CN107657677A - Substation inspection monitoring method, device and electronic equipment - Google Patents

Substation inspection monitoring method, device and electronic equipment Download PDF

Info

Publication number
CN107657677A
CN107657677A CN201710830184.8A CN201710830184A CN107657677A CN 107657677 A CN107657677 A CN 107657677A CN 201710830184 A CN201710830184 A CN 201710830184A CN 107657677 A CN107657677 A CN 107657677A
Authority
CN
China
Prior art keywords
tour
information
inspection
numbering
inspection terminal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710830184.8A
Other languages
Chinese (zh)
Other versions
CN107657677B (en
Inventor
郑灿涛
蔚科
徐宝辉
郭宏宇
高梦彤
董聪
李德荣
周莉
郭兵
张超
王正顺
欧庆满
何卫国
胡凤
马萧萧
郭庆军
张华�
袁树民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenshang Power Supply Co Of State Grid Shandong Electric Power Co
State Grid Corp of China SGCC
Original Assignee
Wenshang Power Supply Co Of State Grid Shandong Electric Power Co
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenshang Power Supply Co Of State Grid Shandong Electric Power Co, State Grid Corp of China SGCC filed Critical Wenshang Power Supply Co Of State Grid Shandong Electric Power Co
Priority to CN201710830184.8A priority Critical patent/CN107657677B/en
Publication of CN107657677A publication Critical patent/CN107657677A/en
Application granted granted Critical
Publication of CN107657677B publication Critical patent/CN107657677B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C1/00Registering, indicating or recording the time of events or elapsed time, e.g. time-recorders for work people
    • G07C1/20Checking timed patrols, e.g. of watchman
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C9/00Individual registration on entry or exit
    • G07C9/30Individual registration on entry or exit not involving the use of a pass
    • G07C9/32Individual registration on entry or exit not involving the use of a pass in combination with an identity check

Abstract

The invention provides a kind of substation inspection monitoring method, device and electronic equipment, the substation inspection monitoring method includes:Judge whether the authentication information that tour personnel is sent by entrance guard device meets authentication condition, if so, then sending open command to entrance guard device;Send the inspection terminal that visit program corresponding with job code carries to tour personnel;Each typing list corresponding to each work of transformer substation room that real-time reception inspection terminal is submitted, and judge whether the numbering of each typing list and the numbering that prestores correspond;If it is not, the 2 D code information that then real-time reception inspection terminal is sent;Corresponding blank typing list is sent to inspection terminal according to 2 D code information;If so, task completion notice and navigation way are then sent to inspection terminal.Substation inspection monitoring method, device and electronic equipment provided by the invention, alleviate existing for existing substation inspection monitoring method because monitoring is not in place, cause to make an inspection tour ropy problem.

Description

Substation inspection monitoring method, device and electronic equipment
Technical field
The present invention relates to power system transformer substation technical field, more particularly, to a kind of substation inspection monitoring method, dress Put and electronic equipment.
Background technology
Transformer station is the place for changing voltage, in order to the electrical energy transportation that power plant issues to place farther out, it is necessary to Voltage is raised, is changed into high-tension electricity, nearby voltage is reduced on demand again to user, transformer station is leaned in the work of this buck/boost To complete.
In recent years, power network is constantly receiving industrialization, information-based achievement, and all kinds of new technologies, new material are New Generation of Intelligent Transformer station's technological change provides technical foundation, and New Generation of Intelligent transformer station is the only way of transformer station's scientific research and innovation.With The popularization of automation is communicated, increasing advanced technology is applied to transformer station, and the intelligent management of transformer station has brought up to one Individual new level.
Many transformer stations have been equipped with unattended condition at present, only need to carry out regularly night watching.This requires to patrol Walkaround inspection periodically is carried out to each work of transformer substation room in transformer station region depending on personnel, parameter note is carried out to each equipment Record.Because tour process is unable to effective monitoring, and the subjective questions such as the sense of responsibility of tour personnel, working attitude drastically influence and patrol Apparent mass, therefore often there are the bad phenomenons such as make an inspection tour unclear Standard Memory, equipment missing inspection or do not examine, arbitrarily deal with.
It follows that existing substation inspection monitoring method there is not in place due to monitoring, causes to make an inspection tour of poor quality The problem of.
The content of the invention
In view of this, it is an object of the invention to provide a kind of substation inspection monitoring method, device and electronic equipment, with The overall monitor to making an inspection tour process is realized, and then improves and makes an inspection tour quality.
In a first aspect, the embodiments of the invention provide a kind of substation inspection monitoring method, applied to cloud management platform, bag Include:
The authentication information that tour personnel is sent by entrance guard device is received, the authentication information includes authentication password and work Numbering;
Judge whether the authentication information meets authentication condition, if so, then send open command to the entrance guard device with The tour personnel is set to enter transformer station region;
Send the inspection terminal that visit program corresponding with the job code carries to the tour personnel, the tour Plan includes patrol route, and the numbering of each work of transformer substation room of tour in need and each change are marked in the patrol route The position of power station operating room;
Each typing list corresponding to each work of transformer substation room that inspection terminal described in real-time reception is submitted, and judge each Whether the numbering of the typing list corresponds with the numbering that prestores;
If it is not, the position of next work of transformer substation room for needing to make an inspection tour then is indicated in the patrol route, and in real time The 2 D code information that the inspection terminal is sent is received, wherein the 2 D code information is by described in inspection terminal scanning What the Quick Response Code in work of transformer substation room generated;
Corresponding blank typing list is sent to the inspection terminal according to the 2 D code information, so that the inspection terminal Described in corresponding tour personnel's typing in work of transformer substation room all equipment to be checked parameter information, wherein the blank typing list Including parameter name corresponding to each device numbering to be checked, each equipment to be checked and make an inspection tour points for attention;
If so, task completion notice and navigation way are then sent to the inspection terminal, so that the tour personnel makes an inspection tour After the completion of, leave the transformer station region according to the navigation way.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the first of first aspect, wherein, institute Stating authentication password includes static password and dynamic password, wherein the static password is the default password of the tour personnel;
Before the authentication information for receiving tour personnel and being sent by entrance guard device, in addition to:
The unlatching request that the inspection terminal that tour personnel carries is sent is received, the unlatching request carries job code;
According to the request transmission dynamic password of opening to the inspection terminal.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of second of first aspect, wherein, institute State and judge whether the authentication information meets that authentication condition includes:
Judge whether tour personnel has tour task at current time corresponding to the job code;
If so, then judge whether the authentication password is correct;
If, it is determined that the authentication information meets the authentication condition.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the third of first aspect, wherein, also Including:
Position of the tour personnel in the transformer station region, and real-time storage positional information are monitored in real time;
When listening to the tour personnel and being in danger zone, the inspection for sending hint instructions to the tour personnel is whole End;
When listening to the tour personnel and leaving the transformer station region, patrolled according to the generation of the positional information of storage Depending on the tour track of personnel;
The tour track is preserved to tour in recording.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the 4th of first aspect kind, wherein, also Including:
According to preparatory condition, it is determined whether distribute tour task or renewal distributes the cycle, the preparatory condition includes behaviour Trigger, failure triggering, preset time triggering, weather triggering, load boom period triggering any of;
If the preparatory condition triggers for operation, instruction is distributed according to what monitoring personnel corresponding to cloud management platform was sent Tour task is distributed to corresponding inspection terminal;
If the preparatory condition triggers for failure, the alarm signal sent according to the warning device in the transformer station region Breath distributes tour task to corresponding inspection terminal;
If the preparatory condition triggers for preset time, judge whether current time is preset time;If so, then distribute Tour task is to corresponding inspection terminal;
If the preparatory condition triggers for weather, supervised online according to the microclimate in the transformer station region received Survey the Changes in weather information that device is sent and distribute tour task to corresponding inspection terminal;
If the preparatory condition triggers for load boom period, judge whether current time is in the failure multiple phase, if so, The cycle is distributed described in then shortening.
With reference to the 4th kind of possible embodiment of first aspect, the embodiments of the invention provide the 5th of first aspect kind Possible embodiment, wherein, numbering, failure of the warning message including at least the work of transformer substation room where faulty equipment Device numbering, current failure information;The tour task comprises at least mission planning information;
The warning message that the warning device according in the transformer station region is sent distributes tour task to corresponding Inspection terminal includes:
According to the current failure information, the historical failure information in fault message storehouse is traveled through;
To find with the current failure information identical historical failure information flag is similar fault message;
Extraction failure cause corresponding with the similar fault message, fault solution from the fault message storehouse;
According to the failure cause, the fault solution, the current failure information, mission planning information is generated;
It is non-inspection terminal corresponding to the tour personnel of state of turning out for work that the mission planning information, which is sent to working condition,.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the 6th of first aspect kind, wherein, also Including:
The related information of monitoring personnel input corresponding to cloud management platform is received, wherein the related information includes the change The numbering of power station operating room and the director corresponding with the numbering of work of transformer substation room numbering;
Obtain the collection letter that the harvester corresponding to the numbering of the work of transformer substation room in work of transformer substation room is sent Breath;
The collection information is periodically pushed into mobile terminal corresponding to director's numbering.
With reference to above-mentioned in a first aspect, the embodiments of the invention provide the possible embodiment of the 7th of first aspect kind, its In, in addition to:
When the personnel for listening to the transmission of the thermal infrared imager in the transformer station region enter information, current time is judged Whether it is tour time;
If it is not, alarm command is then sent to the alarm of cloud management platform, and the area entered according to the personnel in information Domain information, open corresponding camera device;
The shooting information of camera device shooting described in real-time reception simultaneously stores.
Second aspect, the embodiment of the present invention also provide a kind of substation inspection supervising device, including:
Certification receiving module, the authentication information sent for receiving tour personnel by entrance guard device, the authentication information Including authentication password and job code;
Condition judgment module, for judging whether the authentication information meets authentication condition;
Instruction sending module, for when the authentication information meets authentication condition, sending open command to the first gate inhibition Device is so that the tour personnel enters transformer station region;
Plan sending module, carried for transmission visit program corresponding with the job code to the tour personnel Inspection terminal, the visit program include patrol route, and each transformer station's work of tour in need is marked in the patrol route Make the numbering of room and the position of each work of transformer substation room;
Typing receiving module, for each corresponding to each work of transformer substation room of inspection terminal submission described in real-time reception Typing list, and judge whether the numbering of each typing list and the numbering that prestores correspond;
Make an inspection tour indicating module, for when each typing list numbering with it is described prestore number non-one-to-one corresponding when, The position of next work of transformer substation room for needing to make an inspection tour is indicated in the patrol route, and inspection terminal described in real-time reception is sent out The 2 D code information sent, wherein the 2 D code information is that two in the work of transformer substation room are scanned by the inspection terminal Tie up code generation;
Typing sending module, the 2 D code information for being sent according to the tour indicating module send corresponding empty White typing list is to the inspection terminal, so that institute in work of transformer substation room described in tour personnel's typing corresponding to the inspection terminal There is the parameter information of equipment to be checked, wherein the blank typing list includes each device numbering to be checked, each equipment to be checked Corresponding parameter name and tour points for attention;
Completion notice module, for when the numbering of each typing list corresponds with the numbering that prestores, sending Task completion notice and navigation way are to the inspection terminal, so that after the completion of the tour personnel makes an inspection tour, according to patrol route Leave the transformer station region.
The third aspect, the embodiment of the present invention also provide a kind of electronic equipment, including memory, processor, the memory On be stored with the computer program that can be run on the processor, described in the computing device during computer program realize on The step of stating the method described in first aspect.
The embodiment of the present invention brings following beneficial effect:
In embodiment provided by the invention, prevent unrelated person from entering area of transformer station by the judgement of authentication information first Domain;Then send and carry the visit program of patrol route to inspection terminal, so as to facilitating tour personnel according to patrol route and The numbering of each work of transformer substation room of mark in patrol route and the position of each work of transformer substation room carry out orderly patrol Look into, prevent tour personnel and take an unnecessary way, take a roundabout way, into danger zone and under-enumeration phenomenon;In addition, pass through the inspection received The 2 D code information that terminal is sent sends corresponding blank typing list to inspection terminal, and the blank typing list includes each to be checked set Parameter name corresponding to standby numbering, each equipment to be checked and tour points for attention, so ensure that tour personnel can accurately, entirely Face, safety each equipment in work of transformer substation room is checked and parameter typing, prevent make an inspection tour Standard Memory not Clearly, the phenomenon that equipment missing inspection, parameter are failed to report;Finally, when listen to inspection terminal submission each work of transformer substation room corresponding to When the numbering of each typing list and the numbering that prestores correspond, determine that tour personnel has been completed all tour tasks, send out Task completion notice and navigation way are sent to inspection terminal, so can prompt and guide tour personnel according to the navigation way from Transformer station region is opened, to prevent tour personnel from staying without reason or arbitrarily walk about and cause danger.Therefore change provided by the invention Monitoring method, device and electronic equipment are maked an inspection tour in power station, can realize the overall monitor to making an inspection tour process, and then improve and make an inspection tour matter Amount.
Other features and advantages of the present invention will illustrate in the following description, also, partly become from specification Obtain it is clear that or being understood by implementing the present invention.The purpose of the present invention and other advantages are in specification, claims And specifically noted structure is realized and obtained in accompanying drawing.
To enable the above objects, features and advantages of the present invention to become apparent, preferred embodiment cited below particularly, and coordinate Appended accompanying drawing, is described in detail below.
Brief description of the drawings
, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical scheme of the prior art The required accompanying drawing used is briefly described in embodiment or description of the prior art, it should be apparent that, in describing below Accompanying drawing is some embodiments of the present invention, for those of ordinary skill in the art, before creative work is not paid Put, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the schematic flow sheet of substation inspection monitoring method provided in an embodiment of the present invention;
Fig. 2 is the flow that collection information periodically pushes process in substation inspection monitoring method provided in an embodiment of the present invention Schematic diagram;
Fig. 3 is the schematic flow sheet of substation inspection supervising device provided in an embodiment of the present invention;
Fig. 4 is the structural representation of a kind of electronic equipment provided in an embodiment of the present invention.
Embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with accompanying drawing to the present invention Technical scheme be clearly and completely described, it is clear that described embodiment is part of the embodiment of the present invention, rather than Whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art are not making creative work premise Lower obtained every other embodiment, belongs to the scope of protection of the invention.
At present because tour process cannot get effective monitoring, and the subjective questions such as the sense of responsibility of tour personnel, working attitude It drastically influence tour quality, therefore it is bad often to occur that make an inspection tour unclear Standard Memory, equipment missing inspection or do not examine, arbitrarily deal with etc. Phenomenon, and then cause to make an inspection tour of poor quality.Based on this, a kind of substation inspection monitoring method provided in an embodiment of the present invention, device And electronic equipment, the overall monitor to making an inspection tour process can be realized, and then improve and make an inspection tour quality.
For ease of understanding the present embodiment, a kind of substation inspection disclosed in the embodiment of the present invention is monitored first Method describes in detail.
Embodiment one:
Fig. 1 shows the schematic flow sheet of substation inspection monitoring method provided in an embodiment of the present invention.As shown in figure 1, The substation inspection monitoring method is applied to cloud management platform, including:
Step S101, receive the authentication information that tour personnel is sent by entrance guard device.
Wherein, the authentication information includes authentication password and job code, and job code corresponds with tour personnel.Certification Password includes static password and dynamic password, and the static password is the default password of tour personnel, and is stored in cloud management platform. It can effectively prevent unrelated person from carrying the inspection terminal of tour personnel and entering transformer station region by static password.
Specifically, before the authentication information that tour personnel is sent by entrance guard device is received, in addition to:Receive perambulator The unlatching request that the inspection terminal that member carries is sent, unlatching request carry job code;Sent according to unlatching request dynamic State password is to the inspection terminal.Wherein inspection terminal can be Intelligent bracelet, mobile phone or other intelligent mobile terminals.
In one embodiment, when tour personnel reach transformer station region it is big behind the door, the inspection terminal for passing through carrying is sent out Open command is sent to cloud management platform, cloud management platform sends dynamic password to the inspection terminal after receiving the open command. The security logged in by setting dynamic password to ensure, without periodic modification password, effectively prevents password from stealing.
Further, tour personnel corresponding to inspection terminal is defeated by the dynamic password received and default static password Enter to entrance guard device, sent by the entrance guard device to cloud management platform.User can disposably input dynamic password and static state is close Code, can also be inputted at twice.
Step S102, judges whether above-mentioned authentication information meets authentication condition.
In one embodiment, step S102 includes:Judge tour personnel corresponding to above-mentioned job code when current Whether quarter has tour task;If so, then judge whether authentication password is correct;If, it is determined that authentication information meets the certification bar Part.
Specifically, arrange an order according to class and grade information of the cloud management platform in information bank on duty, judge to patrol corresponding to above-mentioned job code Whether have tour task at current time depending on personnel, wherein information of arranging an order according to class and grade include job code, it is on duty corresponding to job code when Between and visit program.If tour personnel has tour task at current time, judge entrance guard device send authentication information whether Correctly, determine that authentication information meets authentication condition if correct, perform step S103;If incorrect, send authentification failure and carry Show to inspection terminal corresponding to tour personnel.So by way of condition certification, can prevent non-tour personnel on duty with Just enter transformer station region, and then reduce fortuitous event.
Step S103, open command is sent to entrance guard device so that tour personnel enters transformer station region.
Specifically, entrance guard device opens gate according to the open command received, when tour personnel enters transformer station region Afterwards, gate is closed, and is recovered to locking states.
Step S104, send the inspection terminal that visit program corresponding with job code carries to tour personnel, the tour Plan includes patrol route, and the numbering of each work of transformer substation room of tour in need and each transformer station are marked in patrol route The position of operating room.
Wherein, visit program also includes tour time, that is, needs tour personnel as defined in visit program in tour time Complete the tour to transformer station region.
Specifically, the visit program for carrying patrol route is sent to inspection terminal, can facilitate tour personnel by patrolling Position depending on each work of transformer substation room of the mark in route and patrol route reaches each work of transformer substation room, and according to each The numbering of the operating room of individual transformer station carries out orderly inspection, prevents tour personnel and takes an unnecessary way, takes a roundabout way, into hazardous area Domain and under-enumeration phenomenon.
Step S105, each typing list corresponding to each work of transformer substation room that real-time reception inspection terminal is submitted, and sentence Whether the numbering of each typing list of breaking and the numbering that prestores correspond.
Wherein, typing list include each device numbering to be checked, parameter name corresponding to each equipment to be checked, parameter value and Points for attention are maked an inspection tour, what the parameter value recorded when being each equipment that tour personnel is maked an inspection tour in work of transformer substation room.It is above-mentioned to prestore Numbering can be in patrol route the numbering for each work of transformer substation room that the needs that mark be maked an inspection tour or prestore with it is each Number corresponding to the numbering of individual typing list, be not construed as limiting here.
Specifically, when the numbering of each typing list and the numbering that prestores correspond, determine that tour personnel completes tour Tour task in the works, perform step S108;When the numbering of each typing list and the numbering that prestores can not correspond, it is determined that Tour personnel does not complete the tour task in visit program, performs step S106, step S107 successively.
Step S106, indicates the position of next work of transformer substation room for needing to make an inspection tour in patrol route, and connects in real time The 2 D code information that inspection terminal is sent is received, wherein 2 D code information is that two in work of transformer substation room are scanned by inspection terminal Tie up code generation.
Specifically, it is whole using inspection after the instruction as tour personnel in patrol route enters work of transformer substation room The Quick Response Code in the work of transformer substation room is scanned at end, and generates 2 D code information.Wherein the 2 D code information carries transformer station Job code and barcode scanning time corresponding to the numbering of operating room, inspection terminal.
Step S107, corresponding blank typing list is sent to inspection terminal according to above-mentioned 2 D code information, so that the inspection Corresponding to terminal in tour personnel's typing work of transformer substation room all equipment to be checked parameter information.
Wherein, blank typing list include each device numbering to be checked, parameter name and tour corresponding to each equipment to be checked Points for attention.
After inspection terminal receives corresponding blank typing list, according to points for attention are maked an inspection tour, the tour of specification oneself operates, Then according to each device numbering, parameter name progress equipment inspection and typing parameter value to be checked, tour personnel's energy is so ensured It is enough accurate, comprehensively, safety each equipment in work of transformer substation room is checked and parameter typing, prevent tour mark The phenomenon that standard remembers unclear, equipment missing inspection, parameter is failed to report.
Step S108, task completion notice and navigation way are sent to inspection terminal, so that after the completion of tour personnel makes an inspection tour, Transformer station region is left according to navigation way.
When listening to the numbering of each typing list corresponding to each work of transformer substation room of inspection terminal submission and prestore volume When number corresponding, it is determined that tour personnel has been completed all tour tasks, sends task completion notice and navigation road Line so can prompt and guide tour personnel to leave transformer station region according to the navigation way, to prevent from patrolling to inspection terminal Stay without reason depending on personnel or arbitrarily walk about and cause danger.
In substation inspection monitoring method provided in an embodiment of the present invention, nothing is prevented by the judgement of authentication information first Pass personnel enter transformer station region;Then the visit program for carrying patrol route is sent to inspection terminal, is maked an inspection tour so as to convenient The numbering of each work of transformer substation room of mark of the personnel in patrol route and patrol route and each work of transformer substation room Position carry out orderly inspection, prevent tour personnel and take an unnecessary way, take a roundabout way, into danger zone and under-enumeration phenomenon;Separately Outside, the 2 D code information sent by the inspection terminal received sends corresponding blank typing list to inspection terminal, the blank Typing list includes each device numbering to be checked, parameter name corresponding to each equipment to be checked and makes an inspection tour points for attention, so guarantee Tour personnel can accurately, comprehensively, safety each equipment in work of transformer substation room is checked and parameter typing, prevent There is making an inspection tour the phenomenon that Standard Memory is unclear, equipment missing inspection, parameter are failed to report;Finally, when listen to inspection terminal submission it is each When the numbering of each typing list corresponding to work of transformer substation room and the numbering that prestores correspond, determine that tour personnel has been completed All tour tasks, task completion notice and navigation way are sent to inspection terminal, so can prompt and guide perambulator Member according to the navigation way leaves transformer station region, to prevent tour personnel from staying without reason or arbitrarily walk about and cause danger. Therefore substation inspection monitoring method provided by the invention, the overall monitor to making an inspection tour process can be realized, and then improves and make an inspection tour Quality.
In one embodiment, in order to further strengthen the monitoring to making an inspection tour process, prevent tour personnel in area of transformer station Arbitrarily walked about in domain and Danger Electric shock risk occurs or other power failures occurs, the above method also includes:Perambulator is monitored in real time Position of the member in transformer station region, and real-time storage positional information;When listening to tour personnel and being in danger zone, send Hint instructions to tour personnel inspection terminal;When listening to tour personnel and leaving the transformer station region, according to the position of storage Confidence breath generates the tour track of the tour personnel;The tour track is preserved to tour in recording.
Dangerous tip is carried out by the position for monitoring tour personnel, effectively can prevent tour personnel from causing danger;In addition, By record make an inspection tour track can further specification tour personnel tour behavior, prevent tour personnel from arbitrarily walking about, simultaneously ought When power failure occurs for transformer station region, to make an inspection tour track as according to the related specific power condition of tour personnel of inquiry.
Further, it is contemplated that existing inspection method is typically all periodically to prompt tour personnel to be maked an inspection tour, but is met To the special circumstances such as failure multiple phase such as bad weather, load summit stage, it is also necessary to notify step by step, wasting manpower and material resources.Base In this, substation inspection monitoring method provided in an embodiment of the present invention also includes:According to preparatory condition, it is determined whether distribute tour Task or renewal distribute the cycle, and the preparatory condition includes operation triggering, failure triggering, preset time triggering, weather triggering, negative Any of lotus peak period triggering.
If preparatory condition triggers for operation, distributed according to the instruction that distributes that monitoring personnel corresponding to cloud management platform is sent Tour task is to corresponding inspection terminal.I.e. corresponding monitoring personnel is issued by cloud management platform according to the input operation of oneself Tour task.
If preparatory condition triggers for failure, the warning message sent according to the warning device in transformer station region, which distributes, to patrol Depending on task to corresponding inspection terminal.Specifically, the warning message is including at least the work of transformer substation room where faulty equipment Numbering, faulty equipment numbering, current failure information;Tour task comprises at least mission planning information.
Further, the warning message that the above-mentioned warning device according in transformer station region is sent distributes tour task to right The inspection terminal answered includes:According to current failure information, the historical failure information in fault message storehouse is traveled through;To find with The information flag of current failure information identical historical failure is similar fault message;Extraction and similar failure from fault message storehouse Failure cause, fault solution corresponding to information;According to failure cause, fault solution, current failure information, generation is appointed Business planning information;The mission planning information is sent whole for non-inspection corresponding to the tour personnel of state of turning out for work to working condition End.So, maintenance can be timely performed after the tour personnel of corresponding non-state of turning out for work receives mission planning information to prepare, Actual maintenance program is quickly determined, solves the problems, such as power failure as early as possible.
If preparatory condition triggers for preset time, judge whether current time is preset time;If so, then distribute tour Task is to corresponding inspection terminal.Wherein, the preset time can be set by monitoring personnel, 8 a.m. such as on every Mondays, or 6 pm on every Saturdays.
If preparatory condition triggers for weather, according to the microclimate on-Line Monitor Device hair in the transformer station region received The Changes in weather information sent distributes tour task to corresponding inspection terminal.Such as, when weather change information is heavy rain, severe snow, big During wind, tour task is distributed to corresponding inspection terminal, so that tour personnel is maked an inspection tour corresponding to inspection terminal, is carried out in advance Bad weather prevention work;When showing that heavy rain stops in weather change information, the time stopped according to heavy rain distributes tour times Business, can so allow tour personnel to find power failure caused by heavy rain in time, and carry out respective handling, effectively reduce heavy rain band The loss come.
If preparatory condition triggers for load boom period, judge whether current time is in the failure multiple phase, if so, then contracting It is short to distribute the cycle.Specifically, the failure multiple phase can be set automatically according to electricity consumption data in history power information, or by monitoring Personnel are voluntarily set according to the judgement of oneself.
Further, in order that related take responsibility can in time, accurately, targetedly understand oneself responsible transformer station The running situation of each equipment in operating room, failure problems are found in time and are solved, as shown in Fig. 2 the embodiment of the present invention provides Substation inspection monitoring method also include:
Step S201, receive the related information of monitoring personnel input corresponding to cloud management platform.
Wherein the numbering of the related information including work of transformer substation room and corresponding with the numbering of work of transformer substation room bear Blame people's numbering.
Step S202, obtain adopting for the transmission of the harvester corresponding to the numbering of work of transformer substation room in work of transformer substation room Collect information.
Wherein, harvester includes location equipment, picture pick-up device, thermal infrared imager, Temperature Humidity Sensor and microclimate One or more in monitoring device.Gathering information includes location information, image information, Infrared Image Information, temperature and humidity value And the one or more in Weather information, in addition to convenient obtain collection letter corresponding with the numbering of work of transformer substation room Breath, gather the number information that the work of transformer substation room where harvester is also carried in information.
Step S203, above-mentioned collection information is periodically pushed into mobile terminal corresponding to director's numbering.
Specifically, can in the form of short message, in the form of mail, mobile terminal is sent in the form of numeric messaging, it is such as negative The mobile phone of responsibility, tablet personal computer etc..
Further, above-mentioned substation inspection monitoring method also includes:When listening to the infrared thermal imagery in transformer station region When the personnel that instrument is sent enter information, judge whether current time is tour time;If it is not, alarm command is then sent to cloud management The alarm of platform, and the area information entered according to above-noted persons in information, open corresponding camera device;Real-time reception should The shooting information of camera device shooting simultaneously stores.Then alarm, and taken the photograph into transformer station region in non-tour time someone Picture;Monitoring personnel sees if there is people according to shooting information view and arbitrarily swarms into transformer station's region progress illegal activities.So can and Shi Faxian unrelated persons arbitrarily swarm into transformer station region, prevent transformer station's theft, power failure from occurring, while when occurrence of equipment is stolen Surreptitiously, during the illegal activities such as destruction, above-mentioned shooting information can be investigated for case and provide foundation.
Embodiment two:
Fig. 3 shows the schematic flow sheet of substation inspection supervising device provided in an embodiment of the present invention.As shown in figure 3, The substation inspection supervising device includes:
Certification receiving module 11, the authentication information sent for receiving tour personnel by entrance guard device, the authentication information Including authentication password and job code;
Condition judgment module 12, for judging whether above-mentioned authentication information meets authentication condition;
Instruction sending module 13, for when the authentication information meets authentication condition, sending open command to the first gate inhibition Device is so that tour personnel enters transformer station region;
Plan sending module 14, the inspection end carried for sending visit program corresponding with job code to tour personnel End, the visit program includes patrol route, marked in patrol route each work of transformer substation room of tour in need numbering and The position of each work of transformer substation room;
Typing receiving module 15, each record corresponding to each work of transformer substation room submitted for real-time reception inspection terminal Enter list, and judge whether the numbering of each typing list and the numbering that prestores correspond;
Indicating module 16 is maked an inspection tour, for when the numbering of each typing list numbers non-one-to-one corresponding with prestoring, making an inspection tour road The position of next work of transformer substation room for needing to make an inspection tour, and the Quick Response Code letter that real-time reception inspection terminal is sent are indicated in line Breath, wherein 2 D code information are to scan the Quick Response Code in work of transformer substation room by inspection terminal to generate;
Typing sending module 17, for the corresponding blank record of 2 D code information transmission sent according to indicating module 16 is maked an inspection tour Enter it is single to inspection terminal so that corresponding to inspection terminal in tour personnel's typing work of transformer substation room all equipment to be checked parameter Information, wherein the blank typing list include each device numbering to be checked, parameter name corresponding to each equipment to be checked and make an inspection tour note Meaning item;
Completion notice module 18, for when the numbering of each typing list corresponds with the numbering that prestores, it is complete to send task Into notice and navigation way to inspection terminal, so that after the completion of personnel make an inspection tour, transformer station region is left according to patrol route.
In substation inspection supervising device provided in an embodiment of the present invention, condition judgment module 12 passes through authentication information Judgement prevents unrelated person from entering transformer station region;Plan sending module 14, which is sent, carries the visit program of patrol route to patrolling Terminal is examined, so as to facilitate the numbering of each work of transformer substation room of mark of the tour personnel in patrol route and patrol route And the position of each work of transformer substation room carries out orderly inspection, prevent tour personnel and take an unnecessary way, take a roundabout way, into danger Region and under-enumeration phenomenon;In addition, the 2 D code information that typing sending module 17 is sent by the inspection terminal received sends phase For the blank typing list answered to inspection terminal, the blank typing list includes each device numbering to be checked, corresponding to each equipment to be checked Parameter name and make an inspection tour points for attention, so ensure tour personnel can accurately, it is comprehensive, safe in work of transformer substation room Each equipment is checked and parameter typing, prevents the phenomenon for making an inspection tour that Standard Memory is unclear, equipment missing inspection, parameter are failed to report; Finally, when listening to the numbering of each typing list corresponding to each work of transformer substation room of inspection terminal submission and prestore numbering one A pair seasonable, determines that tour personnel has been completed all tour tasks by completion notice module 18, the task that sends is completed logical Know and navigation way is to inspection terminal, so can prompt and guide tour personnel to leave area of transformer station according to the navigation way Domain, to prevent tour personnel from staying without reason or arbitrarily walk about and cause danger.Therefore substation inspection prison provided by the invention Device is controlled, the overall monitor to making an inspection tour process can be realized, and then improve and make an inspection tour quality.
Embodiment three:
Referring to Fig. 4, the embodiment of the present invention also provides a kind of electronic equipment 100, including:Processor 40, memory 41, bus 42 and communication interface 43, the processor 40, communication interface 43 and memory 41 connected by bus 42;Processor 40 is used to hold The executable module stored in line storage 41, such as computer program.
Wherein, memory 41 may include high-speed random access memory (RAM, Random Access Memory), Non-labile memory (non-volatile memory), for example, at least a magnetic disk storage may also be included.By extremely A few communication interface 43 (can be wired or wireless) is realized logical between the system network element and at least one other network element Letter connection, can use internet, wide area network, LAN, Metropolitan Area Network (MAN) etc..
Bus 42 can be isa bus, pci bus or eisa bus etc..The bus can be divided into address bus, data Bus, controlling bus etc..Only represented for ease of representing, in Fig. 4 with a four-headed arrow, it is not intended that an only bus or A type of bus.
Wherein, memory 41 is used for storage program, and the processor 40 performs the journey after execute instruction is received Sequence, the method performed by device that the stream process that foregoing any embodiment of the embodiment of the present invention discloses defines can apply to handle In device 40, or realized by processor 40.
Processor 40 is probably a kind of IC chip, has the disposal ability of signal.In implementation process, above-mentioned side Each step of method can be completed by the integrated logic circuit of the hardware in processor 40 or the instruction of software form.Above-mentioned Processor 40 can be general processor, including central processing unit (Central Processing Unit, abbreviation CPU), network Processor (Network Processor, abbreviation NP) etc.;It can also be digital signal processor (Digital Signal Processing, abbreviation DSP), application specific integrated circuit (Application Specific Integrated Circuit, referred to as ASIC), ready-made programmable gate array (Field-Programmable Gate Array, abbreviation FPGA) or other are programmable Logical device, discrete gate or transistor logic, discrete hardware components.It can realize or perform in the embodiment of the present invention Disclosed each method, step and logic diagram.General processor can be microprocessor or the processor can also be appointed What conventional processor etc..The step of method with reference to disclosed in the embodiment of the present invention, can be embodied directly in hardware decoding processing Device performs completion, or performs completion with the hardware in decoding processor and software module combination.Software module can be located at Machine memory, flash memory, read-only storage, programmable read only memory or electrically erasable programmable memory, register etc. are originally In the ripe storage medium in field.The storage medium is located at memory 41, and processor 40 reads the information in memory 41, with reference to Its hardware completes the step of above method.
Substation inspection supervising device and electronic equipment provided in an embodiment of the present invention, the power transformation provided with above-described embodiment Tour monitoring method of standing has identical technical characteristic, so can also solve identical technical problem, reaches identical technology effect Fruit.
The computer program product for the progress substation inspection monitoring method that the embodiment of the present invention is provided, including store The computer-readable recording medium of the executable non-volatile program code of processor, the instruction that described program code includes can use In the method described in previous methods embodiment that performs, specific implementation can be found in embodiment of the method, will not be repeated here.
It is apparent to those skilled in the art that for convenience and simplicity of description, the device of foregoing description With the specific work process of electronic equipment, the corresponding process in preceding method embodiment is may be referred to, will not be repeated here.
In all examples being illustrated and described herein, any occurrence should be construed as merely exemplary, without It is that therefore, other examples of exemplary embodiment can have different values as limitation.
Flow chart and block diagram in accompanying drawing are shown to be produced according to the method and computer program of multiple embodiments of the present invention Architectural framework in the cards, function and the operation of product.At this point, each square frame in flow chart or block diagram can represent one A part for individual module, program segment or code, a part for the module, program segment or code include one or more be used in fact The executable instruction of logic function as defined in existing.It should also be noted that marked at some as in the realization replaced in square frame Function can also be with different from the order marked in accompanying drawing generation.For example, two continuous square frames can essentially substantially simultaneously Perform capablely, they can also be performed in the opposite order sometimes, and this is depending on involved function.It is also noted that frame The combination of figure and/or each square frame and block diagram in flow chart and/or the square frame in flow chart, it can use as defined in performing Function or the special hardware based system of action realize, or can with the combination of specialized hardware and computer instruction come Realize.In addition, term " first ", " second ", " the 3rd " are only used for describing purpose, and it is not intended that instruction or implying relatively heavy The property wanted.
In several embodiments provided herein, it should be understood that disclosed electronic equipment, apparatus and method, It can realize by another way.Device embodiment described above is only schematical, for example, the unit is drawn Point, only a kind of division of logic function, there can be other dividing mode when actually realizing, in another example, multiple units or group Part can combine or be desirably integrated into another system, or some features can be ignored, or not perform.It is another, it is shown Or the mutual coupling discussed or direct-coupling or communication connection can be by some communication interfaces, device or unit INDIRECT COUPLING or communication connection, can be electrical, mechanical or other forms.
The unit illustrated as separating component can be or may not be physically separate, show as unit The part shown can be or may not be physical location, you can with positioned at a place, or can also be distributed to multiple On NE.Some or all of unit therein can be selected to realize the mesh of this embodiment scheme according to the actual needs 's.
In addition, each functional unit in each embodiment of the present invention can be integrated in a processing unit, can also That unit is individually physically present, can also two or more units it is integrated in a unit.
If the function is realized in the form of SFU software functional unit and is used as independent production marketing or in use, can be with It is stored in the executable non-volatile computer read/write memory medium of a processor.Based on such understanding, the present invention The part that is substantially contributed in other words to prior art of technical scheme or the part of the technical scheme can be with software The form of product is embodied, and the computer software product is stored in a storage medium, including some instructions are causing One computer equipment (can be personal computer, server, or network equipment etc.) performs each embodiment institute of the present invention State all or part of step of method.And foregoing storage medium includes:USB flash disk, mobile hard disk, read-only storage (ROM, Read- Only Memory), random access memory (RAM, Random Access Memory), magnetic disc or CD etc. are various can be with The medium of store program codes.
Finally it should be noted that:Embodiment described above, it is only the embodiment of the present invention, to illustrate the present invention Technical scheme, rather than its limitations, protection scope of the present invention is not limited thereto, although with reference to the foregoing embodiments to this hair It is bright to be described in detail, it will be understood by those within the art that:Any one skilled in the art The invention discloses technical scope in, it can still modify to the technical scheme described in previous embodiment or can be light Change is readily conceivable that, or equivalent substitution is carried out to which part technical characteristic;And these modifications, change or replacement, do not make The essence of appropriate technical solution departs from the spirit and scope of technical scheme of the embodiment of the present invention, should all cover the protection in the present invention Within the scope of.Therefore, protection scope of the present invention described should be defined by scope of the claims.

Claims (10)

  1. A kind of 1. substation inspection monitoring method, applied to cloud management platform, it is characterised in that including:
    The authentication information that tour personnel is sent by entrance guard device is received, the authentication information includes authentication password and work is compiled Number;
    Judge whether the authentication information meets authentication condition, if so, then sending open command to the entrance guard device so that institute State tour personnel and enter transformer station region;
    Send the inspection terminal that visit program corresponding with the job code carries to the tour personnel, the visit program Including patrol route, the numbering of each work of transformer substation room of tour in need and each transformer station are marked in the patrol route The position of operating room;
    Each typing list corresponding to each work of transformer substation room that inspection terminal described in real-time reception is submitted, and judge each described Whether the numbering of typing list corresponds with the numbering that prestores;
    If it is not, the position of next work of transformer substation room for needing to make an inspection tour then is indicated in the patrol route, and real-time reception The 2 D code information that the inspection terminal is sent, wherein the 2 D code information is to scan the power transformation by the inspection terminal The Quick Response Code generation stood in operating room;
    Corresponding blank typing list is sent to the inspection terminal according to the 2 D code information, so that the inspection terminal is corresponding Tour personnel's typing described in work of transformer substation room all equipment to be checked parameter information, wherein the blank typing list includes Parameter name corresponding to each device numbering to be checked, each equipment to be checked and tour points for attention;
    If so, then sending task completion notice and navigation way to the inspection terminal, completed so that the tour personnel makes an inspection tour Afterwards, the transformer station region is left according to the navigation way.
  2. 2. according to the method for claim 1, it is characterised in that the authentication password includes static password and dynamic password, Wherein described static password is the default password of the tour personnel;
    Before the authentication information for receiving tour personnel and being sent by entrance guard device, in addition to:
    The unlatching request that the inspection terminal that tour personnel carries is sent is received, the unlatching request carries job code;
    According to the request transmission dynamic password of opening to the inspection terminal.
  3. 3. according to the method for claim 1, it is characterised in that described to judge whether the authentication information meets authentication condition Including:
    Judge whether tour personnel has tour task at current time corresponding to the job code;
    If so, then judge whether the authentication password is correct;
    If, it is determined that the authentication information meets the authentication condition.
  4. 4. according to the method for claim 1, it is characterised in that also include:
    Position of the tour personnel in the transformer station region, and real-time storage positional information are monitored in real time;
    When listening to the tour personnel and being in danger zone, hint instructions are sent to the inspection terminal of the tour personnel;
    When listening to the tour personnel and leaving the transformer station region, the perambulator is generated according to the positional information of storage The tour track of member;
    The tour track is preserved to tour in recording.
  5. 5. according to the method for claim 1, it is characterised in that also include:
    According to preparatory condition, it is determined whether distribute tour task or renewal distributes the cycle, the preparatory condition includes operation and touched Any of hair, failure triggering, preset time triggering, weather triggering, load boom period triggering;
    If the preparatory condition triggers for operation, distributed according to the instruction that distributes that monitoring personnel corresponding to cloud management platform is sent Tour task is to corresponding inspection terminal;
    If the preparatory condition triggers for failure, the warning message sent according to the warning device in the transformer station region is sent Tour task is sent out to corresponding inspection terminal;
    If the preparatory condition triggers for preset time, judge whether current time is preset time;If so, then distribute tour Task is to corresponding inspection terminal;
    If the preparatory condition triggers for weather, according to the microclimate on-line monitoring dress in the transformer station region received The Changes in weather information for putting transmission distributes tour task to corresponding inspection terminal;
    If the preparatory condition triggers for load boom period, judge whether current time is in the failure multiple phase, if so, then contracting The cycle is distributed described in short.
  6. 6. according to the method for claim 5, it is characterised in that the warning message comprises at least the change where faulty equipment Numbering, faulty equipment numbering, the current failure information of power station operating room;The tour task comprises at least mission planning information;
    The warning message that the warning device according in the transformer station region is sent distributes tour task to corresponding inspection Terminal includes:
    According to the current failure information, the historical failure information in fault message storehouse is traveled through;
    To find with the current failure information identical historical failure information flag is similar fault message;
    Extraction failure cause corresponding with the similar fault message, fault solution from the fault message storehouse;
    According to the failure cause, the fault solution, the current failure information, mission planning information is generated;
    It is non-inspection terminal corresponding to the tour personnel of state of turning out for work that the mission planning information, which is sent to working condition,.
  7. 7. according to the method for claim 1, it is characterised in that also include:
    The related information of monitoring personnel input corresponding to cloud management platform is received, wherein the related information includes the transformer station The numbering of operating room and the director corresponding with the numbering of work of transformer substation room numbering;
    Obtain the collection information that the harvester corresponding to the numbering of the work of transformer substation room in work of transformer substation room is sent;
    The collection information is periodically pushed into mobile terminal corresponding to director's numbering.
  8. 8. according to the method described in claim any one of 1-7, it is characterised in that also include:
    When the personnel for listening to the transmission of the thermal infrared imager in the transformer station region enter information, whether current time is judged For tour time;
    If it is not, alarm command is then sent to the alarm of cloud management platform, and the region entered according to the personnel in information is believed Breath, opens corresponding camera device;
    The shooting information of camera device shooting described in real-time reception simultaneously stores.
  9. A kind of 9. substation inspection supervising device, it is characterised in that including:
    Certification receiving module, the authentication information sent for receiving tour personnel by entrance guard device, the authentication information include Authentication password and job code;
    Condition judgment module, for judging whether the authentication information meets authentication condition;
    Instruction sending module, for when the authentication information meets authentication condition, sending open command to the first entrance guard device So that the tour personnel enters transformer station region;
    Plan sending module, the inspection carried for sending visit program corresponding with the job code to the tour personnel Terminal, the visit program include patrol route, and each work of transformer substation room of tour in need is marked in the patrol route Numbering and each work of transformer substation room position;
    Typing receiving module, each typing corresponding to each work of transformer substation room submitted for inspection terminal described in real-time reception It is single, and judge whether the numbering of each typing list and the numbering that prestores correspond;
    Make an inspection tour indicating module, for when each typing list numbering with it is described prestore number non-one-to-one corresponding when, described The position of next work of transformer substation room for needing to make an inspection tour, and inspection terminal transmission described in real-time reception are indicated in patrol route 2 D code information, wherein the 2 D code information is that the Quick Response Code in the work of transformer substation room is scanned by the inspection terminal Generation;
    Typing sending module, the 2 D code information for being sent according to the tour indicating module send corresponding blank and recorded Enter list to the inspection terminal, so as to be needed described in tour personnel's typing corresponding to the inspection terminal in work of transformer substation room The parameter information of equipment is examined, wherein the blank typing list includes each device numbering to be checked, each equipment to be checked corresponds to Parameter name and make an inspection tour points for attention;
    Completion notice module, for when the numbering of each typing list corresponds with the numbering that prestores, sending task Completion notice and navigation way, so that after the completion of the tour personnel makes an inspection tour, leave to the inspection terminal according to patrol route The transformer station region.
  10. 10. a kind of electronic equipment, including memory, processor, it is stored with and can runs on the processor on the memory Computer program, it is characterised in that the claims 1 to 8 are realized described in the computing device during computer program The step of method described in one.
CN201710830184.8A 2017-09-14 2017-09-14 Substation patrol monitoring method and device and electronic equipment Active CN107657677B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710830184.8A CN107657677B (en) 2017-09-14 2017-09-14 Substation patrol monitoring method and device and electronic equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710830184.8A CN107657677B (en) 2017-09-14 2017-09-14 Substation patrol monitoring method and device and electronic equipment

Publications (2)

Publication Number Publication Date
CN107657677A true CN107657677A (en) 2018-02-02
CN107657677B CN107657677B (en) 2020-02-11

Family

ID=61130179

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710830184.8A Active CN107657677B (en) 2017-09-14 2017-09-14 Substation patrol monitoring method and device and electronic equipment

Country Status (1)

Country Link
CN (1) CN107657677B (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108448723A (en) * 2018-03-28 2018-08-24 合肥云智物联科技有限公司 A kind of transformer substation remote monitoring system and its method
CN108564675A (en) * 2018-03-28 2018-09-21 合肥云智物联科技有限公司 A kind of substation inspection system based on mobile terminal
CN109587448A (en) * 2018-12-12 2019-04-05 国网山西省电力公司大同供电公司 A kind of intelligent substation inspection tour system
CN109859369A (en) * 2019-03-21 2019-06-07 深圳市城市公共安全技术研究院有限公司 Intelligent lock for limited space and control method thereof
CN110321770A (en) * 2019-03-25 2019-10-11 西安长城数字软件有限公司 Pipeline monitoring method, device, equipment and storage medium
CN110648418A (en) * 2019-09-04 2020-01-03 广东纬德信息科技有限公司 Passive intelligent lock, terminal, inspection system and inspection method
CN111130006A (en) * 2019-12-11 2020-05-08 深圳供电局有限公司 Key type transmission line field operation method and system
CN111311777A (en) * 2020-02-14 2020-06-19 北京明略软件系统有限公司 Dynamic inspection method, server, terminal, storage medium and equipment
CN111555162A (en) * 2020-04-06 2020-08-18 连云港市港圣开关制造有限公司 High-efficient intelligent power distribution operation and maintenance system
CN112001197A (en) * 2020-08-24 2020-11-27 精英数智科技股份有限公司 Safety inspection method and device, electronic equipment and readable storage medium
CN114301129A (en) * 2021-12-29 2022-04-08 安徽佑赛科技股份有限公司 Transformer substation inspection system and control method thereof
CN115202312A (en) * 2022-09-16 2022-10-18 山东神驰化工集团有限公司 Intelligent chemical industry safety production patrol and control system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008305332A (en) * 2007-06-11 2008-12-18 Synchro Co Ltd Security management system
CN102081815A (en) * 2010-12-17 2011-06-01 山东电力集团公司济宁供电公司 Transformer substation comprehensive security platform applying Internet of Things (IOT) technology
CN103208140A (en) * 2012-01-12 2013-07-17 国家电网公司 Substation access control authorization method and system
CN103325153A (en) * 2013-06-17 2013-09-25 深圳市共济科技有限公司 Inspection method and inspection system
CN105894626A (en) * 2016-03-31 2016-08-24 杨晓斌 Transformer substation entrance guard system
CN106384208A (en) * 2016-10-12 2017-02-08 国网江苏省电力公司徐州供电公司 Interactive inspection system and method based on two-dimensional code technology

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008305332A (en) * 2007-06-11 2008-12-18 Synchro Co Ltd Security management system
CN102081815A (en) * 2010-12-17 2011-06-01 山东电力集团公司济宁供电公司 Transformer substation comprehensive security platform applying Internet of Things (IOT) technology
CN103208140A (en) * 2012-01-12 2013-07-17 国家电网公司 Substation access control authorization method and system
CN103325153A (en) * 2013-06-17 2013-09-25 深圳市共济科技有限公司 Inspection method and inspection system
CN105894626A (en) * 2016-03-31 2016-08-24 杨晓斌 Transformer substation entrance guard system
CN106384208A (en) * 2016-10-12 2017-02-08 国网江苏省电力公司徐州供电公司 Interactive inspection system and method based on two-dimensional code technology

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108564675A (en) * 2018-03-28 2018-09-21 合肥云智物联科技有限公司 A kind of substation inspection system based on mobile terminal
CN108448723A (en) * 2018-03-28 2018-08-24 合肥云智物联科技有限公司 A kind of transformer substation remote monitoring system and its method
CN109587448A (en) * 2018-12-12 2019-04-05 国网山西省电力公司大同供电公司 A kind of intelligent substation inspection tour system
CN109859369A (en) * 2019-03-21 2019-06-07 深圳市城市公共安全技术研究院有限公司 Intelligent lock for limited space and control method thereof
CN110321770A (en) * 2019-03-25 2019-10-11 西安长城数字软件有限公司 Pipeline monitoring method, device, equipment and storage medium
CN110648418A (en) * 2019-09-04 2020-01-03 广东纬德信息科技有限公司 Passive intelligent lock, terminal, inspection system and inspection method
CN110648418B (en) * 2019-09-04 2021-09-07 广东纬德信息科技有限公司 Passive intelligent lock, terminal, inspection system and inspection method
CN111130006B (en) * 2019-12-11 2021-08-24 深圳供电局有限公司 Key type transmission line field operation method and system
CN111130006A (en) * 2019-12-11 2020-05-08 深圳供电局有限公司 Key type transmission line field operation method and system
CN111311777A (en) * 2020-02-14 2020-06-19 北京明略软件系统有限公司 Dynamic inspection method, server, terminal, storage medium and equipment
CN111555162A (en) * 2020-04-06 2020-08-18 连云港市港圣开关制造有限公司 High-efficient intelligent power distribution operation and maintenance system
CN111555162B (en) * 2020-04-06 2022-02-11 连云港市港圣开关制造有限公司 High-efficient intelligent power distribution operation and maintenance system
CN112001197A (en) * 2020-08-24 2020-11-27 精英数智科技股份有限公司 Safety inspection method and device, electronic equipment and readable storage medium
CN114301129A (en) * 2021-12-29 2022-04-08 安徽佑赛科技股份有限公司 Transformer substation inspection system and control method thereof
CN114301129B (en) * 2021-12-29 2023-07-04 安徽佑赛科技股份有限公司 Substation inspection system and control method thereof
CN115202312A (en) * 2022-09-16 2022-10-18 山东神驰化工集团有限公司 Intelligent chemical industry safety production patrol and control system

Also Published As

Publication number Publication date
CN107657677B (en) 2020-02-11

Similar Documents

Publication Publication Date Title
CN107657677A (en) Substation inspection monitoring method, device and electronic equipment
CN105581411B (en) Intelligent safety helmet and personnel positioning management system and method
CN109980781A (en) A kind of transformer substation intelligent monitoring system
CN103762723B (en) Method and system for managing a power grid
CN106056690B (en) Shield line intelligent polling method and system based on big data, cloud platform and Internet of Things
CN113450065B (en) Production operation management system and method for wind power plant
CN107885170A (en) The method of safety in production control device, system and management and control of keeping the safety in production
CN202815875U (en) Routing inspection system
CN107527155A (en) Construction project supervisory systems
CN104866982A (en) Internet+hazardous waste management system and method
CN110957811B (en) Full-flow intelligent monitoring method and system for temporary grounding wire
CN103065196A (en) Method for optimal and efficient guard tour configuration utilizing building information model and adjacency information
CN105867347B (en) Cross-space cascading fault detection method based on machine learning technology
CN114881808B (en) Big data-based accurate identification method for electric power larceny and electric power larceny prevention system
CN104463696A (en) Power grid operating risk recognition and prevention method and system
CN105574698A (en) Intelligent storage management system based on big data
CN106251240A (en) Power transmission network method for early warning based on big data
CN110070155A (en) A kind of comprehensive Activity recognition method and system of the inmate based on wearable device
CN107689954A (en) Power information system monitoring method and device
CN103093192A (en) High voltage transmission line galloping identification method
CN107977718A (en) Substation equipment maintaining method and system based on BIM models
CN109243139A (en) A kind of personnel safety monitoring method, terminal device, system and storage medium
CN110347694A (en) A kind of apparatus monitoring method based on Internet of Things, apparatus and system
CN115248873A (en) Cable tunnel safety monitoring method and system based on data fusion
TWM607740U (en) Smart construction site management equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant