CN107704931A - A kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation - Google Patents

A kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation Download PDF

Info

Publication number
CN107704931A
CN107704931A CN201710549025.0A CN201710549025A CN107704931A CN 107704931 A CN107704931 A CN 107704931A CN 201710549025 A CN201710549025 A CN 201710549025A CN 107704931 A CN107704931 A CN 107704931A
Authority
CN
China
Prior art keywords
maintenance
equipment
fault
approval
responsible
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710549025.0A
Other languages
Chinese (zh)
Inventor
沈曙明
徐永进
李熊
周永佳
殷杰
戴磊华
徐世予
李舜
宋磊
丁徐楠
胡书红
唐迪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of State Grid Zhejiang Electric Power Co Ltd
Zhejiang Huayun Information Technology Co Ltd
Original Assignee
Electric Power Research Institute of State Grid Zhejiang Electric Power Co Ltd
Zhejiang Huayun Information Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of State Grid Zhejiang Electric Power Co Ltd, Zhejiang Huayun Information Technology Co Ltd filed Critical Electric Power Research Institute of State Grid Zhejiang Electric Power Co Ltd
Priority to CN201710549025.0A priority Critical patent/CN107704931A/en
Publication of CN107704931A publication Critical patent/CN107704931A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation, is related to equipment fault closed-loop process method.In the past, in everyday devices maintenance work, the responsibility obscure boundary between multiple professional posts is clear, and the trouble ticket dispatch in multi-disciplinary post is mainly carried out by line under type, and O&M is inefficient and can not carry out effectively tracking and management and control.The present invention builds from fault discovery, analysis according to each work group post and responsibility for participating in equipment O&M, sends work, maintenance to be implemented, the closed loop management flow of field maintenance feedback;Equipment fault closed-loop process method includes the monitoring step being responsible for by monitoring personnel, the O&M step being responsible for by operation maintenance personnel, the fault handling steps being responsible for by expert, the examination & approval step being responsible for by sole duty.The technical program structure metering fully-automatic production system everyday devices O&M closed loop management flow, the Intelligent closed-loop that the work cooperative achievement by participating in each each post of specialty of everyday devices O&M is precisely found from failure, science diagnosis is repaired to agility.

Description

A kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation
Technical field
The present invention relates to equipment fault closed-loop process method, more particularly to a kind of it is used to measure setting for fully-automatic production operation Standby failure closed-loop process method.
Background technology
Measure fully-automatic production operating system, integrate intelligent storage, automatic Verification, it is unified dispense continuously run it is comprehensive Conjunction property mass automatic production operating system, as the construction of the production operation system so extensive, complexity is high is completed, Daily equipment maintenance work is more and more important.The working contents of everyday devices O&M include equipment routing inspection, equipment fault Processing and the maintenance of intelligent operation platform main website etc., the O&M main body being related to include main business personnel, outer committee's unit etc., wherein main business Personnel include the personnel in multiple multiple posies of specialty such as operation room, calibrating room, Material Distribution Room, and outer committee personnel are mainly responsible for including producer The personnel in multiple posies such as people, producer's monitoring personnel, producer's operation maintenance personnel.In the past, in everyday devices maintenance work, Duo Gezhuan Responsibility obscure boundary between industry post is clear, and the trouble ticket dispatch in multi-disciplinary post is mainly carried out by line under type, O&M efficiency It is not high and can not carry out effectively tracking and management and control.
The content of the invention
The technical problem to be solved in the present invention and the technical assignment proposed are prior art to be improved with being improved, A kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation is provided, to reach the efficiency of lifting maintenance work And the purpose of quality.Therefore, the present invention takes following technical scheme.
A kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation, according to each of participation equipment O&M Individual work group post and responsibility, build from fault discovery, analysis, send work, maintenance to be implemented, the closed loop management stream of field maintenance feedback Journey;Equipment fault closed-loop process method include be responsible for by monitoring personnel monitoring step, be responsible for by operation maintenance personnel O&M step, The fault handling steps being responsible for by expert, the examination & approval step being responsible for by sole duty;
In monitoring step, when failure main website report or failure artificially find after, check main website receive equipment fault whether be Wrong report, wrong report are then directly filed;After failure is defined as, remote analysis positioning failure cause, and attempt to carry out artificial long-range place Reason, file after remote processing success and fault recovery;When remote analysis processing can not make fault recovery, it is judged as needing scene The failure of processing, carry out work order and send work;When remote analysis processing made fault recovery when, judge reparation verify whether by, if By the way that then fault ticket is filed;When repair checking not over when, into O&M step;
In O&M step, scene is analyzed and processed, when processing completion, monitoring step is fed back to, fault ticket is carried out Filing;Otherwise judge whether equipment has repaired, if without maintenance of equipment, maintenance application, if equipment has been repaired, be transferred to difficulty Flow;When examination & approval step issues field maintenance task, field maintenance is carried out, judges whether equipment needs to change, when equipment needs During replacing, approval request is changed to examination & approval step initiating equipment, when equipment is without changing, and repairs failure, to examination & approval step Initiate extension approval request;
In fault handling steps, when O&M step initiates difficult flow, difficult tripartite's consultation of doctors, generation consultation of doctors information point are carried out Analyse and collect feedback;Applied implementing maintenance according to maintenance, breakdown maintenance is classified and optimizes defect elimination class, while by failure by maintenance Planned time makes a distinction to be responsible for initiating different approval requests with corresponding to full-time;
In step is examined, examined according to maintenance approval request.
The technical program is built multi-disciplinary by clearly participating in tissue, post and the responsibility of everyday devices maintenance work Slave unit fault discovery, analysis, work, maintenance is sent to be implemented, the closed loop management flow of field maintenance processing feedback.Lift maintenance work Efficiency and quality.
As further improving and supplementing to above-mentioned technical proposal, present invention additionally comprises following additional technical feature.
Examination & approval step is divided into department's sole duty approval process and department head's approval process, in fault handling steps, works as meter Maintenance time is drawn when being less than setting value, into department's sole duty approval process, when the planned maintenance time being more than setting value, into portion The full-time approval process of door.
Each work group post of equipment O&M and responsibility include:
Producer responsible person:It is responsible for overall arrangement during equipment fault maintenance.
Producer technical staff:It is responsible for analysis, solves the knotty problem of production system equipment O&M.
Producer's monitoring personnel:It is responsible for the equipment event that monitoring production system equipment fault and receiving device inspection are artificially found Barrier, is uniformly analyzed, sends work.
Producer's operation maintenance personnel:It is responsible for scene investigation and the processing of equipment fault, and feedback processing result.
Department is full-time:The examination & approval control for being responsible for equipment fault maintenance application entirely repairs progress.
Department head:The examination & approval for being responsible for equipment fault maintenance application or the examination & approval control for repairing extension request are entirely repaired Progress;The examination & approval of equipment replacement application.
Closed loop management flow comprises the following steps:
1) it is to be confirmed:Check that main website receives whether equipment fault is wrong report, wrong report is then directly filed;
2) remote analysis is handled:Remote analysis positions failure cause and attempting and carries out artificial remote processing, remote processing success and File after fault recovery;
3) work is sent:Failure for needing in-situ processing, carry out work order and send work;
4) field assay is handled:Knowledge base according to existing structure instructs equipment fault occurrence cause, actual treatment means to go forward side by side Row feedback;
5) maintenance application:Maintenance application is carried out if field assay needs maintenance of equipment to solve failure;
6) maintenance is implemented:Maintenance program, planned maintenance time and maintenance points for attention are confirmed according to field condition;
7) maintenance examination & approval:The maintenance program proposed to producer is examined;
8) equipment replacement is handled:Intelligent operation platform service class equipment replacement management is then quoted if necessary to change device hardware;
9) knotty problem is handled:It is difficult that intelligent operation platform service class is quoted if it can not repair and repair with live operation maintenance personnel Fault management assists Resolving probiems
10) extension request:Can not as scheduled be solved in original plan time range content, carry out extension request;
11) maintenance delays to examine:It is proposed that the actual cause that maintenance is delayed is checked and examined to producer;
Result verifies:By corresponding production system checking treatment result after troubleshooting.
Beneficial effect:The present invention combines mobile job-oriented terminal APP, constructs metering fully-automatic production system everyday devices fortune Closed loop management flow is tieed up, the work cooperative achievement by participating in each each post of specialty of everyday devices O&M precisely finds from failure, Intelligent closed-loop of the science diagnosis to quick reparation.Metering fully-automatic production operation system is included by current each special information system System, turn-key system, intelligent operation platform system it is integrated, the work order that will circulate under original each post line is unified to carrying out on line, On the one hand across post cooperative ability is improved, improves the operating efficiency of daily O&M;On the other hand improve to daily O&M The management and control ability of work, be finally reached the daily O&M quality of lifting, support metering fully-automatic production operating system it is stable, it is reliable, The purpose of Effec-tive Function.
Brief description of the drawings
Fig. 1 is flow chart of the present invention.
Fig. 2 is closed-loop process flow chart of the present invention.
Embodiment
Technical scheme is described in further detail below in conjunction with Figure of description.
As shown in figure 1, the present invention according to participate in equipment O&M each work group post and responsibility, build from fault discovery, Analysis, work, maintenance is sent to be implemented, the closed loop management flow of field maintenance feedback;Equipment fault closed-loop process method is included by monitoring It is monitoring step that personnel are responsible for, the O&M step being responsible for by operation maintenance personnel, the fault handling steps being responsible for by expert, negative by sole duty The examination & approval step of duty;
In monitoring step, when failure main website report or failure artificially find after, check main website receive equipment fault whether be Wrong report, wrong report are then directly filed;After failure is defined as, remote analysis positioning failure cause, and attempt to carry out artificial long-range place Reason, file after remote processing success and fault recovery;When remote analysis processing can not make fault recovery, it is judged as needing scene The failure of processing, carry out work order and send work;When remote analysis processing made fault recovery when, judge reparation verify whether by, if By the way that then fault ticket is filed;When repair checking not over when, into O&M step;
In O&M step, scene is analyzed and processed, when processing completion, monitoring step is fed back to, fault ticket is carried out Filing;Otherwise judge whether equipment has repaired, if without maintenance of equipment, maintenance application, if equipment has been repaired, be transferred to difficulty Flow;When examination & approval step issues field maintenance task, field maintenance is carried out, judges whether equipment needs to change, when equipment needs During replacing, approval request is changed to examination & approval step initiating equipment, when equipment is without changing, and repairs failure, to examination & approval step Initiate extension approval request;
In fault handling steps, when O&M step initiates difficult flow, difficult tripartite's consultation of doctors, generation consultation of doctors information point are carried out Analyse and collect feedback;Applied implementing maintenance according to maintenance, breakdown maintenance is classified and optimizes defect elimination class, while by failure by maintenance Planned time makes a distinction to be responsible for initiating different approval requests with corresponding to full-time;
In step is examined, examined according to maintenance approval request.
The technical program is built multi-disciplinary by clearly participating in tissue, post and the responsibility of everyday devices maintenance work Slave unit fault discovery, analysis, work, maintenance is sent to be implemented, the closed loop management flow of field maintenance processing feedback.Lift maintenance work Efficiency and quality.
Examination & approval step is divided into department's sole duty approval process and department head's approval process, in fault handling steps, works as meter Maintenance time is drawn when being less than setting value, into department's sole duty approval process, when the planned maintenance time being more than setting value, into portion The full-time approval process of door.
Each work group post of equipment O&M and responsibility include:
Producer responsible person:It is responsible for overall arrangement during equipment fault maintenance.
Producer technical staff:It is responsible for analysis, solves the knotty problem of production system equipment O&M.
Producer's monitoring personnel:It is responsible for the equipment event that monitoring production system equipment fault and receiving device inspection are artificially found Barrier, is uniformly analyzed, sends work.
Producer's operation maintenance personnel:It is responsible for scene investigation and the processing of equipment fault, and feedback processing result.
Department is full-time:The examination & approval control for being responsible for equipment fault maintenance application entirely repairs progress.
Department head:The examination & approval for being responsible for equipment fault maintenance application or the examination & approval control for repairing extension request are entirely repaired Progress;The examination & approval of equipment replacement application.
As shown in Fig. 2 closed loop management flow comprises the following steps:
1) it is to be confirmed:Check that main website receives whether equipment fault is wrong report, wrong report is then directly filed;
2) remote analysis is handled:Remote analysis positions failure cause and attempting and carries out artificial remote processing, remote processing success and File after fault recovery;
3) work is sent:Failure for needing in-situ processing, carry out work order and send work;
4) field assay is handled:Knowledge base according to existing structure instructs equipment fault occurrence cause, actual treatment means to go forward side by side Row feedback;
5) maintenance application:Maintenance application is carried out if field assay needs maintenance of equipment to solve failure;
6) maintenance is implemented:Maintenance program, planned maintenance time and maintenance points for attention are confirmed according to field condition;
7) maintenance examination & approval:The maintenance program proposed to producer is examined;
8) equipment replacement is handled:Intelligent operation platform service class equipment replacement management is then quoted if necessary to change device hardware;
9) knotty problem is handled:It is difficult that intelligent operation platform service class is quoted if it can not repair and repair with live operation maintenance personnel Fault management assists Resolving probiems
10) extension request:Can not as scheduled be solved in original plan time range content, carry out extension request;
11) maintenance delays to examine:It is proposed that the actual cause that maintenance is delayed is checked and examined to producer;
12) result verifies:By corresponding production system checking treatment result after troubleshooting.
Figure 1 above, a kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation shown in 2 are this hairs Bright specific embodiment, substantive distinguishing features of the present invention and progress are embodied, can be according to the use needs of reality, in the present invention Enlightenment under, carry out the equivalent modifications of shape, structure etc. to it, this programme protection domain row.

Claims (4)

  1. A kind of 1. equipment fault closed-loop process method for being used to measure fully-automatic production operation, it is characterised in that:Set according to participation Received shipment dimension each work group post and responsibility, build from fault discovery, analysis, send work, maintenance implement, field maintenance feed back close Ring management process;Monitoring step that equipment fault closed-loop process method includes being responsible for by monitoring personnel, it is responsible for by operation maintenance personnel O&M step, the fault handling steps being responsible for by expert, the examination & approval step being responsible for by sole duty;
    In monitoring step, when failure main website report or failure artificially find after, check main website receive equipment fault whether be Wrong report, wrong report are then directly filed;After failure is defined as, remote analysis positioning failure cause, and attempt to carry out artificial long-range place Reason, file after remote processing success and fault recovery;When remote analysis processing can not make fault recovery, it is judged as needing scene The failure of processing, carry out work order and send work;When remote analysis processing made fault recovery when, judge reparation verify whether by, if By the way that then fault ticket is filed;When repair checking not over when, into O&M step;
    In O&M step, scene is analyzed and processed, when processing completion, monitoring step is fed back to, fault ticket is carried out Filing;Otherwise judge whether equipment has repaired, if without maintenance of equipment, maintenance application, if equipment has been repaired, be transferred to difficulty Flow;When examination & approval step issues field maintenance task, field maintenance is carried out, judges whether equipment needs to change, when equipment needs During replacing, approval request is changed to examination & approval step initiating equipment, when equipment is without changing, and repairs failure, to examination & approval step Initiate extension approval request;
    In fault handling steps, when O&M step initiates difficult flow, difficult tripartite's consultation of doctors, generation consultation of doctors information point are carried out Analyse and collect feedback;Applied implementing maintenance according to maintenance, breakdown maintenance is classified and optimizes defect elimination class, while by failure by maintenance Planned time makes a distinction to be responsible for initiating different approval requests with corresponding to full-time;
    In step is examined, examined according to maintenance approval request.
  2. 2. a kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation according to claim 1, its It is characterised by:Examination & approval step is divided into department's sole duty approval process and department head's approval process, in fault handling steps, works as meter Maintenance time is drawn when being less than setting value, into department's sole duty approval process, when the planned maintenance time being more than setting value, into portion The full-time approval process of door.
  3. 3. a kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation according to claim 2, its It is characterised by:Each work group post of equipment O&M and responsibility include:
    Producer responsible person:It is responsible for overall arrangement during equipment fault maintenance;
    Producer technical staff:It is responsible for analysis, solves the knotty problem of production system equipment O&M;
    Producer's monitoring personnel:It is responsible for the equipment fault that monitoring production system equipment fault and receiving device inspection are artificially found, system One is analyzed, sends work;
    Producer's operation maintenance personnel:It is responsible for scene investigation and the processing of equipment fault, and feedback processing result;
    Department is full-time:The examination & approval control for being responsible for equipment fault maintenance application entirely repairs progress;
    Department head:Be responsible for equipment fault maintenance application examination & approval or repair extension request examination & approval control entirely repair into Degree;The examination & approval of equipment replacement application.
  4. 4. a kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation according to claim 3, its It is characterised by:Closed loop management flow comprises the following steps:
    1) it is to be confirmed:Check that main website receives whether equipment fault is wrong report, wrong report is then directly filed;
    2) remote analysis is handled:Remote analysis positions failure cause and attempting and carries out artificial remote processing, remote processing success and File after fault recovery;
    3) work is sent:Failure for needing in-situ processing, carry out work order and send work;
    4) field assay is handled:Knowledge base according to existing structure instructs equipment fault occurrence cause, actual treatment means to go forward side by side Row feedback;
    5) maintenance application:Maintenance application is carried out if field assay needs maintenance of equipment to solve failure;
    6) maintenance is implemented:Maintenance program, planned maintenance time and maintenance points for attention are confirmed according to field condition;
    7) maintenance examination & approval:The maintenance program proposed to producer is examined;
    8) equipment replacement is handled:Intelligent operation platform service class equipment replacement management is then quoted if necessary to change device hardware;
    9) knotty problem is handled:It is difficult that intelligent operation platform service class is quoted if it can not repair and repair with live operation maintenance personnel Fault management assists Resolving probiems
    10) extension request:Can not as scheduled be solved in original plan time range content, carry out extension request;
    11) maintenance delays to examine:It is proposed that the actual cause that maintenance is delayed is checked and examined to producer;
    12) result verifies:By corresponding production system checking treatment result after troubleshooting.
CN201710549025.0A 2017-07-07 2017-07-07 A kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation Pending CN107704931A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710549025.0A CN107704931A (en) 2017-07-07 2017-07-07 A kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710549025.0A CN107704931A (en) 2017-07-07 2017-07-07 A kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation

Publications (1)

Publication Number Publication Date
CN107704931A true CN107704931A (en) 2018-02-16

Family

ID=61170607

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710549025.0A Pending CN107704931A (en) 2017-07-07 2017-07-07 A kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation

Country Status (1)

Country Link
CN (1) CN107704931A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109325601A (en) * 2018-08-21 2019-02-12 国网江苏省电力有限公司泰州供电分公司 Logistics equipment malfunction monitoring operation management method
CN109389293A (en) * 2018-09-20 2019-02-26 国网天津市电力公司电力科学研究院 A kind of remote recharge method for upgrading success rate based on acquisition closed loop management
CN110648085A (en) * 2019-10-30 2020-01-03 新奥数能科技有限公司 Operation and maintenance method and system for comprehensive energy park
CN111915127A (en) * 2020-06-17 2020-11-10 成都美迅检测设备有限公司 Equipment monitoring method and device, electronic equipment and storage medium
CN112346415A (en) * 2020-09-29 2021-02-09 江苏南高智能装备创新中心有限公司 Workshop information physical monitoring management system
CN113361722A (en) * 2020-03-06 2021-09-07 华晨宝马汽车有限公司 Method and device for assisting in solving production equipment fault and storage medium
CN113807805A (en) * 2021-08-13 2021-12-17 重庆川仪调节阀有限公司 On-line processing method for abnormal parts in valve assembly

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100094676A1 (en) * 2008-10-10 2010-04-15 Bowe Bell + Howell Company Closed loop self corrective maintenance within a document processing environment
CN104394020A (en) * 2014-12-04 2015-03-04 国家电网公司 Automatic fault processing and safety control system and method for power information collection device
CN104573914A (en) * 2014-12-05 2015-04-29 国家电网公司 Gateway measurement acquisition and operation maintenance management system and application thereof
CN105868876A (en) * 2015-01-21 2016-08-17 国家电网公司 Centralized operation and maintenance fault closed-loop processing method based on process monitoring
CN106096741A (en) * 2016-06-14 2016-11-09 国电南瑞科技股份有限公司 A kind of implementation method of Intelligent fault O&M DSS

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100094676A1 (en) * 2008-10-10 2010-04-15 Bowe Bell + Howell Company Closed loop self corrective maintenance within a document processing environment
CN104394020A (en) * 2014-12-04 2015-03-04 国家电网公司 Automatic fault processing and safety control system and method for power information collection device
CN104573914A (en) * 2014-12-05 2015-04-29 国家电网公司 Gateway measurement acquisition and operation maintenance management system and application thereof
CN105868876A (en) * 2015-01-21 2016-08-17 国家电网公司 Centralized operation and maintenance fault closed-loop processing method based on process monitoring
CN106096741A (en) * 2016-06-14 2016-11-09 国电南瑞科技股份有限公司 A kind of implementation method of Intelligent fault O&M DSS

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
韩霄汉等: "计量全自动作业智能运维平台的研发与应用", 《华东科技:学术版》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109325601A (en) * 2018-08-21 2019-02-12 国网江苏省电力有限公司泰州供电分公司 Logistics equipment malfunction monitoring operation management method
CN109325601B (en) * 2018-08-21 2022-05-06 国网江苏省电力有限公司泰州供电分公司 Logistics equipment fault monitoring operation and maintenance management method
CN109389293A (en) * 2018-09-20 2019-02-26 国网天津市电力公司电力科学研究院 A kind of remote recharge method for upgrading success rate based on acquisition closed loop management
CN110648085A (en) * 2019-10-30 2020-01-03 新奥数能科技有限公司 Operation and maintenance method and system for comprehensive energy park
CN110648085B (en) * 2019-10-30 2022-04-29 新奥数能科技有限公司 Operation and maintenance method and system for comprehensive energy park
CN113361722A (en) * 2020-03-06 2021-09-07 华晨宝马汽车有限公司 Method and device for assisting in solving production equipment fault and storage medium
CN113361722B (en) * 2020-03-06 2024-05-31 华晨宝马汽车有限公司 Method and device for assisting in solving production equipment faults and storage medium
CN111915127A (en) * 2020-06-17 2020-11-10 成都美迅检测设备有限公司 Equipment monitoring method and device, electronic equipment and storage medium
CN112346415A (en) * 2020-09-29 2021-02-09 江苏南高智能装备创新中心有限公司 Workshop information physical monitoring management system
CN112346415B (en) * 2020-09-29 2021-10-15 江苏南高智能装备创新中心有限公司 Workshop information physical monitoring management system
CN113807805A (en) * 2021-08-13 2021-12-17 重庆川仪调节阀有限公司 On-line processing method for abnormal parts in valve assembly

Similar Documents

Publication Publication Date Title
CN107704931A (en) A kind of equipment fault closed-loop process method for being used to measure fully-automatic production operation
CN110009525A (en) Power information acquisition system and application method
CN107688893A (en) One kind measures abnormal closed-loop process method
CN107392495A (en) A kind of acquisition abnormity closed-loop process method based on multi-specialized more post collaborations
CN106707988A (en) MES system for engine online assembly control
CN103279063B (en) It is applicable to the detection error-preventing method of electronic part production line
CN102682361A (en) Elevator maintenance managing system and method
CN110989413A (en) Rail transit electromechanical equipment operation and maintenance management method based on mobile equipment
CN109709940A (en) A kind of real-time O&M resource sharing system and its O&M method based on Internet of Things
CN106681143B (en) A kind of adjustment method of the automation equipment based on cloud platform
CN109064140A (en) Internet of things equipment operation management system
CN110084485B (en) Park-associated enterprise incubation management method
CN109034404A (en) A kind of thermal power plant's multi-person synergy examination and repair system based on AR glasses, method and a kind of AR glasses
CN111222756A (en) Construction quality supervision method in engineering supervision
CN110378273A (en) A kind of method and apparatus of monitoring results process
CN106022582A (en) Work order control system service automatic analyzing and processing method and system
CN103679333A (en) Workflow-based quick response system and application thereof
CN109150653A (en) Remote hardware-in-loop HIL (hardware in loop) automatic testing method and system
CN117114359A (en) Electric power metering operation safety on-line monitoring system and method thereof
CN110266811B (en) Workshop abnormal information pushing device and method based on MQTT technology
WO2021018741A1 (en) Method and device for planning maintenance on at least one machine
CN115566803B (en) Line fault tracing method and system
CN110531718A (en) The method for inspecting and cruising inspection system of equipment in a kind of petrochemical industry production line
CN115086391A (en) Fault expert system based on wearable distribution network inspection equipment and use method thereof
CN109676297A (en) Multi-vehicle-type mixed production solder joint information management system and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180216