CN107651546B - The main replacing lifting ropes of multi-rope technique of vertical - Google Patents

The main replacing lifting ropes of multi-rope technique of vertical Download PDF

Info

Publication number
CN107651546B
CN107651546B CN201711077974.XA CN201711077974A CN107651546B CN 107651546 B CN107651546 B CN 107651546B CN 201711077974 A CN201711077974 A CN 201711077974A CN 107651546 B CN107651546 B CN 107651546B
Authority
CN
China
Prior art keywords
rope
group
container
old
vehicle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711077974.XA
Other languages
Chinese (zh)
Other versions
CN107651546A (en
Inventor
曹彬
操礼发
杨友来
高万斌
陈伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huainan Mining Group Co Ltd
Original Assignee
Huainan Mining Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huainan Mining Group Co Ltd filed Critical Huainan Mining Group Co Ltd
Priority to CN201711077974.XA priority Critical patent/CN107651546B/en
Publication of CN107651546A publication Critical patent/CN107651546A/en
Application granted granted Critical
Publication of CN107651546B publication Critical patent/CN107651546B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • B66B19/02Installing or exchanging ropes or cables

Abstract

The invention belongs to coal mine shaft lining lifting system Maintenance and Repair technical fields, more particularly to a kind of main replacing lifting ropes of multi-rope technique of vertical, all main hoisting ropes are divided at least two groups, and ensure when any one group of main hoisting rope unloads power, the load-carrying ability of the main hoisting rope of remaining each group is all enough to carry unloaded two container of A, B;The main hoisting rope of each group is replaced in batches, utilize the phenomenon that the quiet tension difference of midway winch of the above-mentioned appearance of the construction method effective solution for changing the rope vehicle replacement main hoisting rope of vertical is inadequate, and from mechanization degree for, also original replacing options primary innovation has been subjected to, so that the Mechanization Level of entire replacement process improves, from labor intensity of workers and construction cost is largely reduced, the efficiency and construction quality of construction are improved.

Description

The main replacing lifting ropes of multi-rope technique of vertical
Technical field
The invention belongs to coal mine shaft lining lifting system Maintenance and Repair technical fields, and in particular to a kind of main hoisting rope of vertical is more Change technique.
Background technique
Currently, the construction method of each mine vertical multi-rope friction type hoisting gear replacing hoisting ropes need to be put into largely Recovery operation of the manpower for new old master rope clamping and dismounting and old rope, increases the work load of worker, increases construction Cost;And it since it is desired that will newly restrict and old rope is clamped, it cannot be guaranteed that the construction quality of the rigid change steel rope of institute;And individual well winches Quiet tension difference is inadequate, cannot be constructed using the previous method with four old ropes, four, band newly rope decentralization simultaneously to shaft bottom.
Summary of the invention
The object of the present invention is to provide a kind of high degree of automation, the main replacing lifting ropes of multi-rope technique of vertical easy to implement.
To achieve the above object, the present invention provides following technical schemes: a kind of main replacing lifting ropes of multi-rope technique of vertical, by institute There is main hoisting rope to be divided at least two groups, and ensures when any one group of main hoisting rope unloads power, the load of the main hoisting rope of remaining each group Ability is all enough to carry unloaded two container of A, B;The main hoisting rope of each group is replaced in batches, each group of main hoisting rope is more The process of changing includes the following steps:
Step 1: changing rope vehicle, guide wheel group arrangement, change rope vehicle and take root and be fixed on pithead position;Guide wheel group arrangement is taken root On well head stock crossbeam;
Step 2: B container is promoted to above well head horizontal plane, will new rope across changing rope vehicle, and A container side with it is corresponding First group of old rope securely connected using wire line shoe;
Step 3: changing rope vehicle and put new rope, while hoisting gear is transferred with inspection speed and stopped below B container to well head horizontal plane Vehicle;
Step 4: messenger is passed through and changes rope vehicle and is pulled to well head, it is then that messenger is old B container side and corresponding first group Rope is securely connected using wire line shoe;
Step 5: changing rope vehicle and put messenger, receive new rope, while hoisting gear above mentions B container, makes B container suspension operation to well head Near horizontal plane;
Step 6: all main hoisting rope cards in well head A container side set four rope fixtures;It is mentioned on adjusting rope device in addition to first group Other each main hoisting rope head ropes, make first group of steel wire rope looseness on B container, cut off above B container side mounting first group it is old First group of old rope is detached winch drum rope groove by rope, hoist house;
Step 7: changing rope vehicle and receive new rope, put messenger, while the old rope of A container side relaxation is hauled out into well head, new and old rope connection Rope stopping when snapping into up to well head guide wheel group position, cut off first group of old rope below new and old rope connecting rope card;
Step 8: starting and change rope vehicle spasm rope, put new rope, carry out turning over rope, turn over rope when the connecting rope of messenger and old rope snaps into reach Stop after sheave, removes messenger and old rope connecting rope card;
Step 9: change rope vehicle exit messenger, the old rope rope end cut off in step 6 is penetrated change rope vehicle rope closing unit and with receipts Rope drum is connected, and starts and changes the old rope of rope vehicle receipts, puts new rope, takes new rope end to B container suspension position from A container side and stop Only, and first group of B container side suspension arrangement of newly restricting is made;
Step 10: first starting and change rope vehicle new old master is made to restrict after stress, remove the rope locking machine of A container side, start winch decentralization B Container above mentions A container, by new rope band to shaft bottom, while transferring new rope using change rope vehicle will be in old rope receipts to rope closing disk;
Step 11: all main hoisting ropes being blocked with rope locking machine in well head B container side, A container is above mentioned with adjusting rope device, is made First group of main rope is in relaxed state, and replacement production first group of A container side suspension arrangement of newly restricting is completed first group of main rope replacement and applied Work;
Step 12: repeat the above steps 2-11, completes the replacement of the main hoisting rope of other each groups.
The technical effects of the invention are that: utilize the construction method effective solution for changing the rope vehicle replacement main hoisting rope of vertical The inadequate phenomenon of the quiet tension difference of midway winch of above-mentioned appearance, and from mechanization degree for, also by original replacement side Method has carried out primary innovation, so that the Mechanization Level of entire replacement process improves, works from worker is largely reduced Intensity and construction cost improve the efficiency and construction quality of construction.
Detailed description of the invention
Fig. 1 to Figure 11 is of the invention to change the corresponding structure principle chart of each step in rope technical process.
Specific embodiment
By taking the mine shaft hoist system of four main hoisting ropes as an example, situation implementation process of the invention is described in detail.
As shown in figs. 1-11, all main hoisting ropes are divided into two groups, wherein 1,4 by the main replacing lifting ropes of multi-rope technique of a kind of vertical Number rope be one group, 2, No. 3 rope be another group, 1, No. 4 rope replacement process include the following steps:
Step 1: changing rope vehicle 1, the arrangement of guide wheel group 2, change rope vehicle 1 and take root and be fixed on pithead position;The arrangement life of guide wheel group 2 Root is on well head stock crossbeam;
Step 2: B container 7 being promoted at 20m above well head horizontal plane, two new ropes 8 are passed through and change rope vehicle 1, and in A Container side is with corresponding 1, No. 4 old rope 6 using the first securely connection of rope card 9;
Step 3: changing rope vehicle 1 and put rope drum 4 and put new rope 8, while hoisting gear is held with inspection speed (0.2m/s) decentralization B It stops at 15m below device 7 to well head horizontal plane;
Step 4: two messengers 10 are passed through and changes rope and vehicle 1 and is pulled to well head, then by messenger 10 7 side of B container with it is corresponding 1, No. 4 it is old rope 6 using second rope card 11 securely connection;
Step 5: changing rope vehicle 1 and put messenger 10, receive new rope 8, while hoisting gear above mentions B container 7, make the suspension operation of B container 7 Below to well head horizontal plane at 1m;
Step 6: all main hoisting rope cards in 13 side of well head A container set four the first rope fixtures 12;2, No. 3 are mentioned on adjusting rope device Main hoisting rope head rope makes 1, No. 4 steel wire rope looseness on B container 7, and 1, No. 4 old rope 6, winch are cut off above 7 side mounting of B container 1, No. 4 old rope 6 is detached winch drum rope groove by room;
Step 7: it changes rope vehicle 1 and receives new rope 8, put messenger 10, while the old rope 6 of 13 side of A container relaxation is hauled out into well head, it is new and old Stop when 9 arrival 2 position of well head guide wheel group of the first rope card of 6 connection of rope, cuts off 1, No. 4 old rope in the lower section of the first rope card 9 6;
Step 8: starting and change rope 1 spasm rope 10 of vehicle, put new rope 8, carry out turning over rope, turn over rope sheave when the second rope card 11 reaches Stop after 3, removes the second rope card 11;
Step 9: changing rope vehicle 1 and exit messenger 10,6 rope end of old rope cut off in step 6 is penetrated and changes rope 1 rope closing unit of vehicle simultaneously It is connected with rope closing roller 5, starts and change rope vehicle 1 and receive old rope 6, put new rope 8, take new 8, rope to B container 7 from 13 side of A container and hang Setting position stops, and makes 7 side of B container 1,4,8 suspension arrangements of new rope;
Step 10: first starting and change rope vehicle 1 new old master is made to restrict after stress, remove the first rope fixture 12 of 13 side of A container, start Winch transfers B container 7, above mentions A container 13, and 8 bands that will newly restrict are to shaft bottom, using changing rope vehicle 1 for old rope 6 while transferring new rope 8 It receives to rope closing disk;
Step 11: all main hoisting ropes being blocked with the second rope fixture 14 in 7 side of well head B container, above mention A with adjusting rope device Container 13, makes 1, No. 4 main rope in relaxed state, and 8 suspension arrangements of new rope of replacement production 13 side of A container 1,4 complete 1, No. 4 master Rope replacement construction;
Step 12: repeat the above steps 2-11, completes the replacement of 2, No. 3 main hoisting ropes.
The present invention utilizes the construction method effective solution for changing the rope replacement main hoisting rope of vertical of vehicle 1 midway of above-mentioned appearance The inadequate phenomenon of the quiet tension difference of winch, and from mechanization degree for, original replacing options have also been subjected to primary leather Newly, so that the Mechanization Level of entire replacement process improves, from largely reducing labor intensity of workers and construction cost, Improve the efficiency and construction quality of construction.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (1)

1. a kind of main replacing lifting ropes of multi-rope technique of vertical, it is characterised in that: all main hoisting ropes are divided at least two groups, and ensure to work as When any one group of main hoisting rope unloads power, the load-carrying ability of the main hoisting rope of remaining each group is all enough to carry unloaded two container of A, B;It will The main hoisting rope of each group is replaced in batches, and the replacement process of each group of main hoisting rope includes the following steps:
Step 1: changing rope vehicle, guide wheel group arrangement, change rope vehicle and take root and be fixed on pithead position;Guide wheel group arrangement is taken root in well head On stock crossbeam;
Step 2: B container is promoted to above well head horizontal plane, will new rope across changing rope vehicle, and in A container side and corresponding the One group of old rope is securely connected using wire line shoe;
Step 3: changing rope vehicle and put new rope, while hoisting gear transfers parking below B container to well head horizontal plane with inspection speed;
Step 4: messenger being passed through and changes rope vehicle and is pulled to well head, then adopts messenger with corresponding first group old rope in B container side It is securely connected with wire line shoe;
Step 5: changing rope vehicle and put messenger, receive new rope, while hoisting gear above mentions B container, makes B container suspension operation to well head level Near face;
Step 6: all main hoisting rope cards in well head A container side set four rope fixtures;Its in addition to first group is mentioned on adjusting rope device Its each main hoisting rope head rope, makes first group of steel wire rope looseness on B container, and first group of old rope is cut off above B container side mounting, twists First group of old rope is detached winch drum rope groove by garage;
Step 7: changing rope vehicle and receive new rope, put messenger, while the old rope of A container side relaxation is hauled out into well head, the rope of new and old rope connection Stopping when reaching well head guide wheel group position is snapped into, cuts off first group of old rope below new and old rope connecting rope card;
Step 8: starting and change rope vehicle spasm rope, put new rope, carry out turning over rope, turn over rope conductor rope when the connecting rope of messenger and old rope snaps into reach Stop after wheel, removes messenger and old rope connecting rope card;
Step 9: changing rope vehicle and exit messenger, the old rope rope end cut off in step 6 is penetrated and changes rope vehicle rope closing unit and is rolled with rope closing Cylinder is connected, and starts and changes the old rope of rope vehicle receipts, puts new rope, takes new rope end to B container suspension position from A container side and stop, and Make first group of B container side suspension arrangement of newly restricting;
Step 10: first starting and change rope vehicle new old master is made to restrict after stress, remove the rope fixture of A container side, start winch decentralization B and hold Device above mentions A container, by new rope band to shaft bottom, while transferring new rope using change rope vehicle will be in old rope receipts to rope closing disk;
Step 11: all main hoisting ropes being blocked with rope locking machine in well head B container side, A container is above mentioned with adjusting rope device, makes first The main rope of group is in relaxed state, and replacement production first group of A container side suspension arrangement of newly restricting completes first group of main rope replacement construction;
Step 12: repeat the above steps 2-11, completes the replacement of the main hoisting rope of other each groups.
CN201711077974.XA 2017-11-06 2017-11-06 The main replacing lifting ropes of multi-rope technique of vertical Active CN107651546B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711077974.XA CN107651546B (en) 2017-11-06 2017-11-06 The main replacing lifting ropes of multi-rope technique of vertical

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711077974.XA CN107651546B (en) 2017-11-06 2017-11-06 The main replacing lifting ropes of multi-rope technique of vertical

Publications (2)

Publication Number Publication Date
CN107651546A CN107651546A (en) 2018-02-02
CN107651546B true CN107651546B (en) 2019-07-09

Family

ID=61119990

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711077974.XA Active CN107651546B (en) 2017-11-06 2017-11-06 The main replacing lifting ropes of multi-rope technique of vertical

Country Status (1)

Country Link
CN (1) CN107651546B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108975138B (en) * 2018-07-27 2020-09-15 首钢集团有限公司 Cage guide rope replacing method
CN109019278B (en) * 2018-08-31 2019-11-05 中信重工机械股份有限公司 A kind of deep-well multi-rope friction hoisting machine steel rope replacing method
CN109516356A (en) * 2019-01-11 2019-03-26 淮南矿业(集团)有限责任公司 The main method for replacing lifting ropes of multi-rope of mine
CN109911748B (en) * 2019-04-03 2022-08-26 徐州市三森威尔矿山科技有限公司 Construction process for replacing mine hoisting head rope
CN109835801B (en) * 2019-04-03 2022-04-26 徐州市工大三森科技有限公司 Construction process for replacing leading rope in mine hoisting head rope process
CN109879147A (en) * 2019-04-03 2019-06-14 徐州市三森威尔矿山科技有限公司 A kind of replacement mine hoisting head rope turns over the construction technology of rope in the process
CN112723123B (en) * 2020-12-23 2022-04-05 莱芜莱新铁矿有限责任公司 First rope replacing equipment of multi-rope friction well tower type elevator

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
PL76933B1 (en) * 1971-05-05 1975-02-28
RO101155B1 (en) * 1988-02-25 1993-02-15 Adjusting device for winding rope
CN101786570A (en) * 2010-03-17 2010-07-28 山东煤安矿山提升设备安装有限公司 Process for replacing hoisting ropes
CN102849587A (en) * 2012-08-30 2013-01-02 徐州市工大三森科技有限公司 Method and device for replacing mine hoisting ropes
CN105016184A (en) * 2015-07-08 2015-11-04 徐州九益科技有限公司 Replacement process for lifting steel wire rope of vertical shaft multi-rope friction lifter

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
PL76933B1 (en) * 1971-05-05 1975-02-28
RO101155B1 (en) * 1988-02-25 1993-02-15 Adjusting device for winding rope
CN101786570A (en) * 2010-03-17 2010-07-28 山东煤安矿山提升设备安装有限公司 Process for replacing hoisting ropes
CN102849587A (en) * 2012-08-30 2013-01-02 徐州市工大三森科技有限公司 Method and device for replacing mine hoisting ropes
CN105016184A (en) * 2015-07-08 2015-11-04 徐州九益科技有限公司 Replacement process for lifting steel wire rope of vertical shaft multi-rope friction lifter

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
千米深井多绳摩擦提升机首绳更换工艺;董佩等;《江西煤炭科技》;20141231(第4期);第68-70页

Also Published As

Publication number Publication date
CN107651546A (en) 2018-02-02

Similar Documents

Publication Publication Date Title
CN107651546B (en) The main replacing lifting ropes of multi-rope technique of vertical
CN108910668B (en) Method for quickly replacing vertical shaft lifting rope and lifting container in same cycle
CN104631329A (en) Method for adjusting overall line shape of continuous catwalk of suspension bridge
CN203638992U (en) Break-proof rope device of tower-type crane
CN108190742A (en) A kind of operating method for replacing lifting equipment steel wire rope
CN204980828U (en) Hook rigging
CN203865920U (en) Steel wire rope winding structure for large-tonnage crane hoisting mechanism
CN205011193U (en) Spacing locking means of bbservation elevator
CN203529710U (en) Special device for hoisting cable reel
CN202609847U (en) Double-row rope synchronous hoister for window-cleaning machine
CN104724615A (en) Penetrating and winding method of large-diameter variable-amplitude steel wire rope of large moving-arm type tower crane
CN210029678U (en) Cage lifting anti-falling device for shaft well building construction
CN202992022U (en) Dedicated device for connecting steel wire ropes of hoisting mechanism of crane
CN102358598A (en) Special lift truck for steel wire rope
CN208429744U (en) A kind of new and old rope connection
CN102237654A (en) Tool and method for replacing jumper string at double angle hanging point
CN203006760U (en) Crane cable wire adjusting device
CN102040136A (en) Elevator rope pulley
CN104495645A (en) Structure capable of mounting and dismounting balancing weight automatically by tower crane
CN206395759U (en) One kind rotation clamp crane rope protector
CN204416891U (en) A kind of head four rope lifting wheels
CN204434124U (en) Tower machine is from the structure installing and certainly dismantle counterbalanced weight
CN105398919A (en) Traction structure of lower-driven type counterweight-free elevator
CN204643682U (en) Traffic guideboard column hanging apparatus
CN204416979U (en) One can accelerate hanging device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant