CN107725057A - Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method - Google Patents
Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method Download PDFInfo
- Publication number
- CN107725057A CN107725057A CN201711001750.0A CN201711001750A CN107725057A CN 107725057 A CN107725057 A CN 107725057A CN 201711001750 A CN201711001750 A CN 201711001750A CN 107725057 A CN107725057 A CN 107725057A
- Authority
- CN
- China
- Prior art keywords
- construction
- predicament
- driving
- towns
- cities
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/15—Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
- E21D11/152—Laggings made of grids or nettings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/18—Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/003—Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/10—Making by using boring or cutting machines
Abstract
The invention belongs to tunnel excavation technical field of construction, specifically related to a kind of cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method, construction is cleaved when rock stratum is harder, it is accurately positioned using excavation line, swung by the upper and lower, left and right of development machine front cutting mechanism and cutting head rotates broken rock, effective control over-excavation phenomenon, reduce the time that first branch is closed, working face security is substantially increased, reduces influence of the vibration to surrounding building.
Description
Technical field
The invention belongs to tunnel excavation technical field of construction, and in particular to a kind of cities and towns Shi Zhi tunnels cantilever tunneling construction
Engineering method.
Background technology
Rock stratum section tunnel traditional at present typically uses blast working.Blast working construction risk itself is larger, to week
Casing soil disturbance is larger, easily causes surrounding soil to cave in.Face rock stratum is backbreak more serious, the cubic metre of earth and stone during blast working
Outward transport increases with first branch spray shield amount, causes the waste of people, material, machinery, and the lengthening of spray shield time, sealing cycle lengthen danger in addition
Dangerous increasing.Particularly job location is located at city proper, and surface line is complicated, and both sides house is nearer, and blast working is dangerous
It is bigger.
The content of the invention
The present invention is solution the deficiencies in the prior art, there is provided a kind of cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method.
The present invention is achieved by the following technical solutions:A kind of cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method, including
Following steps:
(1)Surveying setting-out:Contour line is released, laser is positioned;
(2)Face punching splitting:Splitting is coordinated using splitting machine and rock drill is constructed, using auxiliary bore hole splitting as auxiliary
Mode, rock texture is destroyed, tunneled after discharging rock stress;Boring aperture is 5.5cm, and cloth pitch of holes is 0.5m, into plum blossom-shaped
Arrangement;
(3)Top bar tunneling construction:Driving contour line is determined using laser orientation instru-ment, top bar is highly 5.6m;Tunneling process
Middle boom-type roadheader cutterhead external spraying system sprays water smoke and carries out depositing dust, and air exhauster system opens in boom-type roadheader construction
It is dynamic, flue dust is discharged backward;
(4)Steel arch-shelf reinforced mesh is constructed:After tunnel top bar driving, scarfing cinder, unwrapping wire, steel arch-shelf and bar-mat reinforcement are installed
Piece;
(5)Advanced conduit construction:Headed into using air drill jewel hole, and by steel pipe in hole, steel pipe tail end welds with steelframe or system anchor bolt
It is connected together, adds circumferential reinforcement if necessary;Slip casting determines to terminate the time according to pressure condition and running pulp situation;
(6)Gunite concrete:Using wet shot machine operation, spraying operation from arch springing or foundation from bottom to top, segmentation, burst, layering
Spray to design thickness;
(7)Get out of a predicament or an embarrassing situation tunneling construction:Height of getting out of a predicament or an embarrassing situation is 2.4m, and first branch inverted arch is highly 0.85m;Tunnel get out of a predicament or an embarrassing situation driving when,
Boom-type roadheader first digs centre, and main hole bow member both sides respectively retain 1m;Both sides are staggeredly tunneled when driving is got out of a predicament or an embarrassing situation, a side seal
Close and carry out opposite side construction after cyclization again;Pin framves edge is abolished using oil hammer during first branch inverted arch driving makes up a deficiency;Hanged in tunneling process
Road headers cutterhead external spraying system sprays water smoke and carries out depositing dust, and air exhauster system starts in boom-type roadheader construction,
Flue dust is discharged backward.
Preferably:
In step(7)In, after the completion of tunneling construction of getting out of a predicament or an embarrassing situation, first branch inverted arch abolishes remaining rock stratum using oil hammer.
Beneficial effects of the present invention are:
First, boom-type roadheader construction not only avoid the greater impact of explosion, and the damage to country rock is small, is nearly free from pine
Relax, chip off-falling, avalanche it is dangerous minimum, also substantially increase working face security, reduce and vibrate influence to surrounding building;
2nd, tunnel cross-section forming accuracy is high, can control out break by drill bit driving, especially be abolished with oil hammer, cleaves and abolish
Compared etc. cold digging method weak surrounding rock, efficiency of construction is high;
3rd, cantilever excavator continuously excavate, without concussion of blasting, can more freely determine opportune moment of surrounding rock supporting, reduce super
Dig, the expense of rock support and lining cutting can be saved.
Embodiment
Specific embodiment of the invention given below is, it is necessary to which explanation is that the invention is not limited in implement in detail below
Example, all equivalents done on the basis of technical scheme each fall within protection scope of the present invention.
A kind of cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method, comprises the following steps:
(1)Surveying setting-out
Contour line is released, laser is positioned;
(2)Face punching splitting
Splitting is coordinated using splitting machine and rock drill is constructed, and using auxiliary bore hole splitting as supplementary mode, destroys rock texture,
Tunneled after release rock stress;Boring aperture is 5.5cm, and cloth pitch of holes is 0.5m, is arranged into plum blossom-shaped;
(3)Top bar tunneling construction
Driving contour line is determined using laser orientation instru-ment, top bar is highly 5.6m;Boom-type roadheader cut in tunneling process
Head external spraying system sprays water smoke and carries out depositing dust, and air exhauster system starts in boom-type roadheader construction, and flue dust is discharged backward;
(4)Steel arch-shelf reinforced mesh is constructed
After tunnel top bar driving, scarfing cinder, unwrapping wire, steel arch-shelf and reinforced mesh are installed;
(5)Advanced conduit construction
Headed into using air drill jewel hole, and by steel pipe in hole, steel pipe tail end welds together with steelframe or system anchor bolt, adds if necessary
Circumferential reinforcement;Slip casting determines to terminate the time according to pressure condition and running pulp situation;
(6)Gunite concrete
Using wet shot machine operation, spraying operation from arch springing or foundation from bottom to top, segmentation, burst, layering injection to design thickness;
(7)Get out of a predicament or an embarrassing situation tunneling construction
Height of getting out of a predicament or an embarrassing situation is 2.4m, and first branch inverted arch is highly 0.85m;Tunnel get out of a predicament or an embarrassing situation driving when, during boom-type roadheader is first dug
Between, main hole bow member both sides respectively retain 1m;Both sides are staggeredly tunneled when driving is got out of a predicament or an embarrassing situation, and are carried out again after one side closed cyclization another
Construct side;Pin framves edge is abolished using oil hammer during first branch inverted arch driving makes up a deficiency;In tunneling process outside boom-type roadheader cutterhead
Spraying system sprays water smoke and carries out depositing dust, and air exhauster system starts in boom-type roadheader construction, and flue dust is discharged backward.Leave office
After the completion of rank tunneling construction, first branch inverted arch abolishes remaining rock stratum using oil hammer.
One kind of embodiment described above, simply more preferably embodiment of the invention, those skilled in the art
The usual variations and alternatives that member is carried out in the range of technical solution of the present invention should all include within the scope of the present invention.
Claims (2)
- A kind of 1. cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method, it is characterised in that:Comprise the following steps:(1)Surveying setting-out:Contour line is released, laser is positioned;(2)Face punching splitting:Splitting is coordinated using splitting machine and rock drill is constructed, using auxiliary bore hole splitting as auxiliary Mode, rock texture is destroyed, tunneled after discharging rock stress;Boring aperture is 5.5cm, and cloth pitch of holes is 0.5m, into plum blossom-shaped Arrangement;(3)Top bar tunneling construction:Driving contour line is determined using laser orientation instru-ment, top bar is highly 5.6m;Tunneling process Middle boom-type roadheader cutterhead external spraying system sprays water smoke and carries out depositing dust, and air exhauster system opens in boom-type roadheader construction It is dynamic, flue dust is discharged backward;(4)Steel arch-shelf reinforced mesh is constructed:After tunnel top bar driving, scarfing cinder, unwrapping wire, steel arch-shelf and bar-mat reinforcement are installed Piece;(5)Advanced conduit construction:Headed into using air drill jewel hole, and by steel pipe in hole, steel pipe tail end welds with steelframe or system anchor bolt It is connected together, adds circumferential reinforcement if necessary;Slip casting determines to terminate the time according to pressure condition and running pulp situation;(6)Gunite concrete:Using wet shot machine operation, spraying operation from arch springing or foundation from bottom to top, segmentation, burst, layering Spray to design thickness;(7)Get out of a predicament or an embarrassing situation tunneling construction:Height of getting out of a predicament or an embarrassing situation is 2.4m, and first branch inverted arch is highly 0.85m;Tunnel get out of a predicament or an embarrassing situation driving when, Boom-type roadheader first digs centre, and main hole bow member both sides respectively retain 1m;Both sides are staggeredly tunneled when driving is got out of a predicament or an embarrassing situation, a side seal Close and carry out opposite side construction after cyclization again;Pin framves edge is abolished using oil hammer during first branch inverted arch driving makes up a deficiency;Hanged in tunneling process Road headers cutterhead external spraying system sprays water smoke and carries out depositing dust, and air exhauster system starts in boom-type roadheader construction, Flue dust is discharged backward.
- 2. cantilever tunneling construction engineering method in cities and towns Shi Zhi tunnels according to claim 1, it is characterised in that:In step(7)In, Get out of a predicament or an embarrassing situation after the completion of tunneling construction, first branch inverted arch abolishes remaining rock stratum using oil hammer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711001750.0A CN107725057A (en) | 2017-10-24 | 2017-10-24 | Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711001750.0A CN107725057A (en) | 2017-10-24 | 2017-10-24 | Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107725057A true CN107725057A (en) | 2018-02-23 |
Family
ID=61213449
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711001750.0A Pending CN107725057A (en) | 2017-10-24 | 2017-10-24 | Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107725057A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110145315A (en) * | 2019-05-13 | 2019-08-20 | 中铁十六局集团第四工程有限公司 | A kind of driving method weakening city shallow tunnel concussion of blasting |
CN111550259A (en) * | 2020-05-23 | 2020-08-18 | 中电建十一局工程有限公司 | Construction method of small-section long-distance soft rock tunnel |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1191187B1 (en) * | 2000-09-20 | 2006-03-01 | Volker Hentschel | Device for mounting tunnel lining elements |
CN103291308A (en) * | 2013-05-29 | 2013-09-11 | 王卓 | Boom-type roadheader for tunnel construction and tunnel construction method |
CN103321644A (en) * | 2013-05-29 | 2013-09-25 | 王卓 | Mechanical mode and control blasting combined tunneling method |
CN103643963A (en) * | 2013-12-23 | 2014-03-19 | 中铁工程装备集团有限公司 | Multifunctional tunneling machine |
CN103643959A (en) * | 2013-12-23 | 2014-03-19 | 中铁工程装备集团有限公司 | Novel tunneling device |
CN106246193A (en) * | 2016-09-06 | 2016-12-21 | 中铁二十四局集团南昌铁路工程有限公司 | Strong karst high rich water urban shallow tunnel cantilever excavator construction |
-
2017
- 2017-10-24 CN CN201711001750.0A patent/CN107725057A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1191187B1 (en) * | 2000-09-20 | 2006-03-01 | Volker Hentschel | Device for mounting tunnel lining elements |
CN103291308A (en) * | 2013-05-29 | 2013-09-11 | 王卓 | Boom-type roadheader for tunnel construction and tunnel construction method |
CN103321644A (en) * | 2013-05-29 | 2013-09-25 | 王卓 | Mechanical mode and control blasting combined tunneling method |
CN103643963A (en) * | 2013-12-23 | 2014-03-19 | 中铁工程装备集团有限公司 | Multifunctional tunneling machine |
CN103643959A (en) * | 2013-12-23 | 2014-03-19 | 中铁工程装备集团有限公司 | Novel tunneling device |
CN106246193A (en) * | 2016-09-06 | 2016-12-21 | 中铁二十四局集团南昌铁路工程有限公司 | Strong karst high rich water urban shallow tunnel cantilever excavator construction |
Non-Patent Citations (3)
Title |
---|
漆泰岳等: "悬臂掘进机在复杂断面地铁隧道中的应用研究", 《现代隧道技术》 * |
谢达文: "城市浅埋及超浅埋隧道非爆破技术设备选型与配套研究", 《现代隧道技术》 * |
邱昌德: "悬臂掘进机在铁路泄水洞工程的施工应用", 《低碳世界》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110145315A (en) * | 2019-05-13 | 2019-08-20 | 中铁十六局集团第四工程有限公司 | A kind of driving method weakening city shallow tunnel concussion of blasting |
CN111550259A (en) * | 2020-05-23 | 2020-08-18 | 中电建十一局工程有限公司 | Construction method of small-section long-distance soft rock tunnel |
CN111550259B (en) * | 2020-05-23 | 2021-07-09 | 中电建十一局工程有限公司 | Construction method of small-section long-distance soft rock tunnel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105257301B (en) | A kind of shallow-depth-excavation tunnel weak surrounding rock landslide reinforcing and processing method | |
CN103291308B (en) | For boom-type roadheader and the method for tunnel construction of constructing tunnel | |
CN108756894B (en) | Tunnel micro- three step top Core Soil construction | |
CN103643958B (en) | Hydraulic breaking hammer excavation Modelling of Tunnel Excavation in Soft Rock method | |
CN103899318B (en) | The milling of medium ground tunnel is dug and supporting machinery construction | |
CN109736827B (en) | Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing | |
CN107842368A (en) | The non-quick-fried excavation technology of city tunnel Drilling milling mechanical combination | |
CN103244133B (en) | The milling of coal measure strata tunnel is dug and is combined construction with explosion | |
CN108005660A (en) | A kind of Optimization of Expressway Tunnel Construction method | |
CN102518470B (en) | Method for preventing and controlling water by using freezing pipes in annular water intercepting tunnel | |
CN104790959B (en) | A kind of Shallow-buried Tunnels with Small Spacing ground method for tunnel construction | |
CN106545007A (en) | The method of pile in stratum of the bottom for hard rock stratum | |
CN110469340A (en) | A kind of rock burst tunnel double-shielded TBM card machine is got rid of poverty construction method | |
CN104831733A (en) | Arch bridge abutment tunnel type large-angle inclined pile construction method | |
CN111472801A (en) | Construction method for passing existing line under shallow-buried underground excavation drainage gallery | |
CN107254878A (en) | A kind of hydroelectric project dam abutment high gradient slope controls the excavation method of dust | |
CN104141500B (en) | One hardens sand and gravel stratum cavern con struction method | |
CN109057802A (en) | Shallow tunnel with big cross-section underpass of freeways construction method | |
CN109209443A (en) | A kind of construction method of breaking surrounding rock tunnel structure | |
CN107725057A (en) | Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method | |
CN110566236B (en) | Combined supporting device and supporting method for pipe shed and steel support | |
CN105065004B (en) | A kind of Shallow Large Span rock tunnel Portal Section weak blast excavation construction method | |
CN105019917B (en) | Impact drilling type advanced jet grouting pipe shed construction device and construction method | |
CN104790971B (en) | A kind of advanced pre-add solid method of steel tube shed of the small spacing ground constructing tunnel of shallow embedding | |
CN204099720U (en) | The protective housing that under soil stone combination geological condition, artificial pipe jacking construction method is used |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180223 |