CN107513963A - A kind of roadbed concrete guardrail recycles construction method - Google Patents
A kind of roadbed concrete guardrail recycles construction method Download PDFInfo
- Publication number
- CN107513963A CN107513963A CN201610422468.9A CN201610422468A CN107513963A CN 107513963 A CN107513963 A CN 107513963A CN 201610422468 A CN201610422468 A CN 201610422468A CN 107513963 A CN107513963 A CN 107513963A
- Authority
- CN
- China
- Prior art keywords
- guardrail
- concrete
- precast block
- roadbed
- concrete precast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01F—ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
- E01F15/00—Safety arrangements for slowing, redirecting or stopping errant vehicles, e.g. guard posts or bollards; Arrangements for reducing damage to roadside structures due to vehicular impact
- E01F15/02—Continuous barriers extending along roads or between traffic lanes
- E01F15/04—Continuous barriers extending along roads or between traffic lanes essentially made of longitudinal beams or rigid strips supported above ground at spaced points
- E01F15/0484—Installing; Repairing; Adjusting
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
The present invention relates to roadbed concrete guardrail to recycle construction method, belongs to traffic safety protection field, it is comprised the following steps that:(1) concrete precast block is made.(2) concrete precast block is assembled, forms temporary guard rail.(3) when guardrail is removed, first by the longitudinally connected dismounting of concrete precast block, then concrete precast block is removed standby.(4) concrete precast block is installed as roadbed guardrail and recycled.Construction method of the present invention is simple, reasonable, the construction period is short; it can be reused effectively roadbed concrete guardrail; being one for reconstruction and extension project reduces cost, simplifies the mode of construction, while also complies with the engineering construction theory of " resources conservation and environmental protection ".
Description
Technical field
The present invention relates to roadbed concrete guardrail to recycle construction method, belongs to traffic safety protection field.
Background technology
In recent years, China's expressway construction was fast-developing, and building up and runing for highway greatly facilitates the masses
Trip and various regions on the way economic development.But with China's economy rapid growth and highway transportation cause flourish,
The volume of traffic increases rapidly, and particularly large truck increases, and directly results in highway communication facility frequency of use and load
Increase, the highway much built in early days can not adapt to the operation demand of the current volume of traffic, according to incompletely statistics,
In the highway built before 2004, about 30,000 kilometers have been enter into the reorganization and expansion stage.
At present, so needing to set substantial amounts of temporary guard rail, it is used for often using " protecting logical " policy in reconstruction and extension project
Ensure construction area safety.Temporary guard rail is divided into prefabricated and cast in situs, precast concrete guardrail foundation anchor power Shortcomings, leads
Cause guardrail barrier propterty relatively low, poor, security protection scarce capacity is protected to oversize vehicle;A point band concrete protects in cast-in-place roadbed
Column concrete foundation is connected firmly, and can reach compared with permanent protective property energy, but construction method is complex, is not easy in the case of " protecting logical "
Site operation, and it is usually that destructiveness is removed to be removed after installing, not reproducible utilization.
Based on this, propose that a kind of roadbed concrete guardrail recycles construction method.
The content of the invention
The present invention proposes that a kind of roadbed concrete guardrail recycles construction method, roadbed concrete guardrail is had cast-in-place work concurrently
The security protection performance of skill guardrail and the convenient of precasting process guardrail remove locomotive function, realize that the repetition of concrete guardrail is sharp again
With the temporary guard rail that can be applied not only in reconstruction and extension project, could be applicable to newly-built road, greatly extend the use of guardrail
In the life-span, the waste of material in engineering construction is reduced, and meet security protection demand, met " resources conservation and environmental protection "
Engineering construction theory.
To achieve the above object, technical scheme is as follows:
The roadbed concrete guardrail recycles construction method specific steps:
(1) prefabricated fabrication of concrete prefabricated section;
(2) concrete precast block is assembled, and adjustment is linear, connects longitudinal connecting component, forms temporary guard rail;
(3) when dismantling guardrail, longitudinal connecting component is first opened, is then removed concrete precast block standby;
(4) concrete precast block is recycled and is installed as in roadbed a point band guardrail;
Further, the step (1):Guardrail reinforcing bar built in concrete precast block and longitudinally connected preburied component, when
During the two position conflict, it should ensure that preburied component position is constant, suitably adjust reinforcement location.
Further, the step (2):Connection concrete precast block between it is longitudinally connected after lie against road surface, concrete
Prefabricated section is connectionless with road surface.
Further, the step (3):Can not be to coagulation during opening connecting elements and removing concrete precast block
Native prefabricated section causes transition to damage with preburied component.
Further, the step (4):After paved road basic unit, line setting installs leveling layer, and installation concrete is pre-
Clamp dog, adjustment it is linear, and complete it is longitudinally connected, concrete precast block back install cross-brace block, installation guardrail correlation it is attached
Belong to facility, highway surface layer of finally mating formation.
Further, the step (4):After paved road basic unit, line setting, mounting groove is reserved, public affairs of mating formation afterwards
Supercrust, in installation trench bottom installation leveling layer, standby concrete precast block being positioned in mounting groove, adjustment is linear, and
Complete it is longitudinally connected, concrete precast block back install cross-brace block, finally install guardrail associated satellite facility.
Further, construction muscle should be matched somebody with somebody when the leveling layer is excessive.
Compared with prior art, beneficial effects of the present invention
The roadbed concrete guardrail of the present invention recycles construction method, increases a point band concrete guardrail in roadbed and recycles
Rate, general general work will soon grasp work progress, easy construction, cost-effective, environmental protection.
The roadbed concrete guardrail of the present invention recycles construction method, and guardrail wall body structure is not destroyed in work progress, protects
The integrality and intensity of concrete precast block are demonstrate,proved.
The roadbed concrete guardrail of the present invention recycles construction method, and concrete precast block can be used for multiple times, and use the longevity
Life length, it is easy to maintain.
The roadbed concrete guardrail of the present invention recycles construction method, and concrete guardrail prefabricated section can be used for multiple times, make
It is easy to maintain with long lifespan.
Brief description of the drawings
In order to illustrate more clearly of the technical scheme of patent of the present invention, below by the required accompanying drawing used in embodiment
It is briefly described:
Fig. 1 is that the roadbed concrete guardrail of the present invention recycles the schematic diagram of construction method step (1) process
Fig. 2 is that the roadbed concrete guardrail of the present invention recycles the schematic diagram of construction method step (2) process
Fig. 3 is that the roadbed concrete guardrail of the present invention recycles the schematic diagram of construction method step (3) process
Fig. 4 is that the roadbed concrete guardrail of the present invention recycles the schematic diagram of the step of construction method one (4) installation leveling layer
The roadbed concrete guardrail that Fig. 5 is the present invention recycles the step of construction method one (4) to recycle showing for guardrail installation
It is intended to
The roadbed concrete guardrail that Fig. 6 is the present invention recycles the step of construction method one (4) to recycle guardrail integrally to illustrate
Figure
The roadbed concrete guardrail that Fig. 7 is the present invention recycles the step of construction method two (4) to mat formation the signal of highway surface layer
Figure
Fig. 8 is that the roadbed concrete guardrail of the present invention recycles the schematic diagram of the step of construction method two (4) installation leveling layer
The roadbed concrete guardrail that Fig. 9 is the present invention recycles the step of construction method two (4) to recycle showing for guardrail installation
It is intended to
Figure 10 is that the roadbed concrete guardrail of the present invention recycles the schematic diagram of the step of construction method two (4) installation support block
The roadbed concrete guardrail that Figure 11 is the present invention recycles the step of construction method two (4) to recycle guardrail integrally to illustrate
Figure
The roadbed concrete guardrail that Figure 12 is the present invention recycles construction method construction process figure.
Marked in figure as follows:
1. concrete precast block, 2. is longitudinally connected, 3. preburied components, 4. support blocks, 5. highway surface layers, 6. leveling blocks, and 7.
Sub-surface, 8. affiliated facilities, 9. mounting grooves.
Embodiment
With reference to test example and embodiment, the present invention is described in further detail.But this should not be managed
The scope solved as the above-mentioned theme of the present invention is only limitted to following embodiment, every to be belonged to based on the technology that present invention is realized
The scope of the present invention.
Embodiment 1
Figure 12 is roadbed concrete guardrail recycling construction method flow chart, and its specific implementation process is as follows:
(1) roadbed concrete temporary guard rail makes:
Formwork casting concrete prefabricated section 1, guardrail reinforcing bar built in concrete precast block 1 and longitudinally connected 2 preburied component
3, when the two position conflicts, it should ensure that the position of preburied component 3 is constant, suitably adjust reinforcement location.Concrete precast block 1 pours
Build must strict control, strictly observe drawing requirement construction, longitudinally connected 2 preburied component 3 should ensure that position is accurate.Obtain
The structure of concrete precast block 1 such as Fig. 1.
(2) roadbed concrete temporary guard rail is installed:
Such as Fig. 2, concrete precast block 1 carries out assembly after being transported to scene, and adjustment is linear, connection longitudinally connected 2, and composition is interim
Guardrail, road surface is lain against, it is connectionless with road surface.
(3) roadbed concrete temporary guard rail is removed:
Such as Fig. 3, first open longitudinally connected the 2 of concrete precast block 1, then remove concrete precast block 1 standby, tear open
Except process should ensure that concrete precast block 1 is not destroyed with preburied component 3;
(4) the recycling installation of roadbed concrete guardrail:
Mode one, after paved road basic unit 7, line setting, leveling layer 6 is installed, such as Fig. 4;It is pre- that standby concrete is installed
Clamp dog 1, adjustment is linear, and completes longitudinally connected 2, such as Fig. 5;The installation cross-brace block 4 at the back of concrete precast block 1;Installation
Guardrail associated satellite facility 8;Finally mat formation highway surface layer 5, such as Fig. 6, complete a point band guardrail in roadbed and install.
Mode two, after paved road basic unit 7, then in strict accordance with drawing and combined concrete prefabricated on sub-surface 7
The actual size of block 1 carries out line setting, reserves the position of mounting groove 9, highway surface layer 5 of mating formation afterwards, such as Fig. 7;At the bottom of mounting groove 9
Leveling layer 6 is installed in portion, such as Fig. 8;Standby concrete precast block 1 is positioned in mounting groove 9, adjustment is linear, and completes longitudinal direction
Connection 2, such as Fig. 9;The installation cross-brace block 4 at the back of concrete precast block 1, such as Figure 10;Finally installation guardrail associated satellite is set
8 are applied, such as Figure 11, a point band guardrail in roadbed is completed and installs.
Leveling layer 6 should match somebody with somebody construction muscle when sufficiently large, prevent leveling layer 6 to be broken, and influence guardrail installation.
Support block 4 can be any structure type, and cross-brace effect is played between guardrail.
Support block 4 firmly must make guardrail entirety stress with longitudinally connected 2.
Claims (7)
1. roadbed concrete guardrail recycles construction method, it is characterised in that the roadbed concrete guardrail recycles construction party
Method step is as follows:
(1) prefabricated fabrication of concrete prefabricated section (1);
(2) concrete precast block (1) is assembled, and adjustment is linear, connection longitudinal connecting component (2), forms temporary guard rail;
(3) when dismantling guardrail, longitudinal connecting component (2) is first opened, is then removed concrete precast block (1) standby;
(4) concrete precast block (1) is recycled and is installed as in roadbed a point band guardrail.
2. roadbed concrete guardrail according to claim 1 recycles construction method, it is characterised in that the step (1):
Guardrail reinforcing bar built in concrete precast block (1) and the preburied component (3) of longitudinally connected (2), when the two position conflicts, should ensure that
Preburied component (3) position is constant, suitably adjusts reinforcement location.
3. roadbed concrete guardrail according to claim 1 recycles construction method, it is characterised in that the step (2):
Road surface is lain against behind longitudinally connected (2) between connection concrete precast block (1), concrete precast block (1) and road surface are connectionless.
4. roadbed concrete guardrail according to claim 1 recycles construction method, it is characterised in that the step (3):
Can not be to concrete precast block (1) and preburied component during opening connecting elements (2) and removing concrete precast block (1)
(3) transition is caused to damage.
5. roadbed concrete guardrail according to claim 1 recycles construction method, it is characterised in that the step (4):
After paved road basic unit (7), line setting, installation leveling layer (6), installation concrete precast block (1), adjustment is linear, and completes
Longitudinally connected (2), in concrete precast block (1) back installation cross-brace block (4), guardrail associated satellite facility (8) is installed, most
After mat formation highway surface layer (5).
6. roadbed concrete guardrail according to claim 1 recycles construction method, it is characterised in that the step (4):
After paved road basic unit (7), line setting, mounting groove (9) is reserved, highway surface layer (5) of mating formation afterwards, at mounting groove (9) bottom
Portion's installation leveling layer (6), standby concrete precast block (1) is positioned in mounting groove (9), adjustment is linear, and completes longitudinal direction
Connect (2), in concrete precast block (1) back installation cross-brace block (4), guardrail associated satellite facility (8) is finally installed.
7. the roadbed concrete guardrail according to claim 5 or 6 recycles construction method, it is characterised in that:The leveling
Layer (6) should match somebody with somebody construction muscle when excessive.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610422468.9A CN107513963A (en) | 2016-06-16 | 2016-06-16 | A kind of roadbed concrete guardrail recycles construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610422468.9A CN107513963A (en) | 2016-06-16 | 2016-06-16 | A kind of roadbed concrete guardrail recycles construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107513963A true CN107513963A (en) | 2017-12-26 |
Family
ID=60719830
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610422468.9A Pending CN107513963A (en) | 2016-06-16 | 2016-06-16 | A kind of roadbed concrete guardrail recycles construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107513963A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110195419A (en) * | 2019-06-28 | 2019-09-03 | 山东省交通规划设计院 | A kind of concrete guardrail structure and its construction method |
CN111206528A (en) * | 2020-02-26 | 2020-05-29 | 安徽省交通控股集团有限公司 | Mechanical device for improving installation precision of concrete guardrail |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2011014131A1 (en) * | 2009-07-25 | 2011-02-03 | VÁHOSTAV-SK-PREFA, s. r. o. | Sliding precast reinforced concrete barrier with a cam lock |
CN102392426A (en) * | 2011-10-14 | 2012-03-28 | 东南大学 | Separated concrete barrier with longitudinal connection capable of moving rapidly and manufacturing method thereof |
CN202809533U (en) * | 2012-07-03 | 2013-03-20 | 武汉理工大学 | Precast hollow concrete protective guard for rural highway |
CN104612086A (en) * | 2015-02-15 | 2015-05-13 | 北京中路安交通科技有限公司 | Concrete road barrier wall and road barrier with same |
JP5788840B2 (en) * | 2012-08-09 | 2015-10-07 | ケイコン株式会社 | Continuous partition structure and construction method thereof |
CN204753446U (en) * | 2015-02-13 | 2015-11-11 | 徐州百斯特护栏科技有限公司 | Concrete equipment guardrail |
-
2016
- 2016-06-16 CN CN201610422468.9A patent/CN107513963A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2011014131A1 (en) * | 2009-07-25 | 2011-02-03 | VÁHOSTAV-SK-PREFA, s. r. o. | Sliding precast reinforced concrete barrier with a cam lock |
CN102392426A (en) * | 2011-10-14 | 2012-03-28 | 东南大学 | Separated concrete barrier with longitudinal connection capable of moving rapidly and manufacturing method thereof |
CN202809533U (en) * | 2012-07-03 | 2013-03-20 | 武汉理工大学 | Precast hollow concrete protective guard for rural highway |
JP5788840B2 (en) * | 2012-08-09 | 2015-10-07 | ケイコン株式会社 | Continuous partition structure and construction method thereof |
CN204753446U (en) * | 2015-02-13 | 2015-11-11 | 徐州百斯特护栏科技有限公司 | Concrete equipment guardrail |
CN104612086A (en) * | 2015-02-15 | 2015-05-13 | 北京中路安交通科技有限公司 | Concrete road barrier wall and road barrier with same |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110195419A (en) * | 2019-06-28 | 2019-09-03 | 山东省交通规划设计院 | A kind of concrete guardrail structure and its construction method |
CN111206528A (en) * | 2020-02-26 | 2020-05-29 | 安徽省交通控股集团有限公司 | Mechanical device for improving installation precision of concrete guardrail |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101294447B (en) | Buildings pile underpinning method | |
CN109610263B (en) | Construction method of assembled construction access road | |
CN211144503U (en) | High steep topography bridge tunnel meets section open cut tunnel and connects long structure | |
CN107513939A (en) | A kind of bridge concrete guardrail recycles construction method | |
JP5843413B1 (en) | Lowering method of existing tunnel | |
CN106702912A (en) | Construction method of dismantling old beam top and introducing new bridge on existing railway | |
CN107513963A (en) | A kind of roadbed concrete guardrail recycles construction method | |
JP3893056B2 (en) | Construction method of underground structure | |
CN112921986A (en) | Assembled underground structure and integrated construction method of assembled underground structure and foundation pit | |
JP3789100B2 (en) | How to build a widening tunnel | |
JP6144726B2 (en) | Rehabilitation method for mountain road tunnels on expressway and suspension pier for rehabilitation method | |
JP2612599B2 (en) | How to repair the median strip | |
CN110700116A (en) | Overpass reverse construction method suitable for loess area | |
CN112663431B (en) | Concrete pavement fracture subsidence section treatment structure and construction method | |
CN108343085A (en) | The subway work method of major urban arterial highway | |
KR100782551B1 (en) | abutment construction method was used prefab abutment block | |
CN111501468A (en) | Fabricated road structure and construction process | |
CN111364509A (en) | Construction method for underground space below existing road | |
CN108149570A (en) | Across the railroad bridge roadside barrier of one kind strengthens construction method | |
CN111305078A (en) | Construction method of prefabricated concrete arch channel bridge | |
CN216892163U (en) | Highway roadside safety protection and reinforcement system with limited space | |
KR100411311B1 (en) | Method of Expanding Road Using Reinforced Soil Retaining Wall | |
CN117386384A (en) | Temporary blocking structure of shield borehole hole and construction method | |
CN220598863U (en) | Assembled coincide roof structure of station is dug to subway lid | |
KR100274747B1 (en) | Method for installation of electric pole and supporting device of the same |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171226 |
|
RJ01 | Rejection of invention patent application after publication |