CN107615314A - Production plan generates servicing unit and production plan generating means - Google Patents

Production plan generates servicing unit and production plan generating means Download PDF

Info

Publication number
CN107615314A
CN107615314A CN201680029630.9A CN201680029630A CN107615314A CN 107615314 A CN107615314 A CN 107615314A CN 201680029630 A CN201680029630 A CN 201680029630A CN 107615314 A CN107615314 A CN 107615314A
Authority
CN
China
Prior art keywords
plan
storage part
information storage
information
production plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201680029630.9A
Other languages
Chinese (zh)
Other versions
CN107615314B (en
Inventor
白石孝
山佐礼司
铃木直彦
上田健词
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Mitsubishi Electric Building Solutions Corp
Original Assignee
Mitsubishi Electric Corp
Mitsubishi Electric Building Techno Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp, Mitsubishi Electric Building Techno Service Co Ltd filed Critical Mitsubishi Electric Corp
Publication of CN107615314A publication Critical patent/CN107615314A/en
Application granted granted Critical
Publication of CN107615314B publication Critical patent/CN107615314B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/109Time management, e.g. calendars, reminders, meetings or time accounting
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

Production plan generation servicing unit is provided, the generation of production plan can be aided in, the Specialty Program includes the set plan that operating personnels more than two people gathers in time same date in identity set place.Therefore, production plan generation servicing unit has:Job information storage part (1), the job information that it is prestored to the place of multiple operation fields and the content of upkeep operation that is carried out in each operation field is related;Aggregate information storage part (3), it prestores the aggregate information related to the operating personnel for gathering place, gathering date-time and entering row set;Set plan determination section (5), it determines the set plan that operating personnels more than two people gathers in time same date in identity set place according to the aggregate information being stored in aggregate information storage part (3);And auxiliary information prompting part (6), it is prompted to plan generator by the job information being stored in job information storage part (1) and by gathering the set plan planned determination section (5) and determined, as plan generation auxiliary information.

Description

Production plan generates servicing unit and production plan generating means
Technical field
The present invention relates to production plan (schedule) generation servicing unit and production plan generating means.
Background technology
Known existing production plan generating means have:Information acquisition unit, it receives to determine to be provided with makees as maintenance The article information of each building in multiple buildings of the machinery equipment of industry object, and expression is obtained in the multiple building The upkeep operation information of the content for the upkeep operation that each building in thing is carried out, represent to include in the multiple building The Weather Forecast Information of the weather information of the region in the location of each building and expression are included in the multiple building Each building location region geographical conditions geographical conditions information;And plan generation unit, it is according to institute State the location of each building in multiple buildings, the content, described of upkeep operation shown in the upkeep operation information The geographical conditions shown in weather forecast and the geographical conditions information shown in Weather Forecast Information, generation are represented described more Job date and the operator that upkeep operation is carried out in each building in individual building are each into the multiple building The production plan of the mobile instrument of individual building movement, the plan generation unit distribute same upkeep operation in same work The industry date (for example, referring to patent document 1).
Prior art literature
Patent document
Patent document 1:Japanese Unexamined Patent Publication 2013-242774 publications
The content of the invention
Problems to be solved by the invention
But in the existing production plan generating means shown in patent document 1, by the way that same upkeep operation is distributed In same operation day, to cut down the quantity of the instrument of operating personnel's carrying, but its in same operation day is not accounted for He operating personnel, it is impossible to carry out the instrument between operating personnel exchange or operating personnel between information exchange.I.e., it is impossible to The operation meter for the set plan that generation is such as gathered including operating personnels more than two people in the same time in identity set place Draw, thus when make during production plan more than two people operating personnel gather when, exist can not carry out with operation field, The problem of exchange of instrument required for job content related information exchange and operation etc..
The present invention is precisely in order to solving this problem and completing, there is provided one kind can be to easily generation such as including two people The production plan for the set plan that operating personnel above gathers in the same time in identity set place is aided in, Huo Zheneng The production plan generation servicing unit and production plan generating means of production plan as enough generations.
The means used to solve the problem
The production plan generation servicing unit of the present invention is configured to have:Job information storage part, it prestores and set There is the place of multiple operation fields of the machinery equipment as upkeep operation object and each in the multiple operation field The related job information of the content for the upkeep operation that individual operation field is carried out;Aggregate information storage part, it prestores and gathered Place, the aggregate information gathered date-time and enter operating personnel's correlation of row set;Set plan determination section, its basis are deposited The aggregate information in the aggregate information storage part is stored up, determines operating personnels more than two people in time same date same Gather the set plan of place set;And auxiliary information prompting part, its work that will be stored in the job information storage part Industry information and the set plan determined by the set plan determination section, plan is prompted to as plan generation auxiliary information Generator.
In addition, the production plan generating means of the present invention are configured to have:Job information storage part, it, which is prestored, is provided with With the place of multiple operation fields of the machinery equipment as upkeep operation object and each in the multiple operation field The related job information of the content for the upkeep operation that individual operation field is carried out;Aggregate information storage part, it prestores and gathered Place, the aggregate information gathered date-time and enter operating personnel's correlation of row set;Set plan determination section, its basis are deposited The aggregate information in the aggregate information storage part is stored up, determines operating personnels more than two people in time same date same Gather the set plan of place set;And plan generating unit, it is according to the operation being stored in the job information storage part Information and the set plan that is determined by the set plan determination section generate production plan.
Invention effect
The production plan generation servicing unit and production plan generating means of the present invention plays following effect:Can be to easy The production plan that generation includes the set plan that operating personnels more than two people gathers in the same time in identity set place is entered Row auxiliary, or such production plan can be generated.
Brief description of the drawings
Fig. 1 is the integrally-built block diagram for the production plan generation servicing unit for showing embodiments of the present invention 1.
Fig. 2 is based on the operation generated by the production plan generation servicing unit illustrated using embodiments of the present invention 1 The figure of one drawn.
Fig. 3 is the integrally-built block diagram for the production plan generating means for showing embodiments of the present invention 2.
Embodiment
Below, it is described with reference to the mode for implementing the present invention.In various figures to portion identically or comparably Minute mark note identical label, and suitably simplify or the repetitive description thereof will be omitted.In addition, the invention is not restricted to following embodiment party Formula, various modifications can be carried out without departing from the spirit and scope of the invention.
Embodiment 1
Fig. 1 and Fig. 2 is the figure of embodiment 1 for the present invention, and Fig. 1 is to show that production plan generates the whole of servicing unit The block diagram of body structure, Fig. 2 are the figures of one of the production plan for illustrating to generate using production plan generation servicing unit.
Generation of the production plan generation servicing unit of embodiments of the present invention 1 to production plan aids in, the work Industry is designed for the upkeep operation for the machinery equipment that progress is set in the building such as building or apartment.Production plan refers to operation Person is moved to the multiple buildings for being provided with the machinery equipment as upkeep operation object from the maintenance service strong point of service companies The plan (schedule) of upkeep operation is carried out in (object).Machinery equipment as upkeep operation object be, for example, elevator, from Dynamic staircase, take precautions against video camera, air conditioner and ligthing paraphernalia etc..
As shown in figure 1, embodiments of the present invention 1 production plan generation servicing unit have job information storage part 1, Operating personnel's information storage part 2, aggregate information storage part 3, aggregate information configuration part 4, set plan determination section 5, auxiliary information Prompting part 6, plan input unit 7 and generation plan storage part 8.
Job information storage part 1 prestores job information.Job information is comprised at least with being provided with as upkeep operation The related information in the places of multiple operation fields of the machinery equipment of object and with it is each in these multiple operation fields The related information of the content for the upkeep operation that operation field is carried out.As the information related to the place of operation field, specifically Say, such as the name information of the title of building including being denoted as operation field etc., the address (institute for representing the building etc. On ground) positional information and serve as the building etc. upkeep operation the information for serving as operator.Furthermore it is also possible to wrap The identification information for building of the unique identification as operation field etc. is included, can also include being used to identify in the building etc. The facility information of the machinery equipment of middle setting.
In addition, as the information related to the content of upkeep operation, specifically, such as set including the machine as object Activity duration needed for the job class of standby cleaning, confirmation and replacing etc., the upkeep operation and maintenance work can be implemented Operation feasible period of industry etc..In addition, the activity duration refers to the time required for the upkeep operation of estimation, such as can be according to warp Test or actual achievement etc. determines.Job information storage part 1 can also prestore tool information.Tool information refers to and each maintenance The information of instrument correlation needed for each content of operation.
Operating personnel's information storage part 2 prestores operating personnel's information.Operating personnel's information refers to conventional with operator The related information of operation experience.Operation experience comprises at least the information of the job content carried out in the past about the operator, also The information of the experience number about every job content can be included.
Aggregate information storage part 3 prestores aggregate information.Aggregate information include with set place, set date-time with And enter the information of operating personnel's correlation of row set.Gather place and for example service strong point from warehouse, company or above-mentioned maintenance Selected in.In addition, even set place is identical with the place of operation field.
Aggregate information configuration part 4 is used to be set in advance in the aggregate information stored in aggregate information storage part.Aggregate information Input unit (such as keyboard and mouse operated by operator of the configuration part 4 for example with production plan generation servicing unit Deng).Also, aggregate information configuration part 4 can also have display device (such as display or the monitoring for being used to confirm input results Device etc.).Or can also have and also serve as input unit and the touch-screen of display device.
Set plan determination section 5 carrys out determined set according at least to the aggregate information being stored in aggregate information storage part 3 and added up to Draw.Set plan refers to that operating personnels more than two people is located at same place (set place) in time same date and collected The plan of conjunction.In the case of total stroke of determined set is carried out according only to the aggregate information being stored in aggregate information storage part 3, set Plan determination section 5 and use the letter related to the operating personnel of set place, set date-time and set in aggregate information Breath carrys out total stroke of determined set, that is, determines the operating personnel of set place, set date-time and set.
Also, set plan determination section 5 according to the aggregate information being stored in aggregate information storage part 3 and can also be deposited Store up operating personnel's information in operating personnel's information storage part 2 and carry out total stroke of determined set.In such a situation it is preferred to without using The information related to entering the operating personnel of row set in aggregate information, but consider that the operation experience of operating personnel's information determines The operating personnel of set, exchanged efficiently and effectively to enter row information.
Also, set plan determination section 5 according to the aggregate information being stored in aggregate information storage part 3 and can also be deposited Store up the tool information in operating personnel's information storage part 2 and carry out total stroke of determined set.In such circumstances it is desirable to without using set The information related to entering the operating personnel of row set in information, but consider the work that each operating personnel is served as before and after set Instrument needed for industry determines the operating personnel into row set, efficiently and effectively to carry out the exchange of instrument.In addition, also may be used Carry out total stroke of determined set so that aggregate information, operating personnel's information and tool information all to be taken into account.
Plan generation auxiliary information is prompted plan generator in auxiliary information prompting part 6.Plan generation auxiliary information is at least Including the job information being stored in job information storage part 1 and the set plan determined by set plan determination section 5.It is auxiliary Supplementary information prompting part 6 has the display device for being used for prompting plan generator plan generation auxiliary information.Display device is for example Display or monitor etc. can be used.Also, display device can also use the display used with aggregate information configuration part 4 to fill Put common display device.
Plan input unit 7 to be used to input by the production plan of plan generator's generation of generation upkeep operation plan.Plan Input unit 7 has the input unit operated by plan generator and the display device for confirming inputted production plan. The input unit is such as can use keyboard and mouse.Input unit can also use what is used with aggregate information configuration part 4 The common input unit of input unit.In addition, display device is such as can use display or monitor.Also, display dress Put the display device that the display device used with aggregate information configuration part 4 or auxiliary information prompting part 6 can also be used common.
Plan generator refers to the plan generation auxiliary information generation production plan prompted by auxiliary information prompting part 6, and Operation planning input unit 7 inputs generated production plan.Now, particularly collect total with reference to plan generation auxiliary information Draw, can easily produce such as including the production plan for the particularly set plan prompted by auxiliary information prompting part 6.And And include the production plan of set plan by generation, thus, it is possible to promote multiple operating personnels when being moved to operation field In the set of set place, the instrument needed for the information exchange and operation related to operation field, job content is swimmingly carried out Exchange etc..
In addition, plan input unit 7 can also will pre-enter the set plan that is determined by set plan determination section 5 State is set as given state.By the way that the state for having pre-entered the set plan determined by set plan determination section 5 is made For given state, and set plan is pre-entered to plan input unit 7, plan generator input set is total to draw thus, it is possible to save Time.
Also, now pre-enter the set of plan input unit 7 by being shown by plan input unit 7 as given state Plan, thus, it is possible to prompt plan generator the set plan in plan generation auxiliary information.That is, can also utilize in order to true Recognize the input content of plan input unit 7 and the prompting set plan in auxiliary information prompting part 6 is installed in the part that is shown Part.
Generation plan storage part 8 stores the production plan inputted by planning input unit 7.In storage part 8 is planned in generation The production plan of storage can be shown in display device etc. at any time as needed to be confirmed.
Below, reference picture 2 illustrates the production plan generated using the production plan generation servicing unit formed as described above One.Company 10 is to safeguard service strong point.In this embodiment, make on the 1st operation field 11a, the 2nd operation field 11b, the 3rd Industry scene 11c, the 4th operation field 11d, the 5th operation field 11e, the 6th operation field 11f, the 7th operation field 11g, the 8th operation Live 11h, by two operating personnels (the 1st operating personnel 12a and the 2nd operating personnel 12b) after two days (the 1st operation day and the 2nd Operation day) share carry out upkeep operation.
As shown in Fig. 2 the 1st operation field 11a job content is to examine, it is necessary to put inspection instrument (such as ladder).2nd Operation field 11b job content is repaired, it is necessary to repair outfit (such as spanner).3rd operation field 11c job content It is to examine, it is necessary to put inspection instrument (such as ladder).4th operation field 11d job content is that maintenance uses instrument, it is necessary to repair (such as screwdriver).
In addition, the 5th operation field 11e job content is repaired, it is necessary to repair outfit (such as spanner).6th operation Live 11f job content is to examine, it is necessary to put inspection instrument (such as ladder).7th operation field 11g job content is dimension Repair, it is necessary to repair with instrument (such as screwdriver).8th operation field 11h job content is repaired, it is necessary to repair outfit (such as spanner).
Also, it is to go to the 1st operation field 11a from company 10 first in the plan of the operating personnel 12a of the 1st operation day the 1st An inspection is carried out, then goes to the 2nd operation field 11b to place under repair, then returnes to company 10.Also, equally in the 1st operation day 2nd operating personnel 12b plan is to go to the 8th operation field 11h to place under repair from company 10 first, then goes to the 6th operation Live 11f carries out an inspection, then returnes to company 10.
That is, the 1st operating personnel 12a herein is according to an inspection, the touring operation field of order repaired, the 2nd operating personnel's 12b phases Instead according to the touring operation field of order repaired, point is examined.Therefore, following set plan is set in this embodiment:1st operating personnel 12a is terminating before the 2nd operation field 11b is gone in the 1st operation field 11a operation, to the warehouse as set place 13 assemble, and the 2nd operating personnel 12b is terminating before the 6th operation field 11f is gone in the 8th operation field 11h operation, to Assemble in warehouse 13 as set place.
By gathering plan as setting, in the warehouse 13 as set place, the 1st operating personnel can be exchanged with each other The repair outfit that the point inspection instrument and the 2nd operating personnel 12b that 12a holds are held.Therefore, the 1st operating personnel 12a is leaving An inspection instrument is only carried during company 10, the 2nd operating personnel 12b only carries repair outfit i.e. in the company 10 of leaving Can, it is thus possible to reduce the amount for the instrument that each operating personnel carries.
In addition, the plan in the operating personnel 12a of the 2nd operation day the 1st is to go to the 4th operation field 11d from company 10 first Repaired, then go to the 3rd operation field 11c to carry out an inspection, then return to company 10.Also, equally in the 2nd operation day 2nd operating personnel 12b plan is to go to the 5th operation field 11e to place under repair from company 10 first, then goes to the 7th operation Live 11g is repaired, and then returnes to company 10.
In the example shown in the Fig. 2, the set plan of two operating personnel's set of the 2nd operation day is not set in. But such as following set plan can also be set:1st operating personnel 12a is terminating the operation in the 4th operation field 11d And going to the 3rd operation field 11c forward direction set place to assemble, the 2nd operating personnel 12b is terminating the 5th operation field 11e's Operation and go to the 7th operation field 11g forward direction set place to assemble.
By gathering plan as setting, in set place, the maintenance recruitment that the 1st operating personnel 12a can be held Tool hands to the 2nd operating personnel 12b, it is thus possible to accomplishes that the 2nd operating personnel 12b need not carry maintenance in the company 10 of leaving Use instrument.
Production plan generation servicing unit with functional structure as described above can for example use known calculate Machine is installed.Therefore, one of the hardware configuration for Installation Operating Programme generation servicing unit is illustrated below.
Production plan generation servicing unit has CPU, ROM, RAM and communication interface.CPU is to perform assigned order (including program as command history) and enter the central processing unit (Central of computing or the processing of row information Processing Unit).ROM is reading private memory (Read Only of data storage or program in nonvolatile manner Memory).RAM is for volatibility the i.e. read-write random access memory (Random of interim storage data or program Access Memory)。
Communication interface is hardware of the production plan generation servicing unit progress needed for outside communication.Here, operation meter Generation servicing unit is drawn to be connected with being used as the internet 300 of communication network by communication interface.These CPU, ROM, RAM and communication Interface in a manner of can mutually entering the transmission of row information by bus to be connected.
In addition, production plan generation servicing unit can also have hard disk, CD-ROM etc. to be used as external memory, also may be used With with display output unit (such as monitor), input block (such as keyboard) etc..
Program is previously stored with the ROM of the computer of fabrication process plan generation servicing unit, the program makes as above The computer of the composition is operated as production plan generation servicing unit.Also, CPU reads program from ROM first, and The storage program in the form of RAM is able to carry out.Also, CPU reads program in the RAM is stored while configuration processor.
So, by the way that the program for being used as software is read in computer, the tool to be worked using software and hardware resource collaboration Body unit realizes the computing or processing of information, thus production plan life of the structure with each function shown in Fig. 1 described above Into servicing unit.
That is, the program performed in the CPU of the computer of production plan generation servicing unit, for generating production plan The computer of servicing unit is as job information storage part 1, operating personnel's information storage part 2, aggregate information storage part 3, set The each of storage part 8 is planned in information setting portion 4, set plan determination section 5, auxiliary information prompting part 6, plan input unit 7 and generation Portion plays a role.
In addition, program can also be not stored in ROM, and it is stored in external memory, can also be from outside by Communication interface uses to downloaded program.
The production plan generation servicing unit formed as described above has:Job information storage part 1, it prestores and set There are the place of multiple operation fields of the machinery equipment as upkeep operation object and each work in multiple operation fields The job information of the content correlation for the upkeep operation that industry scene is carried out;Aggregate information storage part 3, it is prestored and set field Institute, the aggregate information gathered date-time and enter operating personnel's correlation of row set;Set plan determination section 5, its basis are deposited The aggregate information in aggregate information storage part 3 is stored up, determines operating personnels more than two people in time same date in same collection Close the set plan of place set;And auxiliary information prompting part 6, it believes the operation being stored in job information storage part 1 Breath and the set plan determined by set plan determination section 5, plan generator is prompted to as plan generation auxiliary information.
It has therefore been proposed to generator, which refers to the plan prompted by auxiliary information prompting part 6, generates auxiliary information, can be easily The operation meter for the set plan that the operating personnel that generating is included more than two people gathers in time same date in identity set place Draw.Also, such as include the production plan of set plan by generating, multiple operating personnels can be promoted to be moved to operation field In the set of set place when dynamic, and swimmingly carry out needed for the information exchange and operation related to operation field, job content The exchange of instrument etc..
Embodiment 2
Fig. 3 is the figure of embodiment 2 for the present invention, is the integrally-built frame for showing production plan generating means Figure.
The production plan generating means of embodiments of the present invention 2 are generated for carrying out in the building such as building or apartment The production plan of the upkeep operation of the machinery equipment of middle setting.As shown in figure 3, the production plan life of embodiments of the present invention 2 There is job information storage part 1, operating personnel's information storage part 2, aggregate information storage part 3, aggregate information configuration part into device 4th, set plan determination section 5, generation plan storage part 8 and plan generating unit 9.
Job information storage part 1, operating personnel's information storage part 2, aggregate information storage part 3, aggregate information configuration part 4 and Set plan determination section 5, these key element phases possessed by servicing unit are generated with the production plan illustrated in embodiment 1 Together, thus description is omitted.
Plan generating unit 9 according to the job information being stored in job information storage part 1 and by set plan determination section 5 The set plan that determines generates production plan.For example, plan generating unit 9 is with reference to the activity duration of each upkeep operation, will be more The several upkeep operations being aggregated within the darg time (such as the 10 hours) distribution of the activity duration of individual upkeep operation In one day, mobile means and mobile route of the operator to each operation field movement are determined.Also, obtain each operating personnel The most short multiple upkeep operations of traveling time combination, the multiple upkeep operations included in combination that this is obtained are distributed same One operation day.Now, generating unit 9 is planned to cause necessarily comprising the set plan determined by set plan determination section 5 Mode generates production plan.
Here, plan generating unit 9 can also be on the basis of job information and set plan always according to being stored in operation people Operating personnel information in member's information storage part 2 generates production plan.Also, planning generating unit 9 can also be in job information On the basis of planning with set, production plan is generated always according to the tool information in operating personnel's information storage part 2 is stored in. Make in addition, can certainly all take job information, set plan, operating personnel's information and tool information into account to generate Industry plan.
Generation plan storage part 8 stores the production plan generated by plan generating unit 9.Deposited in generation plan storage part 8 The production plan of storage can be shown in display device etc. at any time and above be confirmed as needed.
Alternatively, it is also possible to make the plan input unit 7 of embodiment 1 have similar plan modification portion, operator can fit When the production plan that amendment is generated by plan generating unit 9.Also, as embodiment 1, the embodiment that forms as described above 2 production plan generating means for example also can use known computer to be installed.
The production plan generating means formed as described above have:Job information storage part 1, it is prestored makees with being provided with Place for multiple operation fields of the machinery equipment of upkeep operation object and each operation in multiple operation fields show The related job information of the content for the upkeep operation that field is carried out;Aggregate information storage part 3, it is prestored and set place, collection Close date-time and enter the aggregate information of operating personnel's correlation of row set;Set plan determination section 5, its basis are stored in collection The aggregate information in information storage part 3 is closed, determines operating personnels more than two people in time same date in identity set place The set plan of set;And plan generating unit 9, its according to be stored in job information in job information storage part 1 and by Set plan that set plan determination section 5 determines generates production plan.
Therefore, can play with the basis of the identical effect of embodiment 1, additionally it is possible to automatically generate more than two people The set plan that operating personnel gathers in time same date in identity set place, the work of production plan generation can be reduced When.
Industrial applicability
The present invention for example can be used in production plan generation servicing unit, to for carrying out in the building such as building or apartment The generation of the production plan of the upkeep operation of the machinery equipment of middle setting is aided in.Also, such as it can be used in production plan Generating means, generate based on the operation of upkeep operation of the machinery equipment by set in the building such as building or apartment Draw.
Label declaration
1 job information storage part;2 operating personnel's information storage parts;3 aggregate information storage parts;4 aggregate information configuration parts;5 Set plan determination section;6 auxiliary information prompting parts;7 plan input units;8 generation plan storage parts;9 plan generating units;10 is public Department;The operation fields of 11a the 1st;The operation fields of 11b the 2nd;The operation fields of 11c the 3rd;The operation fields of 11d the 4th;The operations of 11e the 5th show ;The operation fields of 11f the 6th;The operation fields of 11g the 7th;The operation fields of 11h the 8th;The operating personnels of 12a the 1st;The operation people of 12b the 2nd Member;13 warehouses.

Claims (5)

1. a kind of production plan generates servicing unit, wherein, production plan generation servicing unit has:
Job information storage part, it is prestored and multiple operation fields provided with the machinery equipment as upkeep operation object The operation that the content for the upkeep operation that place and each operation field in the multiple operation field are carried out is related is believed Breath;
Aggregate information storage part, it is prestored with gathering place, gathering date-time and entering operating personnel's phase of row set The aggregate information of pass;
Set plan determination section, it is determined more than two people according to the aggregate information being stored in the aggregate information storage part The set plan that operating personnel gathers in time same date in identity set place;And
Auxiliary information prompting part, it plans by the job information being stored in the job information storage part and by the set The set plan that determination section determines, plan generator is prompted to as plan generation auxiliary information.
2. production plan according to claim 1 generates servicing unit, wherein,
The production plan generation servicing unit has the plan input for being used for the production plan that input plan generator is generated Portion,
The plan input unit sets the state for having pre-entered the set plan determined by the set plan determination section For given state.
3. production plan according to claim 1 or 2 generates servicing unit, wherein,
The production plan generation servicing unit, which has, prestores the operating personnel information related to the operation experience of operator Operating personnel's information storage part,
The set plan determination section is according to the aggregate information being stored in the aggregate information storage part and is stored in the work Operating personnel's information in industry personal information storage part carrys out total stroke of determined set.
4. production plan according to claim 1 or 2 generates servicing unit, wherein,
The job information storage part also prestores the tool information related to the instrument needed for upkeep operation,
The set plan determination section is according to the aggregate information being stored in the aggregate information storage part and is stored in the work Tool information in industry information storage part carrys out total stroke of determined set.
5. a kind of production plan generating means, wherein, the production plan generating means have:
Job information storage part, it is prestored and multiple operation fields provided with the machinery equipment as upkeep operation object The operation that the content for the upkeep operation that place and each operation field in the multiple operation field are carried out is related is believed Breath;
Aggregate information storage part, it is prestored with gathering place, gathering date-time and entering operating personnel's phase of row set The aggregate information of pass;
Set plan determination section, it is determined more than two people according to the aggregate information being stored in the aggregate information storage part The set plan that operating personnel gathers in time same date in identity set place;And
Plan generating unit, it is determined according to the job information being stored in the job information storage part and by the set plan Set plan that portion determines is determined to generate production plan.
CN201680029630.9A 2015-06-12 2016-06-06 Work plan generation support device and work plan generation device Expired - Fee Related CN107615314B (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2015119091A JP6287966B2 (en) 2015-06-12 2015-06-12 Work schedule creation support device and work schedule creation device
JP2015-119091 2015-06-12
PCT/JP2016/066711 WO2016199705A1 (en) 2015-06-12 2016-06-06 Work schedule creation assisting device and work schedule creating device

Publications (2)

Publication Number Publication Date
CN107615314A true CN107615314A (en) 2018-01-19
CN107615314B CN107615314B (en) 2021-04-09

Family

ID=57503503

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201680029630.9A Expired - Fee Related CN107615314B (en) 2015-06-12 2016-06-06 Work plan generation support device and work plan generation device

Country Status (5)

Country Link
JP (1) JP6287966B2 (en)
KR (1) KR102144848B1 (en)
CN (1) CN107615314B (en)
DE (1) DE112016002659T5 (en)
WO (1) WO2016199705A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112368200A (en) 2018-06-28 2021-02-12 科路实有限责任公司 Railway maintenance planning
JP6750695B2 (en) * 2019-01-31 2020-09-02 株式会社富士通ゼネラル Service proposal timing adjustment device and air conditioning system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003233419A (en) * 2002-02-12 2003-08-22 Mitsubishi Heavy Ind Ltd Plant maintenance support system
CN1875376A (en) * 2003-10-31 2006-12-06 松下电器产业株式会社 Worker-in-charge command system and worker-in-charge command method
JP2008287444A (en) * 2007-05-16 2008-11-27 Chugoku Electric Power Co Inc:The Repair staff calling system, method and program
JP2013242774A (en) * 2012-05-22 2013-12-05 Mitsubishi Electric Building Techno Service Co Ltd Maintenance work schedule preparation device and program
JP2014048047A (en) * 2012-08-29 2014-03-17 Seikou Trans Network Co Ltd Meeting support system, meeting support server, meeting support method, and program

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08329375A (en) * 1995-06-06 1996-12-13 Hitachi Building Syst Eng & Service Co Ltd Support device for maintenance operation or the like
JP2005158046A (en) * 2003-10-31 2005-06-16 Matsushita Electric Ind Co Ltd Worker-in-charge command system and worker-in-charge command method
JP6097105B2 (en) * 2013-03-15 2017-03-15 オムロン株式会社 Information processing apparatus and worker assignment method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003233419A (en) * 2002-02-12 2003-08-22 Mitsubishi Heavy Ind Ltd Plant maintenance support system
CN1875376A (en) * 2003-10-31 2006-12-06 松下电器产业株式会社 Worker-in-charge command system and worker-in-charge command method
JP2008287444A (en) * 2007-05-16 2008-11-27 Chugoku Electric Power Co Inc:The Repair staff calling system, method and program
JP2013242774A (en) * 2012-05-22 2013-12-05 Mitsubishi Electric Building Techno Service Co Ltd Maintenance work schedule preparation device and program
JP2014048047A (en) * 2012-08-29 2014-03-17 Seikou Trans Network Co Ltd Meeting support system, meeting support server, meeting support method, and program

Also Published As

Publication number Publication date
KR102144848B1 (en) 2020-08-14
DE112016002659T5 (en) 2018-02-22
WO2016199705A1 (en) 2016-12-15
JP6287966B2 (en) 2018-03-07
JP2017004345A (en) 2017-01-05
KR20180015240A (en) 2018-02-12
CN107615314B (en) 2021-04-09

Similar Documents

Publication Publication Date Title
Erol et al. Measuring the impact of lean construction practices on project duration and variability: A simulation-based study on residential buildings
Tyagi et al. Immersive virtual reality to vindicate the application of value stream mapping in an US-based SME
JP6682223B2 (en) Plan management system and plan management method
GB2377789A (en) Project and process management system
WO2018180743A1 (en) Work management device, work management method, and program storage medium
JP5885637B2 (en) Scheduling method, scheduling program, and scheduling apparatus
JP2004005461A (en) Rotation planning method and rotation planning device
JP2013025346A (en) Management system and management method
Biruk et al. Minimizing project cost by integrating subcontractor selection decisions with scheduling
CN107615314A (en) Production plan generates servicing unit and production plan generating means
US20140058963A1 (en) Facility control system (fcs-c2) (introduction of traveler form) to manage assets planning, design, construction, fabrication, operating, maintence and products fabrication
JP6605407B2 (en) Human resource development support system
JP2004323162A (en) Maintenance business simulator, maintenance service planning support system and maintenance business support system
JP2009151733A (en) Facility check schedule making support apparatus and method, and facilities management system
KR20160131192A (en) Rebar processing integrated management system
Tatum Integration: emerging management challenge
JP2002244716A (en) Line capacity evaluation system
JP2011170705A (en) Work schedule management device, work schedule management method, and control program for the work schedule management device
JP2005182576A (en) Maintenance estimation system for house
KR100901531B1 (en) Communication system for producing digital contents
JP7298666B2 (en) Secondment planning system, control method and program
JP2007317103A (en) Workforce efectively utilizing system, method, program, and recording medium which stores workforce efectively utilizing program
JP7268719B1 (en) Secondment planning system, control method and program
US20170270459A1 (en) Device, System, and Method for Tracking Job Management
Vishnuraj et al. Optimization of resources in highway construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210409

CF01 Termination of patent right due to non-payment of annual fee