CN107642109A - A kind of town road heavy well cover walling crib ruggedized construction and its construction method - Google Patents
A kind of town road heavy well cover walling crib ruggedized construction and its construction method Download PDFInfo
- Publication number
- CN107642109A CN107642109A CN201710846639.5A CN201710846639A CN107642109A CN 107642109 A CN107642109 A CN 107642109A CN 201710846639 A CN201710846639 A CN 201710846639A CN 107642109 A CN107642109 A CN 107642109A
- Authority
- CN
- China
- Prior art keywords
- walling crib
- prefabricated
- well
- road
- ruggedized construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 39
- 239000004567 concrete Substances 0.000 claims abstract description 42
- 229920001684 low density polyethylene Polymers 0.000 claims abstract description 40
- 239000004702 low-density polyethylene Substances 0.000 claims abstract description 40
- 239000006260 foam Substances 0.000 claims abstract description 23
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 6
- 239000000463 material Substances 0.000 claims description 16
- 238000007689 inspection Methods 0.000 claims description 10
- 239000004575 stone Substances 0.000 claims description 7
- 239000002689 soil Substances 0.000 claims description 6
- 239000004576 sand Substances 0.000 claims description 5
- 210000000981 epithelium Anatomy 0.000 claims description 4
- 239000011150 reinforced concrete Substances 0.000 claims description 4
- 238000005266 casting Methods 0.000 claims description 3
- VGGSQFUCUMXWEO-UHFFFAOYSA-N Ethene Chemical compound C=C VGGSQFUCUMXWEO-UHFFFAOYSA-N 0.000 claims description 2
- 239000005977 Ethylene Substances 0.000 claims 1
- 230000001112 coagulating effect Effects 0.000 claims 1
- 238000012423 maintenance Methods 0.000 abstract description 7
- 238000005336 cracking Methods 0.000 abstract description 5
- 239000010410 layer Substances 0.000 description 37
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 7
- 230000000694 effects Effects 0.000 description 5
- 239000011449 brick Substances 0.000 description 3
- 230000015271 coagulation Effects 0.000 description 3
- 238000005345 coagulation Methods 0.000 description 3
- 239000010881 fly ash Substances 0.000 description 3
- 238000005213 imbibition Methods 0.000 description 3
- 235000008733 Citrus aurantifolia Nutrition 0.000 description 2
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 235000011941 Tilia x europaea Nutrition 0.000 description 2
- 238000009411 base construction Methods 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 239000000567 combustion gas Substances 0.000 description 2
- 230000006378 damage Effects 0.000 description 2
- 239000004571 lime Substances 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 239000010865 sewage Substances 0.000 description 2
- 239000002344 surface layer Substances 0.000 description 2
- 229910001141 Ductile iron Inorganic materials 0.000 description 1
- 239000004698 Polyethylene Substances 0.000 description 1
- 239000010426 asphalt Substances 0.000 description 1
- 239000011384 asphalt concrete Substances 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- -1 polyethylene Polymers 0.000 description 1
- 229920000573 polyethylene Polymers 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 239000000047 product Substances 0.000 description 1
- 239000011241 protective layer Substances 0.000 description 1
- 230000011514 reflex Effects 0.000 description 1
- 238000004062 sedimentation Methods 0.000 description 1
- GOLXNESZZPUPJE-UHFFFAOYSA-N spiromesifen Chemical compound CC1=CC(C)=CC(C)=C1C(C(O1)=O)=C(OC(=O)CC(C)(C)C)C11CCCC1 GOLXNESZZPUPJE-UHFFFAOYSA-N 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
Abstract
The present invention discloses a kind of town road heavy well cover walling crib ruggedized construction, prefabricated walling crib, cystosepiment and pit shaft including setting gradually direction earthwork grille from top to bottom, the bottom face external circumferential of prefabricated walling crib is provided with prefabricated well cycle basis seat, cystosepiment is arranged between prefabricated walling crib and pit shaft, and concrete has been poured between prefabricated well cycle basis seat and road structure layer;Well lid is placed on prefabricated walling crib top by support frame.Ruggedized construction in the present invention, coordinate low density polyethylene (LDPE) closed-cell foam plate shape into the semirigid structure body of rigid flexible system using the prefabricated walling crib with pedestal, the intensity of sub-surface around walling crib is improved, increased car dynamic load lifting surface area, has disperseed well week roadbase load;The semirigid structure body of rigid flexible system, reduce the quality problems such as well week pavement cracking, breakage and well lid sinking, ensure surface evenness so that road-ability and security are greatly improved, while also reduce road maintenance, maintenance costs.
Description
Technical field
The present invention relates to Municipal Road Engineering technical field of construction, more particularly to a kind of town road heavy well cover walling crib
Ruggedized construction and its construction method.
Background technology
Major part urban road in China's is steady using lime stabilized soil, lime-fly-ash stabilization soil, lime fly ash at present
Determine rubble and cement stabilized macadam to belong to semi-rigid plate body as road deck structure as base layer structure, bituminous concrete and hold
Carry structure design.Based on inspection shaft uses armored concrete in road, concrete segment or brick setting are well bore, are used in well week
2:8 dirt or graded sand and stone backfill, armored concrete is prefabricated or preliminary shaft is built in building block (brick) by laying bricks or stones, spheroidal graphite cast-iron walling crib (lid) with 30~
The C30 concrete parcel that 50cm is wide, 25cm is thick, reserved 4cm thickness perform asphalt concrete pavement structure, belong to rigid structure and set
Meter.Overlapped between road and inspection shaft both structure types using bituminous concrete, once multibody system sedimentation is uneven, dynamic
Bituminous concrete lap-joint is easily sheared destruction under load action, or well week backfill (surface layer) roll it is unreal, pour it is not whole,
The reasons such as mortar strength is inadequate, well lid installation is undesirable cause superficial layer cracking herein.If repaired not in time, rainwater enters
Enter roadbase, damage face will progressively expand.
The content of the invention
It is an object of the invention to provide a kind of town road heavy well cover walling crib ruggedized construction, effectively solve it is current I
The inspection shafts such as rainwater, sewage, reclaimed water, upper water, combustion gas and telecommunications in the range of state's urban road occur well lid periphery (10~
35cm) the quality problems such as pavement cracking, breakage and well lid sinking, ensure municipal road pavement flatness so that road-ability
It is greatly improved with safety, while reduces road maintenance, maintenance costs.
To achieve the above object, the invention provides following scheme:The present invention provides a kind of town road heavy well cover well
Ruggedized construction is enclosed, including prefabricated walling crib, cystosepiment and the pit shaft set gradually from top to bottom, the bottom of the prefabricated walling crib have
The prefabricated well cycle basis seat of integrally connected, the cystosepiment are arranged between the prefabricated walling crib and the pit shaft, the prefabricated well
Concrete is poured between circle and road structure layer, the upper surface of the concrete is concordant with the upper surface of the prefabricated walling crib;
Well lid is used for by fixed placement on the prefabricated walling crib top.
Optionally, the prefabricated well cycle basis seat it is wide go out the walling crib the value of top external diameter be more than or equal to 750mm, it is and described
The upper surface of prefabricated well cycle basis seat is inclined-plane.
Optionally, the prefabricated walling crib is prefabricated reinforced concrete walling crib, and the epithelium of the prefabricated walling crib is using at dabbing
Reason.
Optionally, the lateral surface of the prefabricated well cycle basis seat is placed adjacent with the inwall of going to a grassroots level of road structure layer.
Optionally, it is equipped with one layer pair on the surface of the concrete and the upper basic unit of the road structure layer first poured
To GSZ, the top of the direction earthwork grille is roadway base surfaces layer.
Optionally, a screed-coat has been poured between the bottom of the prefabricated well cycle basis seat and the underlayment of road structure layer.
Optionally, the cystosepiment is low density polyethylene (LDPE) closed-cell foam plate, and the low density polyethylene (LDPE) closed-cell foam
The thickness of plate is 100mm.
Optionally, the outside of the pit shaft and be roadbed positioned at the bottom of the road structure layer, the roadbed passes through well
All backfilling materials be filled and it is counter after the completion of filling dig, the well week backfilling material is graded sand and stone backfilling material.
The town road heavy type well curb well lid carried out using above-mentioned town road heavy type well curb well lid ruggedized construction reinforces knot
The construction method of structure, Specific construction step are:
Roadway base surfaces layer and upper roadbed shared by anti-digging inspection shaft and its surrounding etc.;
The roadbed of pit shaft surrounding is complete by the backfilling material backfill of well week according to specification, then lay one layer of pitch coagulation
Soil;
The underlayment of laying road structure sheaf, and lay one layer of bituminous concrete on the surface of underlayment;
Low density polyethylene (LDPE) closed-cell foam plate is fixed on the top of pit shaft, and on the top of the underlayment and described low
The periphery of density polyethylene closed-cell foam plate pours screed-coat by ready-mixed concrete;
Laid on the top of the screed-coat and low density polyethylene (LDPE) closed-cell foam plate prefabricated with prefabricated well cycle basis seat
Walling crib;
The casting concrete between the top surface and road structure layer of prefabricated well cycle basis seat, the upper surface of concrete with it is prefabricated
Walling crib is concordant, 14 days curing periods, road bituminous layers is done after reaching 2/3 intensity;
One layer of direction earthwork grille is laid on the surface of the concrete poured and the road structure layer first poured;
Finally lay and shakeout road surface, periodically conserved.
The present invention achieves following technique effect relative to prior art:
Well lid walling crib ruggedized construction in the present invention, between road deck and basic unit place one layer of direction earthwork grille and
Using with prefabricated well cycle basis seat prefabricated reinforced concrete walling crib coordinate 100mm thickness low density polyethylene (LDPE) closed-cell foam plate shape into
The semirigid structure body of rigid flexible system, the cast-in-place concrete of this structure and prefabricated well cycle basis seat improve road surface base around walling crib
The intensity of layer, increased car dynamic load lifting surface area, and had disperseed well week roadbase load;Direction earthwork grille, can effectively it hinder
Only and delayed reflex crack generation, rapidly absorb and spread as the stress caused by gravity, the life-span is used in extension;Low-density is gathered
Ethene closed-cell foam plate has that return rate is strong, and no water imbibition, impact resistance and against weather are strong, absorbs superstructure load and base
Holder structure counter-force, serve the effect of elastic structure.One layer of direction earthwork grille and just is placed between road deck and basic unit
The semirigid structure body of soft combination, reduce the quality problems such as well week pavement cracking, breakage and well lid sinking, ensure town road
Surface evenness so that road-ability and security are greatly improved, while also reduce road maintenance, upkeep charges
With.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to institute in embodiment
The accompanying drawing needed to use is briefly described, it should be apparent that, drawings in the following description are only some implementations of the present invention
Example, for those of ordinary skill in the art, without having to pay creative labor, can also be according to these accompanying drawings
Obtain other accompanying drawings.
Fig. 1 is the overall structure diagram of town road heavy well cover walling crib ruggedized construction of the present invention;
Wherein, 1 direction earthwork grille;Basic unit on 2;3 go to a grassroots level;4 underlayments;5 roadbeds;6 first anti-digging interfaces;7 coagulations
Soil;8 prefabricated well cycle basis seats;9 screed-coats;10 well week backfilling material;11 prefabricated walling cribs;12 low density polyethylene (LDPE) closed-cell foam plates;
13 pit shafts;14 second anti-digging interfaces;15 well lids.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of creative work is not made
Embodiment, belong to the scope of protection of the invention.
It is an object of the invention to provide a kind of town road heavy well cover walling crib ruggedized construction, effectively solve it is current I
The inspection shafts such as rainwater, sewage, reclaimed water, upper water, combustion gas and telecommunications in the range of state's urban road occur well lid periphery (10~
35cm) the quality problems such as pavement cracking, breakage and well lid sinking, ensure municipal road pavement flatness so that road-ability
It is greatly improved with safety, while reduces road maintenance, maintenance costs.
Town road heavy well cover walling crib ruggedized construction provided by the invention, including two-way geotechnique is set gradually from top to bottom
Prefabricated walling crib, cystosepiment and the pit shaft of grid, the bottom of prefabricated walling crib have the prefabricated well cycle basis seat of integrally connected, and cystosepiment is set
Be placed between prefabricated walling crib and pit shaft, poured concrete between prefabricated walling crib and road structure layer, the upper surface of concrete with
The upper surface of prefabricated walling crib is concordant;Well lid is used for by fixed placement on prefabricated walling crib top.
The well lid walling crib ruggedized construction, place one layer of direction earthwork grille between road deck and basic unit and use carries
The prefabricated walling crib of prefabricated well cycle basis seat coordinates the semirigid structure body of cystosepiment formation rigid flexible system, the cast-in-place coagulation of this structure
Native and prefabricated walling crib improves the intensity of sub-surface around walling crib, increased car dynamic load lifting surface area, it is thoughtful to have disperseed well
Base course load;Low density polyethylene (LDPE) closed-cell foam plate has that return rate is strong, and no water imbibition, impact resistance and against weather are strong,
Superstructure load and base construction counter-force are absorbed, serves the effect of elastic structure.
In order to facilitate the understanding of the purposes, features and advantages of the present invention, it is below in conjunction with the accompanying drawings and specific real
Applying mode, the present invention is further detailed explanation.
Fig. 1 is refer to, wherein, Fig. 1 is that the overall structure of town road heavy well cover walling crib ruggedized construction of the present invention is illustrated
Figure.
As shown in figure 1, the present invention provides a kind of town road heavy well cover walling crib ruggedized construction, including from top to bottom successively
Prefabricated walling crib 11, cystosepiment and the pit shaft 13 set, the bottom of prefabricated walling crib 11 have the prefabricated well cycle basis seat 8 of integrally connected,
Cystosepiment is arranged between prefabricated walling crib 11 and pit shaft 13, and C15 concrete has been poured between prefabricated walling crib 11 and road structure layer
7, the upper surface of concrete seven is concordant with the upper surface of prefabricated walling crib 11;Well lid 15 is used for by fixed placement in prefabricated walling crib 11
Top.
For walling crib using prefabricated, the walling crib pedestal being wholely set with walling crib is pedestal foot, prefabricated well cycle basis seat 8 it is wide go out walling crib 13
The value of top external diameter be more than or equal to 750mm, the thickness of prefabricated well cycle basis seat 8 is not less than 100mm, and intensity is not less than C30, the north
Area, which needs to use, is not less than label D200 frost-resistant concretes, and the upper surface of prefabricated well cycle basis seat 8 is inclined-plane.Prefabricated walling crib 11
For prefabricated reinforced concrete walling crib, reinforcing bar uses HRB400 reinforcing bars, and protective layer 20mm, the epithelium of prefabricated walling crib 11 is using at dabbing
Reason, the lateral surface of prefabricated well cycle basis seat 8 are close to 3 inwalls of going to a grassroots level of road structure layer.
One layer of two-way geotechnological lattice are equipped with concrete seven and the surface of the upper basic unit 2 of the road structure layer first poured
Grid 1, ensure walling crib and surface layer roadbase collective effect, the top of direction earthwork grille 1 by laying direction earthwork grille 1
For roadbase.
A screed-coat 9 is poured between the bottom of prefabricated well cycle basis seat 8 and the underlayment 4 of road structure layer, screed-coat 9 is
The C15 ready-mixed concrete screed-coats poured, horizontal placement basis is provided prefabricated well cycle basis seat 8.
Cystosepiment is low density polyethylene (LDPE) closed-cell foam plate 12, and low density polyethylene (LDPE) closed-cell foam plate 12 has return rate
By force, no water imbibition, impact resistance and against weather are strong, absorb superstructure load and base construction counter-force, serve elastic knot
The effect of structure body, the thickness of low density polyethylene (LDPE) closed-cell foam plate 12 is 100mm.
The outside of pit shaft 13 and be roadbed 5 positioned at the bottom of road structure layer, roadbed 5 is carried out by well week backfilling material 10
Filling, well week backfilling material 10 be graded sand and stone backfilling material.The material of each road structure layer is stablized broken for cement, flyash
Stone, emulsified asphalt, bituminous concrete etc..
The town road heavy type well curb well lid carried out using above-mentioned town road heavy type well curb well lid ruggedized construction reinforces knot
The construction method of structure, Specific construction step are:
It is anti-to dig inspection shaft, first it is anti-dig that interface 6 is counter to be dug, while to roadway base surfaces Ceng Heshang roads shared around
Base etc. is counter to be dug;
The roadbed 5 of the surrounding of pit shaft 13 is backfilled completely according to specification by well week backfilling material 10, then lays one layer of drip
Blue or green concrete, in order to ensure the compactness of inspection shaft surrounding and the bearing capacity of roadbed 5, inspection shaft surrounding is using graded sand and stone backfill point
Layer compacting, width are not less than 400mm, and compactness is not less than 0.94, and the compactness of roadbase should meet《Highway bed construction skill
Art specification》Requirement;
The underlayment 4 of laying road structure sheaf, and lay one layer of bituminous concrete on the surface of underlayment 4;
Fix low density polyethylene (LDPE) closed-cell foam plate 12 on the top of pit shaft 13, and on the top of the underlayment 4 and
The periphery of the low density polyethylene (LDPE) closed-cell foam plate 12 pours screed-coat by ready-mixed concrete;
Laid on the top of the screed-coat 9 and low density polyethylene (LDPE) closed-cell foam plate 12 with prefabricated well cycle basis seat 8
Prefabricated walling crib 11;
The casting concrete 7 between the top surface and road structure layer of prefabricated well cycle basis seat 8, the upper surface of concrete seven with
Prefabricated walling crib 11 is concordant;
One layer of direction earthwork grille 1 is laid on the surface of the concrete seven poured and the road structure layer first poured;
Finally lay and shakeout road surface, periodically conserved.
In work progress, prefabricated well cycle basis seat 8, which is instead dug, to be carried out after the completion of the laying of roadway base surfaces layer, in the second anti-digging
Interface 14 (basic unit is counter to dig interface) is carried out, and when walling crib bottom is road structure layer, the primer thickness of roadbed 5 is not less than
17cm;After the completion of anti-digging, the upper surface of underlayment 4 is cleared up, pours C15 ready-mixed concrete screed-coats in time, pacified on the top of pit shaft 13
Put 100mm thickness low density polyethylene (LDPE) closed-cell foams plate 12;Then walling crib is laid, the placement in whole work progress is required to gently take
Put down gently, forbid to get rid of and touch, pay attention to finished product protection;Walling crib epithelium needs dabbing to handle, and after the completion for the treatment of that walling crib is laid, it is pre- to pour C15 in time
Mixed concrete, upper surface is concordant with walling crib upper surface, 14 days curing periods, road bituminous layers is done again after reaching 2/3 intensity.
The edge bituminous concrete of inspection shaft should use artificial hammer ram, hot iron supplement compacting, and compactness should reach 0.97
More than.
It should be noted that the town road heavy well cover walling crib ruggedized construction in the present invention, the above-mentioned limit on numerical value
It is fixed only for the purpose of illustration, it is not limited to only to be used using above-mentioned numerical value, according to practice of construction and service condition
Appropriate adjustment can be carried out, within the scope of the present invention;The selection of concrete strength etc. can also enter according to actual conditions
Row adjustment;Low density polyethylene (LDPE) closed-cell foam plate in the present invention is also replaced by the sheet material of other materials for meeting to require,
Within the scope of the present invention.
Specific case is applied in the present invention to be set forth the principle and embodiment of the present invention, above example
Illustrate to be only intended to help the method and its core concept for understanding the present invention;Meanwhile for those of ordinary skill in the art, according to
According to the thought of the present invention, in specific embodiments and applications there will be changes.In summary, this specification content
It should not be construed as limiting the invention.
Claims (9)
- A kind of 1. town road heavy well cover walling crib ruggedized construction, it is characterised in that:It is prefabricated including what is set gradually from top to bottom Walling crib, cystosepiment and pit shaft, the bottom of the prefabricated walling crib have the prefabricated well cycle basis seat of integrally connected, and the cystosepiment is set Between the prefabricated walling crib and the pit shaft, concrete has been poured between the prefabricated walling crib and road structure layer, it is described mixed The upper surface for coagulating soil is concordant with the upper surface of the prefabricated walling crib;Well lid is used for by fixed placement on the prefabricated walling crib top End.
- A kind of 2. town road heavy well cover walling crib ruggedized construction according to claim 1, it is characterised in that:It is described prefabricated Walling crib pedestal it is wide go out the walling crib the value of top external diameter be more than or equal to 750mm, and the upper surface of the prefabricated well cycle basis seat is Inclined-plane.
- A kind of 3. town road heavy well cover walling crib ruggedized construction according to claim 1, it is characterised in that:It is described prefabricated Walling crib is prefabricated reinforced concrete walling crib, and the epithelium of the prefabricated walling crib is handled using dabbing.
- A kind of 4. town road heavy well cover walling crib ruggedized construction according to claim 1, it is characterised in that:It is described prefabricated The inwall of going to a grassroots level of the lateral surface of walling crib pedestal and road structure layer is placed adjacent.
- A kind of 5. town road heavy well cover walling crib ruggedized construction according to claim 1, it is characterised in that:Described mixed Solidifying soil and the surface of the upper basic unit of the road structure layer first poured are equipped with one layer of direction earthwork grille, the two-way geotechnique The top of grid is roadway base surfaces layer.
- A kind of 6. town road heavy well cover walling crib ruggedized construction according to claim 1, it is characterised in that:It is described prefabricated A screed-coat has been poured between the bottom of walling crib pedestal and the underlayment of road structure layer.
- A kind of 7. town road heavy well cover walling crib ruggedized construction according to claim 1, it is characterised in that:The foam Plate is low density polyethylene (LDPE) closed-cell foam plate, and the thickness of the low density polyethylene (LDPE) closed-cell foam plate is 100mm.
- A kind of 8. town road heavy well cover walling crib ruggedized construction according to claim 1, it is characterised in that:The pit shaft Outside and be roadbed positioned at the bottom of the road structure layer, the roadbed is filled by well week backfilling material, and Spread it is anti-when walling crib is reinforced after roadway base surfaces layer dig, the well week backfilling material is graded sand and stone backfilling material.
- 9. a kind of construction method of town road heavy type well curb well lid ruggedized construction, including any one of claim 1-8 Town road heavy type well curb well lid ruggedized construction, it is characterised in that:Specific construction step is:Roadway base surfaces layer and upper roadbed shared by anti-digging inspection shaft and its surrounding etc.;The roadbed of pit shaft surrounding is complete by the backfilling material backfill of well week according to specification, then lay one layer of bituminous concrete;The underlayment of laying road structure sheaf, and lay one layer of bituminous concrete on the surface of underlayment;Low density polyethylene (LDPE) closed-cell foam plate is fixed on the top of pit shaft, and on the top of the underlayment and the low-density The periphery of ethylene closed cell cystosepiment pours screed-coat by ready-mixed concrete;The prefabricated walling crib with prefabricated well cycle basis seat is laid on the top of the screed-coat and low density polyethylene (LDPE) closed-cell foam plate;The casting concrete between the top surface and road structure layer of prefabricated well cycle basis seat, the upper surface of concrete and prefabricated walling crib Concordantly, curing period 14 days, road bituminous layers are done after reaching 2/3 intensity;One layer of direction earthwork grille is laid on the surface of the concrete poured and the road structure layer first poured;Finally lay and shakeout road surface, periodically conserved.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710846639.5A CN107642109A (en) | 2017-09-19 | 2017-09-19 | A kind of town road heavy well cover walling crib ruggedized construction and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710846639.5A CN107642109A (en) | 2017-09-19 | 2017-09-19 | A kind of town road heavy well cover walling crib ruggedized construction and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107642109A true CN107642109A (en) | 2018-01-30 |
Family
ID=61111791
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710846639.5A Pending CN107642109A (en) | 2017-09-19 | 2017-09-19 | A kind of town road heavy well cover walling crib ruggedized construction and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107642109A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109440821A (en) * | 2018-12-18 | 2019-03-08 | 温州金德市政建设有限公司 | Pipe well road and municipal well lid integral structure |
CN110284525A (en) * | 2019-04-02 | 2019-09-27 | 贵州磷镁材料有限公司 | A kind of anti-settling manhole cover construction and the maintenance of impaired well lid or replacing options |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006112075A (en) * | 2004-10-13 | 2006-04-27 | Shinichi Tsubakimori | Manhole and installation method of manhole cover supporting frame |
KR100665210B1 (en) * | 2005-09-13 | 2007-01-09 | 조용우 | Concrete mold for manhole manufacture |
CN103806470A (en) * | 2014-03-14 | 2014-05-21 | 江苏华光双顺机械制造有限公司 | Production and installation method for reinforced concrete inspection well |
CN103835217A (en) * | 2013-12-02 | 2014-06-04 | 天津炬实科技发展有限公司 | Method for prevention and treatment on damage and depression of pavement around inspection well |
-
2017
- 2017-09-19 CN CN201710846639.5A patent/CN107642109A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006112075A (en) * | 2004-10-13 | 2006-04-27 | Shinichi Tsubakimori | Manhole and installation method of manhole cover supporting frame |
KR100665210B1 (en) * | 2005-09-13 | 2007-01-09 | 조용우 | Concrete mold for manhole manufacture |
CN103835217A (en) * | 2013-12-02 | 2014-06-04 | 天津炬实科技发展有限公司 | Method for prevention and treatment on damage and depression of pavement around inspection well |
CN103806470A (en) * | 2014-03-14 | 2014-05-21 | 江苏华光双顺机械制造有限公司 | Production and installation method for reinforced concrete inspection well |
Non-Patent Citations (2)
Title |
---|
张迎辉: "检查井周围路面沉陷碎裂的防治技术", 《市政技术》 * |
王水华等: "一种随路基沉降式检查井井盖及支座安装方法介绍", 《特种结构》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109440821A (en) * | 2018-12-18 | 2019-03-08 | 温州金德市政建设有限公司 | Pipe well road and municipal well lid integral structure |
CN110284525A (en) * | 2019-04-02 | 2019-09-27 | 贵州磷镁材料有限公司 | A kind of anti-settling manhole cover construction and the maintenance of impaired well lid or replacing options |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207987964U (en) | A kind of reinforcing inspection shaft | |
CN110578290B (en) | Bridge abutment back backfill structure and construction method thereof | |
CN202787044U (en) | Longitudinal crack treatment structure for bituminous concrete pavement | |
CN104452510B (en) | Immediate construction method of rural road | |
CN106567410A (en) | New construction method of municipal road inspection well | |
CN109914173A (en) | Foam lightweight soil pours platform back structure and its construction method in Expressway Extension Project | |
CN108316089A (en) | It is a kind of that road surface method is repaired using plain concrete and reinforced concrete | |
CN107460890A (en) | A kind of city bituminous concrete pavement inspection shaft construction method | |
CN206625096U (en) | A kind of reinforced rubble frame structure subgrade strengthening system | |
CN106676993A (en) | Roadbed reinforcing system of reinforced gravel framework structure and reinforcing method of roadbed reinforcing system | |
CN107700299B (en) | Overpass lower-layer ground road structure and construction method thereof | |
CN210262555U (en) | Light soil road structure | |
CN202849895U (en) | Structure for repairing urban asphalt pavements | |
CN107642109A (en) | A kind of town road heavy well cover walling crib ruggedized construction and its construction method | |
CN207714057U (en) | A kind of anti-settling road structure | |
CN207211362U (en) | A kind of basement bottom board fish tail and waterproof layer | |
CN106836034B (en) | High-fill cover plate culvert flexible load shedding system and construction method | |
CN207228166U (en) | A kind of town road heavy well cover walling crib ruggedized construction | |
CN210529400U (en) | Solidified building residue soil road structure | |
CN104499397A (en) | Asphalt pavement structure based on coordination of deformation of subgrade and pavement | |
CN108951383A (en) | A kind of construction technology that the regeneration of cement stabilized macadam base presplitting formula is reinforced | |
CN210797245U (en) | Structure is backfilled to bridgehead abutment back of body | |
CN211079810U (en) | Avoid pitch highway of ponding | |
CN210657841U (en) | Rigid and flexible seamless pavement base layer structure | |
CN207597177U (en) | A kind of elevated bridge lower floor road structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180130 |