CN107513939A - A kind of bridge concrete guardrail recycles construction method - Google Patents

A kind of bridge concrete guardrail recycles construction method Download PDF

Info

Publication number
CN107513939A
CN107513939A CN201610422402.XA CN201610422402A CN107513939A CN 107513939 A CN107513939 A CN 107513939A CN 201610422402 A CN201610422402 A CN 201610422402A CN 107513939 A CN107513939 A CN 107513939A
Authority
CN
China
Prior art keywords
guardrail
concrete
bridge
construction method
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610422402.XA
Other languages
Chinese (zh)
Inventor
李卫民
敬敏
吴玉财
滕玉禄
黄正昌
杨福宇
苏敏
闫书明
严琪
亢寒晶
钟纯耀
蒋鹏飞
梁文献
龚帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG HIGHWAY CO Ltd
Beijing Hualuan Traffic Technology Co Ltd
Original Assignee
GUANGDONG HIGHWAY CO Ltd
Beijing Hualuan Traffic Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG HIGHWAY CO Ltd, Beijing Hualuan Traffic Technology Co Ltd filed Critical GUANGDONG HIGHWAY CO Ltd
Priority to CN201610422402.XA priority Critical patent/CN107513939A/en
Publication of CN107513939A publication Critical patent/CN107513939A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/103Parapets, railings ; Guard barriers or road-bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention relates to bridge concrete guardrail to recycle construction method, belongs to traffic safety protection field, it is comprised the following steps that:(1) processing factory's precast concrete guardrail.(2) in-situ layer bar-mat reinforcement is arranged in bridge floor.(3) part in-situ layer and block are poured.(4) concrete precast block is installed.(5) anchor bar and the pre-buried anchor slab of concrete wall are welded.(6) guardrail root mortar bridge deck pavement is poured, remaining bridge deck pavement is poured with pitch.(7) when needing to dismantle guardrail, guardrail basis is removed and removes guardrail.(8) when reusing guardrail, original guardrail is installed according to above-mentioned (2)~(6) construction method.Construction method of the present invention is simple, reasonable, construction is easy; it can be good at being reused bridge concrete guardrail; being one for reconstruction and extension project reduces cost, simplifies the mode of construction, while also complies with the engineering construction theory of " resources conservation and environmental protection ".

Description

A kind of bridge concrete guardrail recycles construction method
Technical field
The present invention relates to bridge concrete guardrail to recycle construction method, belongs to traffic safety protection field.
Background technology
In recent years, China's expressway construction is fast-developing, and highway builds up and runed the trip for greatly facilitating the masses and various regions on the way Economic development.But with the rapid growth of China's economy and flourishing for highway transportation cause, the volume of traffic increases rapidly, particularly large-scale heavy duty car Increase, directly result in the increase of highway communication facility frequency of use and load, the highway much built in early days can not adapt at present The operation demand of the volume of traffic, according to incompletely statistics, in the highway built before 2004, about 30,000 kilometers have been enter into reorganization and expansion rank Section.
At present, concrete guardrail manufacture craft is divided into cast-in-place and prefabricated, precast concrete guardrail foundation anchor power Shortcomings, causes guardrail protective Can be relatively low, it is poor to oversize vehicle protection, bridge section should not be applied to;Cast-in-situ bridge concrete guardrail concrete foundation is connected firmly, and can reach Compared with high-protection level, but construction method is complex, is not easy to site operation, and it is usually that destructiveness is removed to be removed after installing, not reproducible utilization.
Based on this, propose that a kind of bridge concrete guardrail recycles construction method.
The content of the invention
The present invention proposes that a kind of bridge concrete guardrail recycles construction method, bridge concrete guardrail is had cast in place process guardrail function of safety protection concurrently Locomotive function is conveniently removed with precasting process guardrail, realizes that the repetition of guardrail recycles, the temporary guard rail that can be applied not only in reconstruction and extension project, also Newly building bridge is applicable to, the service life of bridge concrete guardrail is greatly extended, reduces the waste of material in engineering construction, meet " resource The engineering construction theory of saving and environmental protection ".
To achieve the above object, technical scheme is as follows:
The bridge concrete guardrail recycles construction method specific steps:
(1) concrete precast block is prefabricated pours;
(2) transverse steel in bridge floor in-situ layer and the longitudinal reinforcement in non-construction groove in-situ layer and shearing resistance block are arranged;
(3) non-construction groove in-situ layer and shearing resistance block and reserved construction groove are poured;
(4) concrete precast block is installed on the non-construction groove in-situ layer of shearing resistance block side, and makes the pre-buried reserved construction groove of anchor slab side direction, Then it is longitudinally connected between connection concrete precast block;
(5) arrange anchor bar in reserved construction groove and weld its one end and pre-buried anchor slab, by the other end and in-situ layer of anchor bar Transverse steel welds, longitudinal reinforcement in the groove in-situ layer of arrangement construction afterwards;
(6) pouring construction groove in-situ layer, paved layer is poured using mortar, pitch pours bridge deck pavement;
(7) guardrail dismantle when, remove guardrail basis connection and it is longitudinally connected, remove concrete precast block;
(8) it is according to above-mentioned (2)~(6) step that the connection of original guardrail basis is upper when recycling concrete precast block.
Further, the step (1):Pre-buried dowel, pre-buried anchor slab and longitudinally connected pre-buried part, pre-buried dowel built in concrete precast block Two-sided welding is used with pre-buried anchor slab, and pre-buried anchor slab side is exposed outside concrete precast block;
Further, first pre-buried anchor slab and longitudinally connected preburied component are positioned, then by the main body reinforcing bar point in pre-buried dowel and concrete precast block Weldering, last casting concrete prefabricated section;
Further, the step (4):It is consistent that concrete precast block will adjust alignment coordination when installing, avoid the occurrence of be uneven, front and rear projection Situation, adjust it is linear after reconnect it is longitudinally connected;
Further, the step (5):Anchor bar carries out two-sided welding with pre-buried anchor slab exposed lateral side, and anchor bar and transverse steel are spot welding.
Further, the step (6):Before paved layer pours, preservative treatment is carried out to pre-buried anchor slab and anchor bar.
Further, the step (7):Paved layer is cut using electric hammer, and anchor bar is cut off to remove guardrail base using flame cutter Plinth connects, and can not destroy concrete prefabricated block main body during construction.
Further, the step (8):When basis connection is carried out to concrete precast block again, anchor bar and the original that staggers during the welding of pre-buried anchor slab Welding position.
Compared with prior art, beneficial effects of the present invention
The bridge concrete guardrail of the present invention recycles construction method, enhances bridge concrete guardrail reuse ratio, and general general work will soon be grasped Work progress, easy construction, cost-effective, environmental protection.
The bridge concrete guardrail of the present invention recycles construction method, does not destroy guardrail wall body structure in work progress, ensure that integrality and intensity.
The bridge concrete guardrail of the present invention recycles construction method, and pre-buried anchor slab can be used for multiple times, service life length, easy to maintain.
Brief description of the drawings
In order to illustrate more clearly of the technical scheme of patent of the present invention, the required accompanying drawing used in embodiment will be briefly described below:
Fig. 1 is that the bridge concrete guardrail of the present invention recycles the schematic diagram of construction method step (1) process
Fig. 2 is that the bridge concrete guardrail of the present invention recycles the schematic diagram of construction method step (2) process
Fig. 3 is that the bridge concrete guardrail of the present invention recycles the schematic diagram of construction method step (3) process
Fig. 4 is that the bridge concrete guardrail of the present invention recycles the schematic diagram of construction method step (4) process
Fig. 5 is that the bridge concrete guardrail of the present invention recycles the schematic diagram of construction method step (5) process
Fig. 6 is that the bridge concrete guardrail of the present invention recycles the schematic diagram of construction method step (6) process
Fig. 7 is that the bridge concrete guardrail of the present invention recycles the schematic diagram of construction method step (7) process
Fig. 8 is that the bridge concrete guardrail of the present invention recycles the schematic diagram of construction method step (8) process
The bridge concrete guardrail that Fig. 9 is the present invention recycles construction method construction process figure.
Marked in figure as follows:
1. concrete precast block, 2. pre-buried dowels, 3. pre-buried anchor slabs, 4. is longitudinally connected, 5. anchor bars, 6. shearing resistance blocks, 7. paved layers, 8. bridge deck pavement, 9. in-situ layers (the non-construction groove in-situ layers of 9a., 9b. construction grooves in-situ layer), (10a. transverse steels, 10b. are indulged 10. bar-mat reinforcements To reinforcing bar), 11. beam slabs.
Embodiment
With reference to test example and embodiment, the present invention is described in further detail.But this should not be interpreted as to the above-mentioned theme of the present invention Scope be only limitted to following embodiment, it is every that the scope of the present invention is belonged to based on the technology that present invention is realized.
Embodiment 1
If Fig. 9 is that bridge concrete guardrail recycles construction method flow chart.
The making of recycling bridge concrete guardrail and the implementation installed first are carried out first.
(1) first concrete precast block 1 carry out it is prefabricated, to the main body reinforcing bar of concrete precast block 1, pre-buried anchor slab 3, pre-buried dowel 2 and longitudinal direction Connection 4 is positioned, and pre-buried anchor slab 3 and pre-buried dowel 2 carry out two-sided welding, main body reinforcing bar and the pre-buried spot welding of dowel 2, then casting concrete, And notice that the pre-buried side of anchor slab 3 will be exposed to outside concrete precast block 1, as shown in Figure 1;
(2) the transverse steel 10a in bridge floor in-situ layer 9, vertical in non-construction groove in-situ layer 9a and shearing resistance block 6 is arranged by the way of the colligation To reinforcing bar 10b, as shown in Figure 2;
(3) non-construction groove in-situ layer 9a and shearing resistance block 6 are poured, forms reserved construction groove, as shown in Figure 3;
(4) after concrete precast block 1 is transported to scene, installation concrete precast block 1 on shearing resistance block 6 is positioned at by lifting, and make pre-buried anchor slab Towards reserved construction groove, concrete precast block 1 will adjust that alignment coordination is consistent when installing for 3 sides, avoid the occurrence of be uneven, front and rear raised feelings Condition, then connection square steel tube in back is installed, connect longitudinally connected 4 between concrete precast block 1, so as to form guardrail entirety, as shown in Figure 4;
(5) arrange anchor bar 5 in reserved construction groove and its one end and the pre-buried exposed lateral side of anchor slab 3 are subjected to two-sided welding, by anchor bar 5 The other end and in-situ layer 9 in transverse steel 10a spot welding, longitudinal reinforcement 10b in the groove in-situ layer 9b of arrangement construction afterwards, as shown in Figure 5;
(6) preservative treatment is carried out to pre-buried anchor slab 3 and anchor bar 5, pouring construction groove in-situ layer 9b, paved layer 7 is poured using mortar, Pitch pours bridge deck pavement 8, as shown in Figure 6.
What secondly the recycling bridge concrete guardrail of progress reused removes and installs implementation.
(7) connection of guardrail basis is removed, mortar pave-load layer 7 is removed using small electric hammer quartering chisel, and anchor bar 5 is cut off using flame cutter, is solved Except longitudinally connected 4, concrete precast block 1 is removed, as shown in fig. 7, paying attention to that during construction the main body of concrete precast block 1 can not be destroyed;
(8) again install concrete precast block 1, according to above-mentioned (2)~(6) step connection guardrail basis, although note that anchor bar 5 with it is pre-buried Anchor slab 3 staggers former welding position when welding, as shown in Figure 8.

Claims (8)

1. bridge concrete guardrail recycles construction method, it is characterised in that the bridge concrete guardrail recycles construction method to comprise the following steps that:
(1) concrete precast block (1) is prefabricated pours;
(2) transverse steel (10a) in bridge floor in-situ layer (9) and the longitudinal reinforcement (10b) in non-construction groove in-situ layer (9a) and shearing resistance block (6) are arranged;
(3) non-construction groove in-situ layer (9a) and shearing resistance block (6) and reserved construction groove are poured;
(4) concrete precast block (1) is installed on the non-construction groove in-situ layer (9a) of shearing resistance block (6) side, and pre-buried anchor slab (3) side is set then to connect longitudinally connected (4) between concrete precast block (1) towards reserved construction groove;
(5) arrange anchor bar (5) in reserved construction groove and weld its one end and pre-buried anchor slab (3), transverse steel (10a) in the other end of anchor bar (5) and in-situ layer (9) is welded, groove in-situ layer (9b) the interior longitudinal reinforcement (10b) of arrangement construction afterwards;
(6) pouring construction groove in-situ layer (9b), paved layer (7) is poured using mortar, pitch pours bridge deck pavement (8);
(7) when guardrail is dismantled, the connection of guardrail basis and longitudinally connected (4) is removed, remove concrete precast block (1);
(8) it is according to above-mentioned (2)~(6) step that the connection of original guardrail basis is upper when recycling concrete precast block (1).
2. bridge concrete guardrail according to claim 1 recycles construction method, it is characterised in that the step (1):The pre-buried part of pre-buried dowel (2), pre-buried anchor slab (3) and longitudinally connected (4) built in concrete precast block (1), pre-buried dowel (2) and pre-buried anchor slab (3) use two-sided welding, pre-buried anchor slab (3) side it is exposed in concrete precast block (1) outside.
3. bridge concrete guardrail according to claim 2 recycles construction method, it is characterised in that:First the preburied component of pre-buried anchor slab (3) and longitudinally connected (4) is positioned, then by the main body reinforcing bar spot welding in pre-buried dowel (2) and concrete precast block (1), last casting concrete prefabricated section (1).
4. bridge concrete guardrail according to claim 1 recycles construction method, it is characterised in that the step (4):Concrete precast block (1) will adjust that alignment coordination is consistent when installing, avoid the occurrence of be uneven, front and rear raised situation, adjust it is linear after reconnect longitudinally connected (4).
5. bridge concrete guardrail according to claim 1 recycles construction method, it is characterised in that the step (5):Anchor bar (5) carries out two-sided welding with pre-buried anchor slab (3) exposed lateral side, and anchor bar (5) and transverse steel (10a) are spot welding.
6. bridge concrete guardrail according to claim 1 recycles construction method, it is characterised in that the step (6):Before paved layer (7) pours, preservative treatment is carried out to pre-buried anchor slab (3) and anchor bar (5).
7. bridge concrete guardrail according to claim 1 recycles construction method, it is characterised in that the step (7):Paved layer (7) is cut using electric hammer, and using flame cutter cuts off anchor bar (5) to remove the connection of guardrail basis, concrete precast block (1) main body can not be destroyed during construction.
8. bridge concrete guardrail according to claim 1 recycles construction method, it is characterised in that the step (8):When basis connection is carried out to concrete precast block (1) again, anchor bar (5) and former welding position of staggering during pre-buried anchor slab (3) welding.
CN201610422402.XA 2016-06-16 2016-06-16 A kind of bridge concrete guardrail recycles construction method Pending CN107513939A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610422402.XA CN107513939A (en) 2016-06-16 2016-06-16 A kind of bridge concrete guardrail recycles construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610422402.XA CN107513939A (en) 2016-06-16 2016-06-16 A kind of bridge concrete guardrail recycles construction method

Publications (1)

Publication Number Publication Date
CN107513939A true CN107513939A (en) 2017-12-26

Family

ID=60720580

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610422402.XA Pending CN107513939A (en) 2016-06-16 2016-06-16 A kind of bridge concrete guardrail recycles construction method

Country Status (1)

Country Link
CN (1) CN107513939A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867480A (en) * 2018-07-16 2018-11-23 广州市市政工程设计研究总院有限公司 A kind of prefabricated assembled FRP tendons material concrete side crashproof guardrail of steel plate connection
CN109750598A (en) * 2018-12-18 2019-05-14 中交第一航务工程局有限公司 A kind of readily removable New Jersey safety barrier structure and construction method removed
CN110453600A (en) * 2019-07-26 2019-11-15 中交公路规划设计院有限公司 Bridge guardrail prefabricated unit, Bridge guardrail construction method and bridge
CN113293700A (en) * 2021-05-08 2021-08-24 南京交通职业技术学院 Urban bridge L-shaped marble railing and design and construction method
CN113463682A (en) * 2021-05-27 2021-10-01 中铁十九局集团第三工程有限公司 Corrugated plate retaining wall structure and construction method thereof
CN114673083A (en) * 2022-05-25 2022-06-28 中铁上海设计院集团有限公司 Road U-shaped groove structure with anti-collision effect and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1347771A (en) * 1970-04-03 1974-02-27 Etat Francais Ministere De Leq Safety barrier
CN202148503U (en) * 2011-05-05 2012-02-22 北京道从交通科技有限公司 Saddle type combined guardrail structure
CN102619173A (en) * 2012-04-25 2012-08-01 中铁大桥局集团第五工程有限公司 Construction method of large bridge steel guardrail concrete base
CN203284750U (en) * 2013-06-07 2013-11-13 上海市城市建设设计研究总院 Cast-in-place concrete anti-collision guardrail
CN203320414U (en) * 2013-06-08 2013-12-04 北京中路安交通科技有限公司 Detachable concrete bridge guardrail
CN204849649U (en) * 2015-05-29 2015-12-09 交通运输部公路科学研究所 Guardrail

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1347771A (en) * 1970-04-03 1974-02-27 Etat Francais Ministere De Leq Safety barrier
CN202148503U (en) * 2011-05-05 2012-02-22 北京道从交通科技有限公司 Saddle type combined guardrail structure
CN102619173A (en) * 2012-04-25 2012-08-01 中铁大桥局集团第五工程有限公司 Construction method of large bridge steel guardrail concrete base
CN203284750U (en) * 2013-06-07 2013-11-13 上海市城市建设设计研究总院 Cast-in-place concrete anti-collision guardrail
CN203320414U (en) * 2013-06-08 2013-12-04 北京中路安交通科技有限公司 Detachable concrete bridge guardrail
CN204849649U (en) * 2015-05-29 2015-12-09 交通运输部公路科学研究所 Guardrail

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
苏高裕: "可拆装混凝土桥梁护栏基础及纵向连接结构形式研究", 《广东公路交通》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867480A (en) * 2018-07-16 2018-11-23 广州市市政工程设计研究总院有限公司 A kind of prefabricated assembled FRP tendons material concrete side crashproof guardrail of steel plate connection
CN108867480B (en) * 2018-07-16 2024-01-23 广州市市政工程设计研究总院有限公司 Steel plate connection prefabricated FRP rib concrete side anti-collision guardrail
CN109750598A (en) * 2018-12-18 2019-05-14 中交第一航务工程局有限公司 A kind of readily removable New Jersey safety barrier structure and construction method removed
CN110453600A (en) * 2019-07-26 2019-11-15 中交公路规划设计院有限公司 Bridge guardrail prefabricated unit, Bridge guardrail construction method and bridge
CN110453600B (en) * 2019-07-26 2024-05-17 中交公路规划设计院有限公司 Bridge guardrail prefabricated unit, bridge guardrail construction method and bridge
CN113293700A (en) * 2021-05-08 2021-08-24 南京交通职业技术学院 Urban bridge L-shaped marble railing and design and construction method
CN113463682A (en) * 2021-05-27 2021-10-01 中铁十九局集团第三工程有限公司 Corrugated plate retaining wall structure and construction method thereof
CN114673083A (en) * 2022-05-25 2022-06-28 中铁上海设计院集团有限公司 Road U-shaped groove structure with anti-collision effect and construction method
CN114673083B (en) * 2022-05-25 2023-12-22 中铁上海设计院集团有限公司 Highway U-shaped groove structure with anti-collision effect and construction method

Similar Documents

Publication Publication Date Title
CN107513939A (en) A kind of bridge concrete guardrail recycles construction method
CN105386405B (en) Based on bolted Precast Concrete Segmental Bridges concrete pier of steel tube
CN210975404U (en) Composite assembled road surface board
CN105256947A (en) Method for constructing recycled mixed concrete beams and slabs
CN102203346A (en) Construction method of steel composite girder bridge
CN111877182B (en) Novel construction method for upper structure of multi-chamber continuous UHPC box girder bridge
CN206428551U (en) A kind of repeatable assembled engagement temporary pavement plate utilized of monoblock type
CN102995746B (en) Beam slab node of renewable hybrid combined floor slab made of U-shaped steel-encased renewable hybrid beam and construction method thereof
CN105672144B (en) A kind of medium-small span bridges are reinforced with spelling wide structure and its construction method
CN107806101A (en) Construction method of the bar shaped foundation ditch cast-in-place concrete to the prefabricated linking beam of support
CN211312247U (en) Prestressed steel strand reinforcing device additionally arranged in hollow plate hinge joint space
CN110863597A (en) Prefabricated floor slab crack prevention and repair method for assembly type steel frame laminated slab factory building
CN105648889B (en) reinforced concrete T-beam bridge and construction method thereof
CN209227836U (en) Prefabricated concrete structure wall-column all steel is keyed structure
CN110552706A (en) Permanent-temporary combined shield hoisting hole sealing structure and method
CN109281422A (en) Prefabricated concrete structure wall-column all steel key connection structure and assembling method
CN106337530B (en) A kind of construction of frame beam seams stifled construction method
KR101270947B1 (en) Deck repairing construction method of bridge using precast concrete slab
CN103850162A (en) Bridge type combined-structure road surface system and construction method thereof
CN205443897U (en) Reinforced concrete T beam bridge
CN205711786U (en) Big cross section porous overlength cast-in-place box culvert formwork system
CN211900603U (en) Face combination shield structure hole of hoist enclosed construction forever
CN113356405A (en) Prefabricated composite wall structure based on embedded profile steel and construction method thereof
CN114561873A (en) Bridge high pier construction method
CN211472128U (en) Continuity combination beam

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171226