CN107585668A - Auxiliary shaft, combined shaft tail rope change construction technology - Google Patents

Auxiliary shaft, combined shaft tail rope change construction technology Download PDF

Info

Publication number
CN107585668A
CN107585668A CN201710792147.2A CN201710792147A CN107585668A CN 107585668 A CN107585668 A CN 107585668A CN 201710792147 A CN201710792147 A CN 201710792147A CN 107585668 A CN107585668 A CN 107585668A
Authority
CN
China
Prior art keywords
tail rope
rope
skip
new
buckets
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710792147.2A
Other languages
Chinese (zh)
Inventor
丁枫
肖燕前
王先军
林勇
王运军
陈诚
许飞
黄辉
苏文矿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huainan Mining Group Co Ltd
Original Assignee
Huainan Mining Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huainan Mining Group Co Ltd filed Critical Huainan Mining Group Co Ltd
Priority to CN201710792147.2A priority Critical patent/CN107585668A/en
Publication of CN107585668A publication Critical patent/CN107585668A/en
Pending legal-status Critical Current

Links

Abstract

The invention belongs to coal mine shaft lining repair and maintenance technical field, construction technology is changed more particularly to a kind of auxiliary shaft, combined shaft tail rope, the mode that the present invention is newly restricted using old rope drawing is laid to new tail rope, new changes rope method compared with traditional method of replacing rope, has safe, efficient, fast construction characteristic.It is embodied in following several respects:Fully solves the problems, such as tail rope magic flower;Do not influenceed by simple lay car, multiple twin car pit shaft, rope is turned over without using slow heave in row;It is simple to operate, personnel's less investment;The whole naked rope in laid processes of newly restricting is run, and new rope preserves from;Shorten and take the pit shaft time, the time has been won for shaft production.

Description

Auxiliary shaft, combined shaft tail rope change construction technology
Technical field
The invention belongs to coal mine shaft lining repair and maintenance technical field, and in particular to a kind of auxiliary shaft, combined shaft tail rope are changed and applied Work technique.
Background technology
During mine safety production, mine hoisting system carries the upper and lower thing of coal gug, well that underground mining goes out Money beats the upper and lower of fortune and workmen, is the throat of shaft production.Balance tail rope by long-term high intensity because being used, rust Erosion and abrasion, every two years or 1 year need to change to it, and full ore deposit stops production during replacing, the length and security pair of engineering time Shaft production is produced and had a strong impact on.
Conventional tail rope change work progress in, first by a container (hereinafter referred to as A containers) be parked in shaft bottom ingate with Upper about 30m, then cut-offs old tail rope at tail rope pin, then above carries A containers and is carried to place is cut-off to ingate, is manually dragged Go out pit shaft to start to tell at rope to A containers arrival ingate, remove the old rope suspension of A containers, new tail rope suspension is installed, while B is held Device side tail rope extracts pit shaft, starts the new rope of band, tells old rope.Wait to tell rope to complete, start to turn over rope, using another winch by remaining tail Rope is put into pit shaft (when not being multiple twin car pit shaft, it is necessary to arranging that a stable car enters to be about to remaining tail rope and is put into pit shaft) utilization The slow heave in row of well head turns over rope (process is cumbersome, not easy to operate), and new tail rope suspension work is done in completion.Using traditional tail rope Replacement procedure Construction at least needs 24 hours, and following several big drawbacks be present:1., turn over rope during, the easy magic flower of tail rope, when doing tail rope suspension Do not pay attention to slightly being easy for causing to do over again, increase workload.2., in simple lay car shaft construction, it is necessary to steady in ground configuration one Car, which coordinates, turns over rope.Stable car puts rope in pit shaft, rope closing takes the duration.3., using winch (stable car) coordinate it is slow twist turn over rope during, The deformation damage of tail rope, influences service life;4., working procedure it is complicated, prepare and construction input be big, take uphole time length, Potential safety hazard point is more in construction.
How safe and efficient could complete balance tail rope and change construction, improve construction safety coefficient, shorten work of constructing Phase, avoid putting into injury, the reduction construction newly restricted, be an extremely urgent task.
The content of the invention
It is an object of the invention to provide a kind of auxiliary shaft that can improve vertical tail rope replacing efficiency, combined shaft tail rope to change and apply Work technique.
To achieve the above object, the invention provides following technical scheme:A kind of auxiliary shaft, combined shaft tail rope change construction work Skill, comprise the following steps:
Step 1:Equipment arrangement, new tail rope disk is arranged in the parking lot tunnel of shaft of vertical well bottom wherein side and puts rope Mechanism, and be that the horizontal conductor rope pipe concordant with Fang Sheng mechanisms is set in the liftway of A skip buckets in skip bucket corresponding to the side tunnel;
Step 2:By one of skip bucket be the A skip hoistings to vertical shaft head, be to be dropped down onto under B skip buckets by another skip bucket Vertical shaft bottom;
Step 3:New tail rope termination on the new tail rope disk of artificial traction, pass through the Fang Sheng mechanisms and conductor rope pipe until At old tail rope below A skip buckets, and with board by together with the fixing of new tail rope termination and old tail rope, then by the fixing position The old tail rope of side blocks;
Step 4:B skip buckets are lifted, until new tail rope termination reaches and the parking lot tunnel ingate of B skip buckets place side is contour Position;At the same time, A skip buckets decline, where the old tail rope below A skip buckets is recycled into A skip buckets in the parking lot tunnel of side;
Step 5:New tail rope termination is separated with old tail rope, and new tail rope termination is fixed on B skip buckets using pulling device On the stock of liftway;
Step 6:B skip buckets are transferred up to concordant with the parking lot tunnel of the side, while the old tail rope below B skip buckets is recycled to In the side parking lot tunnel, and the old suspension in B skip buckets bottom is removed, new suspension is installed, then new tail rope termination and new suspension are connected.
Step 7:B skip buckets are lifted, new tail rope is put in Fang Sheng mechanisms, while the old tail rope of A skip buckets bottom is recycled into parking lot lane In road, until A skip buckets drop to concordant with the parking lot tunnel of the side, the old suspension in A skip buckets bottom is removed, new suspension is installed, most New tail rope is blocked from Fang Sheng mechanisms and connected in the new suspension of A skip buckets bottom afterwards, tail rope more changes jobs completion.
Preferably, the Fang Sheng mechanisms described in step 1 include a wooden handcart, and telpher and brake are along tail rope on wooden handcart Conveying direction is sequentially arranged;The wooden handcart is fixed on the well head stock of ingate, and the brake includes passing through for new tail rope Chute, the notch of chute sets up, and is provided with flashboard above the notch of chute, the flashboard and a depression bar are affixed, depression bar One end be hinged with base, the other end is provided with handle.
Preferably, the rail in side parking lot tunnel where the position where falling behind in the step 2 under B skip buckets is slightly above B skip buckets Face.
Preferably, in the step 6, before the B skip buckets of lower section, first by below the A skip buckets being recycled in the tunnel of parking lot Old tail rope blocks.
Preferably, in the step 5, new tail rope termination is hung on the stock of B skip bucket liftways using chain block.
The technical effects of the invention are that:New rope method of changing has safe efficient, quick compared with traditional method of replacing rope Construction characteristic.It is embodied in following several respects:Fully solves the problems, such as tail rope magic flower;Not by simple lay car, multiple twin car pit shaft shadow Ring, rope is turned over without using slow heave in row;It is simple to operate, personnel's less investment;The whole naked rope in laid processes of newly restricting is run, newly Rope preserves from;Shorten and take the pit shaft time, the time has been won for shaft production.
Brief description of the drawings
Fig. 1 is the Fang Sheng mechanisms top view of the present invention;
Fig. 2 is the schematic diagram of the brake of the present invention;
Fig. 3 is the pit shaft longitudinal sectional drawing under the construction technology step 2 and step 3 state of the present invention;
Fig. 4 is the lens barrel longitudinal sectional drawing under construction technology step 4 state of the present invention.
Embodiment
The present invention is described in detail below in conjunction with accompanying drawing.
As Figure 1-4, a kind of auxiliary shaft, combined shaft tail rope change construction technology, comprise the following steps:
Step 1:Equipment arrangement, arranges new tail rope disk 10 and puts in the parking lot tunnel of shaft of vertical well bottom wherein side Restrict mechanism 11, and is that the water concordant with Fang Sheng mechanisms 11 is set in the liftway of A skip buckets 21 in skip bucket corresponding to the side tunnel Flat conductor rope pipe 12;
Step 2:It is that the A skip buckets 21 are promoted to vertical shaft head by one of skip bucket, is under B skip buckets 22 by another skip bucket Drop down onto vertical shaft bottom;
Step 3:The termination of new tail rope 32 on the new tail rope disk 10 of artificial traction, passes through the Fang Sheng mechanisms 11 and conductor rope Pipe 12 is until at the old tail rope 31 of the lower section of A skip buckets 21, and together with board 13, the new termination of tail rope 32 fixed with old tail rope 31, Then the old tail rope 31 above the fixing position is blocked;
Step 4:B skip buckets 22 are lifted, until the new termination of tail rope 32 reaches the parking lot tunnel ingate with the place side of B skip buckets 22 Contour position;At the same time, A skip buckets 21 decline, and the old tail rope 31 of the lower section of A skip buckets 21 is recycled into the place side of A skip buckets 21 In the tunnel of parking lot;
Step 5:The new termination of tail rope 32 is separated with old tail rope 31, and is fixed on the new termination of tail rope 32 using pulling device On the stock of the liftway of B skip buckets 22;
Step 6:B skip buckets 22 are transferred until concordant with the parking lot tunnel of the side, while by the old tail rope 31 of the lower section of B skip buckets 22 Be recycled in the side parking lot tunnel, and the old suspension in the bottom of B skip buckets 22 removed, new suspension is installed, then by the new termination of tail rope 32 with New suspension connection.
Step 7:B skip buckets 22 are lifted, new tail rope 32 is put in Fang Sheng mechanisms 11, while the old tail rope 31 of the bottom of A skip buckets 21 is returned Receive in the tunnel of parking lot, until A skip buckets 21 drop to concordant with the parking lot tunnel of the side, the old suspension in the bottom of A skip buckets 21 removed, The new suspension of installation, new tail rope 32 finally blocked from Fang Sheng mechanisms 11 and connected in the new suspension of the bottom of A skip buckets 21, Tail rope more changes jobs completion.
Preferably, the Fang Sheng mechanisms 11 described in step 1 include a wooden handcart 111, on wooden handcart 111 telpher 112 with Brake 113 is sequentially arranged along tail rope conveying direction;The wooden handcart 111 is fixed on the well head stock of ingate, the braking Device 113 includes the chute 2 passed through for new tail rope 32, and the notch of chute 2 is set up, and flashboard 3 is provided with above the notch of chute 2, The flashboard 3 and a depression bar 4 are affixed, and one end of depression bar 4 is be hinged with base 1, and the other end is provided with handle 5.B in the step 2 22 times positions for falling behind place of skip bucket are slightly above the rail level in the place side parking lot tunnel of B skip buckets 22.In the step 6, lower section B skip buckets Before 22, first the old tail rope 31 for the lower section of A skip buckets 21 being recycled in the tunnel of parking lot is blocked.In the step 5, new tail rope 32 Hung using chain block on the stock of the liftway of B skip buckets 22 termination.
New rope method of changing has safe, efficient, fast construction characteristic compared with traditional method of replacing rope.It is embodied in Following several respects:Fully solves the problems, such as tail rope magic flower;Do not influenceed by simple lay car, multiple twin car pit shaft, without the slow heave in row of utilization Turn over rope;It is simple to operate, personnel's less investment;The whole naked rope in laid processes of newly restricting is run, and new rope preserves from;Shorten occupancy The pit shaft time, the time is won for shaft production.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement made within refreshing and principle etc., should be included in the scope of the protection.

Claims (5)

1. a kind of auxiliary shaft, combined shaft tail rope change construction technology, it is characterised in that comprise the following steps:
Step 1:Equipment arrangement, new tail rope disk (10) is arranged in the parking lot tunnel of shaft of vertical well bottom wherein side and puts rope Mechanism (11), and be that setting is concordant with Fang Sheng mechanisms (11) in the liftway of A skip buckets (21) in skip bucket corresponding to the side tunnel Horizontal conductor rope pipe (12);
Step 2:It is that the A skip buckets (21) are promoted to vertical shaft head by one of skip bucket, is under B skip buckets (22) by another skip bucket Drop down onto vertical shaft bottom;
Step 3:New tail rope (32) termination on the new tail rope disk (10) of artificial traction, pass through the Fang Sheng mechanisms (11) and lead Rope pipe (12) is until old tail rope (31) place below A skip buckets (21), and with board (13) by new tail rope (32) termination and old tail rope (31) fix together, then block the old tail rope (31) above the fixing position;
Step 4:B skip buckets (22) are lifted, until new tail rope (32) termination reaches the parking lot tunnel head of the horse with side where B skip buckets (22) The contour position of door;At the same time, A skip buckets (21) decline, and the old tail rope (31) below A skip buckets (21) is recycled into A skip buckets (21) where in the parking lot tunnel of side;
Step 5:New tail rope (32) termination is separated with old tail rope (31), and fixed new tail rope (32) termination using pulling device On the stock of B skip buckets (22) liftway;
Step 6:B skip buckets (22) are transferred until concordant with the parking lot tunnel of the side, while by the old tail rope below B skip buckets (22) (31) it is recycled in the side parking lot tunnel, and the old suspension in B skip buckets (22) bottom is removed, new suspension is installed, then by new tail rope (32) termination connects with new suspension.
Step 7:B skip buckets (22) are lifted, new tail rope (32) is put in Fang Sheng mechanisms (11), while by the old tail rope of A skip buckets (21) bottom (31) be recycled in the tunnel of parking lot, until A skip buckets (21) drop to it is concordant with the parking lot tunnel of the side, by A skip buckets (21) bottom Old suspension is removed, and installs new suspension, finally new tail rope (32) is blocked and connected in A skip buckets from Fang Sheng mechanisms (11) (21) in the new suspension of bottom, tail rope more changes jobs completion.
2. auxiliary shaft according to claim 1, combined shaft tail rope change construction technology, it is characterised in that:Described in step 1 Fang Sheng mechanisms (11) include a wooden handcart (111), and telpher (112) conveys with brake (113) along tail rope on wooden handcart (111) Direction is sequentially arranged;The wooden handcart (111) is fixed on the well head stock of ingate, and the brake (113) includes supplying new tail The chute (2) that rope (32) passes through, the notch of chute (2) are set up, and flashboard (3), the lock are provided with above the notch of chute (2) Plate (3) and a depression bar (4) are affixed, and one end of depression bar (4) is be hinged with base (1), and the other end is provided with handle (5).
3. auxiliary shaft according to claim 1, combined shaft tail rope change construction technology, it is characterised in that:B in the step 2 The rail level in side parking lot tunnel where position where falling behind under skip bucket (22) is slightly above B skip buckets (22).
4. auxiliary shaft according to claim 1, combined shaft tail rope change construction technology, it is characterised in that:In the step 6, Before lower section B skip buckets (22), first the old tail rope (31) below the A skip buckets (21) being recycled in the tunnel of parking lot is blocked.
5. auxiliary shaft according to claim 1, combined shaft tail rope change construction technology, it is characterised in that:In the step 5, Hung using chain block on the stock of B skip buckets (22) liftway new tail rope (32) termination.
CN201710792147.2A 2017-09-05 2017-09-05 Auxiliary shaft, combined shaft tail rope change construction technology Pending CN107585668A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710792147.2A CN107585668A (en) 2017-09-05 2017-09-05 Auxiliary shaft, combined shaft tail rope change construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710792147.2A CN107585668A (en) 2017-09-05 2017-09-05 Auxiliary shaft, combined shaft tail rope change construction technology

Publications (1)

Publication Number Publication Date
CN107585668A true CN107585668A (en) 2018-01-16

Family

ID=61050497

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710792147.2A Pending CN107585668A (en) 2017-09-05 2017-09-05 Auxiliary shaft, combined shaft tail rope change construction technology

Country Status (1)

Country Link
CN (1) CN107585668A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108394800A (en) * 2018-03-28 2018-08-14 徐州九益科技有限公司 Vertical shaft hoist tail rope Replacement procedure
CN109335922A (en) * 2018-08-29 2019-02-15 国家能源投资集团有限责任公司 A kind of vertical transportation system and transportation resources
CN111792500A (en) * 2020-07-27 2020-10-20 山东黄金矿业(玲珑)有限公司 Method for replacing tail rope of floor type friction hoist
CN112694001A (en) * 2020-12-09 2021-04-23 徐州市三森威尔矿山科技有限公司 Method for replacing flat tail rope of mine hoisting system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2109377U (en) * 1991-04-09 1992-07-08 扬州市王庄煤矿 Frictional rope releasing device
CN1597491A (en) * 2004-09-27 2005-03-23 山西潞安矿业(集团)有限责任公司常村煤矿 Fast rope changing device of floor type multirope friction elerator
CN101798045A (en) * 2010-04-12 2010-08-11 山东煤安矿山提升设备安装有限公司 Fast exchanging process for tail rope
RU2409512C1 (en) * 2009-06-04 2011-01-20 Федеральное агентство по образованию Государственное образовательное учреждение высшего профессионального образования "Норильский индустриальный институт" Method of installing and replacing equalising ropes of lifting installations
CN105460759A (en) * 2016-01-20 2016-04-06 枣庄矿业(集团)有限责任公司蒋庄煤矿 Method for replacing tail rope of main well winch

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2109377U (en) * 1991-04-09 1992-07-08 扬州市王庄煤矿 Frictional rope releasing device
CN1597491A (en) * 2004-09-27 2005-03-23 山西潞安矿业(集团)有限责任公司常村煤矿 Fast rope changing device of floor type multirope friction elerator
RU2409512C1 (en) * 2009-06-04 2011-01-20 Федеральное агентство по образованию Государственное образовательное учреждение высшего профессионального образования "Норильский индустриальный институт" Method of installing and replacing equalising ropes of lifting installations
CN101798045A (en) * 2010-04-12 2010-08-11 山东煤安矿山提升设备安装有限公司 Fast exchanging process for tail rope
CN105460759A (en) * 2016-01-20 2016-04-06 枣庄矿业(集团)有限责任公司蒋庄煤矿 Method for replacing tail rope of main well winch

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张雷等: "一种快速更换煤矿立井提升机平衡扁尾绳的工艺", 《科技风》 *
王继承著: "《煤矿调度员工作指南》", 30 June 2007, 中国矿业大学出版社 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108394800A (en) * 2018-03-28 2018-08-14 徐州九益科技有限公司 Vertical shaft hoist tail rope Replacement procedure
CN109335922A (en) * 2018-08-29 2019-02-15 国家能源投资集团有限责任公司 A kind of vertical transportation system and transportation resources
CN111792500A (en) * 2020-07-27 2020-10-20 山东黄金矿业(玲珑)有限公司 Method for replacing tail rope of floor type friction hoist
CN111792500B (en) * 2020-07-27 2022-02-22 山东黄金矿业(玲珑)有限公司 Method for replacing tail rope of floor type friction hoist
CN112694001A (en) * 2020-12-09 2021-04-23 徐州市三森威尔矿山科技有限公司 Method for replacing flat tail rope of mine hoisting system
CN112694001B (en) * 2020-12-09 2023-01-06 徐州市三森威尔矿山科技有限公司 Method for replacing flat tail rope of mine hoisting system

Similar Documents

Publication Publication Date Title
CN107585668A (en) Auxiliary shaft, combined shaft tail rope change construction technology
CN204251168U (en) Multi-rope friction hoist head rope changes system without stable car
CN104787652B (en) Friction type winder tail rope replacing options
CN101845958A (en) Fully mechanized coal face bracket withdrawing method and withdrawing bracket traction spring exerciser
CN105460759B (en) A kind of method that main shaft winch tail rope is changed
CN107355248A (en) A kind of fully mechanized coal face fully-mechanized mining equipment method for rapidly mounting
CN101934915A (en) Method for replacing rubber belt by long-distance steel cord rubber belt conveyor
CN108910668B (en) Method for quickly replacing vertical shaft lifting rope and lifting container in same cycle
CN109113745A (en) A method of go down the hill to construct using fully-mechanized digging machine progress high inclination-angle big cross section and cuts eye
CN103964285B (en) A kind of many rope floor types change tower interior shaft elevator system non-stop production reformation method
CN105649672B (en) The integral moving method of elevating conveyor, leather belt head during the small removal of home of high working face
CN103255767B (en) Faceplate sliding formwork with traveling device
CN106246187A (en) Multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility
CN104528506B (en) Mine hoist and unhooking test method thereof
CN203685233U (en) Loading device of coal mine fully-mechanized mining equipment
CN107060474A (en) A kind of sleeve-type chimney people goods shunting vertical transferring apparatus and construction method
CN109607384A (en) The turn-over method of super-large-diameter shield machine knife disk
CN205704131U (en) A kind of electric power overhaul tool car
CN107191200A (en) A kind of turn rock gangway speedy drivage material and Gunning material carrying method
CN204490290U (en) A kind of mine hoist
CN203129148U (en) Panel slide mold with walking devices
CN106939536A (en) A kind of coal mine inclined shaft assembled is laid a railway track construction method
CN107381396A (en) The quick recovery process of mine endless rope winch
CN206008942U (en) A kind of mill of magnetic iron ore underground mill selects system
CN209583477U (en) A kind of safe and simple car hauler rope aligning device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180116

RJ01 Rejection of invention patent application after publication