (site) the ID of middle model, Base position, the model of model are taken identical along the rotation angle information that Z axis is vertical direction to background data base, other users Two-dimensional code scanning mode match coordinate after, by obtaining the model information of the background data base, system is automatically with same position Put and place same model into the scene of job site with angle, so as to realize the storage of dummy model positional information together Enjoy.
The invention has the advantages that mobile augmented reality technology is applied in engineering site construction, realizes and press dummy model Former design size is accurately placed at job site, shows the image after Practical Completion in advance, and unwrapping wire, coordinate are excavated in engineering construction The each side such as measure with elevation inquiry, accurate distance, play auxiliary Contraction in Site, accelerate understanding of each side to engineering, reach To accelerating construction progress, save engineering construction investment purpose.
Brief description of the drawings
Fig. 1 is the applicating flow chart of the present invention.
Fig. 2 is virtual coordinate system of the present invention and site coordinate system conversion and the flow chart matched.
Fig. 3 is virtual coordinate system of the present invention and the schematic diagram of site coordinate system conversion.
Fig. 4 is the principle frame of the present invention that the dummy model information in placing at the construction field (site) is stored and shared Figure.
Embodiment
Embodiments of the invention are elaborated below in conjunction with the accompanying drawings, the present embodiment using technical solution of the present invention before Put and implemented, give detailed embodiment and specific operating process, but protection scope of the present invention is not limited to down State embodiment.
As shown in Fig. 1-4, the engineering construction setting out method of the present invention based on mobile augmented reality technology and BIM, bag Include the preparation of dummy model and platform, virtually the conversion and matching with job site coordinate, job site coordinate elevation are opened up in real time Show and show with job site positioning, the construction of the distance measuring of job site, Virtual Construction boost line of information placement, dummy model Field is drawn, the storage of dummy model positional information is with sharing;
The preparation method of dummy model and platform is:By by using the complete of Three-dimensional Design Software such as Microstation structures Engineering Three Dimensional Design Model, exported to DAE forms in the Scenekit d engines of Mac systems, and use Xcode9.0 with The developing instrument of upper version (is integrated on more than Xcode9.0 developing instruments) development system based on Arkit interfaces, and is arranged on On the mobile terminal device of the versions of IOS more than 11.0, the preparation and scene of completing dummy model are placed.
Want dummy model being accurately placed in job site, it is necessary to realize the conversion of virtual coordinates and live coordinate with Matching.Because engineering construction scene often uses the site coordinate system based on spud pile point, the coordinate system is with certain spud pile Point is the origin of coordinates, using east-west direction as X-axis, using North and South direction as Y-axis, using vertical direction as Z axis.
After engineering Three Dimensional Design Model is imported into the d engines such as Scenekit, increase using Arkit etc. is mobile Strong real interface exploitation engineering mobile augmented reality application system, as shown in Fig. 2 i.e.:When mobile terminal device starts in application Shi Zidong establishes a virtual coordinate system, when the virtual coordinate system is opened with application where the camera of the mobile terminal device Position is origin, using mobile terminal device left and right directions as X-axis, using vertical direction as Y-axis, using fore-and-aft direction as Z axis;Wherein to The right side, it is that just, in the follow-up moving process of mobile terminal device, if do not made an amendment, the virtual coordinate system will upwards, backward It can keep constant, including origin and each direction of principal axis, until application terminates.
Based on the mobile augmented reality interface function such as Arkit, application system be based on mobile terminal device motion sensor and Camera image carries out the space coordinates identification of real-world objects, and can detect real world plane, such as ground, desktop, Thus during dummy model can be placed at the construction field (site), Visual window is used as by mobile terminal device and freely watched and manipulation.
As shown in figure 3, in the construction of engineering construction scene 1, engineering setting out is often using the scene seat based on spud pile point Mark system, i.e., using spud pile point as the origin of coordinates, using east-west direction as X-axis, eastwards for just, using North and South direction as Y-axis, northwards for Just, using vertical direction as Z axis, upwards for just.
As shown in Figure 2,3, virtual coordinates with live coordinate change and concretely comprised the following steps with matching by the present invention:
Step 1:By adding two-dimensional code scanning function in the application(Mature technology), in advance will be by stake point information (including stake point Type, as the stake point or common stake point of origin, the live coordinate of stake point) Quick Response Code of generation is pasted onto two stake points of selection On, wherein first stake point is the live origin of coordinates, second stake is put corrects for direction.
Step 2:By mobile terminal device, closely surface scanning is used as on first stake point of the live origin of coordinates The Quick Response Code of stickup, the identification of the live origin of coordinates is carried out, obtain live coordinate of this point at the scene in coordinate system(Such as), and synchronous recording mobile terminal device is now in the position of virtual coordinate system, i.e. virtual coordinates(By ARKIT interface functions provide, such as).
Step 3:Then mobile terminal device is moved at second stake point, by the two dimension for scanning second stake point Code, obtains the live coordinate of this point(Such as), and synchronous recording mobile terminal device is now virtual The position of coordinate system, i.e. virtual coordinates(Such as).
Step 4:Virtual coordinate system and origin offset, the direction deviation angle of site coordinate system are calculated, principle is shown in Fig. 2, Its algorithm is:Origin offset, two stake point connecting line segments With the angle of positive north orientation, the angle is also the angle with the local site coordinate system Y-axis based on spud pile point simultaneously, using two Stake is put live coordinate and calculated:;The angle of two stake point connecting line segments and virtual coordinate system Z axis, is adopted Calculated with two stake point virtual coordinates:, then virtual coordinates X-axis rotate to East and West direction(Live coordinate X Direction of principal axis)The angle for needing to rotate is:θ=& R+ & V-pi/2;Formula:& R=ATAN () are arctan function, and π is circumference Rate.
Step 5:Virtual coordinate system is changed, it is matched local site coordinate system;Origin skew is carried out first, partially Shifting amount (- & x ,-& y ,-& z), then rotates X-axis for axle center with Y-axis (vertically to), rotation amount θ, finally inverts Z axis, make It is matched with the Y-axis of site coordinate system.
Live coordinate elevation real-time exhibition is with information laying method:After virtual coordinates are matched with live coordinate, As long as then keeping applying opening, mobile terminal device is equivalent to a high-precision GPS instrument, can by ARKit interfaces The real-time virtual coordinate of mobile terminal is obtained with the frequency of 30 times per second, after virtual coordinates conversion, frequency that accordingly can be 30 times per second Rate obtain mobile terminal device at the construction field (site) 1 live coordinate, then shown in real time by building the controls such as label in the application Show live coordinate information;By virtual coordinates information place at the construction field (site) 1 method be:First, mobile terminal device is placed in The position of job site 1 of setting, in two basic models of formation function that the position is provided using SceneKit interfaces, including one Individual simple spherical model and a verbal model, the center of ball are arranged on the virtual coordinates position shown by mobile terminal device Put, radius determines according to visual effect, and the content of word is the X of the virtual coordinates, Y, and Z values, wherein Z values are elevation, finally To make verbal model display effect more preferable, verbal model is set to make it all the time towards shifting using the center of ball as basic point real time rotation Dynamic terminal device, equivalent to user oriented.
The job site localization method of dummy model is:Complete the conversion of virtual coordinates and live coordinate and coordinate elevation It is the accurate field Positioning Creates condition of dummy model after information real-time show;It is 1 to set dummy model ratio first:1, As former design size, write down basic point scene coordinate (each control of each building in engineering three dimensional design achievement of dummy model Point processed, basic point live coordinate known to), and be converted into the live local coordinate based on stake point;Then mobile terminal device is put At the live coordinate shown in basic point, dummy model is placed into job site 1, finally by mobile terminal device screen Gesture rotation process (double-contact rotation) model should be mutually carried out along Z axis(Vertical direction)Rotation so that dummy model essence Really navigate in the scene of job site 1.
The distance measuring method of job site is:It is frequently necessary to carry out the measurement of size at engineering construction scene 1, based on shifting Dynamic augmented reality can realize that two amounts surveys mode, i.e., measured with mobile terminal device screen contact position, and with mobile whole End equipment screen contact ray measures with the plane point of intersection position of job site 1, to meet different measurement demands.Specially:When When measuring 1 size of job site with mobile terminal device contact point mode, mobile terminal device measurement terminal screen is obtained in real time Contact position coordinate information(There is provided by ARKit interfaces), including X, Y of beginning and end, Z coordinate, then pass through range formula Measurement result is obtained, formula is:L =;When in a manner of ray intersection When measuring 1 size of job site, mobile terminal device measurement terminal screen contact position is obtained in real time, and with screen contact position Vertical screen divergent-ray is put, is intersected with the plane of job site 1 that mobile terminal device detects, this intersection point is applying for measurement 1 terminal of work scene, is then calculated measurement result again by range formula.
The job site method for drafting of Virtual Construction boost line is:At the scene in construction process, it is often necessary to carry out Construct the operation of setting-out, such as excavation line, take up an area line, building position line, typically take professional GPS device position after to splash The modes such as pulverized limestone are carried out, less efficient.By applying mobile augmented reality technology, can accurately be painted by mobile terminal device Above-mentioned construction boost line is made, efficiency high simultaneously saves material, and can draw hanging three-dimensional construction boost line.Specially:Enter first The matching of row system coordinates, then according to the design coordinate control point of boost line(There is provided by engineering design), use with mobile whole The mode of end equipment screen contact position draws hanging three-dimensional construction boost line, uses and is penetrated with mobile terminal device screen contact The mode of line and the plane point of intersection of job site 1 draws the construction boost line on patch ground;The drafting of two kinds of boost lines uses The basic model constructing function structure line model that Scenekit is provided, and be placed on the position of job site 1 of corresponding reality.
The storage of dummy model positional information is with sharing method:As shown in figure 4, in a like fashion will when each user adopts After virtual coordinates are matched with live coordinate, place at the construction field (site) 1 model information then can be achieved storage and with multiple use Family is shared, and after dummy model is accurately placed into real construction site by a user, passes through the ID of preservation model, the basic point of model Position, model are along Z axis(Vertical direction)The information such as the anglec of rotation obtain back-end data immediately to background data base, other users The model information in storehouse, same model is placed into the scene of real job site 1 with same location and angle automatically, updates it Place the model information at the construction field (site) in 1, so as to realize the storage of dummy model positional information with it is shared;When each user applies After closing, after being again turned on applying and carrying out coordinate matching, it again may be by obtaining last time each model in background data base and put The positional information put, and the position that corresponding model was recorded in last time, the preservation and reading of implementation model placement information are placed automatically Take function.

Claims (1)

  1. A kind of 1. engineering construction setting out method based on mobile augmented reality technology and BIM, it is characterised in that:Including dummy model Preparation with platform, virtually the conversion and matching with job site coordinate, job site coordinate elevation real-time exhibition and information are put Put, the positioning of the job site of dummy model, the job site of the distance measuring of job site, Virtual Construction boost line are drawn, are empty The storage of analog model positional information is with sharing;
    The preparation method of the dummy model and platform is:By the way that Three-dimensional Design Software will be used as Microstation is built Complete engineering Three Dimensional Design Model, is exported in the Scenekit d engines of Mac systems, and use with DAE forms The developing instrument of more than Xcode9.0 versions is based on Arkit interface exploitation systems, and installs on the mobile terminal device, completes empty The preparation of analog model and scene are placed;
    The virtually conversion with job site coordinate and the matching process, are carried out as steps described below:
    Step 1, the application system based on Arkit interface exploitations is established, i.e.,:When mobile terminal device is built automatically when application starts A virtual coordinate system is found, original is in the camera position of the mobile terminal device when virtual coordinate system is opened using application Point, using mobile terminal device left and right directions as X-axis, using vertical direction as Y-axis, using fore-and-aft direction as Z axis;
    Step 2, by the way that the Quick Response Code with the live coordinate information of stake point is attached on the stake point of job site two;
    Step 3, mobile terminal device is placed in and scanned thereon as low coverage directly over first of the origin of coordinates stake point Quick Response Code, the live coordinate of this point site coordinate system is obtained, and synchronously obtain mobile terminal device now in virtual coordinate system In virtual coordinates;By contrasting the live coordinate and virtual coordinates, the origin of coordinates position of virtual coordinate system is corrected;
    Step 4, in terms of adjustment in direction, pass through scan second stake point on Quick Response Code, obtain second stake point institute Live coordinate, and now virtual coordinates of the mobile terminal device in virtual coordinate system are stated, is then calculated and is somebody's turn to do by geometry Virtual coordinates X-axis points to the angle that East and West direction needs to rotate, and the rotation of respective angles is carried out to the virtual coordinates X-axis, by void Quasi-coordinate Z axis inverts 180 degree, so as to be finally completed the matching of virtual coordinates and live coordinate;
    The job site coordinate elevation real-time exhibition is with information laying method:By ARKit interfaces with the frequency of 30 times per second Rate obtains the real-time virtual coordinates of the mobile terminal device, after Coordinate Conversion, is accordingly obtained with the frequency of 30 times per second The live coordinate of mobile terminal device at the construction field (site) is obtained, then by building live coordinate described in label control real-time displays Information;It is by the method that live coordinate information is placed at the construction field (site):By SceneKit interfaces one is built in specified location Spherical model and a verbal model, and in placement at the construction field (site), the content of word is mobile terminal device real-time coordinates X, Y, Z value;
    The job site localization method of the dummy model is:Dummy model size is set by full-size(d), mobile terminal is set Purchase and place dummy model after the basic point scene coordinate position of the dummy model, and by mobile terminal device screen Gesture rotation process, i.e. double-contact rotation process, dummy model is carried out along Z-direction be vertical direction rotation, make void Analog model is navigated in the construction scene of job site;
    The distance measuring method of the job site is:Including being measured with mobile terminal device screen contact position, and with movement Terminal device screen contact ray measures two methods with job site plane point of intersection position;
    When measuring job site size with mobile terminal device screen contact position, mobile terminal device is obtained in real time and is measured Stop screen contact position coordinate information, then obtains measurement result by range formula;
    When measuring job site size with mobile terminal device screen contact ray and job site plane point of intersection position, in real time Mobile terminal device measurement terminal screen contact position is obtained, and with the screen contact position vertical screen divergent-ray with moving The job site plane that dynamic terminal device detects intersects, with intersecting point coordinate amount of calculation ranging twice from;
    The job site method for drafting of the Virtual Construction boost line is:Point coordinates is controlled to be adopted as foundation using boost line of constructing Virtual Construction boost line is drawn in two ways, is respectively:First, drawn in a manner of mobile terminal device screen contact position outstanding Empty three-dimensional construction boost line;2nd, drawn in a manner of mobile terminal device screen contact ray and job site plane point of intersection Paste the construction boost line on ground;The basic model structure that the drafting of above two Virtual Construction boost line is provided using Scenekit Formation function line model, and be placed on corresponding job site position;
    The storage of the dummy model positional information is with sharing method:By preserve place at the construction field (site) the ID of middle model, Base position, the model of model are taken identical along the rotation angle information that Z axis is vertical direction to background data base, other users Two-dimensional code scanning mode match coordinate after, by obtaining the model information of the background data base, system is automatically with same position Put and place same model into the scene of job site with angle, so as to realize the storage of dummy model positional information together Enjoy.
CN201711275425.3A 2017-12-06 2017-12-06 Engineering construction lofting method based on mobile augmented reality technology and BIM Active CN107729707B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711275425.3A CN107729707B (en) 2017-12-06 2017-12-06 Engineering construction lofting method based on mobile augmented reality technology and BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711275425.3A CN107729707B (en) 2017-12-06 2017-12-06 Engineering construction lofting method based on mobile augmented reality technology and BIM

Publications (2)

Publication Number Publication Date
CN107729707A true CN107729707A (en) 2018-02-23
CN107729707B CN107729707B (en) 2021-03-02

Family

ID=61220959

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711275425.3A Active CN107729707B (en) 2017-12-06 2017-12-06 Engineering construction lofting method based on mobile augmented reality technology and BIM

Country Status (1)

Country Link
CN (1) CN107729707B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109883327A (en) * 2019-04-01 2019-06-14 上海宝冶建筑工程有限公司 A kind of racing track frame system monitoring method
CN110646159A (en) * 2019-10-18 2020-01-03 中国建筑第八工程局有限公司 Construction method for high-precision control and measurement of cast-in-place bare concrete wind tunnel
JP2020008423A (en) * 2018-07-09 2020-01-16 清水建設株式会社 Construction management system
JP2020019129A (en) * 2018-07-30 2020-02-06 サクラインターナショナル株式会社 Marking line drawing work method with use of mr (mixed reality) field of view
CN111248851A (en) * 2019-10-11 2020-06-09 中山大学中山眼科中心 Visual function self-testing method
CN116361996A (en) * 2023-02-10 2023-06-30 广州市第三市政工程有限公司 Unmanned aerial vehicle-based steel mesh frame modeling method, system and storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102538744A (en) * 2010-10-29 2012-07-04 喜利得股份公司 Measuring device for noncontact measurement of distances to a target object
US20170053042A1 (en) * 2015-08-19 2017-02-23 Benjamin John Sugden Holographic building information update
CN106910251A (en) * 2017-03-22 2017-06-30 朱海涛 Model emulation method based on AR and mobile terminal
CN107339984A (en) * 2017-07-07 2017-11-10 四川云图瑞科技有限公司 Three-dimensional indoor locating system based on augmented reality

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102538744A (en) * 2010-10-29 2012-07-04 喜利得股份公司 Measuring device for noncontact measurement of distances to a target object
US20170053042A1 (en) * 2015-08-19 2017-02-23 Benjamin John Sugden Holographic building information update
CN106910251A (en) * 2017-03-22 2017-06-30 朱海涛 Model emulation method based on AR and mobile terminal
CN107339984A (en) * 2017-07-07 2017-11-10 四川云图瑞科技有限公司 Three-dimensional indoor locating system based on augmented reality

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
胡攀辉: "基于BIM与AR的施工现场应用模块集成研究", 《中国优秀硕士学位论文全文数据库 工程科技II辑》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020008423A (en) * 2018-07-09 2020-01-16 清水建設株式会社 Construction management system
JP7097251B2 (en) 2018-07-09 2022-07-07 清水建設株式会社 Construction management system
JP2020019129A (en) * 2018-07-30 2020-02-06 サクラインターナショナル株式会社 Marking line drawing work method with use of mr (mixed reality) field of view
CN109883327A (en) * 2019-04-01 2019-06-14 上海宝冶建筑工程有限公司 A kind of racing track frame system monitoring method
CN109883327B (en) * 2019-04-01 2021-11-26 上海宝冶建筑工程有限公司 Track frame system monitoring method
CN111248851A (en) * 2019-10-11 2020-06-09 中山大学中山眼科中心 Visual function self-testing method
CN111248851B (en) * 2019-10-11 2023-08-11 中山大学中山眼科中心 Visual function self-testing method
CN110646159A (en) * 2019-10-18 2020-01-03 中国建筑第八工程局有限公司 Construction method for high-precision control and measurement of cast-in-place bare concrete wind tunnel
CN116361996A (en) * 2023-02-10 2023-06-30 广州市第三市政工程有限公司 Unmanned aerial vehicle-based steel mesh frame modeling method, system and storage medium

Also Published As

Publication number Publication date
CN107729707B (en) 2021-03-02

Similar Documents

Publication Publication Date Title
CN107729707A (en) Engineering construction setting out method based on mobile augmented reality technology and BIM
Piekarski et al. Interactive augmented reality techniques for construction at a distance of 3D geometry
JP7337104B2 (en) Model animation multi-plane interaction method, apparatus, device and storage medium by augmented reality
JP5920352B2 (en) Information processing apparatus, information processing method, and program
US9430871B2 (en) Method of generating three-dimensional (3D) models using ground based oblique imagery
US8850337B2 (en) Information processing device, authoring method, and program
US8907983B2 (en) System and method for transitioning between interface modes in virtual and augmented reality applications
CN102968809B (en) The method of virtual information mark and drafting marking line is realized in augmented reality field
CN107369205B (en) Mobile terminal city two-dimensional and three-dimensional linkage display method
Portalés et al. Augmented reality and photogrammetry: A synergy to visualize physical and virtual city environments
CN109146954A (en) Augmented reality interface for being interacted with shown map
CN103489214A (en) Virtual reality occlusion handling method, based on virtual model pretreatment, in augmented reality system
CN105509716B (en) A kind of geographical information collection method and device based on augmented reality
Gomez-Jauregui et al. Quantitative evaluation of overlaying discrepancies in mobile augmented reality applications for AEC/FM
KR101989969B1 (en) Contents experience system of architectural sites based augmented reality
CN107945283A (en) Engineering methods of exhibiting based on mobile augmented reality technology and BIM
CN107665505A (en) The method and device of augmented reality is realized based on plane monitoring-network
CN107895048A (en) It is a kind of that drawing method is quickly gone out based on outdoor scene three-dimensional
CN112184786B (en) Target positioning method based on synthetic vision
CN105334525B (en) A kind of geography information display methods based on augmented reality
CN105095314A (en) Point of interest (POI) marking method, terminal, navigation server and navigation system
CN105023294A (en) Fixed point movement augmented reality method combining sensors and Unity3D
Wither et al. Using aerial photographs for improved mobile AR annotation
Liarokapis et al. Mobile augmented reality techniques for geovisualisation
CN107958491B (en) Matching method of mobile augmented reality virtual coordinates and construction site coordinates

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant