CN107487347A - Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique - Google Patents

Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique Download PDF

Info

Publication number
CN107487347A
CN107487347A CN201710850104.5A CN201710850104A CN107487347A CN 107487347 A CN107487347 A CN 107487347A CN 201710850104 A CN201710850104 A CN 201710850104A CN 107487347 A CN107487347 A CN 107487347A
Authority
CN
China
Prior art keywords
chassis
bracket
collecting vehicle
buffer board
connecting shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710850104.5A
Other languages
Chinese (zh)
Inventor
王千
荆凯
于粟
李明
黄琢
冯雁敏
常洪军
房国忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Liaoning Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Liaoning Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710850104.5A priority Critical patent/CN107487347A/en
Publication of CN107487347A publication Critical patent/CN107487347A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B62LAND VEHICLES FOR TRAVELLING OTHERWISE THAN ON RAILS
    • B62BHAND-PROPELLED VEHICLES, e.g. HAND CARTS OR PERAMBULATORS; SLEDGES
    • B62B5/00Accessories or details specially adapted for hand carts
    • B62B5/0006Bumpers; Safety devices
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M3/00Investigating fluid-tightness of structures
    • G01M3/02Investigating fluid-tightness of structures by using fluid or vacuum
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B62LAND VEHICLES FOR TRAVELLING OTHERWISE THAN ON RAILS
    • B62BHAND-PROPELLED VEHICLES, e.g. HAND CARTS OR PERAMBULATORS; SLEDGES
    • B62B2202/00Indexing codes relating to type or characteristics of transported articles

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Transportation (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Body Structure For Vehicles (AREA)

Abstract

Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique, it is characterised in that:For the collecting vehicle to adapt to the anti-collision structure in field, the collecting vehicle includes the chassis of support sample devices(1)It is arranged on chassis(1)The road wheel of bottom(2)And Lateral Collision Avoidance structure;The collecting vehicle protects chassis and its carrier to greatest extent when side is hit by the buffering of two levels; meanwhile mobile chassis can also protect the tie point between road wheel and chassis well, avoid more serious damage; its is practical, uses during beneficial to operation in the wild.

Description

Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique
Technical field
Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique.
Background technology
Upper storehouse, diversion steel pipe and the underground power house in power station are arranged in underground at present, the infiltration situation for underground power house It is difficult to accurately detected by common detection method, it is therefore desirable to find one kind and be suitable for underground workshop seepage The method of detection, the source of underground power house percolating water can be distinguished.This just needs to carry out multipoint acquisition in the wild, and huge sets Standby not portable, this just needs a kind of load bearing equipment and the micro-collection car of experimental result, and this car uses hand push or drawing Realize movement, but use common dolly, impact resistance is poor, once receive in the wild shock car body will be caused it is serious Injury, especially the junction between wheel and chassis is easiest to damage, and so not only easily causes the damage of equipment, also The loss of experimental result can be caused, causes serious consequence.
The content of the invention
Goal of the invention:
Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique, it is in the past existing the purpose is to solve The problem of.
Technical scheme:
For the collecting vehicle to adapt to the anti-collision structure in field, the collecting vehicle includes the chassis of support sample devices(1)It is arranged on chassis (1)The road wheel of bottom(2)And Lateral Collision Avoidance structure;
Road wheel(2)For parallel connection two, two road wheels(2)It is coaxially disposed, two road wheels(2)Common connecting shaft(3) By opening towards sideways U-bracket(4)It is connected to chassis(1);The lower end of U-bracket puts in connecting shaft(3)Interior and energy phase For connecting shaft(3)The movement pulled and pushed is done, the upper end of U-bracket is by founding thick stick(5)It is connected to chassis(1)Bottom;
Lateral Collision Avoidance structure includes buffer board(6), buffer pocket(7)With lifting inserted link(8), buffer board(6)It is arranged on chassis(1)'s Two sides, buffer board(6)Bottom chassis is arranged on by pivot shaft(1)Side formed activity lever construction;Branch Point rotating shaft is arranged on buffer board(6)The position of close bottom end points cause buffer board(6)Top form laborsaving lever;The branch The position of point rotating shaft is also at chassis(1)Side bottom;
Buffer pocket(7)It is arranged on chassis(1)Bottom both sides, buffer pocket(7)Inside it is provided with worm gear(9)With with worm gear(9)Match somebody with somebody The worm screw of conjunction(10), worm screw(10)Perpendicular to chassis(1)Bottom surface set, worm screw(10)Bottom stretch out buffer pocket(7), worm screw (10)Lower section and release lever(11)One end it is corresponding, the release lever(11)Fulcrum be arranged on U-bracket(4)On, solution Lock lever(11)The other end with lifting inserted link(8)It is flexibly connected;Worm gear(9)Rotating shaft on be wound with pulling worm gear(9)Turn Dynamic drawstring(14), drawstring(14)It is connected to buffer board(6)Bottom;
In connecting shaft(3)On be provided with through hole(12), the through hole and U-bracket(4)On pit(13)Position correspondence, normal work When making, inserted link is lifted(8)Through through hole(12)After insert pit(13)It is interior by connecting shaft(3)With U-bracket(4)It is relatively fixed; Work as buffer board(6)Top when being hit, buffer board(6)Bottom pull worm gear(9)Rotation so that worm screw(10)Decline, Worm screw(10)Push release lever(11)So that lifting inserted link(8)Rise, lift inserted link(8)Leave through hole(12)And pit(13) Complete unblock.
Buffer board(6)With chassis(1)Side between be provided with first-level buffer spring(15).
U-bracket(4)Put in connecting shaft(3)Part be cased with level 2 buffering spring(5), level 2 buffering spring(5)One end Connect U-bracket(4), the other end is connected to connecting shaft(3)Inwall, work as U-bracket(4)To connecting shaft(3)When outer mobile, two Level buffer spring(5)In extended state.
Advantageous effect:
The collecting vehicle protects chassis and its carrier to greatest extent when side is hit by the buffering of two levels, Meanwhile mobile chassis can also protect the tie point between road wheel and chassis well, avoid more serious damage, in fact It is strong with property, use during beneficial to operation in the wild.
Brief description of the drawings:
Fig. 1 is overall structure diagram;
Fig. 2 is state diagram when being impacted.
Embodiment:
Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique, it is characterised in that:The collecting vehicle is The anti-collision structure in field is adapted to, the collecting vehicle includes the chassis of support sample devices(1)It is arranged on chassis(1)The road wheel of bottom (2)And Lateral Collision Avoidance structure;
Road wheel(2)For parallel connection two, two road wheels(2)It is coaxially disposed, two road wheels(2)Common connecting shaft(3) By opening towards sideways U-bracket(4)It is connected to chassis(1);The lower end of U-bracket puts in connecting shaft(3)Interior and energy phase For connecting shaft(3)The movement pulled and pushed is done, the upper end of U-bracket is by founding thick stick(5)It is connected to chassis(1)Bottom;
Lateral Collision Avoidance structure includes buffer board(6), buffer pocket(7)With lifting inserted link(8), buffer board(6)It is arranged on chassis(1)'s Two sides, buffer board(6)Bottom chassis is arranged on by pivot shaft(1)Side formed activity lever construction;Branch Point rotating shaft is arranged on buffer board(6)The position of close bottom end points cause buffer board(6)Top form laborsaving lever;The branch The position of point rotating shaft is also at chassis(1)Side bottom;
Buffer pocket(7)It is arranged on chassis(1)Bottom both sides, buffer pocket(7)Inside it is provided with worm gear(9)With with worm gear(9)Match somebody with somebody The worm screw of conjunction(10), worm screw(10)Perpendicular to chassis(1)Bottom surface set, worm screw(10)Bottom stretch out buffer pocket(7), worm screw (10)Lower section and release lever(11)One end it is corresponding, the release lever(11)Fulcrum be arranged on U-bracket(4)On, solution Lock lever(11)The other end with lifting inserted link(8)It is flexibly connected;As shown in figure 1, the release lever at both ends(11)The other end Jointly with lifting inserted link(8)Top be flexibly connected, worm gear(9)Rotating shaft on be wound with pulling worm gear(9)The drawstring of rotation (14), drawstring(14)It is connected to buffer board(6)Bottom;
In connecting shaft(3)On be provided with through hole(12), the through hole and U-bracket(4)On pit(13)Position correspondence, normal work When making, inserted link is lifted(8)Through through hole(12)After insert pit(13)It is interior by connecting shaft(3)With U-bracket(4)It is relatively fixed; Work as buffer board(6)Top when being hit, buffer board(6)Bottom pull worm gear(9)Rotation so that worm screw(10)Decline, Worm screw(10)Push release lever(11)So that lifting inserted link(8)Rise, lift inserted link(8)Leave through hole(12)And pit(13) Complete unblock.
Buffer board(6)With chassis(1)Side between be provided with first-level buffer spring(15).
U-bracket(4)Put in connecting shaft(3)Part be cased with level 2 buffering spring(5), level 2 buffering spring(5)One end connects U Shape support(4), the other end is connected to connecting shaft(3)Inwall, work as U-bracket(4)To connecting shaft(3)When outer mobile, two level is delayed Rush spring(5)In extended state.
The collecting vehicle using when as shown in Fig. 2 when receiving shock, such as shown in Fig. 2 by figure right side hit Hit, buffer board(6)Top is extruded, buffer board(6)Lower end pulls worm gear(9)Rotate so that worm screw(10)Decline, worm screw(10) Push release lever(11)So that lifting inserted link(8)Rise, lift inserted link(8)Leave through hole(12)And pit(13)Complete solution Lock, at the same time, first-level buffer spring(15)Compressed, realize first-level buffer, and when pressure continues, chassis 1 is moved to the left, Level 2 buffering spring(5)Stretching realize level 2 buffering, thus impact is unloaded well, realize buffering, prevent chassis 1 and The damage of its equipment carried, after shock, it is only necessary to reset chassis, inserted link will be lifted(8)Through through hole(12)After insert Pit(13)Interior, the collecting vehicle can be very good to be incorporated in field acquisition operation, push a wide range of popularization and application.

Claims (3)

1. Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique, it is characterised in that:The collecting vehicle To adapt to the anti-collision structure in field, the collecting vehicle includes the chassis of support sample devices(1)It is arranged on chassis(1)The walking of bottom Wheel(2)And Lateral Collision Avoidance structure;
Road wheel(2)For parallel connection two, two road wheels(2)It is coaxially disposed, two road wheels(2)Common connecting shaft(3) By opening towards sideways U-bracket(4)It is connected to chassis(1);The lower end of U-bracket puts in connecting shaft(3)Interior and energy phase For connecting shaft(3)The movement pulled and pushed is done, the upper end of U-bracket is by founding thick stick(5)It is connected to chassis(1)Bottom;
Lateral Collision Avoidance structure includes buffer board(6), buffer pocket(7)With lifting inserted link(8), buffer board(6)It is arranged on chassis(1)'s Two sides, buffer board(6)Bottom chassis is arranged on by pivot shaft(1)Side formed activity lever construction;Branch Point rotating shaft is arranged on buffer board(6)The position of close bottom end points cause buffer board(6)Top form laborsaving lever;The branch The position of point rotating shaft is also at chassis(1)Side bottom;
Buffer pocket(7)It is arranged on chassis(1)Bottom both sides, buffer pocket(7)Inside it is provided with worm gear(9)With with worm gear(9)Match somebody with somebody The worm screw of conjunction(10), worm screw(10)Perpendicular to chassis(1)Bottom surface set, worm screw(10)Bottom stretch out buffer pocket(7), worm screw (10)Lower section and release lever(11)One end it is corresponding, the release lever(11)Fulcrum be arranged on U-bracket(4)On, solution Lock lever(11)The other end with lifting inserted link(8)It is flexibly connected;Worm gear(9)Rotating shaft on be wound with pulling worm gear(9)Turn Dynamic drawstring(14), drawstring(14)It is connected to buffer board(6)Bottom;
In connecting shaft(3)On be provided with through hole(12), the through hole and U-bracket(4)On pit(13)Position correspondence, normal work When making, inserted link is lifted(8)Through through hole(12)After insert pit(13)It is interior by connecting shaft(3)With U-bracket(4)It is relatively fixed; Work as buffer board(6)Top when being hit, buffer board(6)Bottom pull worm gear(9)Rotation so that worm screw(10)Decline, Worm screw(10)Push release lever(11)So that lifting inserted link(8)Rise, lift inserted link(8)Leave through hole(12)And pit(13) Complete unblock.
2. according to claim 1 survey Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle based on isotope tracer technique, It is characterized in that:Buffer board(6)With chassis(1)Side between be provided with first-level buffer spring(15).
3. according to claim 2 survey Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle based on isotope tracer technique, It is characterized in that:U-bracket(4)Put in connecting shaft(3)Part be cased with level 2 buffering spring(5), level 2 buffering spring(5)One End connection U-bracket(4), the other end is connected to connecting shaft(3)Inwall, work as U-bracket(4)To connecting shaft(3)When outer mobile, Level 2 buffering spring(5)In extended state.
CN201710850104.5A 2017-09-15 2017-09-15 Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique Pending CN107487347A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710850104.5A CN107487347A (en) 2017-09-15 2017-09-15 Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710850104.5A CN107487347A (en) 2017-09-15 2017-09-15 Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique

Publications (1)

Publication Number Publication Date
CN107487347A true CN107487347A (en) 2017-12-19

Family

ID=60651652

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710850104.5A Pending CN107487347A (en) 2017-09-15 2017-09-15 Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique

Country Status (1)

Country Link
CN (1) CN107487347A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1351565A (en) * 1972-04-26 1974-05-01 Stubberfield K F Agricultural and industrial trolleys
EP0569988A2 (en) * 1992-05-14 1993-11-18 EXPRESSO-DEUTSCHLAND TRANSPORTGERÄTE GmbH Transport cart for pallet-type objects
CN203335720U (en) * 2012-11-19 2013-12-11 开县人人有余科技有限公司 Anti-collision buffering device
CN106515812A (en) * 2015-09-14 2017-03-22 天津飞天孚泽科技有限公司 Process for making novel cropping receiving device
CN207535961U (en) * 2017-09-15 2018-06-26 国家电网公司 Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1351565A (en) * 1972-04-26 1974-05-01 Stubberfield K F Agricultural and industrial trolleys
EP0569988A2 (en) * 1992-05-14 1993-11-18 EXPRESSO-DEUTSCHLAND TRANSPORTGERÄTE GmbH Transport cart for pallet-type objects
CN203335720U (en) * 2012-11-19 2013-12-11 开县人人有余科技有限公司 Anti-collision buffering device
CN106515812A (en) * 2015-09-14 2017-03-22 天津飞天孚泽科技有限公司 Process for making novel cropping receiving device
CN207535961U (en) * 2017-09-15 2018-06-26 国家电网公司 Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle

Similar Documents

Publication Publication Date Title
CN205604777U (en) Lifting type parking garage
CN105952202A (en) Three-dimensional bicycle garage
CN206609968U (en) A kind of swing type tunnel arch crown detection device
CN201347338Y (en) Electrical cabinet hoisting and convoying device
CN105971329A (en) Lifting take-and-store type bicycle concentrated storage garage
CN204210617U (en) A kind of bicycle anti-dumping reversing ladder
CN207535961U (en) Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle
CN105882697B (en) A kind of hand propelled conveyer applied to construction site
CN109870136B (en) Building settlement measuring point protection device
CN107487347A (en) Pumped Storage Plant Underground Powerhouse infiltration collecting vehicle is surveyed based on isotope tracer technique
CN211398763U (en) Detecting instrument for pipeline installation
CN104443490A (en) Automatic mechanical sleeving machine
CN209922288U (en) Conveying transmission device for coal mine transportation
CN106285179A (en) Line linear cement pole pole centralizing device
CN202815592U (en) Combination multifunctional navigation rail
CN204225107U (en) Gravity type pile engine
CN204383433U (en) Automobile apparatus for pulling
CN203296816U (en) Underground coal mine water collecting device
CN210002997U (en) Movable windproof electric tower
CN105346557A (en) Inclined shaft running cart protecting device used in coal mine
CN206784253U (en) A kind of warning isolated column of municipal works
CN208883331U (en) A kind of derrick crane limiting device
CN207863979U (en) A kind of device for suspending duct pieces of shield machine
CN207211140U (en) A kind of roofbolt construction arrangement of civil engineering
CN205675053U (en) A kind of construction site go-cart being suitable to slope stop

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination