JP5885637B2 - Scheduling method, scheduling program, and scheduling apparatus - Google Patents

Scheduling method, scheduling program, and scheduling apparatus Download PDF

Info

Publication number
JP5885637B2
JP5885637B2 JP2012229030A JP2012229030A JP5885637B2 JP 5885637 B2 JP5885637 B2 JP 5885637B2 JP 2012229030 A JP2012229030 A JP 2012229030A JP 2012229030 A JP2012229030 A JP 2012229030A JP 5885637 B2 JP5885637 B2 JP 5885637B2
Authority
JP
Japan
Prior art keywords
plan
correction
equipment
corrected
previous
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2012229030A
Other languages
Japanese (ja)
Other versions
JP2014081778A (en
Inventor
理人 井筒
理人 井筒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobe Steel Ltd
Original Assignee
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobe Steel Ltd filed Critical Kobe Steel Ltd
Priority to JP2012229030A priority Critical patent/JP5885637B2/en
Publication of JP2014081778A publication Critical patent/JP2014081778A/en
Application granted granted Critical
Publication of JP5885637B2 publication Critical patent/JP5885637B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、修正指示に基づいて、既に作成されたスケジュールの修正を行うスケジューリング方法及びスケジューリングプログラム、並びにスケジューリング装置に関する。   The present invention relates to a scheduling method, a scheduling program, and a scheduling apparatus that correct an already created schedule based on a correction instruction.

従来から、鉄鋼業等の生産管理においては、スケジューラ(計画、即ちスケジュールを生成するコンピュータ等からなる装置)を用いて、所定の制約条件を満たした上で、1つ以上のオーダーについて、当該オーダーの製品を製造するのに必要な工程を、使用する設備に割り付けてスケジュールが作成されている。ここで、スケジュールには、各オーダーの工程毎に、使用する設備と開始時刻及び終了時刻とが決定され、各オーダーの工程毎に使用する設備と開始時刻及び終了時刻の表として出力されたり、オーダー毎又は設備毎のガントチャートとして出力されたりする。   Conventionally, in production management in the steel industry, etc., a scheduler (a device comprising a plan, that is, a computer that generates a schedule) is used to satisfy one or more orders, while satisfying predetermined constraints. Schedules are created by assigning the processes necessary to manufacture the products to the equipment to be used. Here, in the schedule, the equipment to be used and the start time and end time are determined for each process of each order, and the equipment to be used for each order process and output as a table of the start time and end time, It is output as a Gantt chart for each order or equipment.

そして、生産現場の実績や進捗、受注の変化等に対応するため、既に作成されたスケジュール(以下、「前回計画」と称する。)について、修正が必要となることがある。かかる場合には、入力装置を介して、前回計画において修正が必要となる所定のオーダーの工程について、使用する設備や開始時刻を修正する複数の修正指示が行われる。そして、再度スケジューラを用いて、複数の修正指示に基づいて前回計画が修正される。具体的には、特許文献1に示すように、ガントチャートとして表示装置の画面上に表示された前回計画に対して、入力装置により、所定のオーダーの工程がガントチャート上で移動されたり、入れ替えられたりすることにより、前回計画が修正される。
Then, in order to cope with the actual results and progress at the production site, changes in orders, etc., it may be necessary to modify the already created schedule (hereinafter referred to as “previous plan”). In such a case, a plurality of correction instructions for correcting the equipment to be used and the start time are given via the input device for a predetermined order process that needs to be corrected in the previous plan. Then, using the scheduler again, the previous plan is corrected based on a plurality of correction instructions . Specifically, as shown in Patent Document 1, a process of a predetermined order is moved or replaced on the Gantt chart by the input device with respect to the previous plan displayed on the screen of the display device as a Gantt chart. The previous plan will be revised.

特開2007−157124号公報JP 2007-157124 A

しかしながら、前回計画は既に生産現場に配布されており、前回計画に従って作業が行われているため、修正指示が行われて修正されたスケジュールが前回計画と大きく変化してしまい、生産現場が混乱するという問題が生じてしまう。例えば、前回計画から所定の工程の作業順番が大きく変わったり、工程を作業する設備の変更が多くなったりすると、準備していた作業が無駄になってしまったり、作業の準備が間に合わなくなったりしてしまい、生産現場が混乱してしまう。   However, since the previous plan has already been distributed to the production site and work is being carried out according to the previous plan, the correction instructions are given and the revised schedule changes significantly from the previous plan, which disrupts the production site. The problem will arise. For example, if the work order of a given process changes significantly from the previous plan, or if there are many changes in the equipment that operates the process, the work that has been prepared may be wasted, or the preparation for the work may not be in time. The production site will be confused.

そこで、本発明が解決しようとする課題は、前回計画に対して複数の修正指示が行われた場合であっても、既存の前回計画に対する変化の度合いに基づいて、前回計画を修正することができるスケジューリング方法及びスケジューリングプログラム、並びにスケジューリング装置を提供するものである。
Therefore, the problem to be solved by the present invention is to correct the previous plan based on the degree of change with respect to the existing previous plan, even when a plurality of correction instructions are given to the previous plan. A scheduling method, a scheduling program, and a scheduling apparatus are provided.

本発明に係るスケジューリング方法は、計算機の演算部により実行される処理が、複数のオーダーについての納期、各オーダーの製品を製造するために通過する工程とその通過工程の順序、各工程で使用する設備、各工程の作業時間、設備間の搬送時間がマスタ情報として記憶されるマスタ情報記憶ステップと、前記各オーダーの工程毎に、使用する設備と、開始時刻及び終了時刻と、が決定されて既に作成されたスケジュールを前回計画として記憶する前回計画記憶ステップと、前記前回計画に関して、入力手段を介して複数入力された修正対象となる工程についての開始時刻または設備の変更を、複数の修正指示として記憶する修正指示記憶ステップと、前記複数の修正指示のそれぞれについて、1台の設備で複数の工程を同時に作業することができない制約、及び、前後工程で使用される設備間には前記搬送時間が空いているという制約を考慮して、オーダー単位で通過工程順に工程を抽出し、抽出した工程が前記修正対象となる工程の場合は変更された開始時刻を、抽出した工程が前記修正対象となる工程でない場合は前記前回計画で記憶された開始時刻を比較し、開始時刻が最も早い工程を、前記修正対象となる工程の場合は変更された設備に、前記修正対象となる工程でない場合は前記マスタ情報で記憶された設備に割り付けてスケジュールを作成し、前記複数の修正指示のそれぞれに対応する複数の修正計画案として出力する修正計画案作成ステップと、前記複数の修正計画案のそれぞれについて、工程毎に前記前回計画と比較して、次順の工程が当該工程よりも前に変化している工程の数と、設備毎に前記前回計画と比較して、当該設備に追加された工程の数と当該設備から削除された工程の数と、の総和を、前記複数の修正計画案のそれぞれに対応する評価値として計算する評価値算出ステップと、前記評価値が最も小さい修正計画案を、修正計画として選択する修正計画決定ステップと、を有することを特徴とする。   In the scheduling method according to the present invention, the processing executed by the computing unit of the computer is used in each step, delivery time for a plurality of orders, a process that passes to manufacture a product of each order, a sequence of the passing processes, Master information storage step in which equipment, work time of each process, transport time between equipment is stored as master information, equipment to be used, start time and end time are determined for each process of each order A previous plan storage step for storing a schedule that has already been created as a previous plan, and a plurality of correction instructions regarding a change in start time or equipment for a process to be corrected that has been input via the input means with respect to the previous plan. As a correction instruction storage step stored as a plurality of correction instructions, a plurality of processes are simultaneously performed by one facility. In consideration of the restrictions that cannot be performed and the restriction that the transfer time is vacant between the equipment used in the preceding and following processes, the processes are extracted in order of passing processes in order units, and the extracted processes are the correction targets. If the extracted process is not the process to be corrected, the start time stored in the previous plan is compared, and the process with the earliest start time is referred to as the correction target. If the process is a process that is changed, and if it is not the process to be corrected, the schedule is created by allocating the equipment stored in the master information, and a plurality of correction plans corresponding to each of the plurality of correction instructions For each of the plurality of revision plan proposals to be output as a draft and each of the plurality of revision plan drafts, the next process is preceded by the process in comparison with the previous plan. The total of the number of processes that have changed and the number of processes added to the equipment and the number of processes deleted from the equipment compared to the previous plan for each equipment is the plurality of modified plans. An evaluation value calculating step for calculating as an evaluation value corresponding to each plan, and a correction plan determining step for selecting a correction plan plan having the smallest evaluation value as a correction plan.

本発明に係るスケジューリングプログラムは、複数のオーダーについての納期、各オーダーの製品を製造するために通過する工程とその通過工程の順序、各工程で使用する設備、各工程の作業時間、設備間の搬送時間がマスタ情報として記憶されるマスタ情報記憶ステップと、前記各オーダーの工程毎に、使用する設備と、開始時刻及び終了時刻と、が決定されて既に作成されたスケジュールを前回計画として記憶する前回計画記憶ステップと、前記前回計画に関して、入力手段を介して複数入力された修正対象となる工程についての開始時刻または設備の変更を、複数の修正指示として記憶する修正指示記憶ステップと、前記複数の修正指示のそれぞれについて、1台の設備で複数の工程を同時に作業することができない制約、及び、前後工程で使用される設備間には前記搬送時間が空いているという制約を考慮して、オーダー単位で通過工程順に工程を抽出し、抽出した工程が前記修正対象となる工程の場合は変更された開始時刻を、抽出した工程が前記修正対象となる工程でない場合は前記前回計画で記憶された開始時刻を比較し、開始時刻が最も早い工程を、前記修正対象となる工程の場合は変更された設備に、前記修正対象となる工程でない場合は前記マスタ情報で記憶された設備に割り付けてスケジュールを作成し、前記複数の修正指示のそれぞれに対応する複数の修正計画案として出力する修正計画案作成ステップと、前記複数の修正計画案のそれぞれについて、工程毎に前記前回計画と比較して、次順の工程が当該工程よりも前に変化している工程の数と、設備毎に前記前回計画と比較して、当該設備に追加された工程の数と当該設備から削除された工程の数と、の総和を、前記複数の修正計画案のそれぞれに対応する評価値として計算する評価値算出ステップと、前記評価値が最も小さい修正計画案を、修正計画として選択する修正計画決定ステップと、を有し、計算機において演算部により読み出して各ステップの処理を実行させることを特徴とする。   The scheduling program according to the present invention includes a delivery date for a plurality of orders, a process that passes through to produce a product of each order and an order of the passing process, equipment used in each process, work time of each process, and A master information storage step in which the transport time is stored as master information, and the equipment to be used, the start time and the end time are determined for each order process, and the schedule already created is stored as the previous plan. A previous plan storage step, a correction instruction storage step for storing a plurality of correction instructions as a plurality of correction instructions, with respect to the previous plan; For each of the correction instructions, there is a restriction that it is not possible to work on multiple processes simultaneously with one facility, and before and after Considering the restriction that the transfer time is vacant between the equipment used in the process, the process is extracted in order of the passing process in order unit, and the extracted process is changed if it is the process to be corrected When the extracted process is not the process to be corrected, the start time stored in the previous plan is compared, and the process with the earliest start time is changed for the process to be corrected If the process is not the process to be corrected, create a schedule by allocating the schedule to the equipment stored in the master information, and outputting the schedule as a plurality of correction plans corresponding to each of the plurality of correction instructions For each step and each of the plurality of revised plan proposals, the number of processes in which the next process is changed before the process and the number of processes compared to the previous plan for each process Evaluation that calculates the sum of the number of processes added to the equipment and the number of processes deleted from the equipment as an evaluation value corresponding to each of the plurality of revised plan plans as compared to the previous plan A value calculation step, and a correction plan determination step for selecting a correction plan with the smallest evaluation value as a correction plan, wherein the calculation unit reads out the calculation unit in a computer and executes the processing of each step .

本発明に係るスケジューリング装置は、複数のオーダーについての納期、各オーダーの製品を製造するために通過する工程とその通過工程の順序、各工程で使用する設備、各工程の作業時間、設備間の搬送時間がマスタ情報として記憶されるマスタ情報記憶手段と、前記各オーダーの工程毎に、使用する設備と、開始時刻及び終了時刻と、が決定されて既に作成されたスケジュールを前回計画として記憶する前回計画記憶手段と、前記前回計画に関して、入力手段を介して複数入力された修正対象となる工程についての開始時刻または設備の変更を、複数の修正指示として記憶する修正指示記憶手段と、前記複数の修正指示のそれぞれについて、1台の設備で複数の工程を同時に作業することができない制約、及び、前後工程で使用される設備間には前記搬送時間が空いているという制約を考慮して、オーダー単位で通過工程順に工程を抽出し、抽出した工程が前記修正対象となる工程の場合は変更された開始時刻を、抽出した工程が前記修正対象となる工程でない場合は前記前回計画で記憶された開始時刻を比較し、開始時刻が最も早い工程を、前記修正対象となる工程の場合は変更された設備に、前記修正対象となる工程でない場合は前記マスタ情報で記憶された設備に割り付けてスケジュールを作成し、前記複数の修正指示のそれぞれに対応する複数の修正計画案として出力する修正計画案作成手段と、前記複数の修正計画案のそれぞれについて、工程毎に前記前回計画と比較して、次順の工程が当該工程よりも前に変化している工程の数と、設備毎に前記前回計画と比較して、当該設備に追加された工程の数と当該設備から削除された工程の数と、の総和を、前記複数の修正計画案のそれぞれに対応する評価値として計算する評価値算出手段と、前記評価値が最も小さい修正計画案を、修正計画として選択する修正計画決定手段と、が計算機の演算部に実装されることを特徴とする。   The scheduling apparatus according to the present invention includes a delivery date for a plurality of orders, a process that passes through the order to produce a product of each order, an order of the passing process, equipment used in each process, work time of each process, and The master information storage means for storing the transfer time as master information, the equipment to be used, the start time and the end time for each process of each order, and the schedule already created and stored as the previous plan Previous plan storage means, correction instruction storage means for storing a plurality of correction instructions as a start time or a change in equipment for a process to be corrected, which is input via the input means with respect to the previous plan, and the plural For each of these correction instructions, there is a restriction that a single facility cannot work on multiple processes at the same time. In consideration of the restriction that the transfer time is vacant in the meantime, the process is extracted in order of the passing process in order units, and when the extracted process is the process to be corrected, the changed start time is extracted. If the process is not the process to be corrected, the start time stored in the previous plan is compared, and the process with the earliest start time is compared to the modified equipment if the process is the process to be corrected. If it is not a process to become, a schedule is created by allocating to the equipment stored in the master information, and a plurality of revision plan drafts corresponding to each of the plurality of revision instructions, and a plurality of revision plan draft creation means, For each revised plan, compare the previous plan for each process with the number of processes in which the next process has changed before that process, and compare with the previous plan for each facility. The evaluation value calculating means for calculating the sum of the number of processes added to the equipment and the number of processes deleted from the equipment as an evaluation value corresponding to each of the plurality of revised plan plans, and the evaluation A correction plan determining means for selecting a correction plan plan having the smallest value as a correction plan is mounted on a calculation unit of the computer.

これによると、前回計画に対して複数の修正指示が行われた場合に、複数の修正指示のそれぞれについて修正計画案を作成し、修正計画案のそれぞれについて前回計画と比較し、3種類の変化の度合い(設備の中で作業する予定である作業を同じ設備の中で順序のみ変更する。設備の中で作業する予定である作業以外の作業が追加される。設備の中で作業する予定であった作業を削除する。)に基づいて算出された評価値によって修正計画案のそれぞれの前回計画からの乖離度が算出される。そして、評価値が最も小さく前回計画から乖離度が少ない修正計画案が修正された計画として選択される。従って、前回計画に対して複数の修正指示が行われた場合であっても、既存の前回計画に対する変化の度合いに基づいて、前回計画を修正することができる。
According to this, when a plurality of correction instructions are given for the previous plan, a correction plan is created for each of the plurality of correction instructions, and each of the correction plans is compared with the previous plan in three types of changes. to the degree (change only the order of the work is scheduled to work in the facility in the same equipment. work other than work is scheduled to work in the facility will be added. I plan to work in the facility The degree of divergence of the revised plan from the previous plan is calculated based on the evaluation value calculated based on the above. Then, the revised plan with the smallest evaluation value and the least deviation from the previous plan is selected as the revised plan. Therefore, even when a plurality of correction instructions are issued for the previous plan , the previous plan can be corrected based on the degree of change with respect to the existing previous plan.

ここで、本発明に係るスケジューリング方法及びスケジューリングプログラム、並びにスケジューリング装置では、前記修正指示は、修正対象となる工程についての開始時刻及び設備の変更を含んで良い。   Here, in the scheduling method, the scheduling program, and the scheduling apparatus according to the present invention, the correction instruction may include a change in start time and equipment for a process to be corrected.

これにより、多様な修正指示に対応しつつ、既存の前回計画に対する変化の度合いに基づいて、前回計画を修正することができる。
Thus , the previous plan can be corrected based on the degree of change with respect to the existing previous plan while responding to various correction instructions.

尚、本発明に係るスケジューリングプログラムは、リムーバブル型記録媒体やハードディスクなどの固定型記録媒体に記録して配布可能である他、有線又は無線の電気通信手段によってインターネットなどの通信ネットワークを介して配布可能である。   The scheduling program according to the present invention can be recorded and distributed on a fixed recording medium such as a removable recording medium or a hard disk, or can be distributed via a communication network such as the Internet by wired or wireless telecommunication means. It is.

本発明のスケジューリング方法及びスケジューリングプログラム、並びにスケジューリング装置は、前回計画に対して複数の修正指示が行われた場合であっても、既存の前回計画に対する変化の度合いに基づいて、前回計画を修正することができる。
Scheduling method and scheduling program of the present invention, as well as the scheduling apparatus, even when a plurality of correction instructions is performed on the previous plan, based on the degree of change to existing previous plans, modifies the previous plans be able to.

本実施形態に係るスケジューリング装置のブロック図である。It is a block diagram of the scheduling apparatus which concerns on this embodiment. 本実施形態に係るスケジューリング方法の処理の手順について説明したフローチャートである。It is the flowchart explaining the procedure of the process of the scheduling method which concerns on this embodiment. 本実施形態の一例としてオーダーの納期とオーダーの各工程の作業時間と設備間の搬送時間との関係を示す図である。It is a figure which shows the relationship between the delivery date of an order, the work time of each process of an order, and the conveyance time between facilities as an example of this embodiment. 本実施形態の一例として、前回計画を示すガントチャート図である。It is a Gantt chart figure showing the last plan as an example of this embodiment. 本実施形態の一例として、前回計画に対する修正指示Aを示すガントチャート図である。It is a Gantt chart figure which shows the correction instruction | indication A with respect to the last plan as an example of this embodiment. 本実施形態の一例として、前回計画に対する修正指示Bを示すガントチャート図である。It is a Gantt chart figure which shows the correction instruction | indication B with respect to the last plan as an example of this embodiment. 本実施形態の一例として、複数のオーダーの工程と割付リストとの関係を示す図である。As an example of this embodiment, it is a figure which shows the relationship between the process of a some order, and an allocation list | wrist. 本実施形態の一例として、割付リストを更新する例を示す図である。It is a figure which shows the example which updates the allocation list | wrist as an example of this embodiment. 本実施形態の一例として、修正指示Aに対する修正計画案を示すガントチャート図である。It is a Gantt chart figure which shows the correction plan plan with respect to the correction instruction | indication A as an example of this embodiment. 本実施形態の一例として、修正指示Bに対する修正計画案を示すガントチャート図である。It is a Gantt chart figure which shows the correction plan plan with respect to the correction instruction | indication B as an example of this embodiment. 本実施形態の一例として、3種類の修正指示を示すガントチャート図である。It is a Gantt chart figure which shows three types of correction instructions as an example of this embodiment. 本実施形態の一例として、同じ設備の中での工程の順序のみ変更する修正指示に対して修正した後の工程の順序を示す図である。It is a figure which shows the order of the process after correcting with respect to the correction instruction | indication which changes only the order of the process in the same installation as an example of this embodiment. 本実施形態の一例として、修正指示Aに対する修正計画案の評価値の計算結果を示す図である。It is a figure which shows the calculation result of the evaluation value of the correction plan plan with respect to the correction instruction | indication A as an example of this embodiment.

以下、図面を参照しつつ、本発明に係るスケジューリング方法及びスケジューリングプログラム、並びにスケジューリング装置を実施するための形態について、具体的な一例に即して説明する。   Hereinafter, a scheduling method, a scheduling program, and a mode for carrying out a scheduling device according to the present invention will be described with reference to a specific example.

尚、以下に説明するものは、例示したものにすぎず、本発明に係るスケジューリング方法及びスケジューリングプログラム、並びにスケジューリング装置の適用限界を示すものではない。すなわち、本発明に係るスケジューリング方法及びスケジューリングプログラム、並びにスケジューリング装置は、下記の実施形態に限定されるものではなく、特許請求の範囲に記載した限りにおいてさまざまな変更が可能なものである。   In addition, what is demonstrated below is only what was illustrated and does not show the application limit of the scheduling method, the scheduling program, and the scheduling apparatus according to the present invention. That is, the scheduling method, the scheduling program, and the scheduling apparatus according to the present invention are not limited to the following embodiments, and various modifications are possible as long as they are described in the claims.

本実施形態では、既に作成されたスケジュールである前回計画が存在し、前回計画において修正が必要となる所定のオーダーの工程について、使用する設備や開始時刻を修正する修正指示が行われる場合を想定している。   In the present embodiment, it is assumed that there is a previous plan that is a schedule that has already been created, and a correction instruction for correcting the equipment to be used and the start time is performed for a process of a predetermined order that needs to be corrected in the previous plan. doing.

まず、本実施形態に係るスケジューリング装置について、図1に基づいて説明する。図1は、本実施形態に係るスケジューリング装置のブロック図である。スケジューリング装置1は、演算部と、記憶部と、入力部と、出力部と、から構成されて、計算機上に実装される。ここで、図1に示されているスケジューリング装置1の各部(演算部、記憶部、入力部、及び、出力部)は、例えば汎用のパーソナルコンピュータ等の計算機によって構成されている。かかる計算機には、CPU、ROM、RAM、ハードディスク、CD−ROMの駆動装置などのハードウェアが収納されており、ハードディスクには、プログラム(このプログラムは、リムーバブルな記憶媒体に記録しておくことにより、様々なコンピュータにインストールすることが可能である)を含む各種のソフトウェアが記録されている。そして、これらのハードウェア及びソフトウェアが組み合わされることによって、上述の各部が構築されている。   First, the scheduling apparatus according to the present embodiment will be described with reference to FIG. FIG. 1 is a block diagram of the scheduling apparatus according to the present embodiment. The scheduling device 1 includes a calculation unit, a storage unit, an input unit, and an output unit, and is mounted on a computer. Here, each part (calculation part, memory | storage part, input part, and output part) of the scheduling apparatus 1 shown by FIG. 1 is comprised by computers, such as a general purpose personal computer. Such a computer stores hardware such as a CPU, ROM, RAM, hard disk, and CD-ROM drive, and the hard disk stores a program (this program is recorded on a removable storage medium). Can be installed on a variety of computers). And the above-mentioned each part is constructed | assembled by combining these hardware and software.

図1に示すように、スケジューリング装置1は、マスタ情報11と、修正指示12と、修正計画案13と、前回計画14と、評価値15と、修正計画16と、マスタ情報記憶部21と、修正指示入力部22と、計画エンジン部(修正計画案作成手段)23と、評価値算出部24と、修正計画決定部25と、修正計画出力部26と、から構成される。   As shown in FIG. 1, the scheduling apparatus 1 includes master information 11, a correction instruction 12, a correction plan 13, a previous plan 14, an evaluation value 15, a correction plan 16, a master information storage unit 21, The correction instruction input unit 22, the plan engine unit (correction plan creation means) 23, the evaluation value calculation unit 24, the correction plan determination unit 25, and the correction plan output unit 26 are configured.

マスタ情報記憶部21は、受注した複数のオーダーについて、納期と、オーダーの製品を製造するために通過する工程とその通過工程の順序と、各工程で使用する設備と、各工程の作業時間と、設備間の搬送時間とを、マスタ情報11として外部から登録されて記憶するためのものである。ここで、マスタ情報記憶部21は、前回計画におけるスケジューリング時に、図示しない入力部(キーボード等)から入力されたり、リムーバブルな記憶媒体に記録されて与えられたり、有線又は無線の電気通信手段によってインターネットなどの通信ネットワークを介して与えられたりして、マスタ情報11が記憶装置や補助記憶装置等に記憶される。
マスタ情報11として、具体的には、表1に例示する納期、表2に例示する通過する工程とその通過工程の順序及び各工程で使用する設備、表3に例示する工程の作業時間、表4に例示する設備間の搬送時間が記憶される。また、オーダーの製品を製造するために通過する工程の順序と、各工程の作業時間と、設備間(即ち、前後工程で使用される設備間)の搬送時間を例示すると、図3に示すような関係になる。
For a plurality of orders received, the master information storage unit 21 delivers the delivery date, the process that passes through the order to produce the product, the order of the passing process, the equipment used in each process, and the working time of each process. The transfer time between facilities is registered and stored as master information 11 from the outside. Here, the master information storage unit 21 is input from an input unit (keyboard or the like) (not shown) at the time of scheduling in the previous plan, is recorded on a removable storage medium, or is provided via wired or wireless telecommunication means. The master information 11 is stored in a storage device, an auxiliary storage device, or the like.
As master information 11, specifically, the delivery date illustrated in Table 1, the passing process illustrated in Table 2, the order of the passing process, the equipment used in each process, the working time of the process illustrated in Table 3, a table The conveyance time between the facilities illustrated in 4 is stored. Moreover, as illustrated in FIG. 3, examples of the order of the steps that pass through to produce the ordered product, the working time of each step, and the transfer time between facilities (that is, between the facilities used in the preceding and following processes) It becomes a relationship.

修正指示入力部22は、図示しない入力部を介して、前回計画14において修正を行う必要がある修正対象となる所定のオーダーの工程について、使用する設備や開始時刻を修正する複数の修正指示を入力し、複数の修正指示12として記憶するためのものである。ここで、前回計画14は、既に作成されたスケジュールであって、予め記憶されているものであり、前回計画14として、スケジューリングの対象となったオーダーの各工程について、使用する設備、開始時刻(即ち、前回計画の開始時刻)、終了時刻が記憶されている。
本実施形態において、修正指示は、複数入力されることを前提としており、修正対象となる所定のオーダーの工程について、同一設備内における開始時刻の変更と、作業する設備の変更の2種類を想定している。また、修正指示は、修正対象となる所定のオーダーの工程についての同一設備内における開始時刻の変更と、修正対象となる所定のオーダーの工程についての作業する設備の変更と、修正対象となる所定のオーダーの工程についての開始時刻の変更及び作業する設備の変更と、を含むものである。更に、修正指示入力部22は、前回計画14において修正対象となる所定のオーダーの工程と、変更する開始時刻や作業する設備とを、キーボードなどの入力部により書き込まれることにより入力されるように構成されていても良いし、ディスプレイなどの出力部に表示された前回計画14のガントチャートに対して、修正対象となる所定のオーダーの工程を、マウスなどの入力部により変更する開始時刻や設備に移動されることにより入力されるように構成されても良い。尚、修正指示が修正対象となる所定のオーダーの工程についての開始時刻の変更である場合、マスタ情報11に記憶された同一オーダー内の通過工程の順序の制約に従い、修正指示として変更される開始時刻は、修正対象となる所定のオーダーの工程と同一のオーダーにおいて通過工程が前後となる工程の間の時間に限定しても良い。
The correction instruction input unit 22 provides a plurality of correction instructions for correcting the equipment to be used and the start time for a process of a predetermined order to be corrected that needs to be corrected in the previous plan 14 via an input unit (not shown). It is for inputting and storing as a plurality of correction instructions 12. Here, the previous plan 14 is a schedule that has already been created and is stored in advance. As the previous plan 14, the equipment to be used and the start time ( That is, the last plan start time) and end time are stored.
In the present embodiment, it is assumed that a plurality of correction instructions are input, and for the predetermined order process to be corrected, two types are assumed: a change in the start time in the same equipment and a change in the equipment to be operated. doing. The correction instruction includes a change in start time in the same equipment for a process of a predetermined order to be corrected, a change of equipment to work on a process of a predetermined order to be corrected, and a predetermined to be corrected. Change of the start time for the process of ordering and change of equipment to work on. Furthermore, the correction instruction input unit 22 is configured to input a predetermined order process to be corrected in the previous plan 14, a start time to be changed, and a facility to be operated by being written by an input unit such as a keyboard. It may be configured, and the start time and equipment for changing the process of a predetermined order to be corrected by an input unit such as a mouse with respect to the Gantt chart of the previous plan 14 displayed on the output unit such as a display. It may be configured to be input by being moved. When the correction instruction is a change in the start time for a process of a predetermined order to be corrected, the change instruction is changed as a correction instruction in accordance with the restriction on the order of passing processes in the same order stored in the master information 11 The time may be limited to a time between processes in which the passing process is before and after in the same order as the process of the predetermined order to be corrected.

ここで、本実施形態の一例として、図4〜図6で示す具体例を用いて、修正指示入力部22の作用について説明する。ここで、図4〜6に示す例においては、オーダーはオーダー1〜3の3種類、設備は設備M1〜M3の3種類存在するものとしており、工程をW(オーダー番号)_(通過工程の順番)/(当該工程で使用する設備)として表現している。図4は、前回計画の一例を示すガントチャート図であり、上段の3列はオーダー毎のガントチャートであり、下段の3列は設備毎のガントチャートである。そして、図4に示す前回計画において、オーダー3の第4工程である工程W3_4/M1の優先度を高くする必要があるとする。
かかる場合に、図5に示すように、工程W3_4を設備M1から設備M2に設備変更するべく、入力部を介してガントチャート上で工程W3_4を、開始時刻はそのまま同じにして、設備M1(工程W3_4/M1)から設備M2(工程W3_4/M2)に移動させることにより、修正指示Aを入力する。図5は、図4に示す前回計画に対する修正指示Aを示すガントチャート図であり、上段の3列はオーダー毎のガントチャートであり、下段の3列は設備毎のガントチャートである。そして、修正指示入力部22からなされた修正指示Aとして、工程W3_4に使用する設備を設備M2に変更する情報が、修正指示12に記憶される。
また、図6に示すように、工程W3_4/M1の順序を同一設備M1内における前の工程である工程W2_3/M1の前になるように変更するべく、入力部を介してガントチャート上で同一設備M1内において工程W3_4/M1を工程W2_3/M1の前に移動させことにより、修正指示2を入力する。図6は、図4に示す前回計画に対する修正指示Bを示すガントチャート図であり、上段の3列はオーダー毎のガントチャートであり、下段の3列は設備毎のガントチャートである。そして、修正指示入力部22からなされた修正指示Bとして、工程W3_4/M1の開始時刻を移動後の開始時刻に変更する情報が、修正指示12に記憶される。
Here, as an example of the present embodiment, the operation of the correction instruction input unit 22 will be described using specific examples illustrated in FIGS. 4 to 6. Here, in the examples shown in FIGS. 4 to 6, there are three types of orders, orders 1 to 3, and three types of equipment M1 to M3, and the process is W (order number) _ (passing process). (Order) / (Equipment used in the process) FIG. 4 is a Gantt chart showing an example of the previous plan. The upper three columns are Gantt charts for each order, and the lower three columns are Gantt charts for each facility. In the previous plan shown in FIG. 4, it is assumed that the priority of the process W3_4 / M1 that is the fourth process of the order 3 needs to be increased.
In this case, as shown in FIG. 5, in order to change the process W3_4 from the equipment M1 to the equipment M2, the process W3_4 is set on the Gantt chart via the input unit with the same start time, and the equipment M1 (process By moving from W3_4 / M1) to equipment M2 (process W3_4 / M2), correction instruction A is input. FIG. 5 is a Gantt chart showing a correction instruction A for the previous plan shown in FIG. 4, wherein the upper three columns are Gantt charts for each order, and the lower three columns are Gantt charts for each facility. Then, as the correction instruction A made from the correction instruction input unit 22, information for changing the facility used for the process W3_4 to the facility M2 is stored in the correction instruction 12.
In addition, as shown in FIG. 6, the order of the processes W3_4 / M1 is the same on the Gantt chart via the input unit so as to be changed to be before the process W2_3 / M1, which is the previous process in the same equipment M1. The correction instruction 2 is input by moving the process W3_4 / M1 before the process W2_3 / M1 in the facility M1. FIG. 6 is a Gantt chart showing a correction instruction B for the previous plan shown in FIG. 4, wherein the upper three columns are Gantt charts for each order, and the lower three columns are Gantt charts for each facility. Information for changing the start time of the process W3_4 / M1 to the start time after the movement is stored in the correction instruction 12 as the correction instruction B made from the correction instruction input unit 22.

計画エンジン部(修正計画案作成手段)23は、いわゆるスケジューラであって、複数の修正指示12のそれぞれについてスケジュールを作成し、複数の修正指示12のそれぞれに対応する修正計画案13として記憶するためのものである。即ち、計画エンジン部23は、オーダー単位で通過工程順に(即ち、通過順序が早い順に)工程を抽出する。これにより、複数のオーダーのそれぞれについて、通過順序が早い工程が抽出される。そして、抽出した工程が修正対象となる工程である場合は修正指示12で変更された開始時刻を、抽出した工程が修正対象となる工程でない場合は前回計画14で記憶された開始時刻を比較し、開始時刻が最も早い工程を選択し、所定の制約を考慮して、選択された工程が修正対象となる工程である場合は修正指示12で変更された設備に、選択された工程が修正対象となる工程でない場合はマスタ情報11で記憶された設備に割り付けてスケジュールを作成する作業を複数の修正指示12のそれぞれについて行い、複数の修正指示12のそれぞれに対応する修正計画案13を作成する。ここで、所定の制約条件とは、1台の設備で、複数の工程を同時に作業することができない制約と、前後工程で使用される設備間には、最低搬送時間(設備間の搬送時間)が空いているという制約である。   The plan engine unit (correction plan drafting means) 23 is a so-called scheduler, which creates a schedule for each of the plurality of correction instructions 12 and stores them as a correction plan draft 13 corresponding to each of the plurality of correction instructions 12. belongs to. That is, the plan engine unit 23 extracts processes in order of the passing process in order units (that is, in order of passing order). Thereby, a process with an early passage order is extracted for each of the plurality of orders. If the extracted process is a process to be corrected, the start time changed by the correction instruction 12 is compared. If the extracted process is not a process to be corrected, the start time stored in the previous plan 14 is compared. When the process having the earliest start time is selected and the selected process is a process to be corrected in consideration of a predetermined constraint, the selected process is the correction target in the equipment changed by the correction instruction 12 If it is not a process to be performed, an operation for assigning the equipment stored in the master information 11 and creating a schedule is performed for each of the plurality of correction instructions 12, and a correction plan 13 corresponding to each of the plurality of correction instructions 12 is created. . Here, the predetermined constraint condition is the restriction that a plurality of processes cannot be simultaneously performed with one facility, and the minimum transport time (transport time between facilities) between the facilities used in the preceding and following processes. It is a restriction that is free.

ここで、本実施形態の一例として、図7〜図10で示す具体例を用いて、計画エンジン部23の作用について説明する。ここで、上述した図4〜6で示す具体例と同様に、図7〜10に示す例においては、オーダーはオーダー1〜3の3種類、設備は設備M1〜M3の3種類存在するものとしており、工程をW(オーダー番号)_(通過工程の順番)/(当該工程で使用する設備)として表現している。
具体的には、計画エンジン部23は、図7に例示するように、まず、オーダー単位で、通過順序が最も早い工程を抽出して割付リストに登録する(図7では、オーダー1の第1工程W1_1/M1、オーダー2の第1工程W2_1/M1、オーダー3の第1工程W3_1/M3)。そして、割付リストの中で、抽出した工程が修正対象となる工程である場合は修正指示12で変更された開始時刻を、抽出した工程が修正対象となる工程でない場合は前回計画14で記憶された開始時刻を比較し、開始時刻が最も早い工程を選択する。次に、選択した工程を、「前工程の終了時刻+前後工程で使用される設備間の搬送時間」(第1工程の場合、着手時刻(まだ着手していない場合は計画開始時刻))以降に、選択された工程が修正対象となる工程である場合は修正指示12で変更された設備に、選択された工程が修正対象となる工程でない場合はマスタ情報11で登録された設備に割り付ける。即ち、選択された工程について、使用する設備、開始時刻、終了時刻が決定される。そして、図8に例示するように、選択された工程の次の工程(図8では、オーダー1の工程W1_1/M1の次工程である工程W1_2/M3)が割付リストに登録される。このように、全ての工程を通過工程の順番に割り付けていく。このようにして、修正指示12に記憶された複数の修正指示のそれぞれに対応する修正計画案(具体例として、修正指示Aに対する修正計画案が図9、修正指示Bに対する修正計画案が図10)が作成され(全オーダーの各工程について、使用する設備、開始時刻、終了時刻が決定され)、修正計画案13として記憶される。
Here, as an example of the present embodiment, the operation of the plan engine unit 23 will be described using specific examples shown in FIGS. Here, similarly to the specific examples shown in FIGS. 4 to 6 described above, in the examples shown in FIGS. 7 to 10, the order has three types of orders 1 to 3 and the equipment has three types of equipment M1 to M3. The process is expressed as W (order number) _ (order of passing process) / (equipment used in the process).
Specifically, as illustrated in FIG. 7, the plan engine unit 23 first extracts a process having the earliest passing order in order units and registers it in the allocation list (in FIG. 7, the first order 1 is ordered). Step W1_1 / M1, Order 2 first step W2_1 / M1, Order 3 first step W3_1 / M3). In the allocation list, if the extracted process is a process to be corrected, the start time changed by the correction instruction 12 is stored in the previous plan 14 if the extracted process is not a process to be corrected. The start times are compared, and the process with the earliest start time is selected. Next, after the selected process, "end time of previous process + transfer time between facilities used in the preceding and following processes" (in the case of the first process, start time (plan start time if not yet started)) In addition, when the selected process is a process to be corrected, it is assigned to the equipment changed by the correction instruction 12, and when the selected process is not the process to be corrected, it is assigned to the equipment registered in the master information 11. That is, the equipment to be used, the start time, and the end time are determined for the selected process. Then, as illustrated in FIG. 8, the next process after the selected process (in FIG. 8, process W1_2 / M3, which is the process subsequent to process W1_1 / M1 of order 1) is registered in the allocation list. In this way, all processes are assigned in the order of the passing process. In this way, the modification plan corresponding to each of the plurality of modification instructions stored in the modification instruction 12 (specifically, the modification plan for the modification instruction A is shown in FIG. 9, and the modification plan for the modification instruction B is shown in FIG. ) Is created (the equipment to be used, the start time, and the end time are determined for each process of all orders) and stored as the revised plan 13.

評価値算出部24は、複数の修正計画案13のそれぞれについて、工程毎に前回計画14と比較して、次順の工程が当該工程よりも前に変化している工程の数と、設備毎に前回計画14と比較して、当該設備に追加された工程の数と当該設備から削除された工程の数と、の総和を計算し、複数の修正計画案13のそれぞれに対応する評価値15として記憶するためのものである。
ここで、本実施形態において、評価値は修正計画案13が前回計画14からどれだけ乖離しているかの乖離度を示している。そして、修正計画案は、前回計画に対する次の3種類の操作で変化があったと考え、乖離度は当該3種類の操作による変化の度合いに基づいて算出する。
I.設備の中で作業する予定であった工程を同じ設備の中で開始時刻のみ変更する。
II.設備の中で作業する予定であった工程以外の工程が追加される。
III.設備の中で作業する予定であった工程を削除する。
具体的には、図11に示すような前回計画(設備M1に関してのみ例示)が有った場合に、修正指示αが上記Iの操作に該当し、修正指示βが上記IIの操作に該当し、修正指示γが上記IIIの操作に該当する。そして、全設備に関して上記3種類の操作による変化の度合いの総和を取ることにより、評価値を算出し、評価値15として記憶する。
The evaluation value calculation unit 24 compares the number of processes in which the next process is changed before the process, and the number of processes for each of the plurality of revised plans 13 in comparison with the previous plan 14 for each process. Compared with the previous plan 14, the sum of the number of processes added to the equipment and the number of processes deleted from the equipment is calculated, and an evaluation value 15 corresponding to each of the plurality of revised plan plans 13 is calculated. It is for memorizing as.
Here, in the present embodiment, the evaluation value indicates the degree of deviation of how much the revised plan 13 is deviated from the previous plan 14. The revised plan is considered to have changed in the next three types of operations with respect to the previous plan, and the divergence is calculated based on the degree of change due to the three types of operations.
I. The process that was scheduled to be performed in the facility is changed only in the start time in the same facility.
II. Processes other than those scheduled to work in the facility are added.
III. Delete the process that was scheduled to work in the facility.
Specifically, when there is a previous plan as shown in FIG. 11 (illustrated only for the facility M1), the correction instruction α corresponds to the operation I and the correction instruction β corresponds to the operation II. The correction instruction γ corresponds to the above operation III. Then, an evaluation value is calculated and stored as an evaluation value 15 by taking the sum of the degree of change due to the above three types of operations for all facilities.

ここで、I〜IIIの3種類の操作に関して変化の度合いを算出する方法について説明する。
Iの操作に関して変化の度合いは、各設備の工程毎に当該工程の開始時刻を前回計画14と修正計画案13とで比較し、次順の工程の開始時刻が当該工程よりも前に変化している工程の数をカウントすることにより求める。具体的には、図11に示す修正指示α(同じ設備の中で工程の開始時刻のみ変更)に対する修正計画案13が図12であるとすると、図12に示すように修正計画案13における工程を開始時刻が早い順に左から並べた上で、前回計画14の順序通りに工程を矢印で結んだ際に、左向き(過去方向)の矢印が出ている工程の「リンク数」を1に設定し、そうでなければ0に設定する。そして、上述した図4に示す前回計画と図9に示す修正指示Aに対する修正計画案に関する具体例において、設備M1〜M3の各設備の工程毎のリンク数は、図13に示すような結果となる。
IIの操作に関して変化の度合いは、設備毎に作業する予定である工程を前回計画14と修正計画案13とで比較し、追加されている工程の数をカウントすることにより求める。具体的には、追加された作業に対して「追加フラグ」を1に設定する。そして、上述した図4に示す前回計画と図9に示す修正指示Aに対する修正計画案に関する具体例において、設備M1〜M3の各設備の追加フラグは、図13に示すような結果となる。
IIIの操作に関して変化の度合いは、設備毎に作業する予定である工程を前回計画14と修正計画案13とで比較し、削除されている工程の数をカウントすることにより求める。具体的には、削除された作業に対して「削除フラグ」を1に設定する。そして、上述した図4に示す前回計画と図9に示す修正指示Aに対する修正計画案に関する具体例において、設備M1〜M3の各設備の削除フラグは、図13に示すような結果となる。
以上により、全設備に関して、I〜IIIの操作による変化の度合いである「リンク数」「追加フラグ」「削除フラグ」の総和を取ることにより、評価値を算出する。そして、上述した図4に示す前回計画と図9に示す修正指示Aに対する修正計画案に関する具体例である図13では、設備M1〜M3の全設備に関して、「リンク数」「追加フラグ」「削除フラグ」の総和を取ると評価値が「3」となり、評価値15に記憶される。尚、説明を省略するが、上述した図4に示す前回計画と図10に示す修正指示Bに対する修正計画案に関しても同様に評価値を計算する。
Here, a method for calculating the degree of change for the three types of operations I to III will be described.
Regarding the degree of change in the operation of I, the start time of the process is compared between the previous plan 14 and the revised plan 13 for each process of each facility, and the start time of the next process changes before the process. It is obtained by counting the number of processes. Specifically, if the modification plan 13 for the modification instruction α (changed only at the process start time in the same equipment) shown in FIG. 11 is FIG. 12, the process in the modification plan 13 as shown in FIG. Are arranged from the left in ascending order of the start time, and when the processes are connected with arrows in the order of the previous plan 14, the “number of links” for the process with an arrow pointing left (past direction) is set to 1. Otherwise, set to 0. And in the specific example regarding the previous plan shown in FIG. 4 mentioned above and the correction plan proposal with respect to the correction instruction | indication A shown in FIG. 9, the number of links for every process of each installation of equipment M1-M3 is as a result as shown in FIG. Become.
The degree of change in the operation of II is obtained by comparing the process scheduled to be performed for each facility with the previous plan 14 and the revised plan 13 and counting the number of added processes. Specifically, the “addition flag” is set to 1 for the added work. And in the specific example regarding the previous plan shown in FIG. 4 mentioned above and the correction plan proposal with respect to the correction instruction | indication A shown in FIG. 9, the addition flag of each installation of the installations M1-M3 becomes a result as shown in FIG.
The degree of change with respect to the operation of III is obtained by comparing the process scheduled to be performed for each facility with the previous plan 14 and the revised plan 13 and counting the number of deleted processes. Specifically, “delete flag” is set to 1 for the deleted work. And in the specific example regarding the correction plan proposal with respect to the last plan shown in FIG. 4 mentioned above and the correction instruction | indication A shown in FIG. 9, the deletion flag of each installation of the installations M1-M3 becomes a result as shown in FIG.
As described above, the evaluation value is calculated by taking the sum of the “number of links”, the “addition flag”, and the “deletion flag” that is the degree of change due to the operations I to III for all the facilities. And in FIG. 13 which is a specific example regarding the previous plan shown in FIG. 4 mentioned above and the correction plan proposal with respect to the correction instruction | indication A shown in FIG. 9, regarding all the facilities M1-M3, "number of links""additionflag""deletion" When the sum of the “flags” is taken, the evaluation value becomes “3” and is stored in the evaluation value 15. Although not described, evaluation values are similarly calculated for the previous plan shown in FIG. 4 and the revised plan for the revision instruction B shown in FIG.

修正計画決定部25は、評価値15が最も小さい修正計画案13を、修正計画16として選択して記憶するものである。即ち、本実施形態において、評価値算出部24において、評価値15は修正計画案13が前回計画14からどれだけ乖離しているかの乖離度を計算しているものであるから、評価値15が最も小さい修正計画案13が前回計画14から最も乖離度が小さいということがいえる。尚、評価値が最も小さい修正計画案が複数ある場合は、評価値がも小さい複数の修正計画案を修正計画16として選択するものとする。
具体的には、上述した図9に示す修正指示Aに対する修正計画案と図10に示す修正指示Bに対する修正計画案に関する評価値を比較し、評価値が小さい修正計画案を修正計画16として選択する。
The correction plan determination unit 25 selects and stores the correction plan 13 having the smallest evaluation value 15 as the correction plan 16. That is, in the present embodiment, in the evaluation value calculation unit 24, the evaluation value 15 is the degree of deviation of how much the revised plan 13 is deviated from the previous plan 14, and therefore the evaluation value 15 is It can be said that the smallest revised plan 13 has the smallest deviation from the previous plan 14. Incidentally, if the evaluation value is more than the smallest modified plan, the evaluation value is assumed to select a plurality of modified plan most small as revised plan 16.
More specifically, the evaluation plan regarding the correction plan for the correction instruction A shown in FIG. 9 and the correction plan for the correction instruction B shown in FIG. 10 are compared, and a correction plan with a small evaluation value is selected as the correction plan 16. To do.

修正計画出力部26は、記憶された修正計画16(全オーダーの各工程について決定された、使用する設備、開始時刻、終了時刻)を図示しないディスプレイ、プリンタ等の出力部に出力するためのものである。 The correction plan output unit 26 outputs the stored correction plan 16 (equipment to be used, start time, end time determined for each process of all orders) to an output unit such as a display or a printer (not shown). It is.

次に、本実施形態に係るスケジューリング方法の処理の手順について、図2に基づいて、説明する。図2は、本実施形態に係るスケジューリング方法の処理の手順について説明したフローチャートである。
尚、以下で説明する本実施形態に係るスケジューリング方法の処理は、計算機においても同様に、スケジューリングプログラムとしてCPUにより読み出して実行することができる。また、このスケジューリングプログラムは、リムーバブルな記憶媒体に記録しておくことにより、様々な計算機の記憶装置にインストールすることが可能である。
Next, the processing procedure of the scheduling method according to the present embodiment will be described with reference to FIG. FIG. 2 is a flowchart illustrating the processing procedure of the scheduling method according to the present embodiment.
Note that the processing of the scheduling method according to this embodiment described below can be similarly read and executed by the CPU as a scheduling program in a computer. Further, the scheduling program can be installed in storage devices of various computers by recording it in a removable storage medium.

図2に示すように、計算機において、受注した複数のオーダーについて、納期と、オーダーの製品を製造するために通過する工程とその通過工程の順序と、各工程で使用する設備と、各工程の作業時間と、設備間の搬送時間とを、マスタ情報として外部から登録されて記憶する。(S1:マスタ情報記憶ステップ)。尚、本ステップは、上述したスケジューリング装置1のマスタ情報記憶部21及びマスタ情報11に相当し、その詳細な説明を省略する。   As shown in FIG. 2, in a computer, for a plurality of orders received, a delivery date, a process that passes through to produce a product of the order, an order of the passing process, equipment used in each process, The work time and the transfer time between facilities are registered and stored as master information from the outside. (S1: Master information storage step). This step corresponds to the master information storage unit 21 and the master information 11 of the scheduling device 1 described above, and detailed description thereof is omitted.

そして、図示しない入力部を介して、予め記憶されている前回計画において修正を行う必要がある修正対象となる複数のオーダーの工程について、使用する設備や開始時刻を修正する複数の修正指示を入力し、複数の修正指示として記憶する(S2:修正指示入力ステップ)。尚、本ステップは、上述したスケジューリング装置1の修正指示入力部22と及び修正指示12に相当し、その詳細な説明を省略する。   And, through the input unit (not shown), input a plurality of correction instructions for correcting the equipment to be used and the start time for the processes of a plurality of orders to be corrected that need to be corrected in the previous plan stored in advance. And stored as a plurality of correction instructions (S2: correction instruction input step). This step corresponds to the correction instruction input unit 22 and the correction instruction 12 of the scheduling apparatus 1 described above, and detailed description thereof is omitted.

次に、複数の修正指示のそれぞれについてスケジュールを作成し、複数の修正指示のそれぞれに対応する修正計画案として記憶する(S3:修正計画案作成ステップ)。尚、本ステップは、上述したスケジューリング装置1の計画エンジン部(修正計画案作成手段)23及び修正計画案13に相当し、その詳細な説明を省略する。   Next, a schedule is created for each of the plurality of correction instructions, and stored as a correction plan proposal corresponding to each of the plurality of correction instructions (S3: correction plan preparation step). Note that this step corresponds to the plan engine unit (correction plan creation means) 23 and the correction plan draft 13 of the scheduling apparatus 1 described above, and detailed description thereof will be omitted.

そして、複数の修正計画案のそれぞれについて、工程毎に前回計画と比較して、次順の工程が当該工程よりも前に変化している工程の数と、設備毎に前回計画と比較して、当該設備に追加された工程の数と当該設備から削除された工程の数と、の総和を計算し、複数の修正計画案のそれぞれに対応する評価値として記憶する(S4:評価値算出ステップ)。尚、本ステップは、上述したスケジューリング装置1の評価値算出部24及び評価値15に相当し、その詳細な説明を省略する。   For each of the multiple revised plans, compare with the previous plan for each process, compare the number of processes where the next process has changed before that process, and compare with the previous plan for each facility. The sum of the number of processes added to the equipment and the number of processes deleted from the equipment is calculated and stored as an evaluation value corresponding to each of the plurality of revised plan plans (S4: evaluation value calculation step) ). Note that this step corresponds to the evaluation value calculation unit 24 and the evaluation value 15 of the scheduling device 1 described above, and a detailed description thereof will be omitted.

次に、評価値が最も小さい修正計画案を、修正計画として選択して記憶する(S5:修正計画決定ステップ)。尚、本ステップは、上述したスケジューリング装置1の修正計画決定部25及び修正計画16に相当し、その詳細な説明を省略する。   Next, the correction plan with the smallest evaluation value is selected and stored as the correction plan (S5: correction plan determination step). This step corresponds to the correction plan determination unit 25 and the correction plan 16 of the scheduling apparatus 1 described above, and detailed description thereof is omitted.

最後に、記憶された修正計画(全オーダーの各工程について決定された、使用する設備、開始時刻、終了時刻)を図示しないディスプレイ、プリンタ等の出力部に出力し(S6:修正計画出力ステップ)、スケジューリング方法の処理を終了する。尚、本ステップは、上述したスケジューリング装置1の修正計画出力部26に相当し、その詳細な説明を省略する。   Finally, the stored correction plan (equipment to be used, start time, end time determined for each process of all orders) is output to an output unit such as a display or printer (not shown) (S6: correction plan output step) Then, the scheduling method is terminated. Note that this step corresponds to the correction plan output unit 26 of the scheduling apparatus 1 described above, and a detailed description thereof will be omitted.

このように、本実施形態のスケジューリング装置及びスケジューリング方法、並びにスケジューリングプログラムによれば、前回計画に対して複数の修正指示が行われた場合に、複数の修正指示のそれぞれについて修正計画案を作成し、修正計画案のそれぞれについて前回計画と比較し、3種類の変化(設備の中で作業する予定である作業を同じ設備の中で順序のみ変更する。設備の中で作業する予定である作業以外の作業が追加される。設備の中で作業する予定であった作業を削除する。)に基づいて算出された評価値によって修正計画案のそれぞれの前回計画からの乖離度が算出される。そして、評価値が最も小さく前回計画から乖離度が少ない修正計画案が修正された計画として選択される。従って、前回計画に対して複数の修正指示が行われた場合であっても、既存の前回計画に対する変化の度合いに基づいて、前回計画を修正することができる。
As described above, according to the scheduling apparatus, the scheduling method, and the scheduling program of the present embodiment, when a plurality of correction instructions are performed on the previous plan, a correction plan draft is created for each of the plurality of correction instructions. Compared to the previous plan for each of the revised plans, there are three types of changes (the work that is scheduled to be performed in the equipment is only changed in order within the same equipment. Other than the work that is scheduled to be performed in the equipment) The degree of divergence from the previous plan of the revised plan is calculated based on the evaluation value calculated on the basis of the above. Then, the revised plan with the smallest evaluation value and the least deviation from the previous plan is selected as the revised plan. Therefore, even when a plurality of correction instructions are issued for the previous plan , the previous plan can be corrected based on the degree of change with respect to the existing previous plan.

以上、本発明の好適な実施の形態について説明したが、本発明は、前記実施の形態に限定されるものではなく、特許請求の範囲に記載した限りにおいてさまざまな変更が可能なものである。   The preferred embodiments of the present invention have been described above. However, the present invention is not limited to the above-described embodiments, and various modifications can be made as long as they are described in the claims.

例えば、上記実施形態の具体例では、修正対象となる所定の工程についての開始時刻の変更と、修正対象となる所定の工程についての設備の変更とを別々に行う複数の修正指示として入力されているが、これに限らない。即ち、修正指示が複数入力されればよく、修正対象となる所定の工程についての開始時刻の変更と、修正対象となる所定の工程についての設備の変更とを別々に行う修正指示のほか、修正対象となる所定の工程についての開始時刻の変更及び設備の変更とを同時に行う修正指示が含まれていても良い。これによって、多様な修正指示に対応しつつ、既存の前回計画に対する変化の度合いに基づいて、前回計画を修正することができる。 For example, in the specific example of the above-described embodiment, it is input as a plurality of correction instructions for separately performing a change of the start time for a predetermined process to be corrected and a change of equipment for the predetermined process to be corrected. However, it is not limited to this. In other words, it is only necessary to input a plurality of correction instructions. In addition to a correction instruction for separately performing a start time change for a predetermined process to be corrected and a change of equipment for a predetermined process to be corrected, The correction instruction | indication which performs the change of the start time about the predetermined process used as object, and the change of an installation simultaneously may be contained. Accordingly , the previous plan can be corrected based on the degree of change with respect to the existing previous plan while responding to various correction instructions.

1 スケジューリング装置
11 マスタ情報
12 修正指示
13 修正計画案
14 前回計画
15 評価値
16 修正計画
21 マスタ情報記憶部
22 修正指示入力部
23 計画エンジン部(修正計画案作成手段)
24 評価値算出部
25 修正計画決定部
S1 マスタ情報記憶ステップ
S2 修正指示入力ステップ
S3 修正計画案作成ステップ
S4 評価値算出ステップ
S5 修正計画決定ステップ
DESCRIPTION OF SYMBOLS 1 Scheduling apparatus 11 Master information 12 Correction instruction 13 Correction plan 14 Previous plan 15 Evaluation value 16 Correction plan 21 Master information storage part 22 Correction instruction input part 23 Planning engine part (correction plan draft creation means)
24 evaluation value calculation unit 25 correction plan determination unit S1 master information storage step S2 correction instruction input step S3 correction plan drafting step S4 evaluation value calculation step S5 correction plan determination step

Claims (6)

計算機の演算部により実行される処理が、
複数のオーダーについての納期、各オーダーの製品を製造するために通過する工程とその通過工程の順序、各工程で使用する設備、各工程の作業時間、設備間の搬送時間がマスタ情報として記憶されるマスタ情報記憶ステップと、
前記各オーダーの工程毎に、使用する設備と、開始時刻及び終了時刻と、が決定されて既に作成されたスケジュールを前回計画として記憶する前回計画記憶ステップと、
前記前回計画に関して、入力手段を介して複数入力された修正対象となる工程についての開始時刻または設備の変更を、複数の修正指示として記憶する修正指示記憶ステップと、
前記複数の修正指示のそれぞれについて、1台の設備で複数の工程を同時に作業することができない制約、及び、前後工程で使用される設備間には前記搬送時間が空いているという制約を考慮して、オーダー単位で通過工程順に工程を抽出し、抽出した工程が前記修正対象となる工程の場合は変更された開始時刻を、抽出した工程が前記修正対象となる工程でない場合は前記前回計画で記憶された開始時刻を比較し、開始時刻が最も早い工程を、前記修正対象となる工程の場合は変更された設備に、前記修正対象となる工程でない場合は前記マスタ情報で記憶された設備に割り付けてスケジュールを作成し、前記複数の修正指示のそれぞれに対応する複数の修正計画案として出力する修正計画案作成ステップと、
前記複数の修正計画案のそれぞれについて、工程毎に前記前回計画と比較して、次順の工程が当該工程よりも前に変化している工程の数と、設備毎に前記前回計画と比較して、当該設備に追加された工程の数と当該設備から削除された工程の数と、の総和を、前記複数の修正計画案のそれぞれに対応する評価値として計算する評価値算出ステップと、
前記評価値が最も小さい修正計画案を、修正計画として選択する修正計画決定ステップと、
を有することを特徴とするスケジューリング方法。
The processing executed by the computing unit of the computer is
The delivery date for multiple orders, the process that passes to manufacture products of each order and the order of the passing process, the equipment used in each process, the working time of each process, and the transfer time between equipment are stored as master information. Master information storage step,
For each process of the respective orders, a previous plan storing step for storing a schedule that has already been created by determining the equipment to be used, the start time and the end time, as a previous plan,
A correction instruction storage step for storing, as a plurality of correction instructions, a start time or a change in equipment for a process to be corrected, which is input a plurality of inputs via the input means, with respect to the previous plan,
For each of the plurality of correction instructions, taking into account the restriction that a plurality of processes cannot be performed simultaneously with one equipment, and the restriction that the transfer time is empty between equipment used in the preceding and following processes. If the extracted process is the process to be corrected, the changed start time is extracted, and if the extracted process is not the process to be corrected, the previous plan is extracted. Compare the stored start times, and change the process with the earliest start time to the equipment that has been changed in the case of the process to be corrected, or to the equipment stored in the master information if it is not the process to be corrected. Creating a schedule to allocate, and creating a correction plan draft to output as a plurality of correction plan drafts corresponding to each of the plurality of correction instructions;
For each of the plurality of revised plans, the number of processes in which the next process is changed before the process is compared with the previous plan for each process, and the previous plan is compared for each facility. An evaluation value calculating step for calculating a sum of the number of processes added to the equipment and the number of processes deleted from the equipment as an evaluation value corresponding to each of the plurality of revised plan plans;
A correction plan determination step of selecting a correction plan with the smallest evaluation value as a correction plan;
A scheduling method characterized by comprising:
前記修正指示は、修正対象となる工程についての開始時刻及び設備の変更を含むことを特徴とする請求項1に記載のスケジューリング方法。   The scheduling method according to claim 1, wherein the correction instruction includes a start time and a facility change for a process to be corrected. 複数のオーダーについての納期、各オーダーの製品を製造するために通過する工程とその通過工程の順序、各工程で使用する設備、各工程の作業時間、設備間の搬送時間がマスタ情報として記憶されるマスタ情報記憶ステップと、
前記各オーダーの工程毎に、使用する設備と、開始時刻及び終了時刻と、が決定されて既に作成されたスケジュールを前回計画として記憶する前回計画記憶ステップと、
前記前回計画に関して、入力手段を介して複数入力された修正対象となる工程についての開始時刻または設備の変更を、複数の修正指示として記憶する修正指示記憶ステップと、
前記複数の修正指示のそれぞれについて、1台の設備で複数の工程を同時に作業することができない制約、及び、前後工程で使用される設備間には前記搬送時間が空いているという制約を考慮して、オーダー単位で通過工程順に工程を抽出し、抽出した工程が前記修正対象となる工程の場合は変更された開始時刻を、抽出した工程が前記修正対象となる工程でない場合は前記前回計画で記憶された開始時刻を比較し、開始時刻が最も早い工程を、前記修正対象となる工程の場合は変更された設備に、前記修正対象となる工程でない場合は前記マスタ情報で記憶された設備に割り付けてスケジュールを作成し、前記複数の修正指示のそれぞれに対応する複数の修正計画案として出力する修正計画案作成ステップと、
前記複数の修正計画案のそれぞれについて、工程毎に前記前回計画と比較して、次順の工程が当該工程よりも前に変化している工程の数と、設備毎に前記前回計画と比較して、当該設備に追加された工程の数と当該設備から削除された工程の数と、の総和を、前記複数の修正計画案のそれぞれに対応する評価値として計算する評価値算出ステップと、
前記評価値が最も小さい修正計画案を、修正計画として選択する修正計画決定ステップと、
を有し、計算機において演算部により読み出して各ステップの処理を実行させることを特徴とするスケジューリングプログラム。
The delivery date for multiple orders, the process that passes to manufacture products of each order and the order of the passing process, the equipment used in each process, the working time of each process, and the transfer time between equipment are stored as master information. Master information storage step,
For each process of the respective orders, a previous plan storing step for storing a schedule that has already been created by determining the equipment to be used, the start time and the end time, as a previous plan,
A correction instruction storage step for storing, as a plurality of correction instructions, a start time or a change in equipment for a process to be corrected, which is input a plurality of inputs via the input means, with respect to the previous plan,
For each of the plurality of correction instructions, taking into account the restriction that a plurality of processes cannot be performed simultaneously with one equipment, and the restriction that the transfer time is empty between equipment used in the preceding and following processes. If the extracted process is the process to be corrected, the changed start time is extracted, and if the extracted process is not the process to be corrected, the previous plan is extracted. Compare the stored start times, and change the process with the earliest start time to the equipment that has been changed in the case of the process to be corrected, or to the equipment stored in the master information if it is not the process to be corrected. Creating a schedule to allocate, and creating a correction plan draft to output as a plurality of correction plan drafts corresponding to each of the plurality of correction instructions;
For each of the plurality of revised plans, the number of processes in which the next process is changed before the process is compared with the previous plan for each process, and the previous plan is compared for each facility. An evaluation value calculating step for calculating a sum of the number of processes added to the equipment and the number of processes deleted from the equipment as an evaluation value corresponding to each of the plurality of revised plan plans;
A correction plan determination step of selecting a correction plan with the smallest evaluation value as a correction plan;
A scheduling program that is read out by a calculation unit in a computer and causes each step to be executed.
前記修正指示は、修正対象となる工程についての開始時刻及び設備の変更を含むことを特徴とする請求項3に記載のスケジューリングプログラム。   The scheduling program according to claim 3, wherein the correction instruction includes a start time and a facility change for a process to be corrected. 複数のオーダーについての納期、各オーダーの製品を製造するために通過する工程とその通過工程の順序、各工程で使用する設備、各工程の作業時間、設備間の搬送時間がマスタ情報として記憶されるマスタ情報記憶手段と、
前記各オーダーの工程毎に、使用する設備と、開始時刻及び終了時刻と、が決定されて既に作成されたスケジュールを前回計画として記憶する前回計画記憶手段と、
前記前回計画に関して、入力手段を介して複数入力された修正対象となる工程についての開始時刻または設備の変更を、複数の修正指示として記憶する修正指示記憶手段と、
前記複数の修正指示のそれぞれについて、1台の設備で複数の工程を同時に作業することができない制約、及び、前後工程で使用される設備間には前記搬送時間が空いているという制約を考慮して、オーダー単位で通過工程順に工程を抽出し、抽出した工程が前記修正対象となる工程の場合は変更された開始時刻を、抽出した工程が前記修正対象となる工程でない場合は前記前回計画で記憶された開始時刻を比較し、開始時刻が最も早い工程を、前記修正対象となる工程の場合は変更された設備に、前記修正対象となる工程でない場合は前記マスタ情報で記憶された設備に割り付けてスケジュールを作成し、前記複数の修正指示のそれぞれに対応する複数の修正計画案として出力する修正計画案作成手段と、
前記複数の修正計画案のそれぞれについて、工程毎に前記前回計画と比較して、次順の工程が当該工程よりも前に変化している工程の数と、設備毎に前記前回計画と比較して、当該設備に追加された工程の数と当該設備から削除された工程の数と、の総和を、前記複数の修正計画案のそれぞれに対応する評価値として計算する評価値算出手段と、
前記評価値が最も小さい修正計画案を、修正計画として選択する修正計画決定手段と、
が計算機の演算部に実装されることを特徴とするスケジューリング装置。
The delivery date for multiple orders, the process that passes to manufacture products of each order and the order of the passing process, the equipment used in each process, the working time of each process, and the transfer time between equipment are stored as master information. Master information storage means,
For each process of each order, the plan to be used, the start time and the end time are determined, and the previous plan storage means for storing the schedule already created as the previous plan,
Regarding the previous plan, a correction instruction storage means for storing a start time or a change in equipment for a process to be corrected, which is input a plurality of inputs via the input means, as a plurality of correction instructions;
For each of the plurality of correction instructions, taking into account the restriction that a plurality of processes cannot be performed simultaneously with one equipment, and the restriction that the transfer time is empty between equipment used in the preceding and following processes. If the extracted process is the process to be corrected, the changed start time is extracted, and if the extracted process is not the process to be corrected, the previous plan is extracted. Compare the stored start times, and change the process with the earliest start time to the equipment that has been changed in the case of the process to be corrected, or to the equipment stored in the master information if it is not the process to be corrected. An allocation plan creating means for creating a schedule, and outputting a plurality of correction plan drafts corresponding to each of the plurality of correction instructions;
For each of the plurality of revised plans, the number of processes in which the next process is changed before the process is compared with the previous plan for each process, and the previous plan is compared for each facility. An evaluation value calculating means for calculating the sum of the number of processes added to the equipment and the number of processes deleted from the equipment as an evaluation value corresponding to each of the plurality of revised plan plans;
A correction plan determining means for selecting the correction plan with the smallest evaluation value as a correction plan;
Is mounted on a computing unit of a computer.
前記修正指示は、修正対象となる工程についての開始時刻及び設備の変更を含むことを特徴とする請求項5に記載のスケジューリング装置。   The scheduling apparatus according to claim 5, wherein the correction instruction includes a start time and a facility change for a process to be corrected.
JP2012229030A 2012-10-16 2012-10-16 Scheduling method, scheduling program, and scheduling apparatus Expired - Fee Related JP5885637B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012229030A JP5885637B2 (en) 2012-10-16 2012-10-16 Scheduling method, scheduling program, and scheduling apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012229030A JP5885637B2 (en) 2012-10-16 2012-10-16 Scheduling method, scheduling program, and scheduling apparatus

Publications (2)

Publication Number Publication Date
JP2014081778A JP2014081778A (en) 2014-05-08
JP5885637B2 true JP5885637B2 (en) 2016-03-15

Family

ID=50785922

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012229030A Expired - Fee Related JP5885637B2 (en) 2012-10-16 2012-10-16 Scheduling method, scheduling program, and scheduling apparatus

Country Status (1)

Country Link
JP (1) JP5885637B2 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6174098B2 (en) * 2015-10-28 2017-08-02 三菱電機インフォメーションシステムズ株式会社 Plan support device, supply chain management system, and plan support program
JP6593278B2 (en) * 2016-08-19 2019-10-23 Jfeスチール株式会社 Production plan creation method and production plan creation device
JP6819229B2 (en) * 2016-11-07 2021-01-27 富士通株式会社 Work organization device, work organization method and work organization program
JP6906299B2 (en) * 2016-12-08 2021-07-21 三菱重工業株式会社 Work plan creation system, work plan creation method and work plan creation program
JP2018128919A (en) * 2017-02-09 2018-08-16 三菱重工業株式会社 Work plan creation system, work plan creation method and work plan creation program
JP7031730B2 (en) 2018-03-09 2022-03-08 日本電気株式会社 Control planning device, control planning method, program
JP2022019069A (en) 2020-07-17 2022-01-27 富士フイルムビジネスイノベーション株式会社 Production planning device and program
CN112632861B (en) * 2020-10-21 2023-12-29 中冶南方工程技术有限公司 Method for making tilting plan of eccentric bottom tapping of electric arc furnace

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5657189B2 (en) * 2005-11-09 2015-01-21 株式会社神戸製鋼所 Schedule correction apparatus, schedule correction program, and schedule correction method

Also Published As

Publication number Publication date
JP2014081778A (en) 2014-05-08

Similar Documents

Publication Publication Date Title
JP5885637B2 (en) Scheduling method, scheduling program, and scheduling apparatus
Lu et al. Integrated production and preventive maintenance scheduling for a single machine with failure uncertainty
Gyulai et al. Robust production planning and control for multi-stage systems with flexible final assembly lines
JP5643502B2 (en) How to create production schedules for multiple factories
Oztemel et al. Bees Algorithm for multi-mode, resource-constrained project scheduling in molding industry
JP2007157124A (en) Schedule correcting device, schedule correcting program and schedule correcting method
JP5134601B2 (en) Production schedule creation device
US20160026959A1 (en) Visual Workflow Display and Management
WO2013154164A1 (en) Scheduling device, scheduling method, and computer program
JP6622592B2 (en) Production planning support system and support method
Hu et al. A simulation-based method for effective workface planning of industrial construction projects
JP4852496B2 (en) Project planning method, project planning program, and project planning system
JP5033555B2 (en) Production schedule creation method and system
Valledor et al. Modelling and solving rescheduling problems in dynamic permutation flow shop environments
JP5653333B2 (en) Schedule creation method, schedule creation program, and schedule creation device
JP4746334B2 (en) Production planning method, apparatus, and computer program for manufacturing process
JP6382766B2 (en) Production plan creation method, production plan creation program, and production plan creation device
JP2011221923A (en) Schedule creation method and schedule creation program and schedule creation device
JP4319026B2 (en) Schedule creation method, schedule creation system, and program
JP6005535B2 (en) Production plan creation device, production plan creation method, and production plan creation program
JP7147243B2 (en) Scheduling device, method and program
JP6063764B2 (en) Product development management program and product development management apparatus using the same
JP5857580B2 (en) Work information management apparatus and program
JP6016657B2 (en) Data processing apparatus and program
JP6713963B2 (en) Method and apparatus for generating initial inventory information for supply chain operation simulation

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20140901

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150716

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150825

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20151009

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20151009

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20151009

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160209

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20160209

R150 Certificate of patent or registration of utility model

Ref document number: 5885637

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees