CN107476320A - Ecological revetment digitizes construction method - Google Patents

Ecological revetment digitizes construction method Download PDF

Info

Publication number
CN107476320A
CN107476320A CN201710851273.0A CN201710851273A CN107476320A CN 107476320 A CN107476320 A CN 107476320A CN 201710851273 A CN201710851273 A CN 201710851273A CN 107476320 A CN107476320 A CN 107476320A
Authority
CN
China
Prior art keywords
construction
engineering
engineering material
ecological
ecological revetment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710851273.0A
Other languages
Chinese (zh)
Other versions
CN107476320B (en
Inventor
孙海龙
李绍才
高伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan University
Original Assignee
Sichuan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan University filed Critical Sichuan University
Priority to CN201710851273.0A priority Critical patent/CN107476320B/en
Publication of CN107476320A publication Critical patent/CN107476320A/en
Application granted granted Critical
Publication of CN107476320B publication Critical patent/CN107476320B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Mining & Mineral Resources (AREA)
  • Computer Hardware Design (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Evolutionary Computation (AREA)
  • Pure & Applied Mathematics (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Analysis (AREA)
  • Computational Mathematics (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Revetment (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of ecological revetment to digitize construction method, comprises the following steps, establishes ecological revetment construction scheme storehouse, engineering material database, design of ecological slope protection scheme digital processing module, recording module, output module;Specific organization arrangement and Managed Solution are drawn in construction scheme storehouse by design of ecological slope protection scheme, engineering material database, avoid the defects of being constructed by personal experience, be advantageous to the accurate progress of work progress, and manpower and materials and time can accurately be controlled, operating efficiency is provided, reduces engineering cost.

Description

Ecological revetment digitizes construction method
Technical field
The invention belongs to the technical field of protecting slope ecology, specifically, is related to a kind of ecological revetment digitlization construction Method.
Background technology
Ecological revetment, be the ABC of the subjects such as integration engineering mechanics, agrology, ecology and botany to slope or Side slope carries out supporting, forms the bulkhead tech for the synthesis slope protection system being made up of plant or engineering and plant.Excavation slope is formed After, by planting plants, prevented using plant and interaction (root system anchoring effect) side slope top layer of rock, the soil body Shield, reinforce, be allowed to that the requirement that side slope top layer is stable can be met, and can recovers the bank protection side of destroyed natural ecological environment Formula, it is a kind of effective bank protection, solid slope means.
The engineering constructions such as highway, railway, water conservancy and natural environment are closely related.Its project scale is big, project is more, is related to face Extensively, native stone, which is filled out, digs a large amount of native stone bare side slopings that engineering is formed, and destroys existing vegetation, local environment is had a great influence, The simple engineering protection of conventional generally use, such as builds slabstone, spray anchor protection, and these engineering measures result in original vegetation and broken A series of ecological environments such as bad, soil erosion, landslide, slope instability and engineering problem.Closely during the last ten years it has been developed that more Kind can play good side slope protection effect, and can betterment works environment, embody the beautiful new skill of Way for Slope Plant Protection of natural environment Art, slope project plant protection system is together form with traditional slope engineering safeguard procedures.
Ecological Slope includes:1. Planting Grass bank protection;2. tile grassed slope;3. hydraulic sprinkle grass planting bank protection;4. soil Work grass planting on net bank protection;5. OH liquid grass planting bank protections;6. row plants vetiver bank protection;7. cellular grid grass planting bank protection;8. soil moved in improve the original plants life Vegetation slope pavement;9. spray sowing vegetation slope pavement.The main function and application conditions of all kinds of Way for Slope Plant Protection technologies are different. Many situations can influence the selection for the side slope protection technology without species.Traditional Ecological Slope construction method is that basis is applied Work administrative staff's is constructed, and the supply of raw material and is put and is relied on depositary management personnel, sequence of construction thus easily occurs Entanglement, the supply missing or slowly of raw material, thereby result in that efficiency of construction is relatively low, and artificial consumptive material is more, adds and is constructed into This.
The content of the invention
For deficiency above-mentioned in the prior art, the present invention provides a kind of ecological revetment digitlization construction method, by right Form of construction work digitized processing, so as to greatly promote the accuracy of the arrangements such as efficiency of construction and raw material.
In order to achieve the above object, the solution that uses of the present invention is:Ecological revetment digitizes construction method, its feature It is:Comprise the following steps,
A, ecological revetment construction scheme storehouse is established;Construction scheme storehouse includes some construction schemes, institute Some construction schemes stated with different ecological bank protection type, with different Engineering Zone features, in construction scheme Including organization arrangement and Managed Solution;
B, engineering material database is established;By all engineering material typing engineering material databases needed for ecological revetment In, and information-based coding is carried out to engineering material in engineering material database;
C, design of ecological slope protection scheme digital processing module is established;Digital processing module is by design of ecological slope protection scheme It is converted into material requested data;And processing is numbered in the design drawing in design of ecological slope protection scheme;
D, recording module is established;Material requested data and engineering material information are loaded into construction scheme storehouse, entered Data Enter corresponding to row;
E, output module is established;Drawn by In-put design drawing number, job location longitude and latitude and height above sea level, output module Engineering material information needed for corresponding material requested data and the design, output module is again by recording module from construction Corresponding organization arrangement and Managed Solution are transferred in organization scheme storehouse.
Further, described organization arrangement includes engineering material, construction manpower and construction equipment.
Further, described Managed Solution includes manpower management, construction management, quality management and safety management.
Further, described information-based coding uses barcode encoding, and barcode encoding content is included to engineering material Type, unit and quantity encoded.
Further, the type and quantity of described material requested data including engineering material, floristic species and Quantity, the type and quantity of engineering component.
Further, in described step E, output module can also draw the use of material requested data in use Alphabetic data, and order journal will be used in informationization encodes.
Further, when engineering material is used in work progress, workmen is using portable scanning device to engineering material Material carries out barcode scanning, so as to confirm that used engineering material meets construction scheme storehouse.
The invention has the advantages that
1st, by establishing construction scheme's database and engineering material database, the data needed in construction have been carried out Complete record, in case transferring;
2nd, by design of ecological slope protection scheme digitized processing, enter line label to design drawing, establishing design Linking between database, so as to be advantageous to the organization arrangement in later stage and the output of Managed Solution;
3rd, information-based coding is carried out to engineering material, engineering material can be called in order in construction work, prevented Only malfunction, prevent job site material stacking, and bar code can be utilized before the invoked procedure of engineering material by engineering material Material and construction scheme are compared, and improve accuracy;
4th, this method avoids being constructed by personal experience the defects of, the accurate progress of work progress is advantageous to, and And manpower and materials and time can accurately be controlled, there is provided operating efficiency, reduce engineering cost.
Embodiment
To make the object, technical solutions and advantages of the present invention clearer, the technical scheme in the present invention is carried out below Clearly and completely describe, it is clear that described embodiment is part of the embodiment of the present invention, rather than whole embodiments.Base Embodiment in the present invention, those of ordinary skill in the art obtained under the premise of creative work is not made it is all its His embodiment, belongs to the scope of protection of the invention.
The invention will be further described below:
The present invention provides a kind of ecological revetment digitlization construction method, and this method avoids constructed by personal experience The defects of, be advantageous to the accurate progress of work progress, and manpower and materials and time can accurately be controlled, there is provided work Efficiency, engineering cost being reduced, method comprises the following steps,
A, ecological revetment construction scheme storehouse is established;Construction scheme storehouse includes some construction schemes, institute Some construction schemes stated with different ecological bank protection type, with different Engineering Zone features, in construction scheme Including organization arrangement and Managed Solution;Described organization arrangement includes engineering material, construction manpower and construction equipment;Described Managed Solution includes manpower management, construction management, quality management and safety management;
B, engineering material database is established;By all engineering material typing engineering material databases needed for ecological revetment In, and information-based coding is carried out to engineering material in engineering material database;Described information-based coding uses bar code Coding, barcode encoding content include encoding the type, unit and quantity of engineering material;By establishing construction organization side Case database and engineering material database, the data needed in construction are subjected to complete documentation, in case transferring;
C, design of ecological slope protection scheme digital processing module is established;Digital processing module is by design of ecological slope protection scheme It is converted into material requested data;And processing is numbered in the design drawing in design of ecological slope protection scheme;Described is required Material data includes type and quantity, floristic type and quantity, the type and quantity of engineering component of engineering material;It is logical Cross to design of ecological slope protection scheme digitized processing, line label is entered to design drawing, establish between design and database Link, so as to be advantageous to the organization arrangement in later stage and the output of Managed Solution;Information-based coding is carried out to engineering material, can Engineering material is called in order in construction work, prevents from malfunctioning, prevents job site material stacking, and can be in work Engineering material and construction scheme are compared using bar code before the invoked procedure of journey material, improve accuracy;
D, recording module is established;Material requested data and engineering material information are loaded into construction scheme storehouse, entered Data Enter corresponding to row;
E, output module is established;Drawn by In-put design drawing number, job location longitude and latitude and height above sea level, output module Engineering material information needed for corresponding material requested data and the design, output module is again by recording module from construction Corresponding organization arrangement and Managed Solution are transferred in organization scheme storehouse;Output module can also show that material requested data were using Alphabetic data is used in journey, and order journal will be used in informationization encodes.
When engineering material F, is used in work progress, workmen is swept using portable scanning device to engineering material Code, so as to confirm that used engineering material meets construction scheme storehouse.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although The present invention is described in detail with reference to the foregoing embodiments, it will be understood by those within the art that:It still may be used To be modified to the technical scheme described in foregoing embodiments, or equivalent substitution is carried out to which part technical characteristic; And these modification or replace, do not make appropriate technical solution essence depart from various embodiments of the present invention technical scheme spirit and Scope.

Claims (7)

1. ecological revetment digitizes construction method, it is characterized in that:Comprise the following steps,
A, ecological revetment construction scheme storehouse is established;Construction scheme storehouse includes some construction schemes, described Some construction schemes include with different ecological bank protection type, with different Engineering Zone features, construction scheme Organization arrangement and Managed Solution;
B, engineering material database is established;By in all engineering material typing engineering material databases needed for ecological revetment, and And information-based coding is carried out to engineering material in engineering material database;
C, design of ecological slope protection scheme digital processing module is established;Digital processing module converts design of ecological slope protection scheme For material requested data;And processing is numbered in the design drawing in design of ecological slope protection scheme;
D, recording module is established;Material requested data and engineering material information are loaded into construction scheme storehouse, carried out pair The Data Enter answered;
E, output module is established;By In-put design drawing number, job location longitude and latitude and height above sea level, output module is drawn accordingly Material requested data and the design needed for engineering material information, output module is again by recording module from construction organization Corresponding organization arrangement and Managed Solution are transferred in scheme base.
2. ecological revetment according to claim 1 digitizes construction method, it is characterized in that:Described organization arrangement includes Engineering material, construction manpower and construction equipment.
3. ecological revetment according to claim 1 digitizes construction method, it is characterized in that:Described Managed Solution includes people Power management, construction management, quality management and safety management.
4. ecological revetment according to claim 1 digitizes construction method, it is characterized in that:Described information-based coding uses Barcode encoding, barcode encoding content include encoding the type, unit and quantity of engineering material.
5. ecological revetment according to claim 1 digitizes construction method, it is characterized in that:Described material requested packet Include the type and quantity, floristic type and quantity, the type and quantity of engineering component of engineering material.
6. ecological revetment according to claim 1 digitizes construction method, it is characterized in that:In described step E, mould is exported Block can also draw the use alphabetic data of material requested data in use, and will use order journal in information Change in coding.
7. ecological revetment according to claim 6 digitizes construction method, it is characterized in that:Engineering is used in work progress During material, workmen carries out barcode scanning using portable scanning device to engineering material, so as to confirm used engineering material symbol Close construction scheme storehouse.
CN201710851273.0A 2017-09-20 2017-09-20 Ecological slope protection digitizes construction method Expired - Fee Related CN107476320B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710851273.0A CN107476320B (en) 2017-09-20 2017-09-20 Ecological slope protection digitizes construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710851273.0A CN107476320B (en) 2017-09-20 2017-09-20 Ecological slope protection digitizes construction method

Publications (2)

Publication Number Publication Date
CN107476320A true CN107476320A (en) 2017-12-15
CN107476320B CN107476320B (en) 2019-04-09

Family

ID=60586963

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710851273.0A Expired - Fee Related CN107476320B (en) 2017-09-20 2017-09-20 Ecological slope protection digitizes construction method

Country Status (1)

Country Link
CN (1) CN107476320B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW200715132A (en) * 2005-10-05 2007-04-16 Univ Nat Pingtung Sci & Tech Mobile extension reality system applicable on calamity prevention plan on the slope
JP2008025138A (en) * 2006-07-19 2008-02-07 Public Works Research Institute Safety degree evaluating method for rock-bed slope
CN101968825A (en) * 2010-11-23 2011-02-09 中国矿业大学 Method for intelligently designing bolting of coal mine tunnels
CN106529065A (en) * 2016-11-15 2017-03-22 中建六局土木工程有限公司 Installation construction method for carrying out component optimization by software

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW200715132A (en) * 2005-10-05 2007-04-16 Univ Nat Pingtung Sci & Tech Mobile extension reality system applicable on calamity prevention plan on the slope
JP2008025138A (en) * 2006-07-19 2008-02-07 Public Works Research Institute Safety degree evaluating method for rock-bed slope
CN101968825A (en) * 2010-11-23 2011-02-09 中国矿业大学 Method for intelligently designing bolting of coal mine tunnels
CN106529065A (en) * 2016-11-15 2017-03-22 中建六局土木工程有限公司 Installation construction method for carrying out component optimization by software

Also Published As

Publication number Publication date
CN107476320B (en) 2019-04-09

Similar Documents

Publication Publication Date Title
Jin et al. Late Cenozoic mammalian faunal evolution at the Jinyuan Cave site of Luotuo Hill, dalian, northeast China
CN103758139A (en) Vegetation type anchor rod ecological bag and slope protection method thereof
CN107476320A (en) Ecological revetment digitizes construction method
CN207392215U (en) A kind of rock side slope ecological afforestation slope protection device
ARONSON et al. 20• Semi-arid woodlands and desert fringes
CN105103696A (en) Method for desertification control through salix bangongensis cuttage in high-altitude gobi wind-blown sand region
CN110396984A (en) A kind of reservoir drawdown band rock slope plant cover concrete bank protecting method
CN107491625A (en) Ecological revetment Design of digital model
CN213508506U (en) Ecological slope protection for water and soil conservation
Adhikari Tehri dam: An engineering marvel
Nickum et al. The Yellow River Basin
Du Application of vetiver grass in slope retaining and consolidation project in suide test area
Moffat Climate change and land regeneration
Xiao et al. Research on Ecological Protection and Restoration Technology of Fushun West Open pit Mine in Liaoning Province
Xiao et al. An Analysis on the Construction Technology and Management of Water Resources and Hydropower Projects
Renard et al. History of small watershed research in non-forested watersheds in Arizona and New Mexico
Li et al. Practice of Ecological Restoration of Slope in Power Transmission and Transformation Project
Spears et al. Climate Resilient Slope Stability Improvement Using Vetiver on a Test Levee
Jin et al. Research on the evaluation of ecological restoration and greening effect of rocky slopes based on hierarchical analysis method
Lu et al. Ecological benefit assessment of the South-North water transfer project: an eastern route
Binbin et al. Planning of land reclamation and ecological restoration in the coal mining subsidence areas of Wangwa coal mine
Ganguly et al. NETC's 400 kV Palatana-Silchar-Bongaigaon Double Circuit Corridor in North Eastern part of India–Challenges & Their Mitigation
Paton The Eighth Royal Society Technology Lecture Dams and their interfaces
Webley et al. Heritage Impact Assessment: Proposed construction of Letsoai and Enamandla 400kV powerline and substation facilities, near Aggeneys, Northern Cape
CHEN et al. Study on Ecological Restoration Technology of Slope for Power Transmission and Transformation Facilities

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190409

Termination date: 20190920

CF01 Termination of patent right due to non-payment of annual fee