CN107725086A - A kind of reinforcement means of the non-structural longitudinal crack of lining cutting - Google Patents

A kind of reinforcement means of the non-structural longitudinal crack of lining cutting Download PDF

Info

Publication number
CN107725086A
CN107725086A CN201711324607.5A CN201711324607A CN107725086A CN 107725086 A CN107725086 A CN 107725086A CN 201711324607 A CN201711324607 A CN 201711324607A CN 107725086 A CN107725086 A CN 107725086A
Authority
CN
China
Prior art keywords
bolthole
anchor pole
crackle
longitudinal crack
lining cutting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711324607.5A
Other languages
Chinese (zh)
Other versions
CN107725086B (en
Inventor
翟朝晖
龙廷
于忠永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Civil Engineering Co Ltd
Original Assignee
China Construction Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Civil Engineering Co Ltd filed Critical China Construction Civil Engineering Co Ltd
Priority to CN201711324607.5A priority Critical patent/CN107725086B/en
Publication of CN107725086A publication Critical patent/CN107725086A/en
Application granted granted Critical
Publication of CN107725086B publication Critical patent/CN107725086B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/003Machines for drilling anchor holes and setting anchor bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01DMEASURING NOT SPECIALLY ADAPTED FOR A SPECIFIC VARIABLE; ARRANGEMENTS FOR MEASURING TWO OR MORE VARIABLES NOT COVERED IN A SINGLE OTHER SUBCLASS; TARIFF METERING APPARATUS; MEASURING OR TESTING NOT OTHERWISE PROVIDED FOR
    • G01D21/00Measuring or testing not otherwise provided for
    • G01D21/02Measuring two or more variables by means not covered by a single other subclass

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Inorganic Chemistry (AREA)
  • Chemical & Material Sciences (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

A kind of reinforcement means of the non-structural longitudinal crack of lining cutting, including step have the location parameter for determining secondary lining crackle section, detection supporting construction quality, data analysis, measurement and pore-creating, wash the steps such as bolthole, sealing, slip casting, quality inspection and monitoring measurement.Pin of the present invention effectively slows down or prevents the expansion of crackle, enhancing structure stability.Distribution of the present invention to crackle carries out whole detection, the longitudinal crack for filtering out unstructuredness is reinforced, reinforcing uses country rock and the dual reinforcing of anchor pole, surrounding rock consolidation uses self-advancing type hollow grouting anchor, collection drilling, borehole cleaning and slip casting are integrated, ensure to carry out cracks minimum disturbance, it is floating that concrete at the aperture of crackle bolthole rejects water-filling cement mortar of going forward side by side, ensure roof bolt plate uniform force, it is alternately distributed simultaneously in cracks anchor pole using the junction of the edges of two sheets of paper, obstruct the developing direction of crackle, effectively prevention and reinforcing crackle, the stress of enhancing structure, the concrete that liner structure is effectively ensured no longer comes off.

Description

A kind of reinforcement means of the non-structural longitudinal crack of lining cutting
Technical field
The present invention is applied to tunnels and underground engineering liner structure longitudinal crack and reinforced, and especially unstructuredness is longitudinally grown up and split Line is reinforced.
Background technology
Tunnel concrete secondary lining is the important step in constructing tunnel, secondary in the presence of no external force After lining construction lags behind preliminary bracing, secondary lining shrinks, vibrates and irrigated operation in constraint, concrete temperature and drying In the case of improper measures, the concrete surface of secondary lining can produce unstructuredness crackle, if crack initiation, expansion, deterioration It is overall when be in three-dimensional state, it is possible to peeling and the chip off-falling of secondary lining are caused, not only the Stability Analysis of Structures in influence tunnel, can also be because Crackle infiltration influences the safe for operation of tunnel.Conventional Crack handling is that slip casting and superficial closing are carried out at crack, but conventional Slip casting or superficial closing measure only effect be present to country rock and surface, when such a processing mode is applied into unstructuredness crackle The complex procedures of use, grouting amount are difficult to control.
The content of the invention
It is an object of the invention to provide a kind of reinforcement means of the non-structural longitudinal crack of lining cutting, to solve unstructuredness crackle Complex procedures when being closed using slip casting and superficial, grouting amount are difficult to control technical problem.
To achieve the above object, the present invention adopts the following technical scheme that:
A kind of reinforcement means of the non-structural longitudinal crack of lining cutting, construction procedure are as follows:
Step 1, determine the location parameter of secondary lining crackle section:
Lining cutting scope internal fissure section is checked, confirms scope, width and the depth of crackle section, draws the plane exhibition of crackle section Diagram, establish account;
Step 2, detect supporting construction quality:
The preliminary bracing quality of lining cutting scope internal fissure section is detected, detection content includes the construction matter of preliminary bracing steelframe Amount, detection mode use GPR detection;
The secondary lining quality of lining cutting scope internal fissure section is detected, detection content includes secondary lining arch and abutment wall is carried on the back Rear leakiness degree, with the presence or absence of cavity, inverted arch bottom it whether there is the empty tiny fragments of stone, coal, etc., detection mode uses GPR detection;Inspection Surveying content also includes the intensity and thickness of secondary lining, and detection mode uses resilience Non-Destructive Testing;
The adverse geological condition of lining cutting scope internal fissure section is detected, detection content includes the poorly quality inspection of Hidden Karst Under Look into, detection mode uses geological radar;
Step 3, data analysis:Whether the detection data according to being obtained in step 2 use exclusive method to determine crackle for knot Structure, whether penetrate, whether there is faulting of slab ends;By observing whether crackle continues to develop;To it is therein it is non-structural, non-penetrating, without faulting of slab ends, The longitudinal crack not continued in development carries out reinforcing preparation;
Step 4, measure simultaneously pore-creating:
The pore depth of bolthole from the surface of secondary lining by preliminary bracing until preliminary bracing behind country rock in, anchor pole Hole junction of the edges of two sheets of paper at left and right sides of longitudinal crack is staggeredly set in blossom type, and the beeline of each bolthole and longitudinal crack is homogeneous Together, the distance of two adjacent boltholes of longitudinal crack homonymy also all same;Determined using total powerstation the position for opening bolthole Position, anchor pole use self-advancing type hollow grouting anchor, anchor pole are connected with rig, and is directly used on the precalculated position of bolthole Anchor pole pore-creating;
Step 5, wash bolthole:
By bolthole and rig disengaging, a blower fan connection anchor pole then will be played, it is directly interior to anchor pole to be blown into bolthole using high-pressure blast Hole is disposably purged;
Step 6, sealing:The aperture of longitudinal crack and bolthole is closed using Anchor Agent, to two in the range of the aperture of bolthole The Surface layer's concrete of secondary lining cutting is cut, and the part cut is floating using cement mortar;Concrete surface peace after floating simultaneously The intimate surface contact of the backing plate and nut of anchor pole, backing plate and concrete is filled, anchor pole is then connected into slip casting machine;
Step 7, slip casting:
Surrounding rock consolidation:It is 0.6 to prepare the ratio of mud:1~1:1 cement single slurry filling bolthole, is passed through using anchor rock mud filling machine Slurry outlet on anchor pole carries out consolidation grouting to country rock, and slip casting stops slip casting after reaching design requirement;Then at the beginning of cement single slurry Before solidifying, the steam vent on anchor pole is opened, discharges cement grout unnecessary in anchor pole;
Anchor pole is closed:Change slurry and use the ratio of mud as 0.45:1~0.3:1 cement single slurry filling closing anchor pole, cement is using general Logical portland cement, label is not less than 42.5R, when slurries flow out from steam vent, completes slip casting;
Step 8, quality inspection:Bolt grouting complete 7 days after, using sound wave physical prospecting instrument test bolthole in body of cement it is closely knit Property;
Step 9, monitoring measurement:
The content of monitoring includes tunnel arch top settlement and headroom change is observed;Tunnel inverted arch and filling position settlement observation;Tunnel Arch wall, inverted arch and crack growth observation;Percolating water condition survey.
In the step 4, the beeline of each bolthole and longitudinal crack is 500mm;The two neighboring anchor pole of homonymy The distance in hole is not more than 3000mm.
In the step 4, the hole position deviation of bolthole is not more than 5cm, and hole depth deviation is not more than 5cm, bore angle deviation No more than 3%.
In the step 4, the model R25N of self-advancing type hollow grouting anchor, the length of every anchor pole is 3.5m;
The backing plate uses spherical backing plate;
Backing plate and the exposed termination of anchor pole carry out preservative treatment using Zinc-Nickel coating layer;
The withdrawal resistance of self-advancing type hollow grouting anchor is not less than 50KN, and anti-pulling of anchor bar is inspected by random samples using drawing meter, often located The sampling observation rate of longitudinal crack is not less than 5%, and no less than 3.
Monitoring position in the step 9 is longitudinally set together in crackle section every 10m, and per pass monitoring point is arranged in Vault, the haunch of both sides, the arch springing of both sides and bottom plate are at totally five;Wherein settlement observation is carried out using embedded observation station position in tunnel Observation, stablizing datum mark in tunnel is chosen, field observation is carried out using total powerstation.
In the step 9, the observation time limit is 3 months, and observing frequency is 1 time a day.
The structure in the step 9, observe every time, monitored is recorded and preserved, and periodically each profile data is carried out Arrange, and draw each Section Settlement observation data variation trend curve and crack growth observational record table;Observed by the cycle, Carry out periodical evaluation to settlement observation data variation trend curve and crack growth situation, evaluation structure security, and according to commenting Valency result adjusts observing frequency and treatment measures.
Compared with prior art the invention has the characteristics that and beneficial effect:
The present invention proposes a kind of reinforcement means for the producing cause of unstructuredness crackle, this reinforcement means can effectively slow down or Prevent the expansion of crackle, enhancing structure stability.Distribution of the present invention first to crackle carries out whole detection, filters out non-structural Property longitudinal crack reinforced, reinforcing use country rock and the dual reinforcing of anchor pole, the overall stress of surrounding rock consolidation guarantee crackle section, Crackle reinforcement and strengthening crackle bearing capacity.Surrounding rock consolidation uses self-advancing type hollow grouting anchor, and collection drilling, borehole cleaning and slip casting are one Body, ensure to carry out cracks minimum disturbance, the concrete at the aperture of crackle bolthole is rejected water-filling cement mortar of going forward side by side and smeared It is flat, ensure roof bolt plate uniform force, while be alternately distributed in cracks anchor pole using the junction of the edges of two sheets of paper, the developing direction of crackle is obstructed, Effectively prevention and reinforcing crackle, the stress of enhancing structure, the concrete that liner structure is effectively ensured no longer comes off.
Brief description of the drawings
The present invention will be further described in detail below in conjunction with the accompanying drawings.
The continuous longitudinal crack section schematic cross-sectional view in tunnel somewhere of Fig. 1 present invention.
The arrangement schematic diagram of Fig. 2 cracks self-advancing type hollow grouting anchors.
The termination processing figure of Fig. 3 self-advancing type hollow grouting anchors.
The diagrammatic cross-section of Fig. 4 cracks.
The arrangement schematic diagram of wherein one monitoring point of monitoring measurement in Fig. 5 holes of the present invention.
Reference:1- longitudinal cracks, 2- preliminary bracings, 3- secondary linings, 4- country rocks, 5- anchor poles, 6- anchorings Agent, 7- backing plates, 8- nuts, 9- boltholes, 10- vaults, 11- haunches, 12- arch springings and bottom plate.
Embodiment
Embodiment is referring to shown in Fig. 1-5, a kind of reinforcement means of the non-structural longitudinal crack of lining cutting, and construction procedure is as follows:
Step 1, determine the location parameter of secondary lining crackle section:
Lining cutting scope internal fissure section is checked, confirms scope, width and the depth of crackle section, draws the plane exhibition of crackle section Diagram, establish account.
Step 2, detect supporting construction quality:
The preliminary bracing quality of lining cutting scope internal fissure section is detected, detection content includes the construction matter of preliminary bracing steelframe Amount, detection mode use GPR detection;
The secondary lining quality of lining cutting scope internal fissure section is detected, detection content includes secondary lining arch and abutment wall is carried on the back Rear leakiness degree, with the presence or absence of cavity, inverted arch bottom it whether there is the empty tiny fragments of stone, coal, etc., detection mode uses GPR detection, must Verified when wanting by the methods of coring, broken inspection;Detection content also includes the intensity and thickness of secondary lining, and detection mode is adopted With resilience Non-Destructive Testing;
The adverse geological condition of lining cutting scope internal fissure section is detected, detection content includes the poorly quality inspection of Hidden Karst Under Look into, detection mode uses geological radar, and abnormal location is verified using boring and coring.
Step 3, data analysis:Whether detection data according to being obtained in step 2 determine crackle using exclusive method For it is structural, whether penetrate, whether there is faulting of slab ends;By observing whether crackle continues to develop;To non-structural, non-penetrating, nothing therein Faulting of slab ends, the longitudinal crack not continued in development carry out reinforcing preparation.
Illustrated below so that longitudinal crack 1 is located on abutment wall as an example, the longitudinal crack longitudinally splits along tunnel direct of travel The crack penetration of line is located in whole preliminary bracing 2 and secondary lining 3.
Step 4, measure simultaneously pore-creating:
The pore depth of bolthole is from the surface of secondary lining 3 until in the country rock 4 of the behind of preliminary bracing 2, and bolthole 9 is in longitudinal direction The left and right sides junction of the edges of two sheets of paper of crackle 1 is staggeredly set in blossom type, the beeline a all sames of each bolthole 9 and longitudinal crack, longitudinal direction The distance b of two adjacent boltholes 9 of the homonymy of crackle 1 also all sames;The position for opening bolthole 9 is positioned using total powerstation, Anchor pole 5 uses self-advancing type hollow grouting anchor, and anchor pole 5 is connected with rig, and is directly used on the precalculated position of bolthole 9 Anchor pole pore-creating, first check whether body of rod mesopore is unimpeded before pore-creating, if there is foreign matters from being blocked, cleaning in time.
Step 5, wash bolthole:
By bolthole and rig disengaging, a blower fan connection anchor pole then will be played, it is directly interior to anchor pole to be blown into bolthole using high-pressure blast Hole is disposably purged.
Step 6, sealing:The aperture of longitudinal crack and bolthole is closed using Anchor Agent 6, and Anchor Agent is epoxy resin. The Surface layer's concrete of secondary lining 3 in the range of the aperture of bolthole is cut, the part cut is floating using cement mortar;Together When concrete surface installation anchor pole after floating backing plate 7 and nut 8, the intimate surface contact of backing plate and concrete, then Anchor pole is connected into slip casting machine.
Step 7, slip casting:
Surrounding rock consolidation:Surrounding rock consolidation is the integral reinforcing of crackle section, is not less than 1.5m to the width of non-crackle section Longitudinal extending;Match somebody with somebody The ratio of mud processed is 0.6:1~1:1 cement single slurry filling bolthole, passes through the slurry outlet pair on anchor pole using anchor rock mud filling machine Country rock carries out consolidation grouting, and slip casting stops slip casting after reaching design requirement;Then before cement single slurry initial set, open on anchor pole Steam vent, discharge unnecessary cement grout in anchor pole.
Anchor pole is closed:Change slurry and use the ratio of mud as 0.45:1~0.3:1 cement single slurry filling closing anchor pole, cement are adopted With Portland cement, label is not less than 42.5R, when slurries flow out from steam vent, completes slip casting.
Step 8, quality inspection:After bolt grouting is completed 7 days, tested using sound wave physical prospecting instrument in bolthole and bolthole The density of body of cement, closely knit sex ratio should be greater than 85%.
Step 9, monitoring measurement:
The content of monitoring includes tunnel arch top settlement and headroom change is observed;Tunnel inverted arch and filling position settlement observation;Without the tiny fragments of stone, coal, etc. Track settlement monitoring;Tunnel arch wall, inverted arch and crack growth observation;Percolating water condition survey.
Monitor position longitudinally to set together every 10m in crackle section, per pass monitoring point is arranged in vault 10, the arch of both sides Waist 11, the arch springing of both sides and bottom plate 12 are at totally five;Wherein settlement observation is observed using embedded observation station position in tunnel, is chosen Stablizing datum mark in tunnel, field observation is carried out using total powerstation, wherein vault uses to avoid built-in fitting from influenceing traffic safety Expansion bolt pastes reflecting marking.It is 3 months to observe the time limit, and observing frequency is 1 time a day.In the step 9, observe every time, prison The structure of survey is recorded and preserved, and periodically each profile data is arranged, and draws each Section Settlement observation data Change trend curve and crack growth observational record table;Observed by the cycle, to settlement observation data variation trend curve and split Line development carries out periodical evaluation, evaluation structure security, and adjusts observing frequency and treatment measures according to evaluation result.Compile Special construction plan processed, determine that barrel face excavates mileage, supporting parameter, earth's surface duct penetration position and quantity, and draw Detail drawing.
In the present embodiment step 4, the beeline a of each bolthole and longitudinal crack is 500mm;Per side anchor rod aperture The distance b of two neighboring bolthole is 3000mm.The hole position deviation of bolthole is not more than 5cm, and hole depth deviation is not more than 5cm, Bore angle deviation is not more than 3%.
In the present embodiment, the model R25N of self-advancing type hollow grouting anchor, the length of every anchor pole is 3.5m;The pad Plate uses spherical backing plate;Backing plate and the exposed termination of anchor pole carry out preservative treatment using Zinc-Nickel coating layer;The hollow slip casting anchor of self-advancing type The withdrawal resistance of bar is not less than 50KN, and anti-pulling of anchor bar is inspected by random samples using drawing meter, and the sampling observation rate for often locating longitudinal crack is not small In 5%, and no less than 3.

Claims (7)

1. a kind of reinforcement means of the non-structural longitudinal crack of lining cutting, it is characterised in that construction procedure is as follows:
Step 1, determine the location parameter of secondary lining crackle section:
Lining cutting scope internal fissure section is checked, confirms scope, width and the depth of crackle section, draws the plane exhibition of crackle section Diagram, establish account;
Step 2, detect supporting construction quality:
The preliminary bracing quality of lining cutting scope internal fissure section is detected, detection content includes the construction matter of preliminary bracing steelframe Amount, detection mode use GPR detection;
The secondary lining quality of lining cutting scope internal fissure section is detected, detection content includes secondary lining arch and abutment wall is carried on the back Rear leakiness degree, with the presence or absence of cavity, inverted arch bottom it whether there is the empty tiny fragments of stone, coal, etc., detection mode uses GPR detection;Inspection Surveying content also includes the intensity and thickness of secondary lining, and detection mode uses resilience Non-Destructive Testing;
The adverse geological condition of lining cutting scope internal fissure section is detected, detection content includes the poorly quality inspection of Hidden Karst Under Look into, detection mode uses geological radar;
Step 3, data analysis:Whether the detection data according to being obtained in step 2 use exclusive method to determine crackle for knot Structure, whether penetrate, whether there is faulting of slab ends;By observing whether crackle continues to develop;To it is therein it is non-structural, non-penetrating, without faulting of slab ends, Do not continue the longitudinal crack in development(1)Carry out reinforcing preparation;
Step 4, measure simultaneously pore-creating:
Bolthole(9)Pore depth from secondary lining(3)Surface pass through preliminary bracing(2)Until preliminary bracing behind is enclosed Rock(4)It is interior, bolthole(9)In longitudinal crack(1)The left and right sides junction of the edges of two sheets of paper is staggeredly set in blossom type, each bolthole(9)With indulging To crackle(1)Beeline all same, longitudinal crack(1)Two adjacent boltholes of homonymy(9)Distance also all same;Open The position of bolthole is positioned using total powerstation, anchor pole(5)Using self-advancing type hollow grouting anchor, by anchor pole and rig phase Even, and anchor pole pore-creating is directly used on the precalculated position of bolthole;
Step 5, wash bolthole:
By bolthole and rig disengaging, a blower fan connection anchor pole then will be played, it is directly interior to anchor pole to be blown into bolthole using high-pressure blast Hole is disposably purged;
Step 6, sealing:The aperture of longitudinal crack and bolthole uses Anchor Agent(6)Closing, in the range of the aperture of bolthole The Surface layer's concrete of secondary lining cut, the part cut is floating using cement mortar;Concrete table after floating simultaneously The intimate surface contact of the backing plate and nut of anchor pole, backing plate and concrete is installed in face, and anchor pole then is connected into slip casting machine;
Step 7, slip casting:
Surrounding rock consolidation:It is 0.6 to prepare the ratio of mud:1~1:1 cement single slurry filling bolthole, is passed through using anchor rock mud filling machine Slurry outlet on anchor pole carries out consolidation grouting to country rock, and slip casting stops slip casting after reaching design requirement;Then at the beginning of cement single slurry Before solidifying, the steam vent on anchor pole is opened, discharges cement grout unnecessary in anchor pole;
Anchor pole is closed:Change slurry and use the ratio of mud as 0.45:1~0.3:1 cement single slurry filling closing anchor pole, cement is using general Logical portland cement, label is not less than 42.5R, when slurries flow out from steam vent, completes slip casting;
Step 8, quality inspection:Bolt grouting complete 7 days after, using sound wave physical prospecting instrument test bolthole in body of cement it is closely knit Property;
Step 9, monitoring measurement:
The content of monitoring includes tunnel arch top settlement and headroom change is observed;Tunnel inverted arch and filling position settlement observation;Tunnel Arch wall, inverted arch and crack growth observation;Percolating water condition survey.
2. the reinforcement means of the non-structural longitudinal crack of lining cutting according to claim 1, it is characterised in that:The step 4 In, each bolthole(9)With longitudinal crack(1)Beeline be 500mm;The two neighboring bolthole of homonymy(9)Distance No more than 3000mm.
3. the reinforcement means of the non-structural longitudinal crack of lining cutting according to claim 1 or 2, it is characterised in that:The step In four, bolthole(9)Hole position deviation be not more than 5cm, hole depth deviation is not more than 5cm, and bore angle deviation is not more than 3%.
4. the reinforcement means of the non-structural longitudinal crack of lining cutting according to claim 1, it is characterised in that:The step 4 In, the model R25N of self-advancing type hollow grouting anchor, every anchor pole(5)Length be 3.5m;
The backing plate(7)Using spherical backing plate;
Backing plate(7)And anchor pole(5)Exposed termination carries out preservative treatment using Zinc-Nickel coating layer.
5. the reinforcement means of the non-structural longitudinal crack of lining cutting according to claim 1, it is characterised in that:In the step 9 Monitoring position in crackle section longitudinally every 10m set together, per pass monitoring point is arranged in vault(10), both sides haunch (11), both sides arch springing and bottom plate(12)At totally five;Wherein settlement observation is observed using embedded observation station position in tunnel, is selected Stablizing datum mark in tunnel is taken, field observation is carried out using total powerstation.
6. the reinforcement means of the non-structural longitudinal crack of lining cutting according to claim 1 or 5, it is characterised in that:The step In nine, the observation time limit is 3 months, and observing frequency is 1 time a day.
7. the reinforcement means of the non-structural longitudinal crack of lining cutting according to claim 6, it is characterised in that:The step 9 In, the structure observe every time, monitored is recorded and preserved, and periodically each profile data is arranged, and is drawn each disconnected Face settlement observation data variation trend curve and crack growth observational record table;Observed by the cycle, settlement observation data are become Change trend curve and crack growth situation carries out periodical evaluation, evaluation structure security, and observation frequency is adjusted according to evaluation result Rate and treatment measures.
CN201711324607.5A 2017-12-13 2017-12-13 A kind of reinforcement means of the non-structural longitudinal crack of lining cutting Expired - Fee Related CN107725086B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711324607.5A CN107725086B (en) 2017-12-13 2017-12-13 A kind of reinforcement means of the non-structural longitudinal crack of lining cutting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711324607.5A CN107725086B (en) 2017-12-13 2017-12-13 A kind of reinforcement means of the non-structural longitudinal crack of lining cutting

Publications (2)

Publication Number Publication Date
CN107725086A true CN107725086A (en) 2018-02-23
CN107725086B CN107725086B (en) 2019-11-12

Family

ID=61221135

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711324607.5A Expired - Fee Related CN107725086B (en) 2017-12-13 2017-12-13 A kind of reinforcement means of the non-structural longitudinal crack of lining cutting

Country Status (1)

Country Link
CN (1) CN107725086B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109441505A (en) * 2018-08-15 2019-03-08 福建陆海工程勘察设计有限公司 Based on clad steel plate or steel band highway tunnel lining thickness deficiency quick reinforcement method
CN110080802A (en) * 2019-04-03 2019-08-02 核工业井巷建设集团有限公司 A kind of quick reinforcement construction method in tunnel
CN110924997A (en) * 2019-12-09 2020-03-27 中铁十六局集团有限公司 Tunnel secondary lining crack trimming and reinforcing method
CN111255488A (en) * 2020-03-18 2020-06-09 福建工程学院 High-strength corrugated plate structure and method for tunnel reinforcement
CN112663646A (en) * 2020-12-18 2021-04-16 南京康泰建筑灌浆科技有限公司 Stable in-situ reinforcing method for grouting control
CN114033433A (en) * 2021-11-16 2022-02-11 中铁十二局集团有限公司 Plateau high-geostress tunnel secondary lining crack monitoring construction method
CN114033432A (en) * 2021-11-16 2022-02-11 中铁十二局集团有限公司 Two-lining crack renovation construction method for plateau high-ground stress tunnel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001227295A (en) * 2000-02-16 2001-08-24 Nissho Astec Co Ltd Reinforcement method for concrete wall face in tunnel
JP2006225906A (en) * 2005-02-16 2006-08-31 Public Works Research Institute Method for reinforcing tunnel lining concrete
CN101603429A (en) * 2009-07-09 2009-12-16 西安理工大学 Anti-seepage structure of composite lining deformation joints of ground fissure stratum tunnel and construction method thereof
CN101737063A (en) * 2009-11-16 2010-06-16 西安理工大学 Ground fissure tunnel asphalt concrete composite lining and supporting method thereof
CN105201530A (en) * 2015-10-28 2015-12-30 北京工业大学 Repairing and strengthening method for large cracks on rock tunnel lining

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001227295A (en) * 2000-02-16 2001-08-24 Nissho Astec Co Ltd Reinforcement method for concrete wall face in tunnel
JP2006225906A (en) * 2005-02-16 2006-08-31 Public Works Research Institute Method for reinforcing tunnel lining concrete
CN101603429A (en) * 2009-07-09 2009-12-16 西安理工大学 Anti-seepage structure of composite lining deformation joints of ground fissure stratum tunnel and construction method thereof
CN101737063A (en) * 2009-11-16 2010-06-16 西安理工大学 Ground fissure tunnel asphalt concrete composite lining and supporting method thereof
CN105201530A (en) * 2015-10-28 2015-12-30 北京工业大学 Repairing and strengthening method for large cracks on rock tunnel lining

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109441505A (en) * 2018-08-15 2019-03-08 福建陆海工程勘察设计有限公司 Based on clad steel plate or steel band highway tunnel lining thickness deficiency quick reinforcement method
CN110080802A (en) * 2019-04-03 2019-08-02 核工业井巷建设集团有限公司 A kind of quick reinforcement construction method in tunnel
CN110924997A (en) * 2019-12-09 2020-03-27 中铁十六局集团有限公司 Tunnel secondary lining crack trimming and reinforcing method
CN111255488A (en) * 2020-03-18 2020-06-09 福建工程学院 High-strength corrugated plate structure and method for tunnel reinforcement
CN112663646A (en) * 2020-12-18 2021-04-16 南京康泰建筑灌浆科技有限公司 Stable in-situ reinforcing method for grouting control
CN114033433A (en) * 2021-11-16 2022-02-11 中铁十二局集团有限公司 Plateau high-geostress tunnel secondary lining crack monitoring construction method
CN114033432A (en) * 2021-11-16 2022-02-11 中铁十二局集团有限公司 Two-lining crack renovation construction method for plateau high-ground stress tunnel

Also Published As

Publication number Publication date
CN107725086B (en) 2019-11-12

Similar Documents

Publication Publication Date Title
CN107725086B (en) A kind of reinforcement means of the non-structural longitudinal crack of lining cutting
CN108678777B (en) Support method for tunnel fault fracture zone section
CN101638987B (en) Tunnel construction method for crossing high-pressure water-enriched fracture zone with curtain grouting and grout stopping wall
CN106837351A (en) Tunnel Karst water detects Treatment Methods
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN106837353A (en) Filling karst constructing tunnel processing method
CN101922302A (en) Fault processing method of high pressure water enrichment area
CN106087997A (en) A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method
Zingg et al. An investigation into efficient drainage layouts for the stabilization of tunnel faces in homogeneous ground
CN102296621B (en) Construction method of ground sectional water-stop curtain
CN110792450B (en) Method for determining advanced support of grouting anchor cable
CN108979670A (en) A kind of high polymer rich water tunnel slip casting fast repairing method
CN115126441B (en) Vertical deep drilling grouting and stopping process
CN104863148A (en) Crossed anchor group structure and construction method thereof
CN108005662B (en) A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone
CN110565493B (en) Highway subgrade disease treatment method
CN116104502B (en) Method for reinforcing mountain tunnel crossing coal mine goaf
CN104389294A (en) Concrete faced rockfill dam on deep covering layer and construction method
CN104763437B (en) A kind of highly permeable formation tunnel excavation method
CN109209448A (en) Tunnel surface grouting blocks water construction method
CN114961790A (en) Shield synchronous grouting construction method and construction effect evaluation method thereof
CN110528522B (en) Accurate tracking grouting construction method
Haß et al. Westerscheldetunnel—Use of brine freezing for the construction of the traverse galleries
Andrén et al. Degradation of the Reinforcing Effect of Shotcrete: Freeze-Thaw Tests on Shotcrete-Rock Panels
Aldiamar et al. Evaluation of lateral and axial deformation for earth pressure balance (EPB) tunnel construction using 3-dimension finite element method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191112