CN107622381A CN201710928610.1A CN201710928610A CN107622381A CN 107622381 A CN107622381 A CN 107622381A CN 201710928610 A CN201710928610 A CN 201710928610A CN 107622381 A CN107622381 A CN 107622381A
Authority
CN
China
Prior art keywords
information
target
worker
engineering
registration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710928610.1A
Other languages
Chinese (zh)
Inventor
王成荣
袁公民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Migrant Workers Plus Network Technology Co Ltd
Original Assignee
Sichuan Migrant Workers Plus Network Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Migrant Workers Plus Network Technology Co Ltd filed Critical Sichuan Migrant Workers Plus Network Technology Co Ltd
Priority to CN201710928610.1A priority Critical patent/CN107622381A/en
Publication of CN107622381A publication Critical patent/CN107622381A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

Recorded workpoints account checking method and device the invention provides one kind, it is related to the technical field that architectural engineering is recorded workpoints, this method includes obtaining first and recorded workpoints information, and first records workpoints the engineering information to purpose project that information is recorded by worker, wherein, engineering information includes labor service information and labour and capital information;Obtain second to record workpoints information, second records workpoints engineering information of the information by the worker that the shift management personnel of purpose project record to purpose project;First information of recording workpoints is compared with the second information of recording workpoints, to determine working condition and wages situation of the worker to purpose project.The present invention alleviates traditional method of recording workpoints and the technical problem of mistake easily occurs.

Description

Method and device for checking account by recording work
Technical Field
The invention relates to the technical field of construction engineering work recording, in particular to a work recording and account checking method and device.
Background
The building industry is an important material production department of national economy, and has close relation with the development of the economy of the whole country and the improvement of the life of people. China is in the transition stage from low-income countries to medium-income countries, the building industry is growing rapidly, and the building industry also contributes greatly to the increase of national economy. The production value of the construction industry in 2016 is nearly 20 trillion and accounts for 7 percent of GDP.
The vigorous development of the construction industry cannot be supported by a plurality of workers, the efforts of the workers make the progress of the construction project change from time to time, wherein the engineering information of each worker also changes, the engineering information comprises labor information and labor information, the labor information is the working condition information of the workers in the construction project, and the labor information is the salary condition information of the workers in the construction project. The engineering information of workers is very important for workers and projects, at present, the engineering information of the workers is recorded in a paper mode, or is recorded in a computer of the workers by team managers, or is recorded in the computer of the workers, the engineering recording modes cause errors of workers due to personal information acquisition errors or writing errors and the like, and the personal information acquisition errors or writing errors are inevitable problems.
For the technical problem that the above traditional construction method of the building engineering inevitably has errors, an effective solution is lacked at present.
Disclosure of Invention
In view of the above, the present invention provides a work accounting method and a work accounting device, so as to solve the technical problem that the conventional work accounting method is prone to error.
In a first aspect, an embodiment of the present invention provides a record work reconciliation method, applied to a management platform, including:
acquiring first labor information, wherein the first labor information is project information of a target project recorded by a worker, and the project information comprises labor information and labor information;
acquiring second work recording information, wherein the second work recording information is the project information of the target project, recorded by team managers of the target project, of the workers;
and comparing the first project recording information with the second project recording information to determine the working condition and the salary condition of the worker on the target project.
With reference to the first aspect, an embodiment of the present invention provides a first possible implementation manner of the first aspect, where the obtaining the second labor information includes:
pushing the first engineering information to the team manager so that the team manager compares the first engineering information with first target engineering information to obtain different information in the first engineering information and the first target engineering information, verifying the different information to obtain the verified first target engineering information, wherein the first target engineering information is the engineering information of the worker on the target engineering, which is obtained in advance by the team manager;
receiving the verified first target engineering information sent by the team manager, and storing the verified first target engineering information in a storage module indicated by target tag information to determine the verified first target engineering information as the second work recording information,
the target tag information is tag information set for the worker in advance.
With reference to the first possible implementation manner of the first aspect, an embodiment of the present invention provides a second possible implementation manner of the first aspect, where before acquiring the second recording information, the method further includes:
and pushing a work statistic page to the team managers so that the team managers operate the statistic information in the work statistic page, wherein the statistic information after operation comprises the target tag information.
With reference to the first aspect, an embodiment of the present invention provides a third possible implementation manner of the first aspect, where the obtaining the first labor information includes:
after detecting that the worker logs in a target account, acquiring recording request information sent by the worker, wherein the target account is an account which is allocated to the worker in advance;
after the recording request information is acquired, a target page is pushed to the worker according to account information, wherein the account information is the account information of the target account;
receiving the first recording information input by the worker in the target page.
With reference to the third possible implementation manner of the first aspect, an embodiment of the present invention provides a fourth possible implementation manner of the first aspect, where pushing a target page to the worker according to account information includes:
pushing a first working form, a second working form and a third working form to the worker according to the account information,
wherein the first work form is set to the worker record the completed work amount;
the second work table is set to the worker record total work volume of the contract and/or remaining unfinished work volume;
the third work form is set to the worker record payroll settlement condition;
the first working table, the second working table and the third working table are tables on the same page or tables on different pages.
With reference to the third possible implementation manner of the first aspect, an embodiment of the present invention provides a fifth possible implementation manner of the first aspect, where before the obtaining of the first labor information, the method further includes:
acquiring first sub-registration information received through a first receiving mode and second sub-registration information received through a second receiving mode, wherein the first receiving mode and the second receiving mode are different receiving modes;
determining different information between the first sub-registration information and the second sub-registration information so that a supervisor of the management platform obtains correction information based on the different information;
receiving the correction information sent by the supervisor, and correcting the first sub-registration information and the second sub-registration information according to the correction information to obtain corrected first sub-registration information and corrected second sub-registration information;
and allocating the target account to the worker according to the corrected first sub-registration information or the corrected second sub-registration information.
With reference to the fifth possible implementation manner of the first aspect, an embodiment of the present invention provides a sixth possible implementation manner of the first aspect, where acquiring the first sub-registration information received by the first receiving manner includes:
receiving access information submitted by the worker, pushing a first registration page to the worker according to the access information, and generating first sub-registration information according to information filled in the first registration page by the worker; or,
receiving invitation information sent by the team managers, pushing a second registration page to the worker according to the invitation information, and generating first sub-registration information according to information filled in the second registration page by the worker; or receiving registration information sent by personnel management personnel, and determining the registration information as the first sub-registration information, wherein the registration information is information registered by the personnel management personnel when the worker joins the target project.
In a second aspect, an embodiment of the present invention further provides a record work reconciliation apparatus, including:
the system comprises a first acquisition module, a second acquisition module and a third acquisition module, wherein the first acquisition module is used for acquiring first labor information which is the project information of a target project recorded by a worker, and the project information comprises labor service information and labor resource information;
the second acquisition module is used for acquiring second engineering information, wherein the second engineering information is the engineering information of the target engineering, recorded by team management personnel of the target engineering, of the worker;
and the first determining module is used for comparing the first project recording information with the second project recording information to determine the working condition and the salary condition of the worker on the target project.
The embodiment of the invention has the following beneficial effects: first, first engineering information and second engineering information are obtained, wherein the first engineering information is project information of a target project recorded by a worker, and the second engineering information is project information of the target project recorded by a team manager of the target project, and the project information comprises labor service information and labor resource information. And then, comparing the first work recording information with the second work recording information to determine the working condition and the salary condition of the worker on the target project, namely, ensuring the recording accuracy of the worker on the project information of the target project in an account checking mode, thereby relieving the technical problem that the traditional work recording method is easy to make mistakes.
Additional features and advantages of the invention will be set forth in the description which follows, and in part will be obvious from the description, or may be learned by practice of the invention. The objectives and other advantages of the invention will be realized and attained by the structure particularly pointed out in the written description and claims hereof as well as the appended drawings.
In order to make the aforementioned and other objects, features and advantages of the present invention comprehensible, preferred embodiments accompanied with figures are described in detail below.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and other drawings can be obtained by those skilled in the art without creative efforts.
Fig. 1 is a flowchart of a record keeping and reconciliation method according to an embodiment of the present invention;
fig. 2 is a flowchart of a method for obtaining second labor information according to an embodiment of the present invention;
fig. 3 is a flowchart of a method for obtaining first labor information according to an embodiment of the present invention;
fig. 4 is a block diagram of a structure of a journaling reconciliation apparatus according to a second embodiment of the present invention.
Icon: 1-a first acquisition module; 2-a second acquisition module; 3-a first determination module.
Detailed Description
To make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings, and it is apparent that the described embodiments are some, but not all embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
At present, the work load of workers is recorded in a paper mode, or a team manager records in a computer of the workers, or the workers record in the computer of the workers, and the engineering labor recording modes have the technical problem that labor recording errors are easy to occur due to personal factors. Based on this, the method and the device for checking account for work in the embodiment of the invention can alleviate the technical problem that errors inevitably occur in the traditional work checking method.
Example one
The method for checking account for work in the embodiment of the invention is applied to a management platform, and as shown in fig. 1, the method comprises the following steps:
step S102, first labor information is obtained, wherein the first labor information is project information of a target project recorded by workers, and the project information comprises labor information and labor information.
Specifically, the labor information at least includes one of the following: the total amount of work a worker needs to complete, the amount of work a worker has completed, and the amount of work a worker has not completed; the labor information includes at least one of: total payroll, loans, outstanding payroll. The engineering quantity refers to a parameter calculated based on an engineering task, for example, a 10-meter long beam; the amount of time refers to a parameter calculated based on the time required to complete the engineering task, including: a parameter calculated by day for day work and a parameter calculated by hour for hour work, for example, a workload of 10 days or a workload of 3 hours.
It is emphasized that the first labor information record is the engineering information of the worker himself in the target engineering.
In addition, the order of acquiring the first recording information and the second recording information is not limited in the embodiments of the present invention.
And step S104, acquiring second engineering information, wherein the second engineering information is the engineering information of workers on the target engineering, which is recorded by the team managers of the target engineering.
Specifically, the team manager is a person who manages worker engineering information in the target engineering.
And S106, comparing the first project recording information with the second project recording information to determine the workload of the worker on the target project.
Specifically, comparing the first engineering information with the second engineering information to determine the workload of the worker on the target engineering, includes: the first labor information and the second labor information are compared to obtain different parts between the first labor information and the second labor information, so that a worker and a manager can check the different parts, and the first labor information and the second labor information are corrected according to a check result, so that the purpose of determining the workload of the worker on the target project is achieved, and the correctness of the workload of the worker on the target project is guaranteed.
The labor reconciliation method is applied to the management platform, namely, the first labor information and the second labor information are acquired, and the first labor information and the second labor information are stored in the management platform.
In the embodiment of the invention, the acquired first and second labor information are stored in the management platform, so that the first and second labor information can be conveniently shared, and then account checking is realized based on the first and second labor information in the management platform, so that the recording accuracy of the workload of a worker on a target project is ensured, and the technical problem that the traditional labor method is easy to make mistakes is solved.
In an optional implementation manner of the embodiment of the present invention, the acquiring the second labor information, as shown in fig. 2, includes:
step S201, first work recording information is pushed to team managers so that the team managers can compare the first work recording information with first target engineering information to obtain different information in the first work recording information and the first target engineering information, the different information is verified to obtain verified first target engineering information, and the first target engineering information is engineering information of workers on target engineering, wherein the first target engineering information is obtained in advance by the team managers;
step S202, receiving the verified first target engineering information sent by the team manager, and storing the verified first target engineering information in a storage module indicated by target label information, so as to determine the verified first target engineering information as second work recording information, wherein the target label information is label information preset for workers.
Specifically, a plurality of label information are arranged in a module which can be accessed by team managers in the management platform, one label information corresponds to one worker, and a page indicated by the label information is used for storing second work recording information of the corresponding worker.
The embodiment of the invention is suitable for the situation that first work recording information is obtained first and then second work recording information is obtained, wherein in the process of obtaining the second work recording information, a team manager can obtain the first work recording information, further, the team manager obtains the verified target engineering information by comparing the first work recording information with the target engineering information so as to ensure the correctness of the verified first target engineering information, and the verified first target engineering information is determined to be the second work recording information so as to ensure the correctness of the obtained second work recording information and be beneficial to ensuring the correctness of the engineering information of the target engineering for workers.
It should be noted that, when the management platform acquires the second engineering information first and then acquires the first engineering information, similarly, the worker may acquire the second engineering information, then compare the second engineering information with the second target engineering information to obtain different information in the second engineering information and the second target engineering information, and verify the different information to obtain the second target engineering information after verification, where the second target engineering information is the engineering information of the worker to the target engineering that is acquired by the worker in advance, so as to ensure the correctness of the acquired first engineering information, which is beneficial to ensuring the correctness of the engineering information of the worker to the target engineering.
In another optional implementation manner of the embodiment of the present invention, before the obtaining of the second labor information, the labor reconciliation method further includes:
and pushing a work statistic page to team managers so that the team managers operate the statistic information in the work statistic page, wherein the operated statistic information comprises target tag information.
Specifically, the work statistic page may include a statistic table, where the statistic table has a plurality of headers, one header stores one tag information, and a table corresponding to one header stores the second labor information. For example, if the table corresponding to the header is at the head of a row, the table corresponding to the header is the other table in the row where the header is located.
In addition, the team manager operates the statistical information in the work statistics page, including: and when the statistical information does not contain the target label information, adding the target label information to the statistical information to ensure the comprehensiveness of the statistical information, so that the second recording information has a corresponding storage module.
In another optional implementation manner of the embodiment of the present invention, as shown in fig. 3, the acquiring the first labor information includes:
step S301, after a worker is detected to log in a target account, acquiring work recording request information sent by the worker, wherein the target account is an account pre-allocated to the worker;
step S302, after the recording request information is obtained, a target page is pushed to a worker according to account information, wherein the account information is the account information of a target account;
step S303, receiving first recording information input by the worker in the target page.
Specifically, the worker has a target account on the management platform, after the worker logs in the target account, the management platform may push a page with successful login to the worker, the page with successful login has a work recording module, and the worker may click the work recording module to send work recording request information.
In addition, after the worker sends the recording request information, the management platform pushes a target page to the worker according to the account information of the worker, and the target page can comprise a table for recording the engineering information by the worker, so that the worker can fill the corresponding engineering information in the table.
In the embodiment of the invention, the first recording information is acquired based on the own account of the worker, the worker logs in the own account to fill in the own engineering information, the first recording information cannot be falsified by other people, and the first recording information is ensured to be filled by the worker.
In another optional implementation manner of the embodiment of the present invention, pushing a target page to a worker according to account information includes:
pushing the first working form, the second working form and the third working form to the worker according to the account information,
wherein the first work form is set to a work load of the worker record having been completed;
the second work table is set to the worker recording the total work volume of the contract and/or the remaining unfinished work volume;
a third work form is set for the worker to record the payroll settlement condition;
the first working table, the second working table and the third working table are tables on the same page or tables on different pages.
The embodiment of the invention realizes the purpose of enabling workers to count the completed workload, the total workload and/or the remaining unfinished workload and the condition of payroll settlement.
In another optional implementation manner of the embodiment of the present invention, before the obtaining of the first labor information, the labor reconciliation method further includes:
acquiring first sub-registration information received through a first receiving mode and second sub-registration information received through a second receiving mode, wherein the first receiving mode and the second receiving mode are different receiving modes;
determining different information between the first sub-registration information and the second sub-registration information so that a supervisor of the management platform obtains correction information based on the different information;
receiving correction information sent by a supervisor, and correcting the first sub-registration information and the second sub-registration information according to the correction information to obtain corrected first sub-registration information and corrected second sub-registration information;
and allocating a target account to the worker according to the corrected first sub-registration information or the corrected second sub-registration information.
Specifically, the registration in the construction project is the real-name registration, and similarly, the first sub-registration information and the second sub-registration information are the real-name registration information.
In the embodiment of the invention, in the process of allocating the target account to the worker, the registration information of the worker is checked through the first sub-registration information and the second registration information, so that the correctness of real-name registration is ensured.
In another optional implementation manner of the embodiment of the present invention, acquiring the first sub-registration information received by the first receiving manner includes:
receiving access information submitted by a worker, pushing a first registration page to the worker according to the access information, and generating first sub-registration information according to information filled in the first registration page by the worker; or,
receiving invitation information sent by team managers, pushing a second registration page to the worker according to the invitation information, and generating first sub-registration information according to information filled in the second registration page by the worker; or,
and receiving registration information sent by personnel management personnel, and determining the registration information as first sub-registration information, wherein the registration information is information registered by the personnel management personnel when a worker joins the target project.
It should be noted that, the embodiment of the present invention provides three ways of obtaining the first sub-registration information received by the first receiving way; similarly, the second sub-registration information received by the second receiving method may also adopt any one of the three methods as long as the first receiving method and the second receiving method are different.
Example two
As shown in fig. 4, the accounting device for record work according to an embodiment of the present invention includes:
the system comprises a first acquisition module 1, a second acquisition module and a third acquisition module, wherein the first acquisition module is used for acquiring first engineering information, and the first engineering information is engineering information of a target project recorded by a worker, and the engineering information comprises engineering quantity and/or duration;
the second acquisition module 2 is used for acquiring second work recording information, wherein the second work recording information is the project information of workers on the target project, which is recorded by team managers of the target project;
and the first determining module 3 is used for comparing the first recording information with the second recording information to determine the workload of the worker on the target project.
In the embodiment of the invention, a first obtaining module 1 obtains first engineering information, and a second obtaining module 2 obtains second engineering information, wherein the first engineering information is engineering information of a target project recorded by a worker, and the second engineering information is engineering information of the target project recorded by a team manager of the target project, and the engineering information includes a working date and/or a working duration. Then the first determining module 3 compares the first engineering information with the second engineering information to determine the workload of the worker on the target engineering. Namely, the register account checking device ensures the accuracy of the record of the workload of the worker on the target project in an account checking mode, thereby relieving the technical problem that the traditional register method is easy to make mistakes.
In an optional implementation manner of the embodiment of the present invention, the second obtaining module is configured to:
pushing first work recording information to team managers so that the team managers can compare the first work recording information with first target engineering information to obtain different information in the first work recording information and the first target engineering information, verifying the different information to obtain verified first target engineering information, wherein the first target engineering information is engineering information of workers on target engineering, which is obtained in advance by the team managers;
receiving the verified first target engineering information sent by the team manager, storing the verified first target engineering information in a storage module indicated by the target tag information, determining the verified first target engineering information as second labor recording information, wherein,
the target tag information is tag information set in advance for a worker.
In another optional implementation manner of the embodiment of the present invention, the journaling reconciliation apparatus further includes:
and the pushing module is used for pushing the work statistic page to the team managers before the second labor recording information is obtained so that the team managers can operate the statistic information in the work statistic page, wherein the statistic information after operation comprises the target label information.
In another optional implementation manner of the embodiment of the present invention, the first obtaining module includes:
the system comprises an acquisition unit, a processing unit and a processing unit, wherein the acquisition unit is used for acquiring the work recording request information sent by a worker after the worker is detected to log in a target account, and the target account is an account which is allocated to the worker in advance;
the pushing unit is used for pushing a target page to a worker according to the account information after the recording request information is acquired, wherein the account information is the account information of the target account;
the receiving unit is used for receiving first recording information input by a worker in the target page.
In another optional implementation manner of the embodiment of the present invention, the pushing unit is configured to:
pushing the first working form, the second working form and the third working form to the worker according to the account information,
wherein the first work form is set to a work load of the worker record having been completed;
the second work table is set to the worker recording the total work volume of the contract and/or the remaining unfinished work volume;
a third work form is set for the worker to record the payroll settlement condition;
the first working table, the second working table and the third working table are tables on the same page or tables on different pages.
In another optional implementation manner of the embodiment of the present invention, the journaling reconciliation apparatus further includes:
a third obtaining module, configured to obtain first sub-registration information received through a first receiving manner and second sub-registration information received through a second receiving manner, where the first receiving manner and the second receiving manner are different receiving manners;
the second determining module is used for determining different information between the first sub-registration information and the second sub-registration information so as to enable a supervisor of the management platform to obtain correction information based on the different information;
the correction module is used for receiving correction information sent by a supervisor, correcting the first sub-registration information and the second sub-registration information according to the correction information, and obtaining the corrected first sub-registration information and the corrected second sub-registration information;
and the allocation module is used for allocating the target account to the worker according to the corrected first sub-registration information or the corrected second sub-registration information.
In another optional implementation manner of the embodiment of the present invention, the third obtaining module is configured to:
receiving access information submitted by a worker, pushing a first registration page to the worker according to the access information, and generating first sub-registration information according to information filled in the first registration page by the worker; or,
receiving invitation information sent by team managers, pushing a second registration page to the worker according to the invitation information, and generating first sub-registration information according to information filled in the second registration page by the worker; or,
and receiving registration information sent by personnel management personnel, and determining the registration information as first sub-registration information, wherein the registration information is information registered by the personnel management personnel when a worker joins the target project.
The computer program product of the work-recording and account-checking method and device provided by the embodiment of the invention comprises a computer readable storage medium storing a program code, and instructions included in the program code can be used for executing the method in the foregoing method embodiment.
It is clear to those skilled in the art that, for convenience and brevity of description, the specific working processes of the system and the apparatus described above may refer to the corresponding processes in the foregoing method embodiments, and are not described herein again.
In addition, in the description of the embodiments of the present invention, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The functions, if implemented in the form of software functional units and sold or used as a stand-alone product, may be stored in a computer readable storage medium. Based on such understanding, the technical solution of the present invention may be embodied in the form of a software product, which is stored in a storage medium and includes instructions for causing a computer device (which may be a personal computer, a server, or a network device) to execute all or part of the steps of the method according to the embodiments of the present invention. And the aforementioned storage medium includes: a U-disk, a removable hard disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a magnetic disk or an optical disk, and other various media capable of storing program codes.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention.
Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art will understand that: any person skilled in the art can modify or easily conceive the technical solutions described in the foregoing embodiments or equivalent substitutes for some technical features within the technical scope of the present disclosure; such modifications, changes or substitutions do not depart from the spirit and scope of the embodiments of the present invention, and they should be construed as being included therein. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (10)

1. A work-recording account-checking method is applied to a management platform and comprises the following steps:
acquiring first labor information, wherein the first labor information is project information of a target project recorded by a worker, and the project information comprises labor information and labor information;
acquiring second work recording information, wherein the second work recording information is the project information of the target project, recorded by team managers of the target project, of the workers;
and comparing the first project recording information with the second project recording information to determine the working condition and the salary condition of the worker on the target project.
2. The method of claim 1, wherein obtaining second labor information comprises:
pushing the first engineering information to the team manager so that the team manager compares the first engineering information with first target engineering information to obtain different information in the first engineering information and the first target engineering information, verifying the different information to obtain the verified first target engineering information, wherein the first target engineering information is the engineering information of the worker on the target engineering, which is obtained in advance by the team manager;
receiving the verified first target engineering information sent by the team manager, and storing the verified first target engineering information in a storage module indicated by target tag information to determine the verified first target engineering information as the second work recording information,
the target tag information is tag information set for the worker in advance.
3. The method of claim 2, wherein prior to obtaining the second labor information, the method further comprises:
and pushing a work statistic page to the team managers so that the team managers operate the statistic information in the work statistic page, wherein the statistic information after operation comprises the target tag information.
4. The method of claim 1, wherein obtaining first labor information comprises:
after detecting that the worker logs in a target account, acquiring recording request information sent by the worker, wherein the target account is an account which is allocated to the worker in advance;
after the recording request information is acquired, a target page is pushed to the worker according to account information, wherein the account information is the account information of the target account;
receiving the first recording information input by the worker in the target page.
5. The method of claim 4, wherein pushing a target page to the worker based on account information comprises:
pushing a first work form, a second work form and a third work form to the worker according to the account information, wherein,
the first work table is set to record the completed work amount for the worker;
the second work table is set to the worker record total work volume of the contract and/or remaining unfinished work volume;
the third work form is set to the worker record payroll settlement condition;
the first working table, the second working table and the third working table are tables on the same page or tables on different pages.
6. The method of claim 4, wherein prior to obtaining the first labor information, the method further comprises:
acquiring first sub-registration information received through a first receiving mode and second sub-registration information received through a second receiving mode, wherein the first receiving mode and the second receiving mode are different receiving modes;
determining different information between the first sub-registration information and the second sub-registration information so that a supervisor of the management platform obtains correction information based on the different information;
receiving the correction information sent by the supervisor, and correcting the first sub-registration information and the second sub-registration information according to the correction information to obtain corrected first sub-registration information and corrected second sub-registration information;
and allocating the target account to the worker according to the corrected first sub-registration information or the corrected second sub-registration information.
7. The method of claim 6, wherein obtaining the first sub-registration information received via the first receiving manner comprises:
receiving access information submitted by the worker, pushing a first registration page to the worker according to the access information, and generating first sub-registration information according to information filled in the first registration page by the worker; or,
receiving invitation information sent by the team managers, pushing a second registration page to the worker according to the invitation information, and generating first sub-registration information according to information filled in the second registration page by the worker; or,
and receiving registration information sent by personnel management personnel, and determining the registration information as the first sub-registration information, wherein the registration information is information registered by the personnel management personnel when the worker joins the target project.
8. A register reconciliation apparatus, comprising:
the system comprises a first acquisition module, a second acquisition module and a third acquisition module, wherein the first acquisition module is used for acquiring first labor information which is the project information of a target project recorded by a worker, and the project information comprises labor service information and labor resource information;
the second acquisition module is used for acquiring second engineering information, wherein the second engineering information is the engineering information of the target engineering, recorded by team management personnel of the target engineering, of the worker;
and the first determining module is used for comparing the first labor recording information with the second labor recording information so as to determine the working condition and the salary condition of the worker.
9. The apparatus of claim 8, wherein the second obtaining module is configured to:
pushing the first engineering information to the team manager so that the team manager compares the first engineering information with first target engineering information to obtain different information in the first engineering information and the first target engineering information, verifying the different information to obtain the verified first target engineering information, wherein the first target engineering information is the engineering information of the worker on the target engineering, which is obtained in advance by the team manager;
receiving the verified first target project information sent by the team manager, and storing the verified first target project information in a page indicated by target tag information to determine the verified first target project information as the second work recording information,
the target tag information is tag information set for the worker in advance.
10. The apparatus of claim 9, further comprising:
and the pushing module is used for pushing a work statistic page to the team managers before the second labor recording information is acquired so that the team managers operate the statistic information in the work statistic page, wherein the statistic information after the operation comprises the target tag information.
CN201710928610.1A 2017-09-30 2017-09-30 Record workpoints account checking method and device Pending CN107622381A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710928610.1A CN107622381A (en) 2017-09-30 2017-09-30 Record workpoints account checking method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710928610.1A CN107622381A (en) 2017-09-30 2017-09-30 Record workpoints account checking method and device

Publications (1)

Publication Number Publication Date
CN107622381A true CN107622381A (en) 2018-01-23

Family

ID=61091356

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710928610.1A Pending CN107622381A (en) 2017-09-30 2017-09-30 Record workpoints account checking method and device

Country Status (1)

Country Link
CN (1) CN107622381A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110619563A (en) * 2019-09-25 2019-12-27 张少杰 Salary management system operated by mobile phone
CN111626837A (en) * 2020-05-18 2020-09-04 成都集致生活科技有限公司 Accounting module method for building settlement or borrowing

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1474322A (en) * 2002-08-09 2004-02-11 英新达股份有限公司 Personnel salary calculation system and method
CN105427031A (en) * 2015-11-06 2016-03-23 中国南方电网有限责任公司 Three-party data check method and system
CN106355514A (en) * 2016-08-31 2017-01-25 中国南方电网有限责任公司 Management system and process for realizing electric charge collection through bank and power supply enterprise network on basis of account checking identification codes
CN106408407A (en) * 2016-09-12 2017-02-15 北海和思科技有限公司 Comprehensive accounting matters managing system
CN205992243U (en) * 2016-05-18 2017-03-01 杭州班博科技有限公司 A kind of wage supervisory systems
CN106713294A (en) * 2016-12-14 2017-05-24 李昕龙 Building data processing method and system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1474322A (en) * 2002-08-09 2004-02-11 英新达股份有限公司 Personnel salary calculation system and method
CN105427031A (en) * 2015-11-06 2016-03-23 中国南方电网有限责任公司 Three-party data check method and system
CN205992243U (en) * 2016-05-18 2017-03-01 杭州班博科技有限公司 A kind of wage supervisory systems
CN106355514A (en) * 2016-08-31 2017-01-25 中国南方电网有限责任公司 Management system and process for realizing electric charge collection through bank and power supply enterprise network on basis of account checking identification codes
CN106408407A (en) * 2016-09-12 2017-02-15 北海和思科技有限公司 Comprehensive accounting matters managing system
CN106713294A (en) * 2016-12-14 2017-05-24 李昕龙 Building data processing method and system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110619563A (en) * 2019-09-25 2019-12-27 张少杰 Salary management system operated by mobile phone
CN111626837A (en) * 2020-05-18 2020-09-04 成都集致生活科技有限公司 Accounting module method for building settlement or borrowing

Similar Documents

Publication Publication Date Title
CN109242261B (en) Method for evaluating security risk based on big data and terminal equipment
CN109271321B (en) Method and device for counting contribution code number
US8984360B2 (en) Data quality analysis and management system
CN109800598A (en) Certificate administration method, apparatus, electronic equipment and storage medium based on block chain
CN111027944A (en) Human resource management system
US20070282622A1 (en) Method and system for developing an accurate skills inventory using data from delivery operations
CN102890720A (en) Database inspection and maintenance method
CN111340402B (en) Group insurance service management method, system, device and storage medium
CN108733820A (en) Data adjustment method and device
US20140335485A1 (en) Methods and systems for training a crowdworker
CN104182900A (en) Business data processing method, device and system
CN115222259A (en) Strategic target-based comprehensive performance management method and system
US20030120563A1 (en) Method of managing inventory
US20220019566A1 (en) System and method for integrating systems to implement data quality processing
CN107622381A (en) Record workpoints account checking method and device
CN112231634A (en) Credit limit calculation method, system and equipment based on enterprise information
CN105184467A (en) Quality evaluation system of patent application file and evaluation method thereof
CN108038667B (en) Policy generation method, device and equipment
CN114819688A (en) Work order assignment method, equipment, storage medium and device
CN109743179A (en) A kind of electronics license signs and issues method on demand
CN111353763B (en) Method, device, server and storage medium for processing data
CN113128188A (en) Bank payroll generation method, device and medium
US11030024B2 (en) Assigning a severity level to a computing service using tenant telemetry data
KR101927273B1 (en) Risk value evaluating system for unclaimed construction and risk value evaluating apparatus for unclaimed construction
CN111815272B (en) Application auditing method and device, electronic equipment and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180123