CN107724559A - Existing building base isolation reinforcement construction process - Google Patents

Existing building base isolation reinforcement construction process Download PDF

Info

Publication number
CN107724559A
CN107724559A CN201710993222.1A CN201710993222A CN107724559A CN 107724559 A CN107724559 A CN 107724559A CN 201710993222 A CN201710993222 A CN 201710993222A CN 107724559 A CN107724559 A CN 107724559A
Authority
CN
China
Prior art keywords
pier
support
seismic isolation
column
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710993222.1A
Other languages
Chinese (zh)
Other versions
CN107724559B (en
Inventor
鲁风勇
李小敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kening Engineering Science And Technology Nanjing Co ltd
Original Assignee
Nanjing 100 Seath Construction Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing 100 Seath Construction Technology Co Ltd filed Critical Nanjing 100 Seath Construction Technology Co Ltd
Priority to CN201710993222.1A priority Critical patent/CN107724559B/en
Publication of CN107724559A publication Critical patent/CN107724559A/en
Application granted granted Critical
Publication of CN107724559B publication Critical patent/CN107724559B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/025Structures with concrete columns
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/027Preventive constructional measures against earthquake damage in existing buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明公开了一种既有建筑隔震加固的施工流程;该隔震加固的施工流程是:先施工下支墩、然后施工上支墩,最后在隔震层空间内切割结构柱和安装隔震支座。另外,为了巩固所述隔震加固施工流程的正常实施,本发明设计了特定的上支墩构造、隔震支座的安装构造以及托换结构;本发明通过上述的施工流程,能够提高隔震支座的安装质量,降低造价,并大大缩短施工总工期。

The invention discloses a construction process for seismic isolation reinforcement of an existing building; the construction process for seismic isolation reinforcement is as follows: firstly construct the lower pier, then construct the upper pier, and finally cut the structural column and install the isolation layer in the space of the isolation layer. Shock mount. In addition, in order to consolidate the normal implementation of the seismic isolation reinforcement construction process, the present invention designs a specific upper pier structure, the installation structure of the seismic isolation bearing and the underpinning structure; the present invention can improve the seismic isolation through the above construction process. The installation quality of the support is improved, the cost is reduced, and the total construction period is greatly shortened.

Description

既有建筑隔震加固施工流程Seismic isolation and strengthening construction process of existing buildings

技术领域technical field

本发明属于既有建筑抗震加固改造技术领域,具体涉及一种既有建筑隔震加固的施工流程,应用于地震区建筑结构隔震加固框架柱托换时使用。The invention belongs to the technical field of anti-seismic strengthening and transformation of existing buildings, and in particular relates to a construction process for anti-seismic strengthening of existing buildings.

背景技术Background technique

在既有建筑的隔震加固改造工程中,隔震层施工的一般次序是:土方开挖、托换支架、切割柱混凝土、浇筑下支墩、安装隔震支座、浇筑上支墩及顶部梁板。之后才能进行上部建筑装潢工程的施工,这种施工可称之“直线式”施工流程。In the seismic isolation reinforcement project of existing buildings, the general sequence of seismic isolation layer construction is: excavation of earthwork, underpinning support, cutting column concrete, pouring of lower buttress, installation of seismic isolation support, pouring of upper buttress and top Beam slab. Only then can the construction of the upper part of the building decoration project be carried out. This kind of construction can be called "straight-line" construction process.

现有的“直线式”施工流程,一般地,从土方开挖、托换支架施工、浇筑下支墩、安装支座、浇筑上支墩,养护,拆除托换支架、浇筑梁板混凝土,养护,地面及首层装饰工程施工,……。施工内容沿一条直线,不能较差施工,造成总工期较长。另外,在开工后很快就需要隔震支座,一般地由于隔震支座的生产与检测需要较长,难免会造成窝工。根据项目施工经验,完成全部隔震加固和必要的恢复和装饰工程,总工期约80~90天。The existing "straight-line" construction process generally consists of earthwork excavation, construction of underpinning supports, pouring of lower buttresses, installation of supports, pouring of upper buttresses, maintenance, removal of underpinning supports, pouring of beam-slab concrete, and maintenance , Ground and first floor decoration engineering construction,……. The construction content is along a straight line, and the construction cannot be poor, resulting in a longer total construction period. In addition, seismic isolation bearings are needed soon after the start of construction. Generally, the production and testing of seismic isolation bearings takes a long time, which will inevitably cause delays. According to the construction experience of the project, complete all seismic isolation reinforcement and necessary restoration and decoration works, with a total construction period of about 80-90 days.

“直线式”施工具有以下主要特征:"Straight-line" construction has the following main characteristics:

(1)设置型钢柱与钢托梁形成的托换支架;(1) Set the underpinning bracket formed by the steel column and the steel joist;

(2)托梁采用对拉螺杆或其他方式与混凝土柱连接;(2) The joist is connected with the concrete column by tension screw or other means;

(3)先切割柱混凝土,再安装隔震支座,最后浇筑上支墩和梁板结构。(3) Cut the column concrete first, then install the seismic isolation bearing, and finally pour the upper pier and beam-slab structure.

(4)托换支架服役时间,始于切割柱混凝土之前,终于支座安装完毕,甚至终于上支墩混凝土养护龄期结束。(4) The service time of the underpinning bracket begins before the concrete of the column is cut, and finally the support is installed, and even the concrete curing age of the upper pier ends.

“直线式”施工,存在以下问题:"Straight line" construction has the following problems:

(1)托架结构的制作,采用型钢梁柱焊接而成,用钢量大,制作费材、费工,且不易重复利用;(1) The manufacture of the bracket structure is welded by shaped steel beams and columns, which consumes a large amount of steel, is expensive in materials and labor, and is not easy to reuse;

(2)柱切割“绳锯”,速度慢,价格高,切割的混凝土面难于满足隔震支座安装的平整度要求;(2) Column cutting "wire saw" is slow and expensive, and the cut concrete surface is difficult to meet the flatness requirements for the installation of seismic isolation bearings;

(3)托架支托时间长,风险大。周围场地的微振动对建筑安全有影响。若偶遇地震,建筑的安全风险极大;(3) The support time of the bracket is long and the risk is high. The micro-vibration of the surrounding site has an impact on building safety. In the event of an earthquake, the safety risk of the building is extremely high;

(4)造价高。这主要体现在材料消耗、托架制作和支托时间上。(4) The cost is high. This is mainly reflected in material consumption, bracket production and support time.

隔震技术在理论研究、隔震支座制造技术、隔震分析与设计都已经相当成熟和完善。但是,现有的托换施工技术却是费材、费时、费工,费钱、风险高。这严重地阻碍了隔震技术在既有建筑的隔震加固中的应用。Seismic isolation technology has been quite mature and perfect in theoretical research, isolation support manufacturing technology, isolation analysis and design. However, the existing underpinning construction technology is expensive in materials, time-consuming, labor-intensive, expensive and risky. This seriously hinders the application of seismic isolation technology in the seismic isolation and reinforcement of existing buildings.

既有的大量中小学校舍和医院,抗震标准不满足国家标准的规定,由于加固施工工期长影响教学工作,致使抗震加固工作无法开展。在抗震加固中,隔震技术相比抗震技术具有突出的技术经济优越性,施工工期也大大缩短,但仍不能满足教学和医院使用的实际需要。因此,需要提高隔震加固的施工水平,降低造价、缩短工期。满足实际工程的需要。For a large number of existing primary and secondary school buildings and hospitals, the anti-seismic standard does not meet the requirements of the national standard. Due to the long construction period of the reinforcement and the impact on the teaching work, the anti-seismic reinforcement cannot be carried out. In seismic reinforcement, seismic isolation technology has outstanding technical and economic advantages compared with seismic technology, and the construction period is also greatly shortened, but it still cannot meet the actual needs of teaching and hospitals. Therefore, it is necessary to improve the construction level of seismic isolation and reinforcement, reduce the cost and shorten the construction period. Meet the needs of practical engineering.

发明内容Contents of the invention

本发明针对现有技术的不足,在充分认知隔震结构特点,充分利用结构构件的承载能力的基础上,通过优化上支墩的构造、隔震支座的安装方法、托换结构的巧妙设置,优化施工流程一系列成套技术,彻底革新了隔震加固的托换施工技术。解决了传统托换技术存在的问题,能够有效地提高隔震加固的施工水平,降低造价、缩短工期。The present invention aims at the deficiencies of the prior art, on the basis of fully understanding the characteristics of the shock-isolation structure and making full use of the bearing capacity of the structural members, by optimizing the structure of the upper pier, the installation method of the shock-isolation bearing, and the ingenious underpinning structure Set up and optimize the construction process A series of complete sets of technologies have completely revolutionized the underpinning construction technology for seismic isolation and reinforcement. It solves the problems existing in the traditional underpinning technology, can effectively improve the construction level of seismic isolation reinforcement, reduce the cost and shorten the construction period.

为实现上述的技术目的,本发明将采取如下的技术方案:For realizing above-mentioned technical purpose, the present invention will take following technical scheme:

一种既有建筑隔震加固施工流程,包括以下步骤:A construction process for seismic isolation and reinforcement of an existing building, comprising the following steps:

(1)根据既有建筑隔震加固的设计需求以及所选择隔震支座的结构特点,确定隔震支座在既有建筑隔震层空间内的安装位置,确定处于隔震支座上方的上支墩、处于隔震支座下方的下支墩,确定用于将隔震支座安装在上支墩、下支墩之间的连接措施,其中:(1) According to the design requirements for seismic isolation reinforcement of existing buildings and the structural characteristics of the selected seismic isolation bearings, determine the installation position of the seismic isolation bearings in the space of the existing building isolation layer, and determine the location above the seismic isolation bearings. For the upper pier and the lower pier under the seismic isolation support, determine the connection measures for installing the seismic isolation support between the upper pier and the lower pier, where:

上支墩、下支墩均为既有结构柱和新浇混凝土结构的组合结构;The upper pier and the lower pier are combined structures of existing structural columns and newly poured concrete structures;

连接措施包括上部连接措施、下部连接措施;上部连接措施包括上预埋板、支座上连接板、焊接锁紧件及灌浆料;下部连接措施包括下预埋板、支座下连接板、焊接锁紧件及灌浆料;The connection measures include the upper connection measures and the lower connection measures; the upper connection measures include the upper embedded plate, the upper connecting plate of the support, welding locking parts and grouting materials; the lower connecting measures include the lower embedded plate, the lower connecting plate of the support, welding Locking parts and grouting materials;

隔震支座的上方通过上部连接措施与上支墩连接,隔震支座的下方通过下部连接措施与下支墩连接;The upper part of the isolation bearing is connected with the upper pier through the upper connection measures, and the lower part of the isolation support is connected with the lower support pier through the lower connection measures;

(2)浇筑上支墩、下支墩(2) Pouring the upper and lower piers

根据步骤(1)确定的上支墩、下支墩的具体结构,分别植筋或绑扎钢筋,先浇筑形成下支墩,再浇筑形成上支墩;According to the specific structure of the upper buttress and the lower buttress determined in step (1), respectively plant bars or bind steel bars, first pour to form the lower buttress, and then pour to form the upper buttress;

浇筑下支墩时,顶面设置下预埋板,下预埋板通过板锚固筋锚固在下支墩的新浇混凝土结构内;浇筑上支墩时,底面设置上预埋板,上预埋板通过板锚固筋锚固在上支墩的新浇混凝土结构内;When pouring the lower pier, set the lower embedded slab on the top surface, and the lower embedded slab is anchored in the newly poured concrete structure of the lower pier through the slab anchor bars; when pouring the upper pier, set the upper embedded slab on the bottom surface, and the upper embedded slab Anchored in the newly poured concrete structure of the upper pier through the plate anchor bar;

(3)安装托换结构(3) Install the underpinning structure

在上、下支墩之间安装若干支柱,各支柱的两端分别与上、下支墩对应顶紧;Install a number of pillars between the upper and lower piers, and the two ends of each pillar are respectively pressed against the upper and lower piers;

(4)切割结构柱(4) Cutting structural columns

切除隔震支座安装高度范围内的结构柱;Cut off the structural columns within the installation height range of the isolation support;

(5)安装隔震支座(5) Install the vibration isolation support

先将隔震支座就位,此时隔震支座的上端通过螺栓组件安装支座上连接板,隔震支座的下端通过螺栓组件安装支座下连接板;接着,分别以支座上连接板、支座下连接板的各螺栓组件的轴线为基准,对应地在上预埋板、下预埋板的板面焊接螺纹锁紧件;然后,通过上预埋板的螺纹锁紧件与支座上连接板上对应的螺栓组件的配合连接,将隔震支座上端通过支座上连接板安装到上预埋板;同理,通过下预埋板的螺纹锁紧件与支座下连接板上对应的螺栓组件的配合连接,将隔震支座下端通过支座下连接板安装到下预埋板;First put the shock-isolation support in place, at this time, the upper end of the shock-isolation support is installed with the upper connecting plate of the support through the bolt assembly, and the lower end of the shock-isolation support is installed with the lower connecting plate of the support through the bolt assembly; The axis of each bolt assembly of the connecting plate and the lower connecting plate of the support is taken as the reference, and the threaded locking parts are welded on the surface of the upper embedded plate and the lower embedded plate correspondingly; then, through the threaded locking parts of the upper embedded plate Cooperate with the corresponding bolt assembly on the connecting plate on the support, install the upper end of the seismic isolation support to the upper embedded plate through the connecting plate on the support; similarly, through the threaded locking parts of the lower embedded plate and the support The matching connection of the corresponding bolt components on the lower connecting plate installs the lower end of the shock-isolation support to the lower embedded plate through the lower connecting plate of the support;

(6)灌注灌浆料拌合物(6) Filling the grouting mixture

在上支墩底面与支座上连接板之间、下支墩顶面与支座下连接板之间,分别灌注灌浆料拌合物;Between the bottom surface of the upper pier and the upper connection plate of the support, between the top surface of the lower pier and the lower connection plate of the support, respectively pour the grouting material mixture;

(7)拆除托换结构。(7) Remove the underpinning structure.

拆除支柱,托换完成。Remove the pillars and the underpinning is complete.

作为本发明的进一步改进,步骤(2)中所述上支墩通过下述步骤浇筑而成:As a further improvement of the present invention, the upper pier described in step (2) is poured through the following steps:

2.1、先将支墩锚固筋与既有结构柱主筋焊接部位对应位置处的外层混凝土保护层剔除,形成周圈的凹槽,并露出该部位的结构柱主筋;2.1. First remove the outer concrete protective layer at the corresponding position between the anchor bar of the pier and the main bar of the existing structural column to form a circumferential groove and expose the main bar of the structural column at this position;

2.2、采用焊接固定的方式,将各支墩锚固筋一一焊接固定到既有结构柱主筋上,使得各支墩锚固筋能够与既有结构柱主筋形成灯笼筋;2.2. By means of welding and fixing, the anchor bars of each pier are welded and fixed to the main bars of the existing structural columns one by one, so that the anchor bars of each pier can form lantern bars with the main bars of the existing structural columns;

2.3、在支墩锚固筋与既有结构柱主筋焊接部位的外侧布置水平封闭箍筋,以使水平封闭箍筋箍紧支墩锚固筋与既有结构柱主筋的焊接部位;2.3. Arrange horizontally closed stirrups on the outside of the welded part of the anchor bar of the pier and the main bar of the existing structural column, so that the horizontal closed stirrup tightens the welded part of the anchor bar of the pier and the main bar of the existing structural column;

2.4、设置上支墩主筋:在灯笼筋范围内布置X、Y、Z三个方向的上支墩主筋,主筋采用箍筋形状,将原承重框架柱混凝土柱围合呈钢筋笼;2.4. Set up the main reinforcement of the upper pier: Arrange the main reinforcement of the upper pier in the three directions of X, Y, and Z within the range of the lantern reinforcement. The main reinforcement adopts the shape of a stirrup, and the original load-bearing frame column concrete column is enclosed to form a reinforcement cage;

2.5、上支墩的下表面布置上预埋板及板锚固筋;2.5. The lower surface of the upper pier is arranged with an upper embedded plate and plate anchor bars;

2.6、按照正常施工要求,浇筑混凝土层,形成上支墩。2.6. According to the normal construction requirements, pour the concrete layer to form the upper pier.

作为本发明的进一步改进,所述支墩锚固筋呈形设置;该形锚固筋的两个焊接端,通过将C形钢筋的两端分别向内弯折以对应形成。As a further improvement of the present invention, the anchor bar of the pier is shape settings; the The two welded ends of the C-shaped anchor bar are formed by bending the two ends of the C-shaped steel bar inwards respectively.

作为本发明的进一步改进,水平封闭箍筋布置于与形锚固筋焊接端相邻的弯折位置处。As a further improvement of the present invention, the horizontal closed stirrups are arranged with The bending position adjacent to the welded end of the shaped anchoring tendon.

作为本发明的进一步改进,所述支墩锚固筋包括柱边锚固筋以及柱角部锚固筋;柱边锚固筋垂直既有结构柱柱边布置;而柱角部锚固筋的布置方式具有两种,其中一种沿既有结构柱对角线方向布置,此时,既有结构柱主筋与支墩锚固筋数量一致,且支墩锚固筋与既有结构柱主筋一一对应布置;另外一种布置方式的柱角部锚固筋包括两根,各自紧靠着既有结构柱对角线垂直于既有结构柱柱边布置。As a further improvement of the present invention, the anchoring bars of the pier include anchoring bars at column edges and anchoring bars at column corners; the anchor bars at column edges are arranged vertically to the column edges of existing structures; and the anchor bars at column corners are arranged in two ways: , one of which is arranged along the diagonal direction of the existing structural column. At this time, the number of the main reinforcement of the existing structural column and the anchoring reinforcement of the pier are the same, and the anchoring reinforcement of the pier is arranged in one-to-one correspondence with the main reinforcement of the existing structural column; the other The arrangement method includes two anchor bars at the corners of the column, each of which is arranged close to the diagonal line of the existing structural column and perpendicular to the edge of the existing structural column.

作为本发明的进一步改进,支柱采用整个钢管柱或钢管混凝土柱。As a further improvement of the present invention, the pillar adopts the whole steel pipe column or steel pipe concrete column.

作为本发明的进一步改进,步骤(5)中,所述螺栓锁紧件为锁紧螺栓或者螺纹套筒。As a further improvement of the present invention, in step (5), the bolt locking member is a locking bolt or a threaded sleeve.

作为本发明的进一步改进,所述上、下预埋板均呈矩形、正方形或圆形;且所述上、下预埋板呈矩形或正方形时,在预埋板的每一条板边的中部位置处均配置一阻或多组板锚固筋。As a further improvement of the present invention, the upper and lower embedded panels are rectangular, square or circular; and when the upper and lower embedded panels are rectangular or square, the middle part of each edge of the embedded panel One or more sets of plate anchoring ribs are arranged at each position.

作为本发明的进一步改进,步骤(4)的切割结构柱具体是采用水钻切割法进行的,包括以下步骤:As a further improvement of the present invention, the cutting of the structural column in step (4) is specifically carried out using a rhinestone cutting method, including the following steps:

4.1、在上支墩底面,钻一排孔,并补钻凸起部分,形成切割面;4.1. Drill a row of holes on the bottom of the upper pier, and re-drill the raised part to form a cutting surface;

4.2、在下支墩顶面,钻一排孔,并补钻凸起部分,形成切割面;4.2. Drill a row of holes on the top surface of the lower pier, and re-drill the raised part to form a cutting surface;

4.3切割时,结构柱的钢筋和混凝土一并切除。4.3 When cutting, the steel bars and concrete of the structural column shall be cut together.

作为本发明的进一步改进,在步骤(6)所述的灌注灌浆料拌合物后,还存在一个二次注浆步骤,具体是:采用压力注浆,将支座上连接板与上支墩之间、支座下连接板与下支墩之间的混凝土收缩裂缝进行注浆,确保隔震支座与上支墩、下支墩之间填充密实。As a further improvement of the present invention, after pouring the grouting material mixture described in step (6), there is also a secondary grouting step, specifically: using pressure grouting, the upper connecting plate of the support and the upper pier Grouting is performed on the concrete shrinkage cracks between the bottom connecting plate of the support and the lower pier to ensure that the space between the isolation support and the upper pier and the lower pier is densely filled.

根据上述的技术方案,相对于现有技术,本发明具有如下的优点:According to above-mentioned technical scheme, with respect to prior art, the present invention has following advantage:

(1)施工组织合理(1) Reasonable construction organization

本发明所述的隔震加固方法,土建施工可以一口气地完成从下支墩到顶板梁板的施工,混凝土养护期间可以进行上部地面和装饰恢复工程的准备,柱切割和隔震支座的准备工作,同时也可施工室外工程。依靠减少混凝土浇筑次数、交叉作业等流程优化,考虑混凝土龄期的变化,总工期一般可提前30天左右。According to the seismic isolation reinforcement method of the present invention, the civil construction can complete the construction from the lower pier to the roof beam slab in one go, and the upper ground and decoration restoration works can be prepared during the concrete maintenance period, and the column cutting and seismic isolation support can be completed. Preparation work, but also the construction of outdoor projects. Relying on process optimization such as reducing the number of concrete pours and cross-operation, and considering changes in the age of concrete, the total construction period can generally be advanced by about 30 days.

(2)充分利用结构构件(2) Make full use of structural components

本发明充分利用结构构件的承载能力进行托换,不再需要型钢托架的制造、安装。仅需钢管短柱(顶托支柱)。材料消耗大大减少。施工简便、易行。The invention makes full use of the bearing capacity of the structural components for underpinning, and does not need the manufacture and installation of steel brackets. Only steel pipe stubs (jacking pillars) are required. Material consumption is greatly reduced. The construction is simple and easy.

(3)风险小、易控(3) Small risk and easy to control

本发明结构柱的切割和减震支座的安装,一般2天即可完成,因此,建筑只有2天时间内有安全风险。The cutting of the structural column of the present invention and the installation of the shock-absorbing support can generally be completed in 2 days, so the building has safety risks in only 2 days.

附图说明Description of drawings

图1是本发明所述既有建筑隔震加固的施工流程图;Fig. 1 is the construction flowchart of existing building seismic isolation reinforcement described in the present invention;

图2是本发明所述既有建筑隔震加固的施工结构图;Fig. 2 is the construction structural drawing of existing building seismic isolation reinforcement described in the present invention;

图3是本发明所述上支墩构造示意图;Fig. 3 is a schematic diagram of the structure of the upper pier of the present invention;

图4是本发明所述隔震支座安装示意图;Fig. 4 is a schematic diagram of the installation of the shock-isolation bearing of the present invention;

图5是本发明所述的托换结构示意图;Fig. 5 is a schematic diagram of the underpinning structure of the present invention;

图中:11、上支墩的新浇混凝土;12、上支墩的原结构柱;2、隔震支座;31、下支墩的新浇混凝土;32、下支墩的原结构柱;In the figure: 11, the newly poured concrete of the upper pier; 12, the original structural column of the upper pier; 2, the seismic isolation bearing; 31, the newly poured concrete of the lower pier; 32, the original structural column of the lower pier;

11‐1、支墩锚固筋;11‐2、水平封闭箍筋;11‐3、保护层凹槽;11‐4、柱主筋;11‐5、外部混凝土层;12、结构柱;11-1, buttress anchor reinforcement; 11-2, horizontal closed stirrup; 11-3, protective layer groove; 11-4, column main reinforcement; 11-5, external concrete layer; 12, structural column;

41‐预埋板;42‐板锚固筋;43‐螺栓锁紧件;44‐灌浆料拌合物;45‐螺栓组件;46‐支座连接板;41-embedded plate; 42-plate anchor rib; 43-bolt locking piece; 44-grouting material mixture; 45-bolt assembly; 46-support connecting plate;

51‐顶托支柱;52‐钢楔;6‐待截断结构柱。51‐Jacking pillar; 52‐Steel wedge; 6‐Structural column to be truncated.

具体实施方式detailed description

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。以下对至少一个示例性实施例的描述实际上仅仅是说明性的,决不作为对本发明及其应用或使用的任何限制。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。除非另外具体说明,否则在这些实施例中阐述的部件和步骤的相对布置、表达式和数值不限制本发明的范围。同时,应当明白,为了便于描述,附图中所示出的各个部分的尺寸并不是按照实际的比例关系绘制的。对于相关领域普通技术人员已知的技术、方法和设备可能不作详细讨论,但在适当情况下,所述技术、方法和设备应当被视为授权说明书的一部分。在这里示出和讨论的所有示例中,任何具体值应被解释为仅仅是示例性的,而不是作为限制。因此,示例性实施例的其它示例可以具有不同的值。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. The following description of at least one exemplary embodiment is merely illustrative in nature and in no way taken as limiting the invention, its application or uses. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention. The relative arrangements, expressions and numerical values of components and steps set forth in these embodiments do not limit the scope of the present invention unless specifically stated otherwise. At the same time, it should be understood that, for the convenience of description, the sizes of the various parts shown in the drawings are not drawn according to the actual proportional relationship. Techniques, methods and devices known to those of ordinary skill in the relevant art may not be discussed in detail, but where appropriate, such techniques, methods and devices should be considered part of the Authorized Specification. In all examples shown and discussed herein, any specific values should be construed as exemplary only, and not as limitations. Therefore, other examples of the exemplary embodiment may have different values.

为了便于描述,在这里可以使用空间相对术语,如“在……之上”、“在……上方”、“在……上表面”、“上面的”等,用来描述如在图中所示的一个器件或特征与其他器件或特征的空间位置关系。应当理解的是,空间相对术语旨在包含除了器件在图中所描述的方位之外的在使用或操作中的不同方位。例如,如果附图中的器件被倒置,则描述为“在其他器件或构造上方”或“在其他器件或构造之上”的器件之后将被定位为“在其他器件或构造下方”或“在其他器件或构造之下”。因而,示例性术语“在……上方”可以包括“在……上方”和“在……下方”两种方位。该器件也可以其他不同方式定位(旋转90度或处于其他方位)。For the convenience of description, spatially relative terms may be used here, such as "on ...", "over ...", "on the surface of ...", "above", etc., to describe the The spatial positional relationship between one device or feature shown and other devices or features. It will be understood that the spatially relative terms are intended to encompass different orientations of the device in use or operation in addition to the orientation depicted in the figures. For example, if the device in the figures is turned over, devices described as "above" or "above" other devices or configurations would then be oriented "beneath" or "above" the other devices or configurations. under other devices or configurations". Thus, the exemplary term "above" can encompass both an orientation of "above" and "beneath". The device may be positioned in other different ways (rotated 90 degrees or at other orientations) as well.

本发明所述的一种既有建筑隔震加固施工流程,如图1、图2所示,包括以下步骤:A kind of existing building seismic isolation strengthening construction process described in the present invention, as shown in Fig. 1, Fig. 2, comprises the following steps:

(1)根据既有建筑隔震加固的设计需求以及所选择隔震支座的结构特点,确定隔震支座在既有建筑隔震层空间内的安装位置,确定处于隔震支座上方的上支墩、处于隔震支座下方的下支墩,确定用于将隔震支座安装在上支墩、下支墩之间的连接措施,其中:(1) According to the design requirements for seismic isolation reinforcement of existing buildings and the structural characteristics of the selected seismic isolation bearings, determine the installation position of the seismic isolation bearings in the space of the existing building isolation layer, and determine the location above the seismic isolation bearings. For the upper pier and the lower pier under the seismic isolation support, determine the connection measures for installing the seismic isolation support between the upper pier and the lower pier, where:

上支墩、下支墩均为既有结构柱和新浇混凝土结构的组合结构;上支墩的上部是框架柱,与首层梁板形成整体刚性水平构件;下支墩的下部是结构的基础。Both the upper pier and the lower pier are combined structures of the existing structural columns and the newly poured concrete structure; the upper part of the upper pier is a frame column, which forms an integral rigid horizontal member with the beam and slab on the first floor; the lower part of the lower pier is a structural Base.

连接措施包括上部连接措施、下部连接措施;上部连接措施包括上预埋板和支座上连接板;下部连接措施包括下预埋板和支座下连接板;The connection measures include the upper connection measures and the lower connection measures; the upper connection measures include the upper embedded plate and the upper connection plate of the support; the lower connection measures include the lower embedded plate and the lower connection plate of the support;

隔震支座的上方通过上部连接措施与上支墩顶紧,隔震支座的下方通过下部连接措施与下支墩顶紧;The upper part of the seismic isolation bearing is tightened with the upper pier through the upper connecting measures, and the lower part of the seismic isolation bearing is tightened with the lower supporting pier through the lower connecting measures;

具体地,隔震支座安装在上、下支墩之间,隔震支座是可拆卸式的,采用螺栓与上、下支墩的预埋板上的焊接螺母连接。并且支座与预埋板之间设置有灌浆料拌合物以及压力注浆。Specifically, the shock-isolation support is installed between the upper and lower piers, and the shock-isolation support is detachable, and is connected with welded nuts on the pre-embedded plates of the upper and lower piers by bolts. Moreover, a grouting material mixture and pressure grouting are arranged between the support and the embedded plate.

隔震结构的托换结构充分利用了上、支墩的承载能力,支柱高度小,托换时间大大缩短,结构的安全可靠性高。The underpinning structure of the seismic isolation structure makes full use of the bearing capacity of the upper and buttress piers, the pillar height is small, the underpinning time is greatly shortened, and the safety and reliability of the structure are high.

(2)浇筑上支墩、下支墩(2) Pouring the upper and lower piers

根据步骤(1)确定的上支墩、下支墩的具体结构,分别植筋或绑扎钢筋,先浇筑形成下支墩,再浇筑形成上支墩;According to the specific structure of the upper buttress and the lower buttress determined in step (1), respectively plant bars or bind steel bars, first pour to form the lower buttress, and then pour to form the upper buttress;

浇筑下支墩时,顶面设置下预埋板,下预埋板通过板锚固筋锚固在下支墩的新浇混凝土结构内;浇筑上支墩时,底面设置上预埋板,上预埋板通过板锚固筋锚固在上支墩的新浇混凝土结构内;所述上、下预埋板均呈矩形、正方形或圆形;且所述上、下预埋板呈矩形或正方形时,在预埋板的每一条板边的中部位置处均配置一阻或多组板锚固筋。When pouring the lower pier, set the lower embedded slab on the top surface, and the lower embedded slab is anchored in the newly poured concrete structure of the lower pier through the slab anchor bars; when pouring the upper pier, set the upper embedded slab on the bottom surface, and the upper embedded slab Anchored in the newly poured concrete structure of the upper pier through the plate anchor bar; the upper and lower embedded plates are rectangular, square or circular; and when the upper and lower embedded plates are rectangular or square, the pre-embedded One or more groups of plate anchoring ribs are arranged at the middle of each plate edge of the buried plate.

下支墩可以采用现有的浇筑方法来浇筑;而上支墩通过下述步骤浇筑而成:The lower buttresses can be poured using existing pouring methods; while the upper buttresses are poured through the following steps:

2.1、先将支墩锚固筋与既有结构柱主筋焊接部位对应位置处的外层混凝土保护层剔除,形成周圈的凹槽,并露出该部位的结构柱主筋;其中:所述支墩锚固筋,如图3所示,呈形设置;该形锚固筋的两个焊接端,通过将C形钢筋的两端分别向内弯折以对应形成;所述支墩锚固筋包括柱边锚固筋以及柱角部锚固筋;柱边锚固筋垂直既有结构柱柱边布置;而柱角部锚固筋的布置方式具有两种,其中一种沿既有结构柱对角线方向布置,此时,既有结构柱主筋与支墩锚固筋数量一致,且支墩锚固筋与既有结构柱主筋一一对应布置;另外一种布置方式的柱角部锚固筋包括两根,各自紧靠着既有结构柱对角线垂直于既有结构柱柱边布置;2.1. First remove the outer concrete protective layer at the corresponding position between the anchor bar of the pier and the main bar of the existing structural column to form a circumferential groove and expose the main bar of the structural column at this position; wherein: the anchoring of the buttress Ribs, as shown in Figure 3, are shape settings; the The two welded ends of the C-shaped anchor bars are formed by bending the two ends of the C-shaped steel bar inwards to form correspondingly; There are two types of arrangement for the column edge of the structural column; there are two ways to arrange the anchor bars at the corner of the column, one of which is arranged along the diagonal direction of the existing structural column. And the anchor bars of the pier are arranged in one-to-one correspondence with the main bars of the existing structural columns; in another arrangement, the anchor bars at the corners of the columns include two, each of which is close to the diagonal line of the existing structural column and perpendicular to the edge of the existing structural column layout;

2.2、采用焊接固定的方式,将各支墩锚固筋一一焊接固定到既有结构柱主筋上,使得各支墩锚固筋能够与既有结构柱主筋形成灯笼筋;2.2. By means of welding and fixing, the anchor bars of each pier are welded and fixed to the main bars of the existing structural columns one by one, so that the anchor bars of each pier can form lantern bars with the main bars of the existing structural columns;

2.3、在支墩锚固筋与既有结构柱主筋焊接部位的外侧布置水平封闭箍筋,以使水平封闭箍筋箍紧支墩锚固筋与既有结构柱主筋的焊接部位;其中:水平封闭箍筋布置于与形锚固筋焊接端相邻的弯折位置处;2.3. Arrange horizontal closed stirrups on the outside of the welded part of the anchor bar of the pier and the main bar of the existing structural column, so that the horizontal closed stirrup tightens the welded part of the anchor bar of the pier and the main bar of the existing structural column; where: the horizontal closed stirrup Ribs are arranged with The bending position adjacent to the welded end of the anchor bar;

2.4、设置上支墩主筋:在灯笼筋范围内布置X、Y、Z三个方向的上支墩主筋,主筋采用箍筋形状,将原承重框架柱混凝土柱围合呈钢筋笼;2.4. Set up the main reinforcement of the upper pier: Arrange the main reinforcement of the upper pier in the three directions of X, Y, and Z within the range of the lantern reinforcement. The main reinforcement adopts the shape of a stirrup, and the original load-bearing frame column concrete column is enclosed to form a reinforcement cage;

2.5、上支墩的下表面布置上预埋板及板锚固筋;2.5. The lower surface of the upper pier is arranged with an upper embedded plate and plate anchor bars;

2.6、按照正常施工要求,浇筑混凝土层,形成上支墩。2.6. According to the normal construction requirements, pour the concrete layer to form the upper pier.

(3)安装托换结构(3) Install the underpinning structure

在上、下支墩之间安装若干支柱,各支柱的两端分别与上、下支墩对应顶紧;Install a number of pillars between the upper and lower piers, and the two ends of each pillar are respectively pressed against the upper and lower piers;

支柱采用整个钢管柱或钢管混凝土柱,设置在于上下支墩之间、隔震支座安装位置处的外侧,支座可以灵活装拆。The pillar adopts the entire steel pipe column or steel pipe concrete column, which is arranged between the upper and lower piers and outside the installation position of the seismic isolation support, and the support can be assembled and disassembled flexibly.

支柱顶紧后,可切割隔震支座安装位置处的柱混凝土,安装隔震支座,填充隔震支座与上、下支墩之间的空隙,并注浆挤密之后,但混凝土强度达到要求后,拆除支柱。After the pillar is tightened, the column concrete at the installation position of the isolation support can be cut, the isolation support can be installed, the gap between the isolation support and the upper and lower piers can be filled, and after grouting and compaction, the concrete strength After reaching the requirements, remove the pillars.

根据这一步骤,可以形成如图(5)所示的托换结构,包括支柱、上支墩与下支墩。上、下支墩分别为隔震支墩上、下的支撑结构,支柱采用楔板与上支墩、下支墩顶紧。According to this step, an underpinning structure as shown in Figure (5) can be formed, including pillars, upper piers and lower piers. The upper and lower piers are respectively the upper and lower support structures of the seismic isolation pier, and the pillars are tightened with the upper and lower piers by wedge plates.

(4)切割结构柱(4) Cutting structural columns

切除隔震支座安装高度范围内的结构柱;Cut off the structural columns within the installation height range of the isolation support;

切割时,需要注意以下几点:When cutting, you need to pay attention to the following points:

(4.1)柱采用水钻切割法;(4.1) The column adopts rhinestone cutting method;

(4.2)在上支墩底面,钻一排孔,并补钻凸起部分,形成切割面;(4.2) Drill a row of holes on the bottom surface of the upper pier, and re-drill the raised part to form a cutting surface;

(4.3)在下支墩顶面,钻一排孔,并补钻凸起部分,形成切割面;(4.3) Drill a row of holes on the top surface of the lower pier, and re-drill the raised part to form a cutting surface;

(4.4)切割时钢筋和一并切除,通过灌浆和注浆,与隔震支座可靠连接;(4.4) When cutting, the steel bars are cut off together, and are reliably connected to the seismic isolation support through grouting and grouting;

(5)安装隔震支座(5) Install the vibration isolation support

先将隔震支座就位,此时隔震支座的上端通过螺栓组件安装支座上连接板,隔震支座的下端通过螺栓组件安装支座下连接板;接着,分别以支座上连接板、支座下连接板的各螺栓组件的轴线为基准,对应地在上预埋板、下预埋板的板面焊接螺纹锁紧件;然后,通过上预埋板的螺纹锁紧件与支座上连接板上对应的螺栓组件的配合连接,将隔震支座上端通过支座上连接板安装到上预埋板;同理,通过下预埋板的螺纹锁紧件与支座下连接板上对应的螺栓组件的配合连接,将隔震支座下端通过支座下连接板安装到下预埋板;其中:所述螺栓锁紧件为锁紧螺栓或者螺纹套筒。通过步骤(5),可以得到如图4所示的隔震支座安装构造。First put the shock-isolation support in place, at this time, the upper end of the shock-isolation support is installed with the upper connecting plate of the support through the bolt assembly, and the lower end of the shock-isolation support is installed with the lower connecting plate of the support through the bolt assembly; The axis of each bolt assembly of the connecting plate and the lower connecting plate of the support is used as the reference, and the threaded locking parts are welded on the surface of the upper embedded plate and the lower embedded plate correspondingly; then, through the threaded locking parts of the upper embedded plate Cooperate with the corresponding bolt assembly on the connecting plate on the support, install the upper end of the shock-isolation support to the upper embedded plate through the connecting plate on the support; The matching connection of the corresponding bolt components on the lower connecting plate installs the lower end of the shock-isolation support to the lower embedded plate through the lower connecting plate of the support; wherein: the bolt locking member is a locking bolt or a threaded sleeve. Through step (5), the installation structure of the shock-isolation support shown in FIG. 4 can be obtained.

(6)灌注灌浆料拌合物(6) Filling the grouting mixture

在上支墩底面与支座上连接板之间、下支墩顶面与支座下连接板之间,分别灌注灌浆料拌合物;Between the bottom surface of the upper pier and the upper connection plate of the support, between the top surface of the lower pier and the lower connection plate of the support, respectively pour the grouting material mixture;

(7)二次注浆(7) Secondary grouting

待灌浆料强度达到设计要求后,利用压力注浆,将灌浆料顶部与结构构件的微细缝隙填充密实。具体是:采用压力注浆,将支座上连接板与上支墩之间、支座下连接板与下支墩之间的混凝土收缩裂缝进行注浆,确保隔震支座与上支墩、下支墩之间填充密实。After the strength of the grouting material meets the design requirements, use pressure grouting to fill and compact the microscopic gaps between the top of the grouting material and the structural components. Specifically: pressure grouting is used to grout the concrete shrinkage cracks between the upper connection plate of the support and the upper pier, and between the lower connection plate of the support and the lower pier, so as to ensure that the seismic isolation support and the upper pier, The filling between the lower buttresses is dense.

(8)拆除托换结构。(8) Remove the underpinning structure.

拆除支柱,托换完成。Remove the pillars and the underpinning is complete.

施工要求:Construction requirements:

(1)结构构件应按照能够满足托换是的受力需求进行强度、刚度的设计,因此,上支墩新旧混凝土之间的抗剪强度设计尤为关键。(1) The strength and stiffness of the structural members should be designed to meet the stress requirements of the underpinning. Therefore, the design of the shear strength between the old and new concrete of the upper pier is particularly critical.

(2)混凝土柱的切割机具,考虑隔震支座安装标高、水平度的精度要求,现场切割面无法达到隔震支座预埋板、连接板的机械支座精度要求,需要采取其他措施,弥补两者之间的空隙。(2) For cutting machines and tools for concrete columns, considering the accuracy requirements of the installation elevation and levelness of the isolation support, the on-site cutting surface cannot meet the precision requirements of the mechanical support of the embedded plate and connecting plate of the isolation support, and other measures need to be taken. bridge the gap between the two.

(3)隔震支座的安装,要充分考虑安装空间、混凝土切割面的标高及水平度精度、连接措施等而设计与之适应的安装方式。(3) For the installation of the seismic isolation bearing, it is necessary to fully consider the installation space, the elevation of the concrete cutting surface, the levelness accuracy, the connection measures, etc., and design the appropriate installation method.

(4)安全应急预案。可设置必要的三角支撑架设置在房屋四角、纵横两当先设置,形成稳定的结构约束机构,防止振动对建筑的破坏。(4) Safety emergency plan. The necessary triangular support frames can be set up at the four corners of the house, vertically and horizontally, forming a stable structural restraint mechanism to prevent damage to the building due to vibration.

3、与现有技术相比,本发明的效果和益处在于:3, compared with prior art, effect and benefit of the present invention are:

(1)省材(1) material saving

“后托换”成套技术,基本不再型钢梁柱等材料,钢材材料消耗大大降低。每个支座大约节省钢材0.6~1.2吨。The complete set of technology of "post-underpinning" basically no longer uses materials such as steel beams and columns, and the consumption of steel materials is greatly reduced. Each support saves about 0.6 to 1.2 tons of steel.

(2)省工(2) labor saving

“后托换”成套技术,取消了型钢托架制作与拆除,混凝土切割采用水钻法,不需要绳锯切割也不需人工凿除,施工快捷方便。The "back underpinning" complete set of technology cancels the manufacture and dismantling of steel brackets, and the concrete cutting adopts the water drilling method, which does not require wire saw cutting or manual chisel removal, and the construction is fast and convenient.

(3)省时(3) Time saving

“后托换”技术施工,减少了混凝土养护次数,隔震层内部托换施工可以和顶板上部的装修施工同时进行。与现有直线式施工相比,能节约总工期30天左右。对比中小学校舍的抗震加固工程,相比原先80~90天的最短工期,可缩短至50~60天,利用暑假期间能够稳妥地完成施工。对于医院建筑的隔震加固,也能缩短工期30天天,大大减少对医护工作的干扰。The "post-underpinning" technology construction reduces the number of concrete maintenance, and the internal underpinning construction of the isolation layer can be carried out simultaneously with the decoration construction on the top of the roof. Compared with the existing linear construction, the total construction period can be saved by about 30 days. Compared with the seismic reinforcement project of primary and middle school buildings, compared with the original minimum construction period of 80-90 days, it can be shortened to 50-60 days, and the construction can be safely completed during the summer vacation. For the seismic isolation and reinforcement of hospital buildings, the construction period can also be shortened by 30 days, greatly reducing the interference to medical work.

(4)安全风险小(4) Small safety risk

现有技术,托换支架的支托时间30天左右,而托架没有与柱等效的抗弯抗剪承载能力,这期间上部建筑完全由托架支撑,建筑的安全风险较大。“后托换技术,托换过程简单快速,1.5天左右就能完成托换。短柱高度小,稳定性好。因此,“后托换”技术对建筑的安全影响很小。In the existing technology, the support time of the underpinning bracket is about 30 days, and the bracket has no bending and shear bearing capacity equivalent to that of the column. During this period, the superstructure is completely supported by the bracket, and the safety risk of the building is relatively large. "Post underpinning technology, the underpinning process is simple and fast, and the underpinning can be completed in about 1.5 days. The height of the short column is small and the stability is good. Therefore, the "post underpinning" technology has little impact on the safety of the building.

(5)造价低(5) Low cost

后托换施工技术,由于省材、省工、省时,托换工程总造价明显降低,在先托换施工造价基础上可节省50%直接费用。With post-underpinning construction technology, the total cost of the underpinning project is significantly reduced due to the saving of materials, labor and time, and 50% of the direct cost can be saved on the basis of the construction cost of the first underpinning.

Claims (10)

1.一种既有建筑隔震加固施工流程,其特征在于,包括以下步骤:1. A kind of existing building seismic isolation reinforcement construction process is characterized in that, comprises the following steps: (1)根据既有建筑隔震加固的设计需求以及所选择隔震支座的结构特点,确定隔震支座在既有建筑隔震层空间内的安装位置,确定处于隔震支座上方的上支墩、处于隔震支座下方的下支墩,确定用于将隔震支座安装在上支墩、下支墩之间的连接措施,其中:(1) According to the design requirements for seismic isolation reinforcement of existing buildings and the structural characteristics of the selected seismic isolation bearings, determine the installation position of the seismic isolation bearings in the space of the existing building isolation layer, and determine the location above the seismic isolation bearings. For the upper pier and the lower pier under the seismic isolation support, determine the connection measures for installing the seismic isolation support between the upper pier and the lower pier, where: 上支墩、下支墩均为既有结构柱和新浇混凝土结构的组合结构;The upper pier and the lower pier are combined structures of existing structural columns and newly poured concrete structures; 连接措施包括上部连接措施、下部连接措施;上部连接措施包括上预埋板、支座上连接板、焊接锁紧件与灌浆料;下部连接措施包括下预埋板、支座下连接板、焊接锁紧件及灌浆料;The connection measures include the upper connection measures and the lower connection measures; the upper connection measures include the upper embedded plate, the upper connecting plate of the support, welding locking parts and grouting materials; the lower connecting measures include the lower embedded plate, the lower connecting plate of the support, welding Locking parts and grouting materials; 隔震支座的上方通过上部连接措施与上支墩连接,隔震支座的下方通过下部连接措施与下支墩连接;The upper part of the isolation bearing is connected with the upper pier through the upper connection measures, and the lower part of the isolation support is connected with the lower support pier through the lower connection measures; (2)浇筑上支墩、下支墩(2) Pouring the upper and lower piers 根据步骤(1)确定的上支墩、下支墩的具体结构,分别植筋或绑扎钢筋,先浇筑形成下支墩,再浇筑形成上支墩;According to the specific structure of the upper buttress and the lower buttress determined in step (1), respectively plant bars or bind steel bars, first pour to form the lower buttress, and then pour to form the upper buttress; 浇筑下支墩时,顶面设置下预埋板,下预埋板通过板锚固筋锚固在下支墩的新浇混凝土结构内;浇筑上支墩时,底面设置上预埋板,上预埋板通过板锚固筋锚固在上支墩的新浇混凝土结构内;When pouring the lower pier, set the lower embedded slab on the top surface, and the lower embedded slab is anchored in the newly poured concrete structure of the lower pier through the slab anchor bars; when pouring the upper pier, set the upper embedded slab on the bottom surface, and the upper embedded slab Anchored in the newly poured concrete structure of the upper pier through the plate anchor bar; (3)安装托换结构(3) Install the underpinning structure 在上、下支墩之间安装若干支柱,各支柱的两端分别与上、下支墩对应顶紧;Install a number of pillars between the upper and lower piers, and the two ends of each pillar are respectively pressed against the upper and lower piers; (4)切割结构柱(4) Cutting structural columns 切除隔震支座安装高度范围内的结构柱;Cut off the structural columns within the installation height range of the isolation support; (5)安装隔震支座(5) Install the vibration isolation support 先将隔震支座就位,此时隔震支座的上端通过螺栓组件安装支座上连接板,隔震支座的下端通过螺栓组件安装支座下连接板;接着,分别以支座上连接板、支座下连接板的各螺栓组件的轴线为基准,对应地在上预埋板、下预埋板的板面焊接螺纹锁紧件;然后,通过上预埋板的螺纹锁紧件与支座上连接板上对应的螺栓组件的配合连接,将隔震支座上端通过支座上连接板安装到上预埋板;同理,通过下预埋板的螺纹锁紧件与支座下连接板上对应的螺栓组件的配合连接,将隔震支座下端通过支座下连接板安装到下预埋板;First put the shock-isolation support in place, at this time, the upper end of the shock-isolation support is installed with the upper connecting plate of the support through the bolt assembly, and the lower end of the shock-isolation support is installed with the lower connecting plate of the support through the bolt assembly; The axis of each bolt assembly of the connecting plate and the lower connecting plate of the support is used as the reference, and the threaded locking parts are welded on the surface of the upper embedded plate and the lower embedded plate correspondingly; then, through the threaded locking parts of the upper embedded plate Cooperate with the corresponding bolt assembly on the connecting plate on the support, install the upper end of the shock-isolation support to the upper embedded plate through the connecting plate on the support; The matching connection of the corresponding bolt components on the lower connecting plate installs the lower end of the shock-isolation support to the lower embedded plate through the lower connecting plate of the support; (6)灌注灌浆料拌合物(6) Filling the grouting mixture 在上支墩底面与支座上连接板之间、下支墩顶面与支座下连接板之间,分别灌注灌浆料拌合物;Between the bottom surface of the upper pier and the upper connection plate of the support, between the top surface of the lower pier and the lower connection plate of the support, respectively pour the grouting material mixture; (7)拆除托换结构。(7) Remove the underpinning structure. 拆除支柱,托换完成。Remove the pillars and the underpinning is complete. 2.根据权利要求1所述的既有建筑隔震加固施工流程,其特征在于,步骤(2)中所述上支墩通过下述步骤浇筑而成:2. The construction process for seismic isolation and strengthening of existing buildings according to claim 1, wherein the upper buttress described in step (2) is poured through the following steps: 2.1、先将支墩锚固筋与既有结构柱主筋焊接部位对应位置处的外层混凝土保护层剔除,形成周圈的凹槽,并露出该部位的结构柱主筋;2.1. First remove the outer concrete protective layer at the corresponding position between the anchor bar of the pier and the main bar of the existing structural column to form a circumferential groove and expose the main bar of the structural column at this position; 2.2、采用焊接固定的方式,将各支墩锚固筋一一焊接固定到既有结构柱主筋上,使得各支墩锚固筋能够与既有结构柱主筋形成灯笼筋;2.2. By means of welding and fixing, the anchor bars of each pier are welded and fixed to the main bars of the existing structural columns one by one, so that the anchor bars of each pier can form lantern bars with the main bars of the existing structural columns; 2.3、在支墩锚固筋与既有结构柱主筋焊接部位的外侧布置水平封闭箍筋,以使水平封闭箍筋箍紧支墩锚固筋与既有结构柱主筋的焊接部位;2.3. Arrange horizontally closed stirrups on the outside of the welded part of the anchor bar of the pier and the main bar of the existing structural column, so that the horizontal closed stirrup tightens the welded part of the anchor bar of the pier and the main bar of the existing structural column; 2.4、设置上支墩主筋:在灯笼筋范围内布置X、Y、Z三个方向的上支墩主筋,主筋采用箍筋形状,将原承重框架柱混凝土柱围合呈钢筋笼;2.4. Set up the main reinforcement of the upper pier: Arrange the main reinforcement of the upper pier in the three directions of X, Y, and Z within the range of the lantern reinforcement. The main reinforcement adopts the shape of a stirrup, and the original load-bearing frame column concrete column is enclosed to form a reinforcement cage; 2.5、上支墩的下表面布置上预埋板及板锚固筋;2.5. The lower surface of the upper pier is arranged with an upper embedded plate and plate anchor bars; 2.6、按照正常施工要求,浇筑混凝土层,形成上支墩。2.6. According to the normal construction requirements, pour the concrete layer to form the upper pier. 3.根据权利要求2所述的既有建筑隔震加固施工流程,其特征在于,所述支墩锚固筋呈形设置;该形锚固筋的两个焊接端,通过将C形钢筋的两端分别向内弯折以对应形成。3. The construction process for seismic isolation and strengthening of existing buildings according to claim 2, wherein the anchoring bars of the pier are in the form of shape settings; the The two welded ends of the C-shaped anchor bar are formed by bending the two ends of the C-shaped steel bar inwards respectively. 4.根据权利要求3所述的既有建筑隔震加固施工流程,其特征在于,水平封闭箍筋布置于与形锚固筋焊接端相邻的弯折位置处。4. The construction process for seismic isolation and strengthening of existing buildings according to claim 3, characterized in that the horizontal closed stirrups are arranged at the same The bending position adjacent to the welded end of the shaped anchoring tendon. 5.根据权利要求2所述的既有建筑隔震加固施工流程,其特征在于,所述支墩锚固筋包括柱边锚固筋以及柱角部锚固筋;柱边锚固筋垂直既有结构柱柱边布置;而柱角部锚固筋的布置方式具有两种,其中一种沿既有结构柱对角线方向布置,此时,既有结构柱主筋与支墩锚固筋数量一致,且支墩锚固筋与既有结构柱主筋一一对应布置;另外一种布置方式的柱角部锚固筋包括两根,各自垂直于既有结构柱相邻两边布置。5. The existing building seismic isolation reinforcement construction process according to claim 2, characterized in that, said pier anchor bars include column edge anchor bars and column corner anchor bars; column edge anchor bars are perpendicular to existing structural columns There are two ways to arrange the anchor bars at the corner of the column, one of which is arranged along the diagonal direction of the existing structural column. The reinforcements are arranged in one-to-one correspondence with the main reinforcements of the existing structural columns; in another arrangement, the anchoring reinforcements at the corners of the columns include two, each perpendicular to the adjacent two sides of the existing structural columns. 6.根据权利要求1所述的既有建筑隔震加固施工流程,其特征在于,支柱采用整个钢管柱或钢管混凝土柱。6. The construction process of seismic isolation and reinforcement of an existing building according to claim 1, characterized in that, the pillar adopts the whole steel pipe column or steel pipe concrete column. 7.根据权利要求1所述的既有建筑隔震加固施工流程,其特征在于,步骤(5)中,所述螺栓锁紧件为锁紧螺栓或者螺纹套筒。7. The construction process for seismic isolation and reinforcement of an existing building according to claim 1, characterized in that, in step (5), the bolt locking member is a locking bolt or a threaded sleeve. 8.根据权利要求1所述的既有建筑隔震加固施工流程,其特征在于,所述上、下预埋板均呈矩形、正方形或圆形;且所述上、下预埋板呈矩形或正方形时,在预埋板的每一条板边的中部位置处均配置一阻或多组板锚固筋。8. The construction process for seismic isolation and strengthening of existing buildings according to claim 1, wherein the upper and lower pre-embedded panels are rectangular, square or circular; and the upper and lower pre-embedded panels are rectangular or square, one or more groups of plate anchoring ribs are arranged at the middle of each plate edge of the embedded plate. 9.根据权利要求1所述的既有建筑隔震加固施工流程,其特征在于,步骤(4)的切割结构柱具体是采用水钻切割法进行的,包括以下步骤:9. The construction process for seismic isolation and strengthening of existing buildings according to claim 1, characterized in that the cutting of the structural column in step (4) is carried out using a rhinestone cutting method, comprising the following steps: 4.1、在上支墩底面,钻一排孔,并补钻凸起部分,形成切割面;4.1. Drill a row of holes on the bottom of the upper pier, and re-drill the raised part to form a cutting surface; 4.2、在下支墩顶面,钻一排孔,并补钻凸起部分,形成切割面;4.2. Drill a row of holes on the top surface of the lower pier, and re-drill the raised part to form a cutting surface; 4.3、切割时,结构柱的钢筋和混凝土一并切除。4.3 When cutting, the steel bars and concrete of the structural column shall be cut together. 10.根据权利要求1所述的既有建筑隔震加固施工流程,其特征在于,在步骤(6)所述的灌注灌浆料拌合物后,还存在一个二次注浆步骤,具体是:采用压力注浆,将支座上连接板与上支墩之间、支座下连接板与下支墩之间的混凝土收缩裂缝进行注浆,确保隔震支座与上支墩、下支墩之间填充密实。10. The construction process for seismic isolation and strengthening of existing buildings according to claim 1, characterized in that, after pouring the grouting material mixture described in step (6), there is also a secondary grouting step, specifically: Pressure grouting is used to grout the concrete shrinkage cracks between the upper connection plate of the support and the upper pier, and between the lower connection plate of the support and the lower pier, so as to ensure the The filling between them is dense.
CN201710993222.1A 2017-10-23 2017-10-23 Seismic isolation and reinforcement construction process of existing buildings Active CN107724559B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710993222.1A CN107724559B (en) 2017-10-23 2017-10-23 Seismic isolation and reinforcement construction process of existing buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710993222.1A CN107724559B (en) 2017-10-23 2017-10-23 Seismic isolation and reinforcement construction process of existing buildings

Publications (2)

Publication Number Publication Date
CN107724559A true CN107724559A (en) 2018-02-23
CN107724559B CN107724559B (en) 2019-07-05

Family

ID=61213231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710993222.1A Active CN107724559B (en) 2017-10-23 2017-10-23 Seismic isolation and reinforcement construction process of existing buildings

Country Status (1)

Country Link
CN (1) CN107724559B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108571004A (en) * 2018-06-29 2018-09-25 北京瑞博远绿色建筑科技有限公司 A kind of timber structure Gu decorated archway base isolation system and its reinforcement means
CN108678416A (en) * 2018-07-04 2018-10-19 浙江理工大学 A kind of assembled underground increasing layer isolation structure and increasing layer shock insulation construction technology
CN108869881A (en) * 2018-07-26 2018-11-23 柳州东方工程橡胶制品有限公司 A kind of pipeline seismic isolation device and its construction method
CN109930854A (en) * 2019-03-12 2019-06-25 北京筑福建筑科学研究院有限责任公司 A kind of toughness building structure and its construction method that existing frame structure uses shock insulation to underpin
CN110805141A (en) * 2019-11-14 2020-02-18 山东建筑大学 Connecting device and method for steel pipe column and shock insulation support after jacking of building
CN114016740A (en) * 2021-12-14 2022-02-08 北京国际建设集团有限公司 Construction method for seismic mitigation and isolation conversion layer of subway upper cover structure
CN115450461A (en) * 2022-08-12 2022-12-09 河北省建筑科学研究院有限公司 Quick installation and construction method of seismic mitigation and isolation support for existing frame structure reinforcement

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EE00888U1 (en) * 2009-05-08 2010-01-15 As Amhold Carrier replacement method
CN102587684A (en) * 2011-12-31 2012-07-18 北京筑福建设工程有限责任公司 Installation underpinning method for existing framed building reinforced by parallel seismic isolation supports
CN202850061U (en) * 2012-10-11 2013-04-03 北京筑福建设工程有限责任公司 Foundation shock insulation structure
CN103147591A (en) * 2013-03-18 2013-06-12 新蒲建设集团有限公司 Construction method for adding earthquake-proof layer to brick concrete building
CN103741832A (en) * 2014-01-26 2014-04-23 昆明天矫力加固技术工程有限公司 Building column-truncating, replacing and seismic-isolating support construction method and supporting device
CN104453268A (en) * 2014-11-11 2015-03-25 云南震安减震技术有限公司 Method for replacing seismic isolation rubber bearing with section steel beams
CN105715068A (en) * 2016-03-11 2016-06-29 江苏鼎达建筑新技术有限公司 Underpinning and reinforcing structure for seismic isolation bearing of existing brick-concrete structure and construction method for underpinning and reinforcing structure
CN106703437A (en) * 2016-12-02 2017-05-24 镇江中谊抗震科技股份有限公司 Shock-insulation underpinning structure and construction method thereof

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EE00888U1 (en) * 2009-05-08 2010-01-15 As Amhold Carrier replacement method
CN102587684A (en) * 2011-12-31 2012-07-18 北京筑福建设工程有限责任公司 Installation underpinning method for existing framed building reinforced by parallel seismic isolation supports
CN202850061U (en) * 2012-10-11 2013-04-03 北京筑福建设工程有限责任公司 Foundation shock insulation structure
CN103147591A (en) * 2013-03-18 2013-06-12 新蒲建设集团有限公司 Construction method for adding earthquake-proof layer to brick concrete building
CN103741832A (en) * 2014-01-26 2014-04-23 昆明天矫力加固技术工程有限公司 Building column-truncating, replacing and seismic-isolating support construction method and supporting device
CN104453268A (en) * 2014-11-11 2015-03-25 云南震安减震技术有限公司 Method for replacing seismic isolation rubber bearing with section steel beams
CN105715068A (en) * 2016-03-11 2016-06-29 江苏鼎达建筑新技术有限公司 Underpinning and reinforcing structure for seismic isolation bearing of existing brick-concrete structure and construction method for underpinning and reinforcing structure
CN106703437A (en) * 2016-12-02 2017-05-24 镇江中谊抗震科技股份有限公司 Shock-insulation underpinning structure and construction method thereof

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108571004A (en) * 2018-06-29 2018-09-25 北京瑞博远绿色建筑科技有限公司 A kind of timber structure Gu decorated archway base isolation system and its reinforcement means
CN108678416A (en) * 2018-07-04 2018-10-19 浙江理工大学 A kind of assembled underground increasing layer isolation structure and increasing layer shock insulation construction technology
CN108678416B (en) * 2018-07-04 2023-09-15 浙江理工大学 Assembled underground storey-adding vibration-isolating structure and storey-adding vibration-isolating construction process
CN108869881A (en) * 2018-07-26 2018-11-23 柳州东方工程橡胶制品有限公司 A kind of pipeline seismic isolation device and its construction method
CN108869881B (en) * 2018-07-26 2023-12-19 柳州东方工程橡胶制品有限公司 Pipeline vibration reduction and isolation device and construction method thereof
CN109930854A (en) * 2019-03-12 2019-06-25 北京筑福建筑科学研究院有限责任公司 A kind of toughness building structure and its construction method that existing frame structure uses shock insulation to underpin
CN110805141A (en) * 2019-11-14 2020-02-18 山东建筑大学 Connecting device and method for steel pipe column and shock insulation support after jacking of building
CN110805141B (en) * 2019-11-14 2021-08-24 山东建筑大学 A connection device and method for a steel pipe column and a seismic isolation support after a building is jacked up
CN114016740A (en) * 2021-12-14 2022-02-08 北京国际建设集团有限公司 Construction method for seismic mitigation and isolation conversion layer of subway upper cover structure
CN114016740B (en) * 2021-12-14 2022-11-18 北京国际建设集团有限公司 Construction method for seismic mitigation and isolation conversion layer of subway upper cover structure
CN115450461A (en) * 2022-08-12 2022-12-09 河北省建筑科学研究院有限公司 Quick installation and construction method of seismic mitigation and isolation support for existing frame structure reinforcement

Also Published As

Publication number Publication date
CN107724559B (en) 2019-07-05

Similar Documents

Publication Publication Date Title
CN107724559A (en) Existing building base isolation reinforcement construction process
CN103195085B (en) Downward story-adding basement and construction method thereof
CN111519653A (en) Modular assembly type retaining wall and construction method thereof
CN106193292A (en) A kind of steel frame assembled integral reinforced concrete shear wall structure system
CN108547311A (en) Isolated footing under a kind of prefabricated assembled profile steel concrete column
CN103174231B (en) Hybrid controlled damping structure construction method
CN216109028U (en) Profile steel connecting structure of precast concrete tubular pile node
CN110656657A (en) Compressor foundation bolt installation method
CN203200745U (en) Underground continuous wall's reinforcement support in reverse construction method construction
CN218060773U (en) Steel construction column foot shear key mounting structure
CN112212135A (en) Horizontal adjustable support structure for loading hole module of reaction force pedestal and construction method thereof
CN115305833B (en) Cap beam construction system and method
CN207700746U (en) The upper buttress of existing building base isolation reinforcement constructs
CN101666069A (en) Construction technology for stretching notch by cast-in-situ prestress box beam
CN214399425U (en) Newly-increased double-elevator supporting structure for reconstruction and extension project
CN101886370B (en) Steel massive pillar beam for bridge pier
CN108978854A (en) One kind being bolted Precast Concrete Frame
CN109518942B (en) Tool-based bracket system for controlling precision of two-dimensional component and application method thereof
CN116516983B (en) Tide-affected steel-concrete combined inner support for deep foundation pit in river and construction method
CN115162697B (en) Special-shaped column construction work I-shaped steel cantilever platform and construction method
CN107806252A (en) The upper buttress construction and its construction method of existing building base isolation reinforcement
CN107795144A (en) The underpinning structure and underpinning construction method of existing building base isolation reinforcement
CN113585278B (en) Variable-rigidity high-adaptability combined inner support
CN207406032U (en) The underpinning structure of existing building base isolation reinforcement
CN211257760U (en) A triangular support device for cantilevered scaffolding

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: No.185, Zhujiang Road, Xuanwu District, Nanjing City, Jiangsu Province, 210000

Patentee after: Nanjing Fenzhen Construction Technology Co.,Ltd.

Address before: No.185, Zhujiang Road, Xuanwu District, Nanjing City, Jiangsu Province, 210000

Patentee before: NANJING BAIXISI BUILDING TECHNOLOGY CO.,LTD.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20250829

Address after: Room 1812, 99 Xinanjiang Street, Jianye District, Nanjing, Jiangsu Province, 210000 (CBD)

Patentee after: KENING ENGINEERING SCIENCE AND TECHNOLOGY (NANJING) Co.,Ltd.

Country or region after: China

Address before: No.185, Zhujiang Road, Xuanwu District, Nanjing City, Jiangsu Province, 210000

Patentee before: Nanjing Fenzhen Construction Technology Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right