CN107542040A CN201710978945.4A CN201710978945A CN107542040A CN 107542040 A CN107542040 A CN 107542040A CN 201710978945 A CN201710978945 A CN 201710978945A CN 107542040 A CN107542040 A CN 107542040A
Authority
CN
China
Prior art keywords
plate
angle steel
steel
supporting
carrier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710978945.4A
Other languages
Chinese (zh)
Inventor
王彬
樊帆
陶永金
宁雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Keensun International Economic And Technical Cooperation Co
Original Assignee
Anhui Keensun International Economic And Technical Cooperation Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Keensun International Economic And Technical Cooperation Co filed Critical Anhui Keensun International Economic And Technical Cooperation Co
Priority to CN201710978945.4A priority Critical patent/CN107542040A/en
Publication of CN107542040A publication Critical patent/CN107542040A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of construction operation supporting mechanism and its installation method, including some support frames being sequentially distributed in left-right direction, two the first angle steel are symmetrically installed between adjacent supports frame top between bottom, the first supporting steel plate is placed between former and later two first angle steel;Support frame includes two ledges of symmetrical distribution, and two the second angle steel are symmetrically installed between bottom between two ledge tops, the second supporting steel plate is placed between former and later two second angle steel.The present invention passes through scientific and reasonable structure design, the actual conditions that construction site can be directed to carry out Fast Installation and dismounting, supporting power is big, structural stability is strong, can effectively it be fixedly mounted on non-smooth soil, its security is greatly improved, there is the extensive scope of application, be worthy to be popularized and use.

Description

A kind of construction operation supporting mechanism and its installation method
Technical field
The invention belongs to the realm of building construction, more particularly to a kind of construction operation supporting mechanism and its installation method.
Background technology
With the rapid development of economy, national or even global building trade is developed rapidly, will repair every year Build substantial amounts of skyscraper, such as dam, bridge, high building building are built, and are frequently necessary to support frame auxiliary in engineering construction Construction, support frame are the support meanss commonly used in skyscraper, the pouring construction of mixed mud can be such as carried out with support shuttering, especially When building outstanding measuring platform or other buildings prominent to surrounding, it is frequently necessary to prop up before mixed mud is poured Support arrangement support shuttering, removed again after the dry and hard stress of mixed mud, reached preventing and treating and come off, the effect of safe construction.It is existing In technology, the structure design of support frame is not ideal enough, and sound construction performance is poor, and handling are inconvenient, and especially support degree is smaller, The needs that the building that weight is big, highly high is constructed can not be met;The height of support can not be adjusted, and the width of support can not Regulation, the pressure of each fulcrum can not be balanced, easily be collapsed when supporting pressure larger;In face of different back-up environments, support Frame can not be reused, and each use is required for remaking.Therefore, it is necessary to design one on the basis of existing technology Kind is sturdy and durable, easy to loading and unloading, the big support meanss for building of supporting power.
The content of the invention
It is an object of the invention to overcome problem above existing for prior art, there is provided a kind of construction operation supports machine Structure and its installation method, easy to loading and unloading, supporting power is big.
To realize above-mentioned technical purpose and the technique effect, the present invention is achieved through the following technical solutions:
A kind of construction operation supporting mechanism, including some support frames being sequentially distributed in left-right direction, adjacent supports Two the first angle steel are symmetrically installed between frame top between bottom, first is placed between former and later two first angle steel Support steel plate;
Support frame as described above includes two ledges of symmetrical distribution, between two ledge tops between bottom Two the second angle steel are symmetrically installed with, the second supporting steel plate is placed between former and later two second angle steel;
The ledge includes two carriers being distributed up and down, and being symmetrically installed with two between two carriers are front and rear erects The support member being directly distributed, it is connected between support member top and carrier by adjusting bolt, support member bottom and carrier Between be connected by polarized plug;
The carrier includes front and rear two symmetrical channel-section steels, is fixedly connected between two channel-section steels by screw rod;Groove Steel or so holds the through hole for being arranged with two horizontal distributions, and channel-section steel bottom symmetrical is provided with two the first positioning holes, channel-section steel top Vertically-mounted limited location dividing plate;Support member includes supporting plate and is symmetrically fixed on the reinforcement side plate of side before and after supporting plate, support The vertical bending in plate top forms top plate, and top board undersurface is connected with strengthening side plane contact, is provided with the second positioning hole among top plate, supports The vertical bending in plate bottom forms bottom plate, and plate top surface is connected with strengthening side plane contact, and the 3rd positioning hole is provided among bottom plate;Screw rod Both ends are fixedly linked through through hole with the first nut, and regulation bolt sequentially passes through the second positioning hole, the first positioning hole, the Two angle steel are fixedly linked with the second nut;Polarized plug bottom sequentially passes through the 3rd positioning hole, the second angle steel and the carrying of bottom Frame, polarized plug top are provided with sheet rubber.
Further, the length of second supporting steel plate is equal to the distance of adjacent ledge, avoids the first supporting steel plate Slip in the horizontal direction.
Further, by being weldingly connected between the supporting plate and reinforcement side plate, structural strength is reliable.
Further, the polarized plug top is provided with annular groove, and annular stop piece, stability are provided with annular groove By force.
The present invention also provides a kind of construction operation supporting mechanism installation method, the described method comprises the following steps:
Step 1:After carrier installation, first in the horizontal positioned carrier in bottom surface, then before and after carrier Side is symmetrically installed two the second angle steel, between two the second angle steel installation place two the second angle steel, second jiao of bottom two The second supporting steel plate is placed between steel;
Step 2:Then in the second angle steel both ends right angle setting support member of bottom, and installed at the top of two support members Carrier, two the second angle steel then will be symmetrically installed between two carriers at top, and in two second angle steel at top Between the second supporting steel plate is installed;
Step 3:Then regulation bolt is sequentially passed through into top plate, channel-section steel, the second angle steel and twisted with the second nut Tightly, support frame is formed;
Step 4:Some support frames are linearly equidistantly put, and the first angle steel is symmetrically installed in upper and lower side, and The first supporting steel plate is placed between former and later two first angle steel.
The beneficial effects of the invention are as follows:
The present invention by scientific and reasonable structure design, quickly pacified by the actual conditions that can be directed to construction site Dress and dismounting, supporting power is big, and structural stability is strong, can be effectively fixedly mounted on non-smooth soil, greatly carried Its high security, has the extensive scope of application, is worthy to be popularized and uses.
Brief description of the drawings
Accompanying drawing described herein is used for providing a further understanding of the present invention, forms the part of the application, this hair Bright schematic description and description is used to explain the present invention, does not form inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the partial structural diagram of the present invention;
Fig. 3 is the partial structural diagram of the present invention;
Fig. 4 is the partial structurtes explosive view of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained all other under the premise of creative work is not made Embodiment, belong to the scope of protection of the invention.
In the description of the invention, it is to be understood that term " perforate ", " on ", " under ", " thickness ", " top ", " in ", Indicating position or the position relationship such as " length ", " interior ", " surrounding ", it is for only for ease of the description present invention and simplifies description, without It is that the component of instruction or hint meaning or element must have specific orientation, with specific azimuth configuration and operation, therefore not It is understood that as limitation of the present invention.
A kind of construction operation supporting mechanism as shown in Figure 1, including some supports being sequentially distributed in left-right direction Frame 1, two the first angle steel 2, former and later two first angle steel 2 are symmetrically installed between bottom between the top of adjacent supports frame 1 Between be placed with the first supporting steel plate 3.
As shown in Fig. 2 support frame 1 includes two ledges 11 of symmetrical distribution, between two tops of ledge 11 Two the second angle steel 12 are symmetrically installed between bottom, the second supporting steel plate is placed between former and later two second angle steel 12 13;The length of second supporting steel plate 13 is equal to the distance of adjacent ledge 11, avoids first supporting steel plate 3 in the horizontal direction Slide.
As shown in figure 3, ledge 11 includes two carriers 111 being distributed up and down, it is right between two carriers 111 are front and rear Title is provided with two support members being distributed vertically 112, by adjusting bolt between the top of support member 112 and carrier 111 113 are connected, and are connected between the bottom of support member 112 and carrier 111 by polarized plug 114.
As shown in figure 4, carrier 111 includes front and rear two symmetrical channel-section steels 1111, lead between two channel-section steels 1111 Screw rod 1112 is crossed to be fixedly connected;Channel-section steel 1111 or so holds the through hole 1113 for being arranged with two horizontal distributions, the bottom of channel-section steel 1111 Portion is arranged with two the first positioning holes 1114, the top vertical of channel-section steel 1111 installation limited location dividing plate 1115;Support member 112 includes Supporting plate 1121 and the reinforcement side plate 1126 for being symmetrically fixed on side before and after supporting plate 1121, the vertical bending in the top of supporting plate 1121 Top plate 1122 is formed, the bottom surface of top plate 1122 contacts with reinforcement side plate 1126 to be connected, and the second positioning hole is provided among top plate 1122 1123, the vertical bending in the bottom of supporting plate 1121 forms bottom plate 1124, and the top surface of bottom plate 1124 contacts connected, bottom with strengthening side plate 1126 The 3rd positioning hole 1125 is provided among plate 1124;The both ends of screw rod 1112 are fixedly linked through through hole 1113 with the first nut, adjust Section bolt 113 sequentially passes through the second positioning hole 1123, the first positioning hole 1114, the second angle steel 12 and the second nut stationary phase Even;The bottom of polarized plug 114 sequentially passes through the carrier 111 of the 3rd positioning hole 1125, the second angle steel 12 and bottom, polarized plug 114 tops are provided with sheet rubber 1141;By being weldingly connected between supporting plate 1121 and reinforcement side plate 1126, structural strength is reliable; The top of polarized plug 114 is provided with annular groove, is provided with annular stop piece in annular groove, stability is strong.
The present invention also provides a kind of construction operation supporting mechanism installation method, and method comprises the following steps:
Step 1:After the installation of carrier 111, first in the horizontal positioned carrier 111 in bottom surface, then carrying Side is symmetrically installed two the second angle steel 12 before and after frame 111, is installed between two the second angle steel 12 and places two the second angle steel 12, The second supporting steel plate 13 is placed between the second angle steel 12 of bottom two;
Step 2:Then in the both ends right angle setting support member 112 of the second angle steel 12 of bottom, and in two support members 112 Carrier 111 is installed at top, then two the second angle steel 12 will be symmetrically installed between two carriers 111 at top, and pushing up The second supporting steel plate 13 is installed between two second angle steel 12 in portion;
Step 3:Then regulation bolt 113 is sequentially passed through into top plate 1122, channel-section steel 1111, the second angle steel 12 to be used in combination Second nut is tightened, and forms support frame 1;
Step 4:Some support frames 1 are linearly equidistantly put, and the first angle steel 2 is symmetrically installed in upper and lower side, And the first supporting steel plate 3 is placed between former and later two first angle steel 2.
The present invention by scientific and reasonable structure design, quickly pacified by the actual conditions that can be directed to construction site Dress and dismounting, supporting power is big, and structural stability is strong, can be effectively fixedly mounted on non-smooth soil, greatly carried Its high security, has the extensive scope of application, is worthy to be popularized and uses.
In the description of this specification, the description of reference term " one embodiment ", " example ", " specific example " etc. means At least one implementation of the present invention is contained in reference to specific features, structure, material or the feature that the embodiment or example describe In example or example.In this manual, identical embodiment or example are not necessarily referring to the schematic representation of above-mentioned term. Moreover, specific features, structure, material or the feature of description can close in any one or more embodiments or example Suitable mode combines.
General principle, principal character and the advantages of the present invention of the present invention has been shown and described above.The technology of the industry Personnel are it should be appreciated that the present invention is not limited to the above embodiments, and the simply explanation described in above-described embodiment and specification is originally The principle of invention, without departing from the spirit and scope of the present invention, various changes and modifications of the present invention are possible, these changes Change and improvement all fall within the protetion scope of the claimed invention.

Claims (5)

  1. A kind of 1. construction operation supporting mechanism, it is characterised in that:Including some support frames being sequentially distributed in left-right direction (1), it is symmetrically installed with two the first angle steel (2) between adjacent supports frame (1) top between bottom, former and later two first jiao The first supporting steel plate (3) is placed between steel (2);
    Support frame as described above (1) includes two ledges (11) of symmetrical distribution, between two ledge (11) tops and bottom Two the second angle steel (12) are symmetrically installed between end, the second supporting steel plate is placed between former and later two second angle steel (12) (13);
    The ledge (11) includes two carriers (111) being distributed up and down, symmetrically pacifies between two carriers (111) are front and rear Equipped with two support members being distributed vertically (112), spiral shell is positioned by adjusting between support member (112) top and carrier (111) Bolt (113) is connected, and is connected between support member (112) bottom and carrier (111) by polarized plug (114);
    The carrier (111) includes front and rear two symmetrical channel-section steels (1111), passes through spiral shell between two channel-section steels (1111) Bar (1112) is fixedly connected;Channel-section steel (1111) left and right end is arranged with the through hole (1113) of two horizontal distributions, channel-section steel (1111) bottom symmetrical is provided with two the first positioning holes (1114), channel-section steel (1111) top vertical installation limited location dividing plate (1115);Support member (112) includes supporting plate (1121) and is symmetrically fixed on the reinforcement side plate of side before and after supporting plate (1121) (1126), the vertical bending in supporting plate (1121) top forms top plate (1122), and top plate (1122) bottom surface is with strengthening side plate (1126) Contact is connected, and the second positioning hole (1123) is provided among top plate (1122), and the vertical bending in supporting plate (1121) bottom forms bottom plate (1124), bottom plate (1124) top surface is contacted with reinforcement side plate (1126) and is connected, and the 3rd positioning hole is provided among bottom plate (1124) (1125);Screw rod (1112) both ends are fixedly linked through through hole (1113) with the first nut, and regulation bolt (113) is successively It is fixedly linked through the second positioning hole (1123), the first positioning hole (1114), the second angle steel (12) with the second nut;Polarized plug (114) bottom sequentially passes through the 3rd positioning hole (1125), the second angle steel (12) and the carrier (111) of bottom, polarized plug (114) top is provided with sheet rubber (1141).
  2. A kind of 2. construction operation supporting mechanism according to claim 1, it is characterised in that:Second supporting steel plate (13) length is equal to the distance of adjacent ledge (11).
  3. A kind of 3. construction operation supporting mechanism according to claim 1, it is characterised in that:The supporting plate (1121) By being weldingly connected between reinforcement side plate (1126).
  4. A kind of 4. construction operation supporting mechanism according to claim 1, it is characterised in that:The polarized plug (114) top is provided with annular groove, and annular stop piece is provided with annular groove.
  5. A kind of 5. construction operation supporting mechanism installation method according to claim 1, it is characterised in that:Methods described Comprise the following steps:
    Step 1:After carrier (111) installation, first in the horizontal positioned carrier (111) in bottom surface, then carrying Side is symmetrically installed two the second angle steel (12) before and after frame (111), is installed between two the second angle steel (12) and places two second jiao Steel (12), the second supporting steel plate (13) is placed between the second angle steel (12) of bottom two;
    Step 2:Then in the second angle steel (12) both ends right angle setting support member (112) of bottom, and in two support members (112) top installation carrier (111), then will be symmetrically installed two the second angle steel between two carriers (111) at top (12) the second supporting steel plate (13), and between two second angle steel (12) at top is installed;
    Step 3:Then regulation bolt (113) is sequentially passed through into top plate (1122), channel-section steel (1111), the second angle steel (12) And tightened with the second nut, form support frame (1);
    Step 4:Some support frames (1) are linearly equidistantly put, and the first angle steel (2) is symmetrically installed in upper and lower side, And place the first supporting steel plate (3) between former and later two first angle steel (2).
CN201710978945.4A 2017-10-19 2017-10-19 A kind of construction operation supporting mechanism and its installation method Pending CN107542040A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710978945.4A CN107542040A (en) 2017-10-19 2017-10-19 A kind of construction operation supporting mechanism and its installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710978945.4A CN107542040A (en) 2017-10-19 2017-10-19 A kind of construction operation supporting mechanism and its installation method

Publications (1)

Publication Number Publication Date
CN107542040A true CN107542040A (en) 2018-01-05

Family

ID=60968019

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710978945.4A Pending CN107542040A (en) 2017-10-19 2017-10-19 A kind of construction operation supporting mechanism and its installation method

Country Status (1)

Country Link
CN (1) CN107542040A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0656216U (en) * 1992-12-30 1994-08-05 株式会社ブレスト工業研究所 Connection tool and support stand
RU80691U1 (en) * 2008-10-09 2009-02-20 Рафаиль Ибрагимович Хисамов NODE CONNECTION
CN101736900A (en) * 2009-12-08 2010-06-16 中国建筑第八工程局有限公司 Detached supporting template system
CN201605675U (en) * 2010-03-24 2010-10-13 安徽瑶海钢结构股份有限公司 Connecting device for steel piece
CN102031869A (en) * 2011-01-28 2011-04-27 中国建筑第八工程局有限公司 Horizontal template steel structure bracket
CN202055532U (en) * 2011-03-09 2011-11-30 浙江省一建建设集团有限公司 Reinforcing bar processing frame structure
CN103206014A (en) * 2013-04-23 2013-07-17 北京工业大学 Multi-high-rise assembled steel structure frame supporting system capable of realizing rigid connection of joints
CN204940821U (en) * 2015-09-10 2016-01-06 江苏南通二建集团有限公司 One can be had enough to meet the need and utilize Finalized rebar operating desk
CN107060095A (en) * 2017-03-29 2017-08-18 沈阳建筑大学 A kind of overall top module system platform universal architecture of combined type

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0656216U (en) * 1992-12-30 1994-08-05 株式会社ブレスト工業研究所 Connection tool and support stand
RU80691U1 (en) * 2008-10-09 2009-02-20 Рафаиль Ибрагимович Хисамов NODE CONNECTION
CN101736900A (en) * 2009-12-08 2010-06-16 中国建筑第八工程局有限公司 Detached supporting template system
CN201605675U (en) * 2010-03-24 2010-10-13 安徽瑶海钢结构股份有限公司 Connecting device for steel piece
CN102031869A (en) * 2011-01-28 2011-04-27 中国建筑第八工程局有限公司 Horizontal template steel structure bracket
CN202055532U (en) * 2011-03-09 2011-11-30 浙江省一建建设集团有限公司 Reinforcing bar processing frame structure
CN103206014A (en) * 2013-04-23 2013-07-17 北京工业大学 Multi-high-rise assembled steel structure frame supporting system capable of realizing rigid connection of joints
CN204940821U (en) * 2015-09-10 2016-01-06 江苏南通二建集团有限公司 One can be had enough to meet the need and utilize Finalized rebar operating desk
CN107060095A (en) * 2017-03-29 2017-08-18 沈阳建筑大学 A kind of overall top module system platform universal architecture of combined type

Similar Documents

Publication Publication Date Title
CN104652236A (en) Combined type channel steel support template rod system and construction method thereof
CN205317460U (en) Prevent test device of frame liangping off -plate unstability under big deformation test condition
CN204040450U (en) A kind of for angle connector in tools type section steel builder's jack
CN206153325U (en) Coalignment of dysmorphism H shaped steel
CN206902571U (en) A kind of construction operation supporting mechanism
CN106703014B (en) The pre-buried steel column of diaphram wall is fixed and secondary deviation correcting device and method
CN107542040A (en) A kind of construction operation supporting mechanism and its installation method
CN210289148U (en) Be used for building aluminium template bracing piece iron pipe
CN204455779U (en) Combined type channel-section steel formwork leverage
CN103225396A (en) Beam frame type construction template system
CN215907403U (en) Fine adjustment tool for supporting large steel formwork
CN205046843U (en) Reinforcing apparatus's stair template of marking time in middle of installation
CN107237515A (en) The support meanss and its application method of circular steel truss structure
KR101182777B1 (en) Supporter of form for concrete crossbeam
CN204455758U (en) Shape-setting clamp formula shuttering supporting leverage
CN207633804U (en) A kind of middle-size and small-size full assembling activity formula reinforcing steel processing shed
CN202220438U (en) Diving platform steel formwork support system
CN205476444U (en) Light -duty support post based on low level jacking die carrier system
CN208604922U (en) A kind of building template
CN206428701U (en) A kind of template of construction of hydro project
CN219654322U (en) Steel column installation and adjustment combination tool
CN211473391U (en) Cantilever beam template clamp
CN216076326U (en) Adjustable template fixing device
CN202559293U (en) Steel-hoop bidirectional suspending support system
CN216176142U (en) Device for conveniently manufacturing bent anchor steel bar

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180105