CN107657399A - A kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination - Google Patents
A kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination Download PDFInfo
- Publication number
- CN107657399A CN107657399A CN201711134038.8A CN201711134038A CN107657399A CN 107657399 A CN107657399 A CN 107657399A CN 201711134038 A CN201711134038 A CN 201711134038A CN 107657399 A CN107657399 A CN 107657399A
- Authority
- CN
- China
- Prior art keywords
- work order
- balance
- defect
- management
- electric energy
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0637—Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/20—Administration of product repair or maintenance
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/80—Management or planning
- Y02P90/82—Energy audits or management systems therefor
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Abstract
The invention discloses a kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination, including establishing balance on-line Centralized Monitoring operational system, electric energy balance Centralized Monitoring group carries out daily monitoring O&M to transformer station of the whole province, uneven exception is found in time, is counted and initiates defect elimination flow;The transmission of defect elimination information is carried out between regulation and control center, each specialty of power transformation transport inspection department and sales department by work order, realizes collaboration defect elimination.The present invention is while state's supporting network same period line loss system Construction needs are met, to in-depth coulomb collection system construction, sound balance monitoring analysis mechanism, it is horizontal to strengthen power system fine-grained management, it is significant to improve the specialty collaboration maintenance work efficiency such as scheduling, marketing, fortune inspection.
Description
Technical field
The present invention relates to a kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination, belong to power scheduling control
Technical field.
Background technology
National grid same period line loss system Construction proposes higher target call to Controlling line loss work.Controlling line loss at present
It is main to use " four points " management method.Transformer station's electric energy balance is as one of Controlling line loss content, also using this manager
Method.This method mainly using division management responsibility, each runs the work in respective range of management well, lacks friendship and encloses the land band and collaboration
Defect elimination management.And in real work, cause that unbalanced reason situation is complicated, it is numerous to be related to face, it is necessary to each professional collaboration processing.
The online management-control method of transformer station's electric energy balance of " Centralized Monitoring, cooperateing with defect elimination ", strengthen collaboration O&M support, meeting state's branch
While support net same period line loss system Construction needs, to in-depth coulomb collection system construction, sound balance monitoring analysis mechanism, add
Strong power system fine-grained management is horizontal, and improving the specialty collaboration maintenance work efficiency such as scheduling, marketing, fortune inspection has important meaning
Justice.
The content of the invention
The technical problems to be solved by the invention are the defects of overcoming prior art, there is provided a kind of transformer station for cooperateing with defect elimination
The online management-control method of electric energy balance, for strengthening collaboration O&M support, meet state's supporting network same period line loss system Construction needs.
To achieve the above object, the present invention takes following technical scheme to be realized:
A kind of online management-control method of transformer station's electric energy balance, comprises the following steps:
1)Develop transformer station of the whole province electric energy balance and concentrate on-line monitoring operational system;The system includes balance index monitoring system
Module is counted, concentrates online monitoring module and the automatic management module of work order flow;
The balance index monitoring and statisticses module be used for statistical regions, plant stand current all equalization points Real-time Balancing situation,
Statistical Distribution and historical variations trend;
It is described to concentrate online monitoring module that all bus unbalance factor results of this area are illustrated in into management figure as a point
In;
The automatic management module of work order flow generates including work order, worksheet, trouble ticket dispatch, work order statistical analysis and work order
Management and inquiry;
The work order generation refers to initiate work order product process for stoichiometric point;The worksheet refers to the event according to stoichiometric point
Barrier type identification simultaneously inserts processing method;The trouble ticket dispatch refers to that work order is forwarded using between unit;The work order
Management refers to work order rights management and inquiry with inquiry;
2)Electric energy balance Centralized Monitoring group carries out daily monitoring O&M to transformer station of the whole province, finds that balance is abnormal in time, and
Initiate defect elimination flow;
3)The transmission of defect elimination information is carried out between regional dispatching control centre, each specialty of transport inspection department and sales department by work order,
Realize collaboration defect elimination.
The Real-time Balancing situation of foregoing current all equalization points is realized by the real-time monitoring chart of region, plant stand;When
The Statistical Distribution of preceding all equalization points is realized by the statistical distribution chart of region, plant stand;Current all equalization points are gone through
History variation tendency is realized by the trend analysis chart of region, plant stand.
The upper and lower border of bus unbalance factor is pre-set in foregoing management figure, it is equal in upper and lower bounds
It is abnormal balance point beyond upper and lower border for normal equilibrium point.
Foregoing support is directed to single metering point, or initiates work order generation stream to the stoichiometric point of multiple same symptoms in same station
Journey;Work order should be automatically filled in area, name of station, stoichiometric point title when generating, and be automatically selected according to the symptom type of selection next
Step processing unit.
The foregoing unit using work order includes Centralized Monitoring work group, provincial company scheduling, provincial company sales department, province
Inspection, DianKeYuan measurement centre, the scheduling of each prefecture-level company and the metering of each prefecture-level company;Each unit all has permission initiation work
Single, all work orders could continue to be forwarded to each unit after having to pass through the small group acknowledge examination & verification of monitoring work.
Foregoing work order statistical analysis includes carrying out statistical analysis to work order content, and work order life-cycle processes are united
Meter is analyzed and carries out statistical analysis to worksheet efficiency.
The detailed process of foregoing collaboration defect elimination is as follows:
31)Balance Centralized Monitoring group discovery balance initiates work order when abnormal, regional dispatching control centre finds defect or change
Work order is initiated during parameter and is committed to balance Centralized Monitoring group, sales department finds defect or work order is initiated when changing meter and is carried
Hand over to balance Centralized Monitoring group, transport inspection department finds to initiate work order when defect or changes terminal and is committed to balance Centralized Monitoring
Group;
32)Balance Centralized Monitoring group and carry out work order statistical analysis, carry out preliminary fault diagnosis, judge whether and D5000 topologys
Figure is consistent, if unanimously, judging whether collection is normal, is then transferred to step 33);, will if inconsistent with D5000 topological diagrams
Work order is committed to regional dispatching control centre, is judged whether to lack meter by regional dispatching control centre, is then transferred to step
38);
33)If collection is normal, judge whether no-load voltage ratio is correct, is then transferred to step 34);If collection is abnormal, judge
It is that meter failure classes acquisition abnormity is also that non-meter fault collection is abnormal, is then transferred to step 37);
34)If no-load voltage ratio is correct, judges whether to need each specialty consultation of doctors, be then transferred to step 35)If no-load voltage ratio is incorrect,
Regional dispatching control centre is then committed to, whether is changed by the clear and definite no-load voltage ratio of regional dispatching control centre, is then transferred to step 36);
35)If necessary to expert consultation, work order is submitted to carry out defect expressivity to Centralized Monitoring group is balanced after the completion of expert consultation
Judge, then go to step 310):
36)If no-load voltage ratio changes, regional dispatching control centre voluntarily safeguards main website parameter, then submits work order to balance to concentrate prison
Control group carries out defect expressivity judgement, then goes to step 310);If no-load voltage ratio does not change, work order is submitted to enter to sales department
Row is actual to examine live no-load voltage ratio, after verification, goes to step 39);
37)If meter failure classes acquisition abnormity, work order to sales department is submitted to carry out meter defect elimination, then by sales department work order
It is committed to transport inspection department and carries out elimination network, terminal, total line defect, is then transferred to step 39);If non-meter fault collection is different
Often, then submit work order to transport inspection department to carry out elimination network, terminal, total line defect, be then transferred to step 39);
38)If meter lacks, work order is committed to sales department by regional dispatching control centre, meter is installed by sales department,
Work order is committed to transport inspection department again, access bus, debugging are carried out by transport inspection department, are then transferred to step 39);If do not lack table
Work order, transport inspection department is directly committed to by regional dispatching control centre by meter, and access bus, debugging, Ran Houzhuan are carried out by transport inspection department
Enter step 39);
39)Submit work order to regional dispatching control centre to carry out main website parameter maintenance, then submit work order small to Centralized Monitoring is balanced
Group carries out defect expressivity judgement;
310)Defect expressivity judges, if it is determined that eliminating, then files, and work order is completed;If do not eliminated, step 32 is jumped to)By
Balance Centralized Monitoring group re-starts preliminary fault diagnosis.
What the present invention was reached has the beneficial effect that:
The present invention to in-depth coulomb collection system construction, is good for while state's supporting network same period line loss system Construction needs are met
Full balance monitoring analysis mechanism, the fine-grained management of reinforcement power system is horizontal, improves scheduling, marketing, transports the specialty collaboration fortune such as inspection
It is significant to tie up operating efficiency.
Brief description of the drawings
Fig. 1 is work order exemplary plot of the present invention;
Fig. 2 is operation management overview flow chart of the present invention.
Embodiment
The invention will be further described below.Following examples are only used for the technical side for clearly illustrating the present invention
Case, and can not be limited the scope of the invention with this.
A kind of online management-control method of transformer station's electric energy balance of collaboration defect elimination of the present invention, main point of four main steps
Suddenly, it is specific as follows:
1st, develop transformer station of the whole province electric energy balance and concentrate on-line monitoring operational system
The system is made up of following module:
1) balance index monitoring and statisticses module
Increase region, plant stand monitoring chart, statistical distribution chart, trend analysis chart etc. in real time respectively, it is convenient to be regarded from the overall situation
Hold Real-time Balancing situation, Statistical Distribution and the historical variations trend of current all equalization points in angle.Region population equilibrium feelings
Condition general view checks that balance is distributed for molecular domains, conveniently checks population equilibrium state, each height of contrast in some region
The balanced distribution situation in region etc., it is easy to the management to each sub-regions imbalance situation.
2) online monitoring module is concentrated
All bus unbalance factor results of this area are all illustrated in management figure as a point.Pre-set in management figure
The upper and lower border of bus unbalance factor, in upper and lower bounds is normal equilibrium point.It is distributed a little more to horizontal stroke
Axle is concentrated, and population equilibrium situation is better.It is abnormal balance point, it is necessary to be analyzed and processed beyond upper and lower border.
3) the automatic management module of work order flow
O&M, troubleshooting process management function, troubleshooting work order is automatically generated, improve system maintenance, operational monitoring etc.
The intelligent level of aspect.Exploitation workform management system is used for the closed loop management for completing electric quantity acquisition event, improves collection O&M
IT application in management is horizontal.Trouble ticket dispatch is as shown in Figure 1.
Work order generates:Entering specific monitoring interface, single metering point can be directed to, or to multiple same symptoms in same station
Stoichiometric point initiate generation work order flow.Area, name of station, stoichiometric point title should be automatically filled in when generating work order;According to selection
Symptom type automatically selects processing unit in next step.
Worksheet:Worksheet process must be filled with processing method.Can according to fault type automatic discrimination processing method,
Failure is such as gathered, may be to change table, changes terminal Service-Port, repair bus, modified address etc., and retain manual typing window
Mouthful.The life cycle of work order include generation, confirm, send processing examination & verification, processing, solve, examination & verification, close etc..Above-mentioned flow is deposited
In syntagmatic, not necessarily linear circulation.
Trouble ticket dispatch:Using work order unit include Centralized Monitoring work group, provincial company scheduling, provincial company sales department,
Economical, DianKeYuan measurement centre, the scheduling of each prefecture-level company, the metering of each prefecture-level company etc.;Each unit all has permission initiation
Work order, all work orders could continue to be forwarded to each specific processing unit after having to pass through the small group acknowledge examination & verification of monitoring work.
Work order statistical analysis:Support to analyze work order content statisticses, such as each management unit, certain types of stoichiometric point are asked
Inscribe quantity etc.;The statistical analysis to work order life-cycle processes is supported, includes the statistics of various state durations, is currently in
Quantity of the work order of each state etc.;Worksheet Efficiency Statistics are analyzed, as work order completion rate, work order are averagely completed averagely to take
Deng.
Workform management and inquiry:File administration, rights management etc. needed for work order;Support is looked into according to work order content, state etc.
Ask, support statistical result inquiry etc..
2nd, electric energy balance Centralized Monitoring group of transformer station of the whole province is set up
The specific function of electric energy balance Centralized Monitoring group includes:(1)Concentrate and carry out daily monitoring maintenance work, including the whole province
Modification scope Nei Tongtiao power plant, the Organization of African Unity adjust the Capital Construction Debugging of the plant stands such as power plant, new energy photovoltaic plant, transformer station, large user, letter
Cease change, the configuration of failure defect elimination, formula, external interface maintenance etc.;(2)Monthly bus balance dimension in the whole province's public transformer substation station
Shield, monthly report generation work, it is ensured that the critical point bore data such as system tune, Organization of African Unity's tune, delivery are reliable;(3)Coulomb collection system
Main website and relevant device maintenance work;(4)Tong Tiao power plant, the Organization of African Unity adjust power plant's critical point maintenance work;(5)Collect coulomb collection system
Correlation function demand, modification etc., software developer is submitted after tissue investigation;(6)Carry out with various regions, county power system keeper
Work contact.
3rd, uneven abnormal defect elimination management and control is carried out based on online work order function
The work of electric energy balance centralized watch is carried out in the normalization of electric energy balance Centralized Monitoring group of transformer station of the whole province, it is ensured that electricity disappears
Lack work closed loop.The transmission of defect elimination information is carried out between regulation and control, fortune inspection, each specialty of marketing by work order.Worksheet
Example is as shown in Figure 1.
4th, each specialty collaboration defect elimination of each management level
By establishing regulation and control, transporting inspection, Trinitarian collaboration O&M mechanism of marketing, find and all kinds of defects of defect elimination in time.Regulation and control
Main website construction, O&M are responsible in center, by monitoring that electric quantity balancing notes abnormalities, initiate defect elimination flow;Sales department is responsible for becoming
The electric energy meter and harvester in power station, and arrange defect elimination;Power transformation transport inspection department is responsible for the defect eliminations such as secondary circuit, power supply.Cooperate with defect elimination
Flow is as shown in Fig. 2 specific as follows:
1)Work order is initiated when finding that balance is abnormal by balance Centralized Monitoring group, regional dispatching control centre finds defect or change
Work order is initiated during parameter and is committed to balance Centralized Monitoring group, sales department (metering class) finds defect or sent out when changing meter
Play work order and be committed to balance Centralized Monitoring group, transport inspection department (secondary class) finds to initiate work order simultaneously when defect or changes terminal
It is committed to balance Centralized Monitoring group;
2)Balance Centralized Monitoring group and carry out work order statistical analysis, carry out preliminary fault diagnosis, judge whether and D5000 topological diagrams
Unanimously, if unanimously, judging whether collection is normal, is then transferred to step 3);If inconsistent with D5000 topological diagrams, by work
Regional dispatching control centre is singly committed to, is judged whether to lack meter by regional dispatching control centre, is then transferred to step 8);
3)If collection is normal, judge whether no-load voltage ratio is correct, is then transferred to step 4);If collection is abnormal, judgement is
Meter failure classes acquisition abnormity is also that non-meter fault collection is abnormal, is then transferred to step 7);
4)If no-load voltage ratio is correct, judges whether to need each specialty consultation of doctors, be then transferred to step 5)If no-load voltage ratio is incorrect,
Regional dispatching control centre is committed to, whether is changed by the clear and definite no-load voltage ratio of regional dispatching control centre, is then transferred to step 6);
5)Work order is submitted to sentence to Centralized Monitoring group progress defect expressivity is balanced if necessary to expert consultation, after the completion of expert consultation
It is disconnected, then go to step 10):
6)If no-load voltage ratio changes, regional dispatching control centre voluntarily safeguards main website parameter, then submits work order to balance to concentrate prison
Control group carries out defect expressivity judgement, then goes to step 10);If no-load voltage ratio does not change, work order is submitted to sales department's (metering
Class), the actual live no-load voltage ratio of verification is carried out, after verification, goes to step 9);
7)If meter failure classes acquisition abnormity, work order to sales department (metering class) is submitted to carry out meter defect elimination, then by marketing
Work order is committed to transport inspection department (secondary class) and carries out elimination network, terminal, total line defect by portion (metering class), is then transferred to step
9);If non-meter fault collection is abnormal, submits work order to carry out elimination network, terminal, bus to transport inspection department (secondary class) and lack
Fall into, be then transferred to step 9);
8)If meter lacks, work order is committed to sales department (metering class) by regional dispatching control centre, by sales department's (metering
Class) meter is installed, then work order is committed to transport inspection department (secondary class), access bus, debugging are carried out by transport inspection department (secondary class),
Then it is transferred to step 9);If not lacking meter, it is (secondary work order to be directly committed to by regional dispatching control centre transport inspection department
Class), access bus, debugging are carried out by transport inspection department (secondary class), are then transferred to step 9);
9)Submit work order to regional dispatching control centre to carry out main website parameter maintenance, then submit work order to balance Centralized Monitoring group
Carry out defect expressivity judgement;
10)Defect expressivity judges, if it is determined that eliminating, then files, and work order is completed;If do not eliminated, step 2 is jumped to)By putting down
Weighing apparatus Centralized Monitoring group re-starts preliminary fault diagnosis.
Described above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, without departing from the technical principles of the invention, some improvement and deformation can also be made, these are improved and deformation
Also it should be regarded as protection scope of the present invention.
Claims (7)
1. a kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination, it is characterised in that comprise the following steps:
1)Develop transformer station of the whole province electric energy balance and concentrate on-line monitoring operational system;The system includes balance index monitoring system
Module is counted, concentrates online monitoring module and the automatic management module of work order flow;
The balance index monitoring and statisticses module be used for statistical regions, plant stand current all equalization points Real-time Balancing situation,
Statistical Distribution and historical variations trend;
It is described to concentrate online monitoring module that all bus unbalance factor results of this area are illustrated in into management figure as a point
In;
The automatic management module of work order flow generates including work order, worksheet, trouble ticket dispatch, work order statistical analysis and work order
Management and inquiry;
The work order generation refers to initiate work order product process for stoichiometric point;The worksheet refers to the event according to stoichiometric point
Barrier type identification simultaneously inserts processing method;The trouble ticket dispatch refers to that work order is forwarded using between unit;The work order
Management refers to work order rights management and inquiry with inquiry;
2)Electric energy balance Centralized Monitoring group carries out daily monitoring O&M to transformer station of the whole province, finds that balance is abnormal in time, and
Initiate defect elimination flow;
3)The transmission of defect elimination information is carried out between regional dispatching control centre, each specialty of transport inspection department and sales department by work order,
Realize collaboration defect elimination.
2. a kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination according to claim 1, its feature exist
In the Real-time Balancing situation of current all equalization points is realized by the real-time monitoring chart of region, plant stand;It is current all flat
The statistical distribution chart that the Statistical Distribution of weighing apparatus point passes through region, plant stand is realized;The historical variations of current all equalization points become
Gesture is realized by the trend analysis chart of region, plant stand.
3. a kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination according to claim 1, its feature exist
In pre-setting the upper and lower border of bus unbalance factor in the management figure, in upper and lower bounds is normal
Equalization point, it is abnormal balance point beyond upper and lower border.
4. a kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination according to claim 1, its feature exist
In support is directed to single metering point, or initiates work order product process to the stoichiometric point of multiple same symptoms in same station;Work order generates
When should be automatically filled in area, name of station, stoichiometric point title, and processing unit in next step is automatically selected according to the symptom type of selection.
5. a kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination according to claim 1, its feature exist
In the unit using work order includes Centralized Monitoring work group, provincial company scheduling, provincial company sales department, economical, DianKeYuan
Measurement centre, the scheduling of each prefecture-level company and the metering of each prefecture-level company;Each unit all has permission initiation work order, all work orders
It could continue to be forwarded to each unit after having to pass through the small group acknowledge examination & verification of monitoring work.
6. a kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination according to claim 1, its feature exist
In the work order statistical analysis includes carrying out statistical analysis to work order content, and statistical analysis is carried out to work order life-cycle processes
And statistical analysis is carried out to worksheet efficiency.
7. a kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination according to claim 1, its feature exist
In the detailed process of the collaboration defect elimination is as follows:
31)Balance Centralized Monitoring group discovery balance initiates work order when abnormal, regional dispatching control centre finds defect or change
Work order is initiated during parameter and is committed to balance Centralized Monitoring group, sales department finds defect or work order is initiated when changing meter and is carried
Hand over to balance Centralized Monitoring group, transport inspection department finds to initiate work order when defect or changes terminal and is committed to balance Centralized Monitoring
Group;
32)Balance Centralized Monitoring group and carry out work order statistical analysis, carry out preliminary fault diagnosis, judge whether and D5000 topologys
Figure is consistent, if unanimously, judging whether collection is normal, is then transferred to step 33);, will if inconsistent with D5000 topological diagrams
Work order is committed to regional dispatching control centre, is judged whether to lack meter by regional dispatching control centre, is then transferred to step
38);
33)If collection is normal, judge whether no-load voltage ratio is correct, is then transferred to step 34);If collection is abnormal, judge
It is that meter failure classes acquisition abnormity is also that non-meter fault collection is abnormal, is then transferred to step 37);
34)If no-load voltage ratio is correct, judges whether to need each specialty consultation of doctors, be then transferred to step 35)If no-load voltage ratio is incorrect,
Regional dispatching control centre is then committed to, whether is changed by the clear and definite no-load voltage ratio of regional dispatching control centre, is then transferred to step 36);
35)If necessary to expert consultation, work order is submitted to carry out defect expressivity to Centralized Monitoring group is balanced after the completion of expert consultation
Judge, then go to step 310):
36)If no-load voltage ratio changes, regional dispatching control centre voluntarily safeguards main website parameter, then submits work order to balance to concentrate prison
Control group carries out defect expressivity judgement, then goes to step 310);If no-load voltage ratio does not change, work order is submitted to enter to sales department
Row is actual to examine live no-load voltage ratio, after verification, goes to step 39);
37)If meter failure classes acquisition abnormity, work order to sales department is submitted to carry out meter defect elimination, then by sales department work order
It is committed to transport inspection department and carries out elimination network, terminal, total line defect, is then transferred to step 39);If non-meter fault collection is different
Often, then submit work order to transport inspection department to carry out elimination network, terminal, total line defect, be then transferred to step 39);
38)If meter lacks, work order is committed to sales department by regional dispatching control centre, meter is installed by sales department,
Work order is committed to transport inspection department again, access bus, debugging are carried out by transport inspection department, are then transferred to step 39);If do not lack table
Work order, transport inspection department is directly committed to by regional dispatching control centre by meter, and access bus, debugging, Ran Houzhuan are carried out by transport inspection department
Enter step 39);
39)Submit work order to regional dispatching control centre to carry out main website parameter maintenance, then submit work order small to Centralized Monitoring is balanced
Group carries out defect expressivity judgement;
310)Defect expressivity judges, if it is determined that eliminating, then files, and work order is completed;If do not eliminated, step 32 is jumped to)By
Balance Centralized Monitoring group re-starts preliminary fault diagnosis.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711134038.8A CN107657399A (en) | 2017-11-16 | 2017-11-16 | A kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711134038.8A CN107657399A (en) | 2017-11-16 | 2017-11-16 | A kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107657399A true CN107657399A (en) | 2018-02-02 |
Family
ID=61120463
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711134038.8A Pending CN107657399A (en) | 2017-11-16 | 2017-11-16 | A kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107657399A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108985470A (en) * | 2018-07-16 | 2018-12-11 | 国网福建省电力有限公司 | A kind of defect process initiating method based on terminal control application |
CN109102255A (en) * | 2018-08-16 | 2018-12-28 | 国网福建省电力有限公司龙岩供电公司 | A kind of electric flux unusual fluctuation and defect whole process collaborative management method |
CN113077289A (en) * | 2021-04-12 | 2021-07-06 | 上海耶汇市场营销策划有限公司 | Social platform operation and maintenance system for product marketing |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120197448A1 (en) * | 2011-02-01 | 2012-08-02 | Samsung Electronics Co., Ltd. | Electric device, power management apparatus and method for controlling the same |
CN103280891A (en) * | 2013-05-30 | 2013-09-04 | 国家电网公司 | Monitoring method for electric energy measurement and acquisition system of uniformly-dispatched power plant |
CN104361419A (en) * | 2014-09-10 | 2015-02-18 | 国家电网公司 | Electric transmission and transformation equipment state monitoring defect management system and method based on regulation and control integration |
-
2017
- 2017-11-16 CN CN201711134038.8A patent/CN107657399A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120197448A1 (en) * | 2011-02-01 | 2012-08-02 | Samsung Electronics Co., Ltd. | Electric device, power management apparatus and method for controlling the same |
CN103280891A (en) * | 2013-05-30 | 2013-09-04 | 国家电网公司 | Monitoring method for electric energy measurement and acquisition system of uniformly-dispatched power plant |
CN104361419A (en) * | 2014-09-10 | 2015-02-18 | 国家电网公司 | Electric transmission and transformation equipment state monitoring defect management system and method based on regulation and control integration |
Non-Patent Citations (2)
Title |
---|
吴静等: ""电能量系统智能告警的实现"", 《安徽电气工程职业技术学院学报》 * |
张远来等: ""基于调度运行管理系统的配电网故障研判方案"", 《电力系统自动化》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108985470A (en) * | 2018-07-16 | 2018-12-11 | 国网福建省电力有限公司 | A kind of defect process initiating method based on terminal control application |
CN109102255A (en) * | 2018-08-16 | 2018-12-28 | 国网福建省电力有限公司龙岩供电公司 | A kind of electric flux unusual fluctuation and defect whole process collaborative management method |
CN113077289A (en) * | 2021-04-12 | 2021-07-06 | 上海耶汇市场营销策划有限公司 | Social platform operation and maintenance system for product marketing |
CN113077289B (en) * | 2021-04-12 | 2022-08-19 | 上海耶汇市场营销策划有限公司 | Social platform operation and maintenance system for product marketing |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113159339B (en) | One-area one-index line loss management method and system based on big data | |
CN104361419B (en) | Power transmission and transformation equipment state monitoring fault management system and method based on regulation and control unification | |
CN103762723B (en) | Method and system for managing a power grid | |
CN107977789A (en) | Based on the audit work method under big data information | |
WO2009040140A1 (en) | Decentralized energy system and method for distributing energy in a decentralized energy system | |
CN104779699A (en) | Multifunctional station line loss management system | |
CN107657399A (en) | A kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination | |
CN108173293A (en) | Meter and the new energy active power output maximum value on-line calculation method of operation of power networks constraint | |
CN110889466B (en) | Transformer area line loss analysis method based on line loss classifier | |
CN105356461B (en) | A kind of accounting method of the load unbalanced administration project carbon emission reduction amount of low voltage electric network | |
CN105335820A (en) | Economic management system | |
CN105469194A (en) | Power distribution network main equipment operation efficiency evaluation method based on load duration curve | |
CN102289731A (en) | Method for maintaining state of power transmission equipment based on system risk | |
CN101771275B (en) | Electric energy monitoring system | |
CN108256772A (en) | A kind of user side flexible resource scheduling uncertainty methods of risk assessment and system | |
CN107666148A (en) | Line fault analysis method based on distribution transforming power cut signal | |
WO2023179280A1 (en) | Lean evaluation method for power grid dispatching operation | |
CN108805429A (en) | " one continuous line " hardware and software platform fine-grained management method for taiwan area line loss | |
CN112560214A (en) | Transformer substation bus balance fault diagnosis method, system, equipment and storage medium | |
CN107748954A (en) | A kind of transformer station's balancing monitor and control system | |
CN109063863B (en) | Distribution network maintenance plan optimization method considering area equipment life cycle cost-efficiency ratio | |
CN201332267Y (en) | Electric energy monitoring system | |
CN109190947A (en) | A kind of traffic control evaluation system | |
CN107085762A (en) | A kind of platform area line loss monitoring and abnormal defect elimination management system | |
CN112200499A (en) | Power distribution network infrastructure project investment execution analysis method and system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180202 |