CN107558501A - A kind of underpass spare interface construction method excavated from the later stage - Google Patents

A kind of underpass spare interface construction method excavated from the later stage Download PDF

Info

Publication number
CN107558501A
CN107558501A CN201710620180.7A CN201710620180A CN107558501A CN 107558501 A CN107558501 A CN 107558501A CN 201710620180 A CN201710620180 A CN 201710620180A CN 107558501 A CN107558501 A CN 107558501A
Authority
CN
China
Prior art keywords
underpass
construction
plot
side bracket
bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710620180.7A
Other languages
Chinese (zh)
Inventor
张伟立
常柱刚
谢明
樊振宇
孙巍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201710620180.7A priority Critical patent/CN107558501A/en
Publication of CN107558501A publication Critical patent/CN107558501A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of underpass spare interface construction method excavated from the later stage, plot side bracket is set on diaphram wall, water-stop glue is set on the end face that plot side bracket is connected with the channel side bracket constructed afterwards, in underpass end set channel side bracket, the interim earth-retaining and water sealing structure to form a closing are constructed by bracket and water-stop glue.Passage directly can cut diaphram wall in inside configuration and complete the structure construction of linkage section when being connected with plot.The permanent waterproof of underpass movement joint is then realized jointly by middle buried water stop and detachable waterstop.By using this construction measure, avoid the situation that excavation of foundation pit is carried out in small space, interim retaining wall structure in top board structure Foot of Upper Retaining Wall and passage is eliminated, is completed without genuine building enclosure to linkage section construction is retained, there is preferable convenience for construction and economy.

Description

A kind of underpass spare interface construction method excavated from the later stage
Technical field
The present invention relates to structure, the technical field of buildings waterproof, specifically a kind of underground excavated from the later stage leads to Road spare interface construction method.
Background technology
With the fast development of urban underground space, the requirement more and more higher that is interconnected between plot, especially at some Urban New District, the construction of all kinds of underpass gradually increase.In general underpass is respectively positioned on below town road, connects both sides Different plot.Underpass as municipal conveyance system facility typically can together with the road above it synchronous construction, and lead to The connection construction in road and both sides plot, it will usually because passage and the different engineerings in two, plot are difficult match the duration the problem of Reach synchronization implementation.Therefore in general, underpass meeting reservation conditions after the completion of leading construction are easy to later stage plot With channel attached construction.Existing reserved way is that genuine construction enters plot red line, on the outside of the supporting construction of plot Prearrangement of deformation amount stitches at 0.3 ~ 0.5m, and sets retaining wall to prevent later stage plot to be connected foundation ditch with tunnel above underpass top plate Built road and below pipeline are influenceed during excavation, while sets temporary plugging wall to prevent backfill from entering tunnel in tunnel Interior, the foundation pit supporting construction for also needing to retain neighbouring plot in addition is with the supporting and retaining system side soil body.
Existing ground pipeline joint reserves way shortcoming and is that the later stage applies if when the supporting construction in plot is diaphram wall When building site road is with plot linkage section, the excavation width of foundation ditch only has 0.3 ~ 0.5m, and machinery is difficult to construct in such a case, Hand excavation is also very difficult.The building enclosure needs of genuine both sides, which are protected to linkage section, simultaneously implements to complete, when using engineering method stake During as building enclosure, its hiring cost can be increased.
The content of the invention
It is an object of the invention to when the building enclosure in underpass plot to be connected is diaphram wall, there is provided one The underpass spare interface construction method that kind is excavated from the later stage, it can overcome some shortcomings of the prior art.
To achieve these goals, the technical scheme is that:A kind of underpass excavated from the later stage is reserved to be connect Outlet structure construction method, the end of underpass are the diaphram wall that plot has been implemented in advance, it is characterised in that the construction Method comprises the following steps:
The first step, reinforcing bar is implanted on diaphram wall, is set on the outside of underpass and the plot linkage segment structure of rear construction One encloses the land block side bracket;
Second step, water-stop glue is set on the end face that plot side bracket is connected with the channel side bracket constructed afterwards;
3rd step, construction underpass, underpass end prearrangement of deformation amount seam, prearrangement of deformation amount seam are in passage top plate, channel side Elongated setting channel side bracket on the outside of wall and channel base plate, in underpass top plate, bottom plate and side wall with it is pre- on the inside of bracket Stay position corresponding to movement joint that reserved middle buried water stop, underpass top plate, bottom plate and side wall inwall and bracket inner side are set The opening position of prearrangement of deformation amount seam is provided with the depressed part for installing waterstop.
Further, during construction in later period, diaphram wall position corresponding with underpass is cut, then constructed respectively Construction linkage section bottom plate, rear construction linkage section top plate and rear construction linkage section side wall afterwards, are set detachable in the depressed part reserved Formula waterstop.
According to a preferred embodiment of the invention, the water-stop glue is one pack system slow expansion type fluid sealant.
According to a preferred embodiment of the invention, prearrangement of deformation amount stitches on the inside of underpass top plate, bottom plate and side wall and bracket Corresponding position sets reserved middle buried water stop, and the opening position that prearrangement of deformation amount stitches on the inside of bracket sets detachable waterstop structure Make, form permanent agent structure waterproof.
According to a preferred embodiment of the invention, the channel side bracket is oblique from the side that prearrangement of deformation amount stitches side farther out Face, the angle between inclined-plane and channel side wall are 30 °.
According to a preferred embodiment of the invention, the bottom of the channel side bracket of the underpass bottom plate and plate outer side is equal It is provided with bed course and fish tail and waterproof layer.
Instant invention overcomes the shortcomings that existing underpass spare interface so that without again from ground when later stage passage connects Excavated, it is only necessary to the diaphram wall at hole is cut out of plot or tunnel, under the protection of outside bracket, at one Construction linkage segment structure in the environment of relative closure.The drawbacks of excavation construction is carried out in narrow and small environment is avoided, eliminates ground The temporary plugging wall inside retaining wall and tunnel above road, genuine constructed is remained into without by the supporting construction in tunnel Into.More convenient the invention enables constructing, cost is also more saved.
Brief description of the drawings
Fig. 1 undergrounds tunnel spare interface construction plan view.
Fig. 2 undergrounds tunnel spare interface structural section.
Fig. 3 top plate interface configurations detail drawings.
Fig. 4 backplane interface details of construction.
Including plot side bracket 1, channel side bracket 2, passage side wall 3, prearrangement of deformation amount seam 4, passage top plate 5, passage Bottom plate 6, one pack system slow expansion type fluid sealant 7, middle buried water stop 8, detachable sealing 9, bar planting 10, diaphram wall 11(Even It need to be cut when connecing), rear construction linkage section side wall 12, rear construction linkage section top plate 13, rear construction linkage section bottom plate 14, bed course and anti- Water conservation layer 15.
Embodiment
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings.
As depicted in figs. 1 and 2, the end of underpass is the diaphram wall 11 that plot has been implemented in advance(The underground connects Construction plot basement and underpass connecting portion, need part be cut in construction in later period after continuous wall is arranged on, general next Say, cut part as the diaphram wall position corresponding with underpass inner space), and it is close in underpass end Diaphram wall position prearrangement of deformation amount seam, underpass are in passage top plate 5, passage side wall 3 and channel floor in prearrangement of deformation amount seam The outside of plate 6(Meet native face)Elongated setting channel side bracket 2, channel side bracket and underpass synchronization implementation.Simultaneously in plot Plot side bracket 1 elongated corresponding to a circle is also provided with subterranean wall by bar planting mode, plot side bracket is arranged on underground company Continuous wall cuts the outside of position, does not influence the construction in follow-up plot and genuine linkage section.It is genuine outer by the resistance of plot side bracket Lateral earth pressure.Movement joint is set in channel side bracket 2 and plot side bracket 1, one pack system slow expansion type fluid sealant is set in movement joint 7, plot is used as by this measure and constructed with the temporary water dash in genuine linkage section work progress.
Fig. 3, Fig. 4 give the detail of construction of interface.Wherein Fig. 3 is illustrated that underpass top plate interface configurations figure, Fig. 4 Underpass backplane interface structural map is illustrated that, underpass side wall interface configurations figure is similar with top plate interface configurations figure, This no longer shows.
As illustrated, genuine outside sets channel side bracket 2, plot side bracket 1 is set on diaphram wall, in passage Side bracket sets water-stop glue with plot side bracket intersection location, and the interim gear to form a closing is constructed by bracket and water-stop glue Soil and water sealing structure.
Buried during position setting corresponding with prearrangement of deformation amount seam on the inside of bracket is reserved in underpass top plate, bottom plate and side wall Formula waterstop 8, in underpass top plate, bottom plate and side wall inwall(Carry on the back native side)Set with the opening position of prearrangement of deformation amount seam on the inside of bracket Depressed part is equipped with, detachable waterstop 9 is set in the depressed part, forms permanent agent structure waterproof.
As illustrated, boring a collar aperture with 1 corresponding position of plot side bracket in diaphram wall 11, reinforcing bar is implanted into, is utilized The reinforcing bar is cast-in-place to set plot side bracket 1.
The construction method of the underpass spare interface excavated from the later stage the construction of the present invention is plot side ox of first constructing Leg, water-stop glue then is set in the end face of plot side bracket, underpass side bracket of finally constructing again, makes itself and plot side bracket Between form water sealing structure, Specific construction step is:
Reinforcing bar is implanted into the first step, the diaphram wall 11 implemented in advance in plot, underpass and plot in rear construction One is set on the outside of linkage segment structure to enclose the land block side bracket 1;
Second step, the sealing of one pack system slow expansion type is set on the end face that plot side bracket 1 is connected with the channel side bracket 2 constructed afterwards Glue 7;
3rd step, construction underpass, underpass end prearrangement of deformation amount seam, prearrangement of deformation amount seam are in passage top plate 5, channel side Wall 3 and the outside of channel base plate 6(Meet native face)Elongated setting channel side bracket 2, in underpass top plate, bottom plate and side wall with Position corresponding to prearrangement of deformation amount seam sets reserved middle buried water stop 8, underpass top plate, bottom plate and side wall inwall on the inside of bracket (Carry on the back native side)The opening position of prearrangement of deformation amount seam on the inside of bracket is provided with the depressed part for installing waterstop, by bracket and only Glue constructs the interim earth-retaining and water sealing structure to form a closing.
During construction in later period, the position corresponding with underpass of diaphram wall 11 is cut, constructed after then constructing respectively Linkage section bottom plate 14, rear construction linkage section top plate 13 and rear construction linkage section side wall 12, are set detachable in reserved depressed part Formula waterstop 9.
Diaphram wall 11 at bottom plate, top plate and side wall needs synchronously to cut, and cuts after-pouring underpass and underground Room linkage section, rear construction section generally poured with diaphram wall together with formed it is overall.Underpass movement joint is forever Long waterproof relies primarily on the middle buried water stop 8 and detachable waterstop 9 reserved on the inside of bracket in genuine wallboard, two brackets Between fluid sealant can also be as later permanent waterproof one of ancillary method.
The specific embodiment of the present invention is described in detail above, but it is intended only as example, it is of the invention and unlimited It is formed on particular embodiments described above.To those skilled in the art, it is any to the equivalent modifications that carry out of the present invention and Substitute also all among scope of the invention.Therefore, the impartial conversion made without departing from the spirit and scope of the invention and Modification, all should be contained within the scope of the invention.

Claims (4)

1. a kind of underpass spare interface construction method excavated from the later stage, the end of underpass is first for plot The diaphram wall that row is implemented, it is characterised in that the construction method comprises the following steps:
The first step, reinforcing bar is implanted on diaphram wall, is set on the outside of underpass and the plot linkage segment structure of rear construction One encloses the land block side bracket;
Second step, water-stop glue is set on the end face that plot side bracket is connected with the channel side bracket constructed afterwards;
3rd step, construction underpass, underpass end prearrangement of deformation amount seam, prearrangement of deformation amount seam are in passage top plate, channel side Elongated setting channel side bracket on the outside of wall and channel base plate, in underpass top plate, bottom plate and side wall with it is pre- on the inside of bracket Stay position corresponding to movement joint that reserved middle buried water stop, underpass top plate, bottom plate and side wall inwall and bracket inner side are set The opening position of prearrangement of deformation amount seam is provided with the depressed part for installing waterstop.
2. tunnel spare interface construction method in underground as claimed in claim 1, it is characterised in that:, will during construction in later period Diaphram wall position corresponding with underpass is cut, constructed after then constructing respectively linkage section bottom plate, linkage section of constructing afterwards Top plate and rear construction linkage section side wall, set detachable waterstop in reserved depressed part.
3. tunnel spare interface construction method in underground as claimed in claim 1, it is characterised in that:The water-stop glue is single Component slow expansion type fluid sealant.
4. tunnel spare interface construction method in underground as claimed in claim 1, it is characterised in that:The underpass bottom The bottom of the channel side bracket of plate and plate outer side is provided with bed course and fish tail and waterproof layer.
CN201710620180.7A 2017-07-26 2017-07-26 A kind of underpass spare interface construction method excavated from the later stage Pending CN107558501A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710620180.7A CN107558501A (en) 2017-07-26 2017-07-26 A kind of underpass spare interface construction method excavated from the later stage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710620180.7A CN107558501A (en) 2017-07-26 2017-07-26 A kind of underpass spare interface construction method excavated from the later stage

Publications (1)

Publication Number Publication Date
CN107558501A true CN107558501A (en) 2018-01-09

Family

ID=60974873

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710620180.7A Pending CN107558501A (en) 2017-07-26 2017-07-26 A kind of underpass spare interface construction method excavated from the later stage

Country Status (1)

Country Link
CN (1) CN107558501A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107604952A (en) * 2017-07-26 2018-01-19 上海市政工程设计研究总院(集团)有限公司 A kind of underpass spare interface construction excavated from the later stage
CN111877407A (en) * 2020-07-27 2020-11-03 中铁十一局集团第一工程有限公司 Construction method for reserved interface of underground space connecting channel
CN112942426A (en) * 2021-03-30 2021-06-11 中冶京诚工程技术有限公司 Temporary plugging structure and plugging method for comprehensive pipe gallery
CN113186984A (en) * 2020-01-14 2021-07-30 中铁第六勘察设计院集团有限公司 Construction process for connecting newly-built underground passage with existing underground structure
CN113653099A (en) * 2021-08-18 2021-11-16 中国建筑第八工程局有限公司 Basement structure and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101205766A (en) * 2006-12-20 2008-06-25 上海市第一建筑有限公司 Waterproof treatment method for joint of new station and old station
CN202577364U (en) * 2012-04-23 2012-12-05 厦门华旸建筑工程设计有限公司 Joint of basement ramp board and basement outer wall
CN203213147U (en) * 2013-04-09 2013-09-25 上海市政工程设计研究总院(集团)有限公司 Temporary plugging wall for underground reinforced concrete box culvert structure
CN204780994U (en) * 2015-06-11 2015-11-18 中建一局集团第六建筑有限公司 Underground continuous wall inwall construction structures
CN105401604A (en) * 2015-11-20 2016-03-16 上海市政工程设计研究总院(集团)有限公司 Reserved connecting port structure for underground pipe gallery and implementation method thereof
CN105421497A (en) * 2015-09-14 2016-03-23 上海建工七建集团有限公司 Water-proof construction method for connected nodes of foundation slab and ground wall in composite surround system
CN105672250A (en) * 2016-01-20 2016-06-15 中铁隆工程集团有限公司 Rabbet connecting mechanism and construction method for underground diaphragm wall and underwater concrete

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101205766A (en) * 2006-12-20 2008-06-25 上海市第一建筑有限公司 Waterproof treatment method for joint of new station and old station
CN202577364U (en) * 2012-04-23 2012-12-05 厦门华旸建筑工程设计有限公司 Joint of basement ramp board and basement outer wall
CN203213147U (en) * 2013-04-09 2013-09-25 上海市政工程设计研究总院(集团)有限公司 Temporary plugging wall for underground reinforced concrete box culvert structure
CN204780994U (en) * 2015-06-11 2015-11-18 中建一局集团第六建筑有限公司 Underground continuous wall inwall construction structures
CN105421497A (en) * 2015-09-14 2016-03-23 上海建工七建集团有限公司 Water-proof construction method for connected nodes of foundation slab and ground wall in composite surround system
CN105401604A (en) * 2015-11-20 2016-03-16 上海市政工程设计研究总院(集团)有限公司 Reserved connecting port structure for underground pipe gallery and implementation method thereof
CN105672250A (en) * 2016-01-20 2016-06-15 中铁隆工程集团有限公司 Rabbet connecting mechanism and construction method for underground diaphragm wall and underwater concrete

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107604952A (en) * 2017-07-26 2018-01-19 上海市政工程设计研究总院(集团)有限公司 A kind of underpass spare interface construction excavated from the later stage
CN113186984A (en) * 2020-01-14 2021-07-30 中铁第六勘察设计院集团有限公司 Construction process for connecting newly-built underground passage with existing underground structure
CN111877407A (en) * 2020-07-27 2020-11-03 中铁十一局集团第一工程有限公司 Construction method for reserved interface of underground space connecting channel
CN112942426A (en) * 2021-03-30 2021-06-11 中冶京诚工程技术有限公司 Temporary plugging structure and plugging method for comprehensive pipe gallery
CN113653099A (en) * 2021-08-18 2021-11-16 中国建筑第八工程局有限公司 Basement structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN107558501A (en) A kind of underpass spare interface construction method excavated from the later stage
CN102704957B (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN105003270B (en) Underwater tunnel construction method suitable for ultra-shallow earthing conditions
CN106948823A (en) Combine the construction method applied with mining sectbn in station air channel
CN104879144B (en) The excavating construction method of the underground space is built with array push pipe in soft clay area
CN107191197A (en) A kind of shield duct piece and its pushed away in shield sky by the application in Tunneling by mining method
CN204098043U (en) After staying soil, excavation is in conjunction with inner support Retaining Structure with Double-row Piles
CN103775110A (en) Underground excavation construction method for multilayer underground space of soft soil area
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN102182464A (en) Construction structure and construction method of channel structure
CN111456773A (en) Close-fitting open-and-underground excavation combined subway station structure and construction method thereof
CN207228168U (en) A kind of underpass spare interface construction excavated from the later stage
CN108071122A (en) Assembled underground pipe gallery and its construction method
CN107604952A (en) A kind of underpass spare interface construction excavated from the later stage
CN207331746U (en) A kind of underground pipe gallery
CN207512777U (en) Assembled underground pipe gallery
CN112145227B (en) Facility for preventing water inrush and mud gushing of tunnel and construction method
CN106351675B (en) The complete deep curtain of the buried Station of rich water sand-pebble layer freezes water-stopping system
CN209760299U (en) light and shade of avoiding house to tear open and move is dug and is combined subway station structure
CN202954367U (en) System for controlling deformation of deep and big foundation pit by utilizing divisional unloading
CN216077128U (en) Subway double-layer full-section freezing underground excavation transfer station structure
CN206189968U (en) Prefabricated assembled underground granary of inside lining plastics echelonment
CN212202085U (en) Close-adhesion type open-and-underground excavation combined subway station structure
CN107574830A (en) A kind of subway station combines the precipitation method of piping lane construction
CN209099394U (en) A kind of waterproof construction of novel piping lane deformation joint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination