CN107503346A - PHC tubular pile head method for repairing damage - Google Patents
PHC tubular pile head method for repairing damage Download PDFInfo
- Publication number
- CN107503346A CN107503346A CN201610419625.0A CN201610419625A CN107503346A CN 107503346 A CN107503346 A CN 107503346A CN 201610419625 A CN201610419625 A CN 201610419625A CN 107503346 A CN107503346 A CN 107503346A
- Authority
- CN
- China
- Prior art keywords
- pile
- punching block
- steel mould
- outer steel
- interior punching
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/64—Repairing piles
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
A kind of PHC tubular pile heads method for repairing damage, it is characterised in that comprise the following steps:A, damaged pile crown is amputated by design requirement;B, outer steel mould is made(2), interior punching block(3)And ring flange(4), the outer steel mould of making and interior punching block are fitted in pile body outer wall and inwall respectively, c, by mixture of epoxy resins(5)It is filled into the space that outer steel mould and interior punching block surround, d, ring flange 4 and outer steel mould by making(2)And interior punching block(3)Upper end is welded and fixed, and completes the damaged reparation of PHC tubular pile heads.The PHC tubular pile head method for repairing damage of the present invention has prosthetic device simple in construction, easy to make, operation is convenient, safe and reliable, keeps original hollow-core construction, the advantages of not increasing piling construction pile inner air pressure, also there is wide applicability, available for PC pile tubes, PTC pile tubes.
Description
Technical field
It is a kind of PHC tubular pile heads method for repairing damage specifically the present invention relates to a kind of damaged reparation of the pile tube in civil engineering.
Background technology
At present, method for repairing and mending generally cuts off damaged part post-grouting filler after tubular pile head breakage, but this kind of method has many deficiencies, and one is increased pile tube casting effect, surrounding stake displacement increase;Second, repair time is grown, then difficulty of construction increase;Third, rehabilitation expense is higher.Fig. 1 is the schematic diagram of known damaged pile crown.
Chinese patent CN105274986A discloses a kind of pile sinking pile crown method for repairing damage of PHC pile tubes on January 27th, 2016, including following steps:1)Cut stake;2)New stake end plate is installed;3)Basetray is installed;4)Stake outer wrapping plate is installed;5)Rubble and sand are inserted;6)Mix and blend thing pours into;7)The plate surface polishing of stake termination;8)Secondary piling construction.The lower end of blast pipe 5 is first passed vertically through basetray 4 and is welded and fixed by the technical scheme as basetray 4, steel pipe using steel plate in repairing as blast pipe 5.This technical scheme is although make the pile sinking pile crown of PHC pile tubes is damaged to repair, but problem is following, basetray therein has shut the original hollow-core construction of pile tube, is only substituted with tiny blast pipe 5, increase piling construction pile inner air pressure, thus derive a series of construction problem.
Therefore the pile sinking pile crown method for repairing damage of known PHC pile tubes there are problems that above-mentioned a variety of inconvenience and.
The content of the invention
The purpose of the present invention, it is to propose a kind of PHC tubular pile head method for repairing damage for keeping the original hollow-core construction of pile tube.
It is a kind of using outer steel mould simple in construction and the PHC tubular pile head method for repairing damage of interior punching block it is another object of the present invention to propose.
To achieve the above object, technical solution of the invention is:
A kind of PHC tubular pile heads method for repairing damage, it is characterised in that comprise the following steps:
A, damaged pile crown is amputated by design requirement;
B, outer steel mould, interior punching block and ring flange are made according to the internal diameter of damaged pile crown and external diameter, the outer steel mould of making and interior punching block is fitted in pile body outer wall and inwall respectively, the gap between outer steel mould and pile body outer wall, interior punching block and pile body inwall is blocked with cement mortar;
C, mixture of epoxy resins is filled into the space that outer steel mould and interior punching block surround;
D, the ring flange of making and outer steel mould and interior punching block upper end are welded and fixed, complete the damaged reparation of PHC tubular pile heads.
The PHC tubular pile heads method for repairing damage of the present invention can also be further achieved by the following technical measures.
Foregoing method, wherein the interior punching block length >=400mm.
Foregoing method, wherein outer steel mould length >=600mm.
Foregoing method, made wherein the outer steel mould, interior punching block and ring flange are steel plate.
After adopting the above technical scheme, the PHC tubular pile head method for repairing damage of the present invention has advantages below:
1st, outer steel mould and interior punching block prosthetic device are simple in construction, easy to make;
2nd, pile crown breakage repairing quality is safe and reliable, and restorative procedure is workable;
3rd, original hollow-core construction is kept, does not increase piling construction pile inner air pressure.
Brief description of the drawings
Fig. 1 is the schematic diagram of known damaged pile crown;
Fig. 2 is the amputation breakage pile crown schematic diagram of the embodiment of the present invention;
Fig. 3 is the schematic diagram of outer steel mould in the installation of the embodiment of the present invention;
Fig. 4 is the schematic diagram of the filling mixture of epoxy resins of the embodiment of the present invention;
Fig. 5 is the schematic diagram of the mounting flange of the embodiment of the present invention, i.e. pile crown after reparation;
Fig. 6 is Fig. 5 top view;
Fig. 7 is Fig. 5 side view.
In figure:1 pile body, 2 outer steel moulds, punching block in 3,4 ring flanges, 5 mixture of epoxy resins, 6 pile crown damaged portions.
Embodiment
With reference to embodiments and its accompanying drawing illustrates further to the present invention.
Embodiment 1
The PHC tubular pile head method for repairing damage of the present invention, comprises the following steps:
A, damaged pile crown is amputated by design requirement.
Referring now to Fig. 2, Fig. 2 is the amputation breakage pile crown schematic diagram of the embodiment of the present invention.
B, outer steel mould 2, interior punching block 3 and ring flange 4 are made according to the internal diameter of damaged pile crown and external diameter, the outer steel mould of making and interior punching block are fitted in pile body outer wall and inwall respectively, the gap between outer steel mould and pile body outer wall, interior punching block and pile body inwall is blocked with cement mortar.Fig. 3 is the schematic diagram of outer steel mould in the installation of the embodiment of the present invention.The long 400mm of interior punching block.The long 600mm of outer steel mould.The outer steel mould(2), interior punching block(3)And ring flange(4)It is that steel plate makes.
C, mixture of epoxy resins 5 is filled into the space that outer steel mould and interior punching block surround.Fig. 4 is the schematic diagram of the filling mixture of epoxy resins of the embodiment of the present invention.
D, the ring flange 4 of making and outer steel mould 2 and the upper end of interior punching block 3 are welded and fixed, complete the damaged reparation of PHC tubular pile heads.Fig. 5 is the schematic diagram of the mounting flange of the embodiment of the present invention, i.e. pile crown after reparation.Fig. 6 is Fig. 5 top view, and Fig. 7 is Fig. 5 side view.
The present invention has substantive distinguishing features and significant technological progress, the PHC tubular pile head method for repairing damage of the present invention has prosthetic device simple in construction, easy to make, operation is convenient, safe and reliable, keeps original hollow-core construction, the advantages of not increasing piling construction pile inner air pressure.The PHC tubular pile heads method for repairing damage of the present invention also has wide applicability, available for PC pile tubes, the damaged reparation of PTC tubular pile heads.
Above example is used for illustrative purposes only, rather than limitation of the present invention, person skilled in the relevant technique, without departing from the spirit and scope of the present invention, can also make various conversion or change.Therefore, all equivalent technical schemes should also belong to scope of the invention, should be limited by each claim.
Claims (4)
1. a kind of PHC tubular pile heads method for repairing damage, it is characterised in that comprise the following steps:
A, damaged pile crown is amputated by design requirement;
B, outer steel mould is made according to the internal diameter of damaged pile crown and external diameter(2), interior punching block(3)And ring flange(4), the outer steel mould of making and interior punching block are fitted in pile body outer wall and inwall respectively, the gap between outer steel mould and pile body outer wall, interior punching block and pile body inwall is blocked with cement mortar;
C, by mixture of epoxy resins(5)It is filled into the space that outer steel mould and interior punching block surround;
D, by the ring flange 4 and outer steel mould of making(2)And interior punching block(3)Upper end is welded and fixed, and completes the damaged reparation of PHC tubular pile heads.
2. PHC tubular pile heads method for repairing damage as claimed in claim 1, it is characterised in that the interior punching block length >=400mm.
3. PHC tubular pile heads method for repairing damage as claimed in claim 1, it is characterised in that the outer steel mould length >=600mm.
4. PHC tubular pile heads method for repairing damage as claimed in claim 1, it is characterised in that the outer steel mould(2), interior punching block(3)And ring flange(4)It is that steel plate makes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610419625.0A CN107503346A (en) | 2016-06-14 | 2016-06-14 | PHC tubular pile head method for repairing damage |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610419625.0A CN107503346A (en) | 2016-06-14 | 2016-06-14 | PHC tubular pile head method for repairing damage |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107503346A true CN107503346A (en) | 2017-12-22 |
Family
ID=60679217
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610419625.0A Pending CN107503346A (en) | 2016-06-14 | 2016-06-14 | PHC tubular pile head method for repairing damage |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107503346A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108149685A (en) * | 2017-12-27 | 2018-06-12 | 福建省大地管桩有限公司 | A kind of pile cover and method of pipe of concrete pile head repairing and reinforcement |
CN109183791A (en) * | 2018-09-10 | 2019-01-11 | 福建宝丰管桩有限公司 | A kind of tubular pile head method for repairing damage |
CN110004964A (en) * | 2019-02-11 | 2019-07-12 | 江苏长风海洋装备制造有限公司 | A kind of single-pile foundation stake top flange Replacement and Repair technique |
CN114232604A (en) * | 2021-12-15 | 2022-03-25 | 深圳市基础工程有限公司 | Reinforced pile cap of tubular pile head and construction method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101748759A (en) * | 2009-12-16 | 2010-06-23 | 江苏建华管桩有限公司 | Method for strengthening and repairing tubular pile head |
CN102900075A (en) * | 2012-01-05 | 2013-01-30 | 云南建工水利水电建设有限公司 | Helical concrete tubular pile device and production method thereof |
CN103276728A (en) * | 2013-05-20 | 2013-09-04 | 福建建华管桩有限公司 | Method for mending and reinforcing pile head |
CN204849752U (en) * | 2015-07-15 | 2015-12-09 | 中国建筑第八工程局有限公司 | Template is repaired to regularization pile head |
CN105274986A (en) * | 2015-10-13 | 2016-01-27 | 中国十七冶集团有限公司 | Pile sinking head damage repairing method of PHC pipe pile |
-
2016
- 2016-06-14 CN CN201610419625.0A patent/CN107503346A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101748759A (en) * | 2009-12-16 | 2010-06-23 | 江苏建华管桩有限公司 | Method for strengthening and repairing tubular pile head |
CN102900075A (en) * | 2012-01-05 | 2013-01-30 | 云南建工水利水电建设有限公司 | Helical concrete tubular pile device and production method thereof |
CN103276728A (en) * | 2013-05-20 | 2013-09-04 | 福建建华管桩有限公司 | Method for mending and reinforcing pile head |
CN204849752U (en) * | 2015-07-15 | 2015-12-09 | 中国建筑第八工程局有限公司 | Template is repaired to regularization pile head |
CN105274986A (en) * | 2015-10-13 | 2016-01-27 | 中国十七冶集团有限公司 | Pile sinking head damage repairing method of PHC pipe pile |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108149685A (en) * | 2017-12-27 | 2018-06-12 | 福建省大地管桩有限公司 | A kind of pile cover and method of pipe of concrete pile head repairing and reinforcement |
CN109183791A (en) * | 2018-09-10 | 2019-01-11 | 福建宝丰管桩有限公司 | A kind of tubular pile head method for repairing damage |
CN110004964A (en) * | 2019-02-11 | 2019-07-12 | 江苏长风海洋装备制造有限公司 | A kind of single-pile foundation stake top flange Replacement and Repair technique |
CN114232604A (en) * | 2021-12-15 | 2022-03-25 | 深圳市基础工程有限公司 | Reinforced pile cap of tubular pile head and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204901197U (en) | Drainage pipe that diameter is 300 -600mm is with local slip casting prosthetic devices | |
CN107503346A (en) | PHC tubular pile head method for repairing damage | |
CN204343285U (en) | A kind of pile foundation pile crown entirety abolishes structure | |
CN203684211U (en) | Pile head processing device of bored pile | |
CN104153295A (en) | Self-compacting concrete jack-up pouring construction method for steel tube arch bridges | |
CN102162255A (en) | Method for reinforcing existing pile foundation in collapsed loess area by slip casting | |
CN104343115A (en) | Structure and method for integrally breaking pile head of pile foundation | |
CN103821141A (en) | Thread pile construction process | |
CN102433878A (en) | Post-grouting device and construction method for pipe pile foundation | |
CN107604902B (en) | Grouting behind shaft or drift lining bored concrete pile and its construction technology | |
KR101751418B1 (en) | Grouting device using a reinforced network is equipped with a small steel pipe | |
CN103276728A (en) | Method for mending and reinforcing pile head | |
CN102561329B (en) | Construction method of underwater concrete cast-in-place pipe pile | |
CN110552371A (en) | Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method | |
CN103938610B (en) | The construction pile pipe of the variable cross-section Reinforced Gravel Pile of a kind of strengthening soft foundation and technique | |
CN106120706A (en) | Foundation-reinforcing device and foundation reinforcement method | |
CN102535446A (en) | Large-cross-section driven-casing cast-in-place post-grouted concrete hollow square pile and production method thereof | |
CN202247897U (en) | Post-grouting device for pipe pile foundation | |
CN108118693B (en) | Construction device for cast-in-situ concrete core cement-soil mixing pile | |
CN208251077U (en) | A kind of positioning constructing device of networking measurement control stake | |
CN103590394B (en) | The construction method of original state soil taking and filling pile | |
CN106087958B (en) | The method of basement process device and basement process | |
JP2013036280A (en) | Method for removing earth retaining member | |
CN105133646A (en) | Underground steel and concrete structure pipeline and manufacturing method thereof | |
CN205502017U (en) | Prevent anti - piecing devices of starching of steel -pipe column on post |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171222 |
|
RJ01 | Rejection of invention patent application after publication |