A kind of petroleum pipeline transport device
Technical field
The present invention relates to a kind of transport device more particularly to a kind of petroleum pipeline transport devices.
Background technique
Petroleum, one of main object of geological prospecting are a kind of sticky, dark brown liquid, referred to as " industrial blood
Liquid ".There are petroleum storage in upper crustal some areas.Main component is the mixture of various alkane, cycloalkane, aromatic hydrocarbon.
Pipeline is connected into pipe, pipe connector and valve etc. for conveying gas, liquid or with solid particle
Fluid device.In general, fluid flows to low pressure from the high pressure of pipeline after the pressurization such as air blower, compressor, pump and boiler
The pressure or gravity conveying of fluid itself can also be used in place.Having many uses for pipeline is general, be used primarily in water supply, draining, heat supply,
It gives gas, in long distance delivery oil and natural gas, agricultural irrigation, hydraulic engineering and various commercial plants.
Under modern economy fast development, the ever-increasing background of the yield of petroleum gas, for the defeated of oil-gas pipeline
Feed technique also proposed higher requirement, however at present petroleum pipeline conveying device on the market be not also it is very perfect, it is current
Petroleum pipeline conveying device can only generally be transported in the horizontal plane, and cannot be conveyed to the ground for having certain slope,
And the surface of also damaged easily petroleum pipeline during transportation.
Therefore needing to research and develop a kind of can also can not only transport in the horizontal plane and transported on the ground for having certain slope
The petroleum pipeline transport device on petroleum pipeline surface will not be damaged in the process, can only be transported in the horizontal plane in the prior art to overcome
It is defeated and transporting petroleum pipeline and petroleum pipeline surface cannot be easily damaged during transportation on the ground for having certain slope
Disadvantage.
Summary of the invention
(1) technical problems to be solved
The present invention in order to overcome can only transport in the horizontal plane in the prior art and cannot be on the ground for having certain slope
The shortcomings that transporting and being easily damaged petroleum pipeline surface during transportation, the technical problem to be solved in the present invention is to provide one
Kind can not only transport in the horizontal plane transporting petroleum pipeline and can also during transportation will not on the ground for having certain slope
Damage the petroleum pipeline transport device on petroleum pipeline surface.
(2) technical solution
It include to place in order to solve the above-mentioned technical problems, the present invention provides such a petroleum pipeline transport device
Frame, the first fixed block, elevating mechanism and driving mechanism are placed with placing frame on ground, it is fixed that first are connected at the top of placing frame
Block, the first fixed block top are connected with elevating mechanism, are connected with driving mechanism in placing frame.
Preferably, elevating mechanism includes bull stick, the first sliding rail, the first sliding block, placement plate, baffle and the first directive wheel,
The first fixed block is connected at the top of placing frame, rotary type is connected with bull stick at the top of the first fixed block, is connected with first on front side of bull stick
Sliding rail, the equal slidingtype in two sides is connected with the first sliding block to the first sliding rail up and down, is connected with placement plate when rotating on the left of the first sliding block,
It is connected with baffle between on the inside of the placement plate of upper and lower two sides, is connected with the first directive wheel at the top of bull stick.
Preferably, driving mechanism includes motor, reel, battery, the first wirerope, the first fixed link and pulling plate,
Right side is equipped with motor in placing frame, and reel is connected on the output shaft of motor, and left side is connected with battery in placing frame, stores
Battery is connect with motor by electric wire connection type, and the first slider top of upside is connected with the first wirerope, the first wirerope
Around the first directive wheel, the first wirerope bottom end is wound on reel, is connected with the first fixed link on the upside of bull stick right wall, and first
Fixed link right wall rotary type is connected with pulling plate.
Preferably, further include have the second sliding rail, the second sliding block, the first spring, the first rubber block, rotating plate, the second rubber block,
The placement plate inside of second fixed link and drawstring, the left and right sides is respectively connected with the second sliding rail, and slidingtype is connected on the second sliding rail
Second sliding block, is respectively connected with the first spring between the second slider bottom and placement plate, the second inner side of slider of the left and right sides turns
Dynamic formula is connected with rotating plate, and the rotating plate bottom of the left and right sides is respectively connected with the second rubber block, is connected with the first rubber block at the top of baffle,
The rotating plate inside top of the left and right sides is respectively connected with the second fixed link, and drawstring is connected in second fixed link in left side, and drawstring is right
End is wound in second fixed link on right side.
Preferably, further include having third fixed link, first connecting rod and headlamp, be connected with third at the top of bull stick and fix
Bar, third fixed link left upper portion are connected with first connecting rod, and first connecting rod bottom left is connected with headlamp.
It preferably, further include having the second fixed block, third fixed block, second spring and inserted link, the rotating plate top right in left side
Side is connected with the second fixed block, and first through hole is provided in the second fixed block, is connected with third fixed block at the top of the rotating plate on right side, the
Three fixed block left lowers are provided with third through-hole, and third fixed block upper right is provided with the second through-hole, is equipped with and inserts in third through-hole
Bar, inserted link pass through the second through-hole, and the left side of inserted link is located in first through hole, on the downside of inserted link right wall and under third fixed block inner right wall
Second spring is connected between side.
It preferably, further include having the second directive wheel, the second connecting rod, third directive wheel and the second wirerope, bull stick right wall
Downside is connected with the second connecting rod, and third directive wheel is connected in the second connecting rod, is connected with the second guiding on the downside of bull stick right wall
Wheel, the second directive wheel are located at below third directive wheel, and the first slider bottom is connected with the second wirerope, and the second wirerope bypasses the
Three directive wheels and the second directive wheel, the second wirerope-winding is on reel.
Working principle: when user of service needs using the device come transporting petroleum pipeline, user of service is by petroleum pipeline
It is placed in placing frame, controls driving mechanism later, driving mechanism will drive elevating mechanism to transport petroleum pipeline.
Because elevating mechanism includes bull stick, the first sliding rail, the first sliding block, placement plate, baffle and the first directive wheel, place
Arch is connected with the first fixed block, and rotary type is connected with bull stick at the top of the first fixed block, is connected with the first sliding rail on front side of bull stick,
The equal slidingtype in two sides is connected with the first sliding block to first sliding rail up and down, is connected with placement plate when rotating on the left of the first sliding block, up and down
It is connected with baffle between on the inside of the placement plates of two sides, is connected with the first directive wheel at the top of bull stick, when needing to transport petroleum pipeline
When to the ground for having certain slope, user of service starts driving mechanism, and driving mechanism will drive the first sliding block upward sliding, thus
Placement plate upward sliding is driven, the petroleum pipeline placed in placement plate can then be transported on the ground on certain slope.
Because driving mechanism includes motor, reel, battery, the first wirerope, the first fixed link and pulling plate, place
Right side is equipped with motor in frame, and reel is connected on the output shaft of motor, and left side is connected with battery, battery in placing frame
It is connect with motor by electric wire connection type, the first slider top of upside is connected with the first wirerope, and the first wirerope bypasses
First directive wheel, the first wirerope bottom end are wound on reel, and the first fixed link is connected on the upside of bull stick right wall, and first is fixed
Bar right wall rotary type is connected with pulling plate, when placement plate to be made carry out petroleum pipeline transport when, user of service enable motor make around
Line wheel rotates counterclockwise, and reel, which rotates counterclockwise, at this time will reel the first wirerope, and the first wirerope pulls on upside
First sliding block upward sliding is completed to need to make to drive placement plate upward sliding transporting petroleum pipeline when petroleum pipeline transports
When placement plate returns to initial position, user of service enables motor and reel is rotated clockwise, and reel turns clockwise at this time
Dynamic to unclasp the first wirerope, under the gravity of placement plate itself, placement plate will slide back downward into home position, work as water
When plane needs transporting petroleum pipeline, since the first fixed block is that rotary type is connect with bull stick, user of service can be by bar rotation
To horizontal plane parallel to the ground, pulling plate is placed on ground level by user of service at this time, and the first fixed link, which will support, to be turned
Bar, to support placement plate, the first fixed link and pulling plate of setting can be stabilized by its in placement plate transporting petroleum pipeline,
It prevents from that the petroleum pipeline in placement plate is caused to fall down because of gravity center instability, the first fixed block and bull stick of setting to put
Petroleum pipeline transport can be carried out on the ground of different gradient by setting plate.
Because further including having the second sliding rail, the second sliding block, the first spring, the first rubber block, rotating plate, the second rubber block,
Two fixed links and drawstring are respectively connected with the second sliding rail on the inside of the placement plate of the left and right sides, and slidingtype is connected with the on the second sliding rail
Two sliding blocks, are respectively connected with the first spring between the second slider bottom and placement plate, the second inner side of slider of the left and right sides rotates
Formula is connected with rotating plate, and the rotating plate bottom of the left and right sides is respectively connected with the second rubber block, is connected with the first rubber block at the top of baffle, left
The rotating plate inside top of right two sides is respectively connected with the second fixed link, and drawstring, drawstring right end are connected in second fixed link in left side
It is wound in second fixed link on right side, when needing for petroleum pipeline to be placed in placement plate, user of service will be wound in the right side
The drawstring of the second fixed link of side is unlocked, and makes the rotating plate of the left and right sides by pulling up the second fixed link of the left and right sides later
It is opened, the second rubber block is also followed by rotating plate and is opened, and the first spring is stretched at this time, and user of service will need to transport later
Petroleum pipeline be placed on the first rubber block, when place complete when, user of service decontrol the left and right sides the second fixed link, this
When the first spring will restore to the original state so that the rotating plate of the left and right sides moves down, the second rubber block will be squeezed and is placed in
Petroleum pipeline on first rubber block, the right end of drawstring is wound in second fixed link on right side by user of service again later, in
The petroleum pipeline being disposed in the first rubber block and the second rubber block is compacted, the first rubber block and the second rubber block of setting
Protective effect is played to the petroleum pipeline being placed in placement plate, it is therefore prevented that petroleum pipeline surface is subject to crushing when compressing, if
The drawstring set is compacted the petroleum pipeline being placed in placement plate, prevents petroleum pipeline during transportation because very loose
It dissipates and falls down.
Because further including having third fixed link, first connecting rod and headlamp, it is connected with third fixed link at the top of bull stick, the
Three fixed link left upper portions are connected with first connecting rod, and first connecting rod bottom left is connected with headlamp, the headlamp of setting
So that the transport device also can be carried out the transport of petroleum pipeline in night or light darker place.
Because further including having the second fixed block, third fixed block, second spring and inserted link, the rotating plate top right side in left side connects
It is connected to the second fixed block, first through hole is provided in the second fixed block, is connected with third fixed block at the top of the rotating plate on right side, third is solid
Determine block left lower and be provided with third through-hole, third fixed block upper right is provided with the second through-hole, is equipped with inserted link in third through-hole, inserts
Bar passes through the second through-hole, and the left side of inserted link is located in first through hole, on the downside of inserted link right wall and third fixed block inner right wall downside
Between be connected with second spring, when placing petroleum pipeline, user of service can pull to the right inserted link, at this time second spring compress, insert
The left side of bar will be moved out of first through hole, and user of service can be by pulling the second fixed block to beat rotating plate later
It opens, then above the first rubber block that the petroleum pipeline that needs transport is placed in placement plate, when petroleum pipeline, which is placed, to be completed,
User of service decontrols inserted link, and second spring restores to the original state at this time, and inserted link will be driven to be moved to the left, when second spring restores former completely
When shape, the left side of inserted link will be returned in first through hole, and the first through hole and inserted link of setting can more stably fix rotating plate, thus
The more stably petroleum pipeline in fixed placement plate.
Because further including having the second directive wheel, the second connecting rod, third directive wheel and the second wirerope, on the downside of bull stick right wall
It is connected with the second connecting rod, third directive wheel is connected in the second connecting rod, is connected with the second directive wheel on the downside of bull stick right wall, the
Two directive wheels are located at below third directive wheel, and the first slider bottom is connected with the second wirerope, and the second wirerope is led around third
To wheel and the second directive wheel, the second wirerope-winding is on reel, when horizontal plane needs to carry out petroleum transportation using the device
When, user of service enables motor and reel is rotated counterclockwise, so that reel reels the first wirerope, and first is sliding
It will be unclasped on the downside of block and around the first wirerope at the second directive wheel and third directive wheel, the first wirerope will will pull
First sliding block moves right, so that placement plate transporting petroleum pipeline to the right, when transport completes that placement plate is needed to return to initially
Position when, user of service enables motor and reel is rotated clockwise so that reel unclasps the first wirerope, and
It will be reeled on the downside of first sliding block and around the first wirerope at the second directive wheel and third directive wheel, the first wirerope will
It will pull the first sliding block to move downward, so that placement plate returns to initial position, the second directive wheel and the third guiding of setting
So that the device is when horizontal plane carries out petroleum pipeline conveying, placement plate can still return to wheel under the action of no self gravity
Initial position.
(3) beneficial effect
The present invention devises a kind of petroleum pipeline transport device, and the first fixed block and bull stick of setting make placement plate not
Ground with the gradient can carry out petroleum pipeline transport, and the first rubber block and the second rubber block of setting are to being placed in placement plate
Petroleum pipeline play protective effect, it is therefore prevented that petroleum pipeline surface compress when be subject to crushing, the drawstring of setting to place
It is compacted in the petroleum pipeline in placement plate, prevents petroleum pipeline from falling down during transportation because of very loose, if
The headlamp set makes the transport device also can be carried out the transport of petroleum pipeline in night or light darker place, setting
First through hole and inserted link can more stably fix rotating plate, thus the more stably petroleum pipeline in fixed placement plate, the of setting
Two directive wheels and third directive wheel make the device when horizontal plane carries out petroleum pipeline conveying, and placement plate is in no self gravity
Under the action of can still return to initial position.
Detailed description of the invention
Fig. 1 is schematic view of the front view of the invention.
Fig. 2 is the schematic view of the front view of elevating mechanism of the present invention.
Fig. 3 is the schematic view of the front view of driving mechanism of the present invention.
Fig. 4 is the first part schematic view of the front view of the invention.
Fig. 5 is second of part schematic view of the front view of the invention.
Fig. 6 is the third part schematic view of the front view of the invention.
Fig. 7 is the 4th kind of part schematic view of the front view of the invention.
The label in accompanying drawing is: 1- placing frame, the ground 2-, the first fixed block of 3-, 4- elevating mechanism, 41- bull stick, 42-
One sliding rail, the first sliding block of 43-, 44- placement plate, 45- baffle, the first directive wheel of 46-, 5- driving mechanism, 51- motor, 52- coiling
Wheel, 53- battery, the first wirerope of 54-, the first fixed link of 55-, 56- pulling plate, the second sliding rail of 6-, the second sliding block of 7-, 8- first
Spring, the first rubber block of 9-, 10- rotating plate, the second rubber block of 11-, the second fixed link of 12-, 13- drawstring, 14- third fixed link,
15- first connecting rod, 16- headlamp, the second fixed block of 17-, 18- first through hole, 19- third fixed block, the second through-hole of 20-,
21- second spring, 22- inserted link, 23- third through-hole, the second directive wheel of 24-, the second connecting rod of 25-, 26- third directive wheel, 27-
Second wirerope.
Specific embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples.
Embodiment 1
A kind of petroleum pipeline transport device includes as shown in figs. 1-7 placing frame 1, the first fixed block 3, elevating mechanism 4
With driving mechanism 5, placing frame 1 is placed on ground 2, and the first fixed block 3,3 top of the first fixed block are connected at the top of placing frame 1
It is connected with elevating mechanism 4, driving mechanism 5 is connected in placing frame 1.
Embodiment 2
A kind of petroleum pipeline transport device includes as shown in figs. 1-7 placing frame 1, the first fixed block 3, elevating mechanism 4
With driving mechanism 5, placing frame 1 is placed on ground 2, and the first fixed block 3,3 top of the first fixed block are connected at the top of placing frame 1
It is connected with elevating mechanism 4, driving mechanism 5 is connected in placing frame 1.
Elevating mechanism 4 includes bull stick 41, the first sliding rail 42, the first sliding block 43, placement plate 44, baffle 45 and the first guiding
Wheel 46, is connected with the first fixed block 3 at the top of placing frame 1, and 3 top rotary type of the first fixed block is connected with bull stick 41, before bull stick 41
Side is connected with the first sliding rail 42, and about the 42 equal slidingtype in two sides of the first sliding rail is connected with the first sliding block 43,43 left side of the first sliding block
It is connected with placement plate 44 when rotating, is connected with baffle 45 between 44 inside of placement plate of upper and lower two sides, is connected at the top of bull stick 41
There is the first directive wheel 46.
Embodiment 3
A kind of petroleum pipeline transport device includes as shown in figs. 1-7 placing frame 1, the first fixed block 3, elevating mechanism 4
With driving mechanism 5, placing frame 1 is placed on ground 2, and the first fixed block 3,3 top of the first fixed block are connected at the top of placing frame 1
It is connected with elevating mechanism 4, driving mechanism 5 is connected in placing frame 1.
Elevating mechanism 4 includes bull stick 41, the first sliding rail 42, the first sliding block 43, placement plate 44, baffle 45 and the first guiding
Wheel 46, is connected with the first fixed block 3 at the top of placing frame 1, and 3 top rotary type of the first fixed block is connected with bull stick 41, before bull stick 41
Side is connected with the first sliding rail 42, and about the 42 equal slidingtype in two sides of the first sliding rail is connected with the first sliding block 43,43 left side of the first sliding block
It is connected with placement plate 44 when rotating, is connected with baffle 45 between 44 inside of placement plate of upper and lower two sides, is connected at the top of bull stick 41
There is the first directive wheel 46.
Driving mechanism 5 includes motor 51, reel 52, battery 53, the first wirerope 54, the first fixed link 55 and draws
Plate 56, the interior right side of placing frame 1 are equipped with motor 51, reel 52 are connected on the output shaft of motor 51, and left side connects in placing frame 1
It is connected to battery 53, battery 53 is connect with motor 51 by electric wire connection type, is connected at the top of the first sliding block 43 of upside
First wirerope 54, the first wirerope 54 bypass the first directive wheel 46, and 54 bottom end of the first wirerope is wound on reel 52, turn
It is connected with the first fixed link 55 on the upside of 41 right wall of bar, 55 right wall rotary type of the first fixed link is connected with pulling plate 56.
Embodiment 4
A kind of petroleum pipeline transport device includes as shown in figs. 1-7 placing frame 1, the first fixed block 3, elevating mechanism 4
With driving mechanism 5, placing frame 1 is placed on ground 2, and the first fixed block 3,3 top of the first fixed block are connected at the top of placing frame 1
It is connected with elevating mechanism 4, driving mechanism 5 is connected in placing frame 1.
Elevating mechanism 4 includes bull stick 41, the first sliding rail 42, the first sliding block 43, placement plate 44, baffle 45 and the first guiding
Wheel 46, is connected with the first fixed block 3 at the top of placing frame 1, and 3 top rotary type of the first fixed block is connected with bull stick 41, before bull stick 41
Side is connected with the first sliding rail 42, and about the 42 equal slidingtype in two sides of the first sliding rail is connected with the first sliding block 43,43 left side of the first sliding block
It is connected with placement plate 44 when rotating, is connected with baffle 45 between 44 inside of placement plate of upper and lower two sides, is connected at the top of bull stick 41
There is the first directive wheel 46.
Driving mechanism 5 includes motor 51, reel 52, battery 53, the first wirerope 54, the first fixed link 55 and draws
Plate 56, the interior right side of placing frame 1 are equipped with motor 51, reel 52 are connected on the output shaft of motor 51, and left side connects in placing frame 1
It is connected to battery 53, battery 53 is connect with motor 51 by electric wire connection type, is connected at the top of the first sliding block 43 of upside
First wirerope 54, the first wirerope 54 bypass the first directive wheel 46, and 54 bottom end of the first wirerope is wound on reel 52, turn
It is connected with the first fixed link 55 on the upside of 41 right wall of bar, 55 right wall rotary type of the first fixed link is connected with pulling plate 56.
It further include having the second sliding rail 6, the second sliding block 7, the first spring 8, the first rubber block 9, rotating plate 10, the second rubber block
11, the second fixed link 12 and drawstring 13, are respectively connected with the second sliding rail 6 on the inside of the placement plate 44 of the left and right sides, sliding on the second sliding rail 6
Dynamic formula is connected with the second sliding block 7, is respectively connected with the first spring 8 between 7 bottom of the second sliding block and placement plate 44, and the of the left and right sides
Two sliding blocks, 7 inside rotary type is connected with rotating plate 10, and 10 bottom of rotating plate of the left and right sides is respectively connected with the second rubber block 11, baffle
45 tops are connected with the first rubber block 9, and 10 inside top of rotating plate of the left and right sides is respectively connected with the second fixed link 12, and the of left side
Drawstring 13 is connected in two fixed links 12,13 right end of drawstring is wound in second fixed link 12 on right side.
Further include having third fixed link 14, first connecting rod 15 and headlamp 16, is connected with third at the top of bull stick 41 and fixes
Bar 14,14 left upper portion of third fixed link are connected with first connecting rod 15, and 15 bottom left of first connecting rod is connected with headlamp
16。
It further include having the second fixed block 17, third fixed block 19, second spring 21 and inserted link 22,10 top of rotating plate in left side
Right side is connected with the second fixed block 17, and first through hole 18 is provided in the second fixed block 17, and is connected at the top of the rotating plate 10 on right side
Three fixed blocks 19,19 left lower of third fixed block are provided with third through-hole 23, and it is logical that 19 upper right of third fixed block is provided with second
Hole 20, third through-hole 23 is interior to be equipped with inserted link 22, and inserted link 22 passes through the second through-hole 20, and the left side of inserted link 22 is located at first through hole 18
It is interior, second spring 21 is connected between 19 inner right wall of third fixed block downside on the downside of 22 right wall of inserted link.
It further include having the second directive wheel 24, the second connecting rod 25, third directive wheel 26 and the second wirerope 27, bull stick 41 is right
It is connected with the second connecting rod 25 on the downside of wall, third directive wheel 26, connection on the downside of 41 right wall of bull stick are connected in the second connecting rod 25
There is the second directive wheel 24, the second directive wheel 24 is located at 26 lower section of third directive wheel, and 43 bottom of the first sliding block is connected with the second steel wire
Rope 27, the second wirerope 27 bypass third directive wheel 26 and the second directive wheel 24, and the second wirerope 27 is wound on reel 52.
Working principle: when user of service needs using the device come transporting petroleum pipeline, user of service is by petroleum pipeline
It is placed in placing frame 1, controls driving mechanism 5 later, driving mechanism 5 will drive elevating mechanism 4 to transport petroleum pipeline.
Because elevating mechanism 4 includes bull stick 41, the first sliding rail 42, the first sliding block 43, placement plate 44, baffle 45 and first
Directive wheel 46 is connected with the first fixed block 3 at the top of placing frame 1, and 3 top rotary type of the first fixed block is connected with bull stick 41, bull stick
41 front sides are connected with the first sliding rail 42, and about the 42 equal slidingtype in two sides of the first sliding rail is connected with the first sliding block 43, the first sliding block 43
Left side is connected with placement plate 44 when rotating, baffle 45,41 top of bull stick are connected between 44 inside of placement plate of upper and lower two sides
It is connected with the first directive wheel 46, when needing to transport petroleum pipeline the ground 2 on certain slope, user of service starts driving
Mechanism 5, driving mechanism 5 will drive 43 upward sliding of the first sliding block, to drive 44 upward sliding of placement plate, can will then put
The petroleum pipeline placed on plate 44 is set to transport on the ground 2 on certain slope.
Because driving mechanism 5 includes motor 51, reel 52, battery 53, the first wirerope 54, the first fixed link 55
With pulling plate 56, the interior right side of placing frame 1 is equipped with motor 51, and reel 52, a left side in placing frame 1 are connected on the output shaft of motor 51
Side is connected with battery 53, and battery 53 is connect with motor 51 by electric wire connection type, connects at the top of the first sliding block 43 of upside
It is connected to the first wirerope 54, the first wirerope 54 bypasses the first directive wheel 46, and 54 bottom end of the first wirerope is wound in reel 52
On, it is connected with the first fixed link 55 on the upside of bull stick 41 right wall, 55 right wall rotary type of the first fixed link is connected with pulling plate 56, when making
When placement plate 44 carries out petroleum pipeline transport, user of service enables motor 51 and reel 52 is rotated counterclockwise, coiling at this time
Wheel 52, which rotates counterclockwise, will reel the first wirerope 54, and the first sliding block 43 that the first wirerope 54 pulls on upside slides up
It is dynamic, so that 44 upward sliding transporting petroleum pipeline of placement plate is driven, when petroleum pipeline transport is completed to need to return to placement plate 44
When initial position, user of service enables motor 51 and reel 52 is rotated clockwise, and reel 52 rotates clockwise just at this time
The first wirerope 54 can be unclasped, under the gravity of placement plate 44 itself, placement plate 44 will slide back downward into home position, when
When horizontal plane needs transporting petroleum pipeline, since the first fixed block 3 is that rotary type is connect with bull stick 41, user of service can be by bull stick
41 turn to the horizontal plane parallel with ground 2, and pulling plate 56 is placed on ground level by user of service at this time, and the first fixed link 55 will
Bull stick 41 can be supported, to support placement plate 44, the first fixed link 55 and pulling plate 56 of setting transport stone in placement plate 44
Can be stabilized by its when oil-piping, it prevents that the petroleum pipeline in placement plate 44 is caused to fall down because of gravity center instability, is arranged
The first fixed block 3 and bull stick 41 make placement plate 44 that can carry out petroleum pipeline transport on the ground of different gradient 2.
Because further including having the second sliding rail 6, the second sliding block 7, the first spring 8, the first rubber block 9, rotating plate 10, the second rubber
Block 11, the second fixed link 12 and drawstring 13, are respectively connected with the second sliding rail 6 on the inside of the placement plate 44 of the left and right sides, on the second sliding rail 6
Slidingtype is connected with the second sliding block 7, and the first spring 8 is respectively connected between 7 bottom of the second sliding block and placement plate 44, the left and right sides
Second sliding block, 7 inside rotary type is connected with rotating plate 10, and 10 bottom of rotating plate of the left and right sides is respectively connected with the second rubber block 11, gear
The first rubber block 9 is connected at the top of plate 45,10 inside top of rotating plate of the left and right sides is respectively connected with the second fixed link 12, left side
It is connected with drawstring 13 in second fixed link 12,13 right end of drawstring is wound in second fixed link 12 on right side, when needing petroleum
When pipeline is placed in placement plate 44, user of service unlocks the drawstring 13 for being wound in the second fixed link 12 of right side, passes through later
The second fixed link 12 for pulling up the left and right sides makes the rotating plate 10 of the left and right sides be opened, and the second rubber block 11 is also followed by
Rotating plate 10 is opened, and the first spring 8 is stretched at this time, and user of service will need the petroleum pipeline transported to be placed in the first rubber later
On blob of viscose 9, when placing completion, user of service decontrols the second fixed link 12 of the left and right sides, and the first spring 8 will restore original at this time
Shape, so that the rotating plate 10 of the left and right sides moves down, the second rubber block 11, which will squeeze, to be placed on the first rubber block 9
Petroleum pipeline, the right end of drawstring 13 is wound in second fixed link 12 on right side by user of service again later, in being disposed on the
Petroleum pipeline in one rubber block 9 and the second rubber block 11 is compacted, and the first rubber block 9 and the second rubber block 11 of setting are to putting
The petroleum pipeline being placed in placement plate 44 plays protective effect, it is therefore prevented that petroleum pipeline surface is subject to crushing when compressing, and is arranged
Drawstring 13 petroleum pipeline being placed in placement plate 44 is compacted, prevent petroleum pipeline during transportation because very
Loosely fall down.
Because further including having third fixed link 14, first connecting rod 15 and headlamp 16, third is connected at the top of bull stick 41
Fixed link 14,14 left upper portion of third fixed link are connected with first connecting rod 15, and 15 bottom left of first connecting rod is connected with photograph
Bright lamp 16, the headlamp 16 of setting make the transport device also can be carried out petroleum pipeline in night or light darker place
Transport.
Because further including having the second fixed block 17, third fixed block 19, second spring 21 and inserted link 22, the rotating plate 10 in left side
Top right side is connected with the second fixed block 17, and first through hole 18 is provided in the second fixed block 17, is connected at the top of the rotating plate 10 on right side
There is third fixed block 19,19 left lower of third fixed block is provided with third through-hole 23, and 19 upper right of third fixed block is provided with
Two through-holes 20, third through-hole 23 is interior to be equipped with inserted link 22, and inserted link 22 passes through the second through-hole 20, and the left side of inserted link 22 is located at first through hole
In 18, it is connected with second spring 21 between 19 inner right wall of third fixed block downside on the downside of 22 right wall of inserted link, is placing petroleum pipeline
When road, user of service can pull to the right inserted link 22, and second spring 21 is compressed at this time, and the left side of inserted link 22 will be from first through hole 18
It is inside moved, user of service can be opened rotating plate 10 by the second fixed block 17 of pulling later, then the stone that needs are transported
Oil-piping is placed in above the first rubber block 9 in placement plate 44, and when petroleum pipeline, which is placed, to be completed, user of service decontrols inserted link
22, second spring 21 restores to the original state at this time, and inserted link 22 will be driven to be moved to the left, and when second spring 21 restores to the original state completely, inserts
The left side of bar 22 will return in first through hole 18, and the first through hole 18 and inserted link 22 of setting can more stably fix rotating plate 10,
To the petroleum pipeline in more stably fixed placement plate 44.
Because further including having the second directive wheel 24, the second connecting rod 25, third directive wheel 26 and the second wirerope 27, bull stick
It is connected with the second connecting rod 25 on the downside of 41 right walls, third directive wheel 26,41 right wall of bull stick downside are connected in the second connecting rod 25
It is connected with the second directive wheel 24, the second directive wheel 24 is located at 26 lower section of third directive wheel, and 43 bottom of the first sliding block is connected with second
Wirerope 27, the second wirerope 27 bypass third directive wheel 26 and the second directive wheel 24, and the second wirerope 27 is wound in reel
On 52, when horizontal plane needs to carry out petroleum transportation using the device, user of service enables motor 51 and makes 52 inverse time of reel
Needle rotation so that reel 52 reels the first wirerope 54, and on the downside of the first sliding block 43 and bypasses 24 He of the second directive wheel
The first wirerope 54 at third directive wheel 26 will be unclasped, and the first wirerope 54 will will pull the first sliding block 43 and transport to the right
It is dynamic, so that transporting petroleum pipeline makes placement plate 44 when transport completes that placement plate 44 is needed to return to initial position to the right
Enabling motor 51 with personnel rotates clockwise reel 52, so that reel 52 unclasps the first wirerope 54, and the
It will be reeled on the downside of one sliding block 43 and around the first wirerope 54 at the second directive wheel 24 and third directive wheel 26, the first steel
Cord 54 will will pull the first sliding block 43 and move downward, so that placement plate 44 returns to initial position, the second guiding of setting
Wheel 24 and third directive wheel 26 make the device when horizontal plane carries out petroleum pipeline conveying, and placement plate 44 is in no self gravity
Under the action of can still return to initial position.
The preferred embodiment of the present invention above described embodiment only expresses, the description thereof is more specific and detailed, but simultaneously
Limitations on the scope of the patent of the present invention therefore cannot be interpreted as.It should be pointed out that for those of ordinary skill in the art
For, without departing from the inventive concept of the premise, several deformations can also be made, improves and substitutes, these belong to this hair
Bright protection scope.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.