CN107563635A - The long-range audit system of distribution line engineering construction quality and method - Google Patents

The long-range audit system of distribution line engineering construction quality and method Download PDF

Info

Publication number
CN107563635A
CN107563635A CN201710758559.4A CN201710758559A CN107563635A CN 107563635 A CN107563635 A CN 107563635A CN 201710758559 A CN201710758559 A CN 201710758559A CN 107563635 A CN107563635 A CN 107563635A
Authority
CN
China
Prior art keywords
camera device
master station
mobile terminal
check
long
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710758559.4A
Other languages
Chinese (zh)
Inventor
张欣强
邱进煊
廖利兴
杜敏敏
贺鹏
李佳进
张永鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Yixinhai Information Technology Co Ltd
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Longyan Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
Fujian Yixinhai Information Technology Co Ltd
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Longyan Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Yixinhai Information Technology Co Ltd, State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd, Longyan Power Supply Co of State Grid Fujian Electric Power Co Ltd filed Critical Fujian Yixinhai Information Technology Co Ltd
Priority to CN201710758559.4A priority Critical patent/CN107563635A/en
Publication of CN107563635A publication Critical patent/CN107563635A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of long-range audit system of distribution line engineering construction quality and method, the audit system includes checking master station, display device, mobile base station, server, mobile terminal, first camera device and the second camera device, the image data of job site is obtained by the first camera device and the second camera device, pass through the measurement data at the APP modules input scene of mobile terminal, the image data and measurement data, which are uploaded to, checks that master station stores, processing, generation report, show and supply remotely to pacify matter person and check, this checks that master station can send order to notify scene peace matter person to be supervised engineering rectification to mobile terminal.The audit system is simple, conveniently, it is easy-to-use;Its real-time, promptness are strong, realize that the overall process of construction process is controlled, strengthen the supervision of engineering construction.

Description

The long-range audit system of distribution line engineering construction quality and method
Technical field
The present invention relates to a kind of long-range audit system of distribution line engineering construction quality and method.
Background technology
In recent years, country accelerates power infrastructures construction, and Guo Wang companies also increase construction and the transformation dynamics of power distribution network. 2016, just there were all kinds of engineerings 108 in company, total investment up to more than 8,700 ten thousand yuan, wherein, distribution transformation and overhaul just have 79 , invest 36,000,000 yuan.Because distribution engineering point is more, wide, task weight, power transmission are anxious, construction quality exist more management and control less than The phenomenon of position, causing to break down in work progress or after putting into operation influences power network normal operation, the serious accident that even results in Occur, entangling its reason mainly has:
First, design strength is weak, designer's professional standards are poor, and projected depth is not in place, and design is not rigorous, and design becomes More not in time etc..The Chevron Research Company (CRC) being largely affiliated to, designer is few, and designer lacks practical experience, the design item of undertaking Mesh is again more, in order to make a dash for task, is often less than the design prospecting that depth is carried out at scene, simply applies mechanically allusion quotation and set drawing, when causing construction Material is inapplicable, design alteration is more, and not in time, design mistake and leak are more for design alteration and offer design drawing and data Deng.
Second, construction team's quality mind is poor, progress is blindly pursued, construction team only does by rule of thumb, and it is new to be unfamiliar with new technology Technique, construction lacks quality surveillance and management and control, phenomenon of using inferior materials and turning out substandard goods are serious.
Third, management weak, site supervision is not in place, and supervisor's responsibility consciousness is not strong, and site supervision is stayed in shape Formula.
Fourth, to manage on behalf of another phenomenon serious to wrap for engineering, quality dynamics of checking in job site is inadequate, check and accept it is not in place, check and accept stay in Form, defect Rectification of hidden dangers not in time, check and accept the length that delays, and engineering band defect puts into operation.
The content of the invention
The invention provides a kind of long-range audit system of distribution line engineering construction quality and method, background skill is which overcomed The deficiencies in the prior art described in art.
The technical solution adopted for the present invention to solve the technical problems is:
The long-range audit system of distribution line engineering construction quality, it includes checking master station, display device, mobile base station, clothes Business device, mobile terminal, the first camera device and the second camera device, second camera device are communicated with mobile terminal by WIFI Connection, the mobile terminal and the first camera device are all communicatively connected to mobile base station, and the mobile base station is communicatively connected to server, The server checks that master station communicates to connect and is located in same LAN with this, the mobile base station and the server and checks master station Set up defences between the LAN of place wall with flues, the display device and check that master station communicates to connect, APP modules are installed on the mobile terminal;
The image data of job site is obtained by first camera device and the second camera device, passes through mobile terminal The measurement data at APP modules input scene, the image data and measurement data, which are uploaded to, checks master station's storage, processing, generation report Accuse, show and checked for long-range peace matter person, this checks that master station can send order to notify scene peace matter person to work to mobile terminal Journey is supervised rectification.
Among one embodiment:Between first camera device and mobile base station, between mobile terminal and mobile base station all Connected by 4G network services.
Among one embodiment:The mobile terminal includes any of mobile phone, tablet personal computer or notebook computer.
Among one embodiment:First camera device is portable cradle head camera, and second camera device is Camera.
The long-range auditing method of distribution line engineering construction quality, the auditing method comprise the following steps:
Step 1, by checking that master station creates engineering project;
Step 2, check that master station imports work ticket, using work ticket to check unit;
Step 3, the image data of job site is gathered by camera device, or by being mounted with the mobile end of APP modules End input field measurement data, the image data and measurement data send to check master station stored, handle, generate report, Show and supply remotely to pacify matter person and check;
Step 4, order is sent to notify scene peace matter person to work to mobile terminal from checking master station not if if checking Journey is supervised rectification, and return to step 3 uploading pictures data or measurement data again;If check by the way that the work ticket is complete Into;
Step 5, judge whether the engineering project checks completion, terminate this if completing and check project, returned if not completing Return step 2.
Compared with background technology, it has the following advantages that the technical program:
1st, audit system of the present invention it is simple, conveniently, it is easy-to-use;Its real-time, promptness are to realizing engineering construction The overall process of journey is controlled, and strengthens the supervision of engineering construction.
2nd, standardization, the standardization application that Phase of Electric Power Projects is checked are promoted.
3rd, the operating efficiency checked is improved.
Brief description of the drawings
The invention will be further described with reference to the accompanying drawings and examples.
Fig. 1 is the system block diagram of the audit system described in the present embodiment.
Fig. 2 is the step flow chart of the auditing method described in the present embodiment.
Embodiment
Fig. 1 is refer to, the long-range audit system of distribution line engineering construction quality, it includes checking master station 10, mobile base station 20th, server 30, mobile terminal 40, the second camera device 50, the first camera device 60 and display device 70, this second shooting Device 50 is communicated to connect with mobile terminal 40 by WIFI, and the camera device 60 of mobile terminal 40 and first is all communicatively connected to shifting Dynamic base station 20, the mobile base station 20 are communicatively connected to server 30, and the server 30 checks the communication connection of master station 10 and position with this In in same LAN, the mobile base station 20 and the server 30 and wall with flues 80 of setting up defences between the place LAN of master station 10 is checked, The display device 70 installs APP modules with checking that master station 10 communicates to connect on the mobile terminal 40;
The image data of job site is obtained by the camera device 50 of the first camera device 60 and second, by mobile whole The measurement data at the APP modules input scene at end 40, the image data and measurement data are uploaded to and check that master station 10 stores, located Reason, generation report, show and checked for long-range peace matter person, it is existing to notify that this checks that master station 10 can send order to mobile terminal 40 Peace matter person is supervised engineering rectification, and this checks that master station 10 is controllable and to transfer the first camera device 60 required to obtain Job site picture.
All pass through 4G between first camera device 60 and mobile base station 20, between mobile terminal 40 and mobile base station 20 Network service connects.
The mobile terminal 40 includes any of mobile phone, tablet personal computer or notebook computer.
Described display device 70 can use the LED display of large-size.
First camera device is portable cradle head camera, and second camera device is camera.
Fig. 2, the long-range auditing method of distribution line engineering construction quality are refer to, the auditing method can pass through above-mentioned distribution The long-range audit system of line project construction quality realizes that the auditing method comprises the following steps:
Step 1, by checking that master station creates engineering project;
Step 2, check that master station imports work ticket, using work ticket to check unit;
Step 3, the picture of camera device (camera device includes cradle head camera and camera) collection job site is passed through Data, or field measurement data is inputted by being mounted with the mobile terminal of APP modules, the image data and measurement data send to Check that master station is stored, handled, generates report, shown and checked for long-range peace matter person;
Step 4, order is sent to notify scene peace matter person to work to mobile terminal from checking master station not if if checking Journey is supervised rectification, and return to step 3 uploading pictures data or measurement data again;If check by the way that the work ticket is complete Into;
Step 5, judge whether the engineering project checks completion, terminate this if completing and check project, returned if not completing Return step 2.
The information of engineering project mainly includes planning item title, (10kV and 0.4kV shaft towers are bright for project construction designing material Thin table, service conductor detail list, scissors crossing detail list, main equipment material, dismounting equipment and materials, recycling equipment and materials etc.), ERP outbound lists etc..During the checking of one engineering project, work ticket is gradually outputed and is articulated in project with engineering progress, Work ticket includes the numbering and task of construction shaft tower, and long-range peace matter person enters according to the code requirement and the standard of checking of work ticket Row quality is checked.Scene peace matter personnel can be by the APP modules or the second camera device of mobile terminal, according to construction task standard Check diagram and check content, the construction technology involved by work ticket and equipment, material installation situation are taken pictures, simultaneously will Related measurement, test data are completed to upload to check master station after inserting APP modules, and scene peace matter person is according to checking that master station retracts Unqualified quality information, supervise construction team to complete rectification, and take pictures again, uploaded to after measurement data and check that master station checks again Core, pass through until checking.
The long-range audit system of distribution line engineering construction quality of the present invention and method, using " internet+" technology, Computer information technology, the mobile 4G communication technologys, successfully by engineering site installation technology and measurement, test data it is real-time on Surveillance center is passed to, cooperates with scene peace matter person to complete checking for construction quality by remotely pacifying matter person, constructs complete engineering construction Quality real-time oversight management and control system, high in technological content, technological precedence.Long-range peace matter person only need to login audit system with browser, All engineering construction qualities can be checked with information is browsed and engineering construction quality is remotely checked.Scene peace matter person Engineering construction installation situation can be uploaded in real time using the mobile phone equipped with APP modules and check master station, man-machine interface is simply straight See, each task has standard quality inspection diagram and required quality inspection project, and general staff is easy to operate and uses.System passes through 4G Network, transmission speed is fast, can be in real time by 1080P high-definition images information transfer to Surveillance center.Distribution line construction quality is long-range Check served as theme with project, using work ticket as pipe unit, to last work since distribution line first opens work ticket Ticket, ticket ticket complete construction quality and check, rectify and improve, and really realize the overall process management and control of engineering construction quality.Distribution line construction matter Amount remotely checks it is to be set to standard with state's net distribution allusion quotation, checks and accepts and blocks according to distribution line engineering specification, according to standard construction technology It is required that formulate standard quality check storehouse it will greatly promote modular design, standard construction etc. application.It is complete in same day construction task Into while, you can complete the examination and rectification of same day task, accomplish Phase of Electric Power Projects " San Tong method " --- while construct, together When check and accept rectify and improve simultaneously, realize Practical Completion, visa and check and accept complete, rectification complete so that engineering complete can zero-fault throw Production operation is possibly realized, and is avoided putting into operation because the acceptance of work time is long, rectifies and improves the delay engineering power transmission such as not in place, is also saved a large amount of Check and accept the manpower and materials of link.
It is described above, only present pre-ferred embodiments, therefore the scope that the present invention is implemented can not be limited according to this, i.e., according to The equivalent changes and modifications that the scope of the claims of the present invention and description are made, all should still it belong in the range of the present invention covers.

Claims (5)

1. the long-range audit system of distribution line engineering construction quality, it is characterised in that:Including checking master station, display device, movement Base station, server, mobile terminal, the first camera device and the second camera device, second camera device pass through with mobile terminal WIFI is communicated to connect, and the mobile terminal and the first camera device are all communicatively connected to mobile base station, mobile base station communication connection To server, the server checks that master station communicates to connect and is located in same LAN with this, the mobile base station and the server Check wall with flues of setting up defences between LAN where master station, the display device and check that master station communicates to connect, pacify on the mobile terminal Fill APP modules;
The image data of job site is obtained by first camera device and the second camera device, passes through the APP of mobile terminal The measurement data at module input scene, the image data and measurement data be uploaded to check master station's storage, processing, generation report, Show and supply remotely to pacify matter person and check, this checks that master station can send order to notify scene peace matter person to add engineering to mobile terminal To supervise rectification.
2. the long-range audit system of distribution line engineering construction quality according to claim 1, it is characterised in that:Described first All connected between camera device and mobile base station, between mobile terminal and mobile base station by 4G network services.
3. the long-range audit system of distribution line engineering construction quality according to claim 1, it is characterised in that:The movement Terminal includes any of mobile phone, tablet personal computer or notebook computer.
4. the long-range audit system of distribution line engineering construction quality according to claim 1, it is characterised in that:Described first Camera device is portable cradle head camera, and second camera device is camera.
5. the long-range auditing method of distribution line engineering construction quality, it is characterised in that:The auditing method comprises the following steps:
Step 1, by checking that master station creates engineering project;
Step 2, check that master station imports work ticket, using work ticket to check unit;
Step 3, it is defeated by the image data of camera device collection job site, or the mobile terminal by being mounted with APP modules Enter field measurement data, the image data and measurement data are sent to checking that master station is stored, handles, generates report, display And checked for long-range peace matter person;
Step 4, order is sent to notify scene peace matter person to add engineering to mobile terminal from checking master station not if if checking To supervise rectification, and return to step 3 uploading pictures data or measurement data again;If check by the way that the work ticket is completed;
Step 5, judge whether the engineering project checks completion, terminate this if completing and check project, step is returned if not completing Rapid 2.
CN201710758559.4A 2017-08-29 2017-08-29 The long-range audit system of distribution line engineering construction quality and method Pending CN107563635A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710758559.4A CN107563635A (en) 2017-08-29 2017-08-29 The long-range audit system of distribution line engineering construction quality and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710758559.4A CN107563635A (en) 2017-08-29 2017-08-29 The long-range audit system of distribution line engineering construction quality and method

Publications (1)

Publication Number Publication Date
CN107563635A true CN107563635A (en) 2018-01-09

Family

ID=60977580

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710758559.4A Pending CN107563635A (en) 2017-08-29 2017-08-29 The long-range audit system of distribution line engineering construction quality and method

Country Status (1)

Country Link
CN (1) CN107563635A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108848337A (en) * 2018-06-12 2018-11-20 中国联合网络通信集团有限公司 Long-range auditing method, device, terminal and the computer storage medium of line project

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105184519A (en) * 2015-10-23 2015-12-23 国家电网公司 Standardized safety operation tracing management system
CN105825329A (en) * 2016-03-14 2016-08-03 国网福建省电力有限公司 Safety and quality inspection method based on remote working site monitoring system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105184519A (en) * 2015-10-23 2015-12-23 国家电网公司 Standardized safety operation tracing management system
CN105825329A (en) * 2016-03-14 2016-08-03 国网福建省电力有限公司 Safety and quality inspection method based on remote working site monitoring system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张欣强 等: "基于"互联网+"配电线路工程施工质量远程稽核的创新实践", 《HTTP://WWW.CHINAQKING.COM/YC/2017/804439.HTML#》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108848337A (en) * 2018-06-12 2018-11-20 中国联合网络通信集团有限公司 Long-range auditing method, device, terminal and the computer storage medium of line project

Similar Documents

Publication Publication Date Title
CN109446668A (en) A kind of component Schedule monitoring system and method based on threedimensional model
CN103578154A (en) PDA-based realization method for intelligent patrol of electric equipment
CN108322475A (en) A kind of equipment remote collaboration method for maintaining and system based on MR live streamings
CN105243440A (en) Marketing mobile working platform based paperless office on-site working method
CN104103098A (en) Electric power distribution network line as well as equipment inspection method and equipment inspection system
CN109034404B (en) AR (augmented reality) -glasses-based multi-user cooperative maintenance system and method for thermal power plant and AR glasses
CN106845809A (en) A kind of engineering course line work dispatching method, system and device, dispatching system
CN103177327A (en) Comprehensive management system for low-voltage power operations based on B/S (browser/server) and C/S (client/server) architectures
CN110032148A (en) For the system of power plant management and the equipment of the 3D dummy model for establishing power plant
CN106845834A (en) Transmission line of electricity hidden danger management method and system based on mobile phone A PP
CN108154340A (en) Prefabricated component informationization management system based on BIM cloud platforms
CN107563635A (en) The long-range audit system of distribution line engineering construction quality and method
CN106408091A (en) Transformer station equipment information management platform
CN102096862A (en) Network-based clothing management method and system
CN107480285A (en) Center monitoring inquiry system and method
CN106993041A (en) A kind of power marketing moves work data synchronous method
CN207337347U (en) It can carry out the AR helmets of power transformation inspection
CN109146329A (en) A kind of power distribution network repairing command comprehensive display platform
CN107392458A (en) Based on field device operation intellectual analysis relative influence equipment topological analysis
CN102479359A (en) Power grid overhauling plan compilation method based on graphic operations
CN102663570A (en) Aluminum product cost accounting processing method and system based on network
KR101841347B1 (en) Mobile Terminal for Maintaining Wind Power Generator and Maintaining Method
CN202454974U (en) Device for electric power production inspection tour
CN108736572A (en) Power equipment intelligence control platform
CN108492395A (en) A kind of cruising inspection system and method for the power matching network equipment based on RFID

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180109

RJ01 Rejection of invention patent application after publication