CN107725057A - Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method - Google Patents

Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method Download PDF

Info

Publication number
CN107725057A
CN107725057A CN201711001750.0A CN201711001750A CN107725057A CN 107725057 A CN107725057 A CN 107725057A CN 201711001750 A CN201711001750 A CN 201711001750A CN 107725057 A CN107725057 A CN 107725057A
Authority
CN
China
Prior art keywords
construction
predicament
driving
towns
cities
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711001750.0A
Other languages
Chinese (zh)
Inventor
韩磊
金宝
张传美
杨守成
马旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Urban Construction Group Co Ltd
Original Assignee
Jinan Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Urban Construction Group Co Ltd filed Critical Jinan Urban Construction Group Co Ltd
Priority to CN201711001750.0A priority Critical patent/CN107725057A/en
Publication of CN107725057A publication Critical patent/CN107725057A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines

Abstract

The invention belongs to tunnel excavation technical field of construction, specifically related to a kind of cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method, construction is cleaved when rock stratum is harder, it is accurately positioned using excavation line, swung by the upper and lower, left and right of development machine front cutting mechanism and cutting head rotates broken rock, effective control over-excavation phenomenon, reduce the time that first branch is closed, working face security is substantially increased, reduces influence of the vibration to surrounding building.

Description

Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method
Technical field
The invention belongs to tunnel excavation technical field of construction, and in particular to a kind of cities and towns Shi Zhi tunnels cantilever tunneling construction Engineering method.
Background technology
Rock stratum section tunnel traditional at present typically uses blast working.Blast working construction risk itself is larger, to week Casing soil disturbance is larger, easily causes surrounding soil to cave in.Face rock stratum is backbreak more serious, the cubic metre of earth and stone during blast working Outward transport increases with first branch spray shield amount, causes the waste of people, material, machinery, and the lengthening of spray shield time, sealing cycle lengthen danger in addition Dangerous increasing.Particularly job location is located at city proper, and surface line is complicated, and both sides house is nearer, and blast working is dangerous It is bigger.
The content of the invention
The present invention is solution the deficiencies in the prior art, there is provided a kind of cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method.
The present invention is achieved by the following technical solutions:A kind of cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method, including Following steps:
(1)Surveying setting-out:Contour line is released, laser is positioned;
(2)Face punching splitting:Splitting is coordinated using splitting machine and rock drill is constructed, using auxiliary bore hole splitting as auxiliary Mode, rock texture is destroyed, tunneled after discharging rock stress;Boring aperture is 5.5cm, and cloth pitch of holes is 0.5m, into plum blossom-shaped Arrangement;
(3)Top bar tunneling construction:Driving contour line is determined using laser orientation instru-ment, top bar is highly 5.6m;Tunneling process Middle boom-type roadheader cutterhead external spraying system sprays water smoke and carries out depositing dust, and air exhauster system opens in boom-type roadheader construction It is dynamic, flue dust is discharged backward;
(4)Steel arch-shelf reinforced mesh is constructed:After tunnel top bar driving, scarfing cinder, unwrapping wire, steel arch-shelf and bar-mat reinforcement are installed Piece;
(5)Advanced conduit construction:Headed into using air drill jewel hole, and by steel pipe in hole, steel pipe tail end welds with steelframe or system anchor bolt It is connected together, adds circumferential reinforcement if necessary;Slip casting determines to terminate the time according to pressure condition and running pulp situation;
(6)Gunite concrete:Using wet shot machine operation, spraying operation from arch springing or foundation from bottom to top, segmentation, burst, layering Spray to design thickness;
(7)Get out of a predicament or an embarrassing situation tunneling construction:Height of getting out of a predicament or an embarrassing situation is 2.4m, and first branch inverted arch is highly 0.85m;Tunnel get out of a predicament or an embarrassing situation driving when, Boom-type roadheader first digs centre, and main hole bow member both sides respectively retain 1m;Both sides are staggeredly tunneled when driving is got out of a predicament or an embarrassing situation, a side seal Close and carry out opposite side construction after cyclization again;Pin framves edge is abolished using oil hammer during first branch inverted arch driving makes up a deficiency;Hanged in tunneling process Road headers cutterhead external spraying system sprays water smoke and carries out depositing dust, and air exhauster system starts in boom-type roadheader construction, Flue dust is discharged backward.
Preferably:
In step(7)In, after the completion of tunneling construction of getting out of a predicament or an embarrassing situation, first branch inverted arch abolishes remaining rock stratum using oil hammer.
Beneficial effects of the present invention are:
First, boom-type roadheader construction not only avoid the greater impact of explosion, and the damage to country rock is small, is nearly free from pine Relax, chip off-falling, avalanche it is dangerous minimum, also substantially increase working face security, reduce and vibrate influence to surrounding building;
2nd, tunnel cross-section forming accuracy is high, can control out break by drill bit driving, especially be abolished with oil hammer, cleaves and abolish Compared etc. cold digging method weak surrounding rock, efficiency of construction is high;
3rd, cantilever excavator continuously excavate, without concussion of blasting, can more freely determine opportune moment of surrounding rock supporting, reduce super Dig, the expense of rock support and lining cutting can be saved.
Embodiment
Specific embodiment of the invention given below is, it is necessary to which explanation is that the invention is not limited in implement in detail below Example, all equivalents done on the basis of technical scheme each fall within protection scope of the present invention.
A kind of cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method, comprises the following steps:
(1)Surveying setting-out
Contour line is released, laser is positioned;
(2)Face punching splitting
Splitting is coordinated using splitting machine and rock drill is constructed, and using auxiliary bore hole splitting as supplementary mode, destroys rock texture, Tunneled after release rock stress;Boring aperture is 5.5cm, and cloth pitch of holes is 0.5m, is arranged into plum blossom-shaped;
(3)Top bar tunneling construction
Driving contour line is determined using laser orientation instru-ment, top bar is highly 5.6m;Boom-type roadheader cut in tunneling process Head external spraying system sprays water smoke and carries out depositing dust, and air exhauster system starts in boom-type roadheader construction, and flue dust is discharged backward;
(4)Steel arch-shelf reinforced mesh is constructed
After tunnel top bar driving, scarfing cinder, unwrapping wire, steel arch-shelf and reinforced mesh are installed;
(5)Advanced conduit construction
Headed into using air drill jewel hole, and by steel pipe in hole, steel pipe tail end welds together with steelframe or system anchor bolt, adds if necessary Circumferential reinforcement;Slip casting determines to terminate the time according to pressure condition and running pulp situation;
(6)Gunite concrete
Using wet shot machine operation, spraying operation from arch springing or foundation from bottom to top, segmentation, burst, layering injection to design thickness;
(7)Get out of a predicament or an embarrassing situation tunneling construction
Height of getting out of a predicament or an embarrassing situation is 2.4m, and first branch inverted arch is highly 0.85m;Tunnel get out of a predicament or an embarrassing situation driving when, during boom-type roadheader is first dug Between, main hole bow member both sides respectively retain 1m;Both sides are staggeredly tunneled when driving is got out of a predicament or an embarrassing situation, and are carried out again after one side closed cyclization another Construct side;Pin framves edge is abolished using oil hammer during first branch inverted arch driving makes up a deficiency;In tunneling process outside boom-type roadheader cutterhead Spraying system sprays water smoke and carries out depositing dust, and air exhauster system starts in boom-type roadheader construction, and flue dust is discharged backward.Leave office After the completion of rank tunneling construction, first branch inverted arch abolishes remaining rock stratum using oil hammer.
One kind of embodiment described above, simply more preferably embodiment of the invention, those skilled in the art The usual variations and alternatives that member is carried out in the range of technical solution of the present invention should all include within the scope of the present invention.

Claims (2)

  1. A kind of 1. cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method, it is characterised in that:Comprise the following steps:
    (1)Surveying setting-out:Contour line is released, laser is positioned;
    (2)Face punching splitting:Splitting is coordinated using splitting machine and rock drill is constructed, using auxiliary bore hole splitting as auxiliary Mode, rock texture is destroyed, tunneled after discharging rock stress;Boring aperture is 5.5cm, and cloth pitch of holes is 0.5m, into plum blossom-shaped Arrangement;
    (3)Top bar tunneling construction:Driving contour line is determined using laser orientation instru-ment, top bar is highly 5.6m;Tunneling process Middle boom-type roadheader cutterhead external spraying system sprays water smoke and carries out depositing dust, and air exhauster system opens in boom-type roadheader construction It is dynamic, flue dust is discharged backward;
    (4)Steel arch-shelf reinforced mesh is constructed:After tunnel top bar driving, scarfing cinder, unwrapping wire, steel arch-shelf and bar-mat reinforcement are installed Piece;
    (5)Advanced conduit construction:Headed into using air drill jewel hole, and by steel pipe in hole, steel pipe tail end welds with steelframe or system anchor bolt It is connected together, adds circumferential reinforcement if necessary;Slip casting determines to terminate the time according to pressure condition and running pulp situation;
    (6)Gunite concrete:Using wet shot machine operation, spraying operation from arch springing or foundation from bottom to top, segmentation, burst, layering Spray to design thickness;
    (7)Get out of a predicament or an embarrassing situation tunneling construction:Height of getting out of a predicament or an embarrassing situation is 2.4m, and first branch inverted arch is highly 0.85m;Tunnel get out of a predicament or an embarrassing situation driving when, Boom-type roadheader first digs centre, and main hole bow member both sides respectively retain 1m;Both sides are staggeredly tunneled when driving is got out of a predicament or an embarrassing situation, a side seal Close and carry out opposite side construction after cyclization again;Pin framves edge is abolished using oil hammer during first branch inverted arch driving makes up a deficiency;Hanged in tunneling process Road headers cutterhead external spraying system sprays water smoke and carries out depositing dust, and air exhauster system starts in boom-type roadheader construction, Flue dust is discharged backward.
  2. 2. cantilever tunneling construction engineering method in cities and towns Shi Zhi tunnels according to claim 1, it is characterised in that:In step(7)In, Get out of a predicament or an embarrassing situation after the completion of tunneling construction, first branch inverted arch abolishes remaining rock stratum using oil hammer.
CN201711001750.0A 2017-10-24 2017-10-24 Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method Pending CN107725057A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711001750.0A CN107725057A (en) 2017-10-24 2017-10-24 Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711001750.0A CN107725057A (en) 2017-10-24 2017-10-24 Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method

Publications (1)

Publication Number Publication Date
CN107725057A true CN107725057A (en) 2018-02-23

Family

ID=61213449

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711001750.0A Pending CN107725057A (en) 2017-10-24 2017-10-24 Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method

Country Status (1)

Country Link
CN (1) CN107725057A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145315A (en) * 2019-05-13 2019-08-20 中铁十六局集团第四工程有限公司 A kind of driving method weakening city shallow tunnel concussion of blasting
CN111550259A (en) * 2020-05-23 2020-08-18 中电建十一局工程有限公司 Construction method of small-section long-distance soft rock tunnel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1191187B1 (en) * 2000-09-20 2006-03-01 Volker Hentschel Device for mounting tunnel lining elements
CN103291308A (en) * 2013-05-29 2013-09-11 王卓 Boom-type roadheader for tunnel construction and tunnel construction method
CN103321644A (en) * 2013-05-29 2013-09-25 王卓 Mechanical mode and control blasting combined tunneling method
CN103643963A (en) * 2013-12-23 2014-03-19 中铁工程装备集团有限公司 Multifunctional tunneling machine
CN103643959A (en) * 2013-12-23 2014-03-19 中铁工程装备集团有限公司 Novel tunneling device
CN106246193A (en) * 2016-09-06 2016-12-21 中铁二十四局集团南昌铁路工程有限公司 Strong karst high rich water urban shallow tunnel cantilever excavator construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1191187B1 (en) * 2000-09-20 2006-03-01 Volker Hentschel Device for mounting tunnel lining elements
CN103291308A (en) * 2013-05-29 2013-09-11 王卓 Boom-type roadheader for tunnel construction and tunnel construction method
CN103321644A (en) * 2013-05-29 2013-09-25 王卓 Mechanical mode and control blasting combined tunneling method
CN103643963A (en) * 2013-12-23 2014-03-19 中铁工程装备集团有限公司 Multifunctional tunneling machine
CN103643959A (en) * 2013-12-23 2014-03-19 中铁工程装备集团有限公司 Novel tunneling device
CN106246193A (en) * 2016-09-06 2016-12-21 中铁二十四局集团南昌铁路工程有限公司 Strong karst high rich water urban shallow tunnel cantilever excavator construction

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
漆泰岳等: "悬臂掘进机在复杂断面地铁隧道中的应用研究", 《现代隧道技术》 *
谢达文: "城市浅埋及超浅埋隧道非爆破技术设备选型与配套研究", 《现代隧道技术》 *
邱昌德: "悬臂掘进机在铁路泄水洞工程的施工应用", 《低碳世界》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145315A (en) * 2019-05-13 2019-08-20 中铁十六局集团第四工程有限公司 A kind of driving method weakening city shallow tunnel concussion of blasting
CN111550259A (en) * 2020-05-23 2020-08-18 中电建十一局工程有限公司 Construction method of small-section long-distance soft rock tunnel
CN111550259B (en) * 2020-05-23 2021-07-09 中电建十一局工程有限公司 Construction method of small-section long-distance soft rock tunnel

Similar Documents

Publication Publication Date Title
CN105257301B (en) A kind of shallow-depth-excavation tunnel weak surrounding rock landslide reinforcing and processing method
CN103291308B (en) For boom-type roadheader and the method for tunnel construction of constructing tunnel
CN108756894B (en) Tunnel micro- three step top Core Soil construction
CN103643958B (en) Hydraulic breaking hammer excavation Modelling of Tunnel Excavation in Soft Rock method
CN103899318B (en) The milling of medium ground tunnel is dug and supporting machinery construction
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN107842368A (en) The non-quick-fried excavation technology of city tunnel Drilling milling mechanical combination
CN103244133B (en) The milling of coal measure strata tunnel is dug and is combined construction with explosion
CN108005660A (en) A kind of Optimization of Expressway Tunnel Construction method
CN102518470B (en) Method for preventing and controlling water by using freezing pipes in annular water intercepting tunnel
CN104790959B (en) A kind of Shallow-buried Tunnels with Small Spacing ground method for tunnel construction
CN106545007A (en) The method of pile in stratum of the bottom for hard rock stratum
CN110469340A (en) A kind of rock burst tunnel double-shielded TBM card machine is got rid of poverty construction method
CN104831733A (en) Arch bridge abutment tunnel type large-angle inclined pile construction method
CN111472801A (en) Construction method for passing existing line under shallow-buried underground excavation drainage gallery
CN107254878A (en) A kind of hydroelectric project dam abutment high gradient slope controls the excavation method of dust
CN104141500B (en) One hardens sand and gravel stratum cavern con struction method
CN109057802A (en) Shallow tunnel with big cross-section underpass of freeways construction method
CN109209443A (en) A kind of construction method of breaking surrounding rock tunnel structure
CN107725057A (en) Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method
CN110566236B (en) Combined supporting device and supporting method for pipe shed and steel support
CN105065004B (en) A kind of Shallow Large Span rock tunnel Portal Section weak blast excavation construction method
CN105019917B (en) Impact drilling type advanced jet grouting pipe shed construction device and construction method
CN104790971B (en) A kind of advanced pre-add solid method of steel tube shed of the small spacing ground constructing tunnel of shallow embedding
CN204099720U (en) The protective housing that under soil stone combination geological condition, artificial pipe jacking construction method is used

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180223