CN107476301A - A kind of full casing follow-up step construction method of bridge pile foundation - Google Patents

A kind of full casing follow-up step construction method of bridge pile foundation Download PDF

Info

Publication number
CN107476301A
CN107476301A CN201710661866.0A CN201710661866A CN107476301A CN 107476301 A CN107476301 A CN 107476301A CN 201710661866 A CN201710661866 A CN 201710661866A CN 107476301 A CN107476301 A CN 107476301A
Authority
CN
China
Prior art keywords
casing
pile foundation
connecting portion
follow
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710661866.0A
Other languages
Chinese (zh)
Inventor
熊利文
刘旭炜
陈永祥
王祥懂
王康乐
姜国胜
刘振炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd, Third Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CN201710661866.0A priority Critical patent/CN107476301A/en
Publication of CN107476301A publication Critical patent/CN107476301A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/68Mould-pipes or other moulds for making bulkheads or elements thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses one kind to be used for the full casing follow-up step construction method of bridge pile foundation, including:(1) casing design and fabrication:Using multiple casings, can mutually be dismantled between each casing;(2) first section casing installation:Head section casings are connected with drill bit of drilling machine;(3) casing Follow-up type bored pile;(4) pile foundation filling concrete and casing are extracted.The present invention is effectively overcome in the easy collapse hole of fracture belt weak broken stratum construction bridges pile foundation boring, the difficulty of easy undergauge; pore-forming hole wall by the synchronous casing that follows up timely protection; no longer occurs the hole wall collapse caused by tomography geology is broken in drilling process, the problems such as excessive velocities occurs in sediment the problems such as so as to efficiently solve the collapse hole occurred in drilling process, bit freezing and after pore-forming borehole cleaning;Bad ground pile foundation construction quality is effectively ensured, it is ensured that the security of pile foundation construction, improve efficiency of construction, reduce cost.

Description

A kind of full casing follow-up step construction method of bridge pile foundation
Technical field
The invention discloses one kind to be used for the full casing follow-up step construction method of bridge pile foundation, and in particular to a kind of Earthquake Faulting With complicated geological layer, soil layer weak broken, rich in the full casing follow-up step construction method in the stratum such as underground water, easy collapse hole.
Background technology
Disorderly on fracture belt stratum at bridge pile foundation, rock mass weak broken, pile foundation passes through dust tomography more, and pore-forming is stranded Difficulty, easy collapse hole in pore forming process, easy undergauge, so that pile foundation construction quality is difficult to control, it is ensured that the bad ground pile foundation construction matter Amount turns into problem.
The content of the invention
The purpose of the present invention is difficult above to solve, and designs a kind of full casing follow-up step construction method of bridge pile foundation, real Border application display, this full casing follow-up pile base construction method is simple and efficient, and cost is low, high safety, and quality is guaranteed.
The technical scheme is that:A kind of full casing follow-up step construction method of bridge pile foundation, including:(1) casing designs With making:Using multiple casings, can mutually be dismantled between each casing;(2) first section casing installation:Head section casings are bored with rig Head is connected, and when drill bit of drilling machine direction of rotation is consistent with drill bit drilling direction, casing fastens with drill bit, when opposite direction rotates Can unlock drill bit of drilling machine and casing state, facilitate and drill bit is carried in borer drilling procedure go out boring mud.Examine after mounting first Concentricity, the perpendicularity of casing and drill bit of drilling machine are saved, ensures perpendicularity of the casing in follow-up drilling process;Head section casing length Determined according to surficial geology and drill bit of drilling machine single drilling depth, to ensure drilling progress, head section casings are typically no less than 2m; (3) casing Follow-up type bored pile:According to the stake position after setting-out, by drill bit of drilling machine center align piles position, vertical drilling, with stake position Face on the basis of ground, when the upper surface of casing is higher by reference plane H, next casing is connect, until reaching projected depth;(4) stake Base concrete is irrigated and casing is extracted:Crept into after stake holes to projected depth, lay pile foundation steel bar cage, concrete perfusion, mixed Coagulate in native filling process, casing Transducers Embedded in Concrete length is calculated according to concrete perfusion quantity and casing diameter, treats that casing buries Enter concrete length to meet when requiring, extract casing.
It is of the invention effective to overcome in the easy collapse hole of fracture belt weak broken stratum construction bridges pile foundation boring, easy undergauge Difficulty, pore-forming hole wall by the synchronous casing that follows up timely protection, no longer occur in drilling process because tomography geology is broken and Caused hole wall collapse, sediment the problems such as so as to efficiently solve the collapse hole occurred in drilling process, bit freezing and after pore-forming borehole cleaning There is the problems such as excessive velocities;Bad ground pile foundation construction quality is effectively ensured, it is ensured that the security of pile foundation construction, improve Efficiency of construction, reduces cost.
Such scheme uses multiple casings, from the surface, using the casing of multiple segmentations than using a long shield Cylinder is more time-consuming, in fact, the casing of multiple segmentations, can reduce the time that drilling is extracted with casing.And long casing is compared, Shorter casing, beneficial to the positioning between drill bit of drilling machine and stake position, positioning is simpler, more accurately.
Formed preferably, casing is rolled using 30mm steel plates, be 2-3m per segmental height, the technical characteristic is that synthesis is examined Consider the factors such as pile foundation drilling diameter, casing intensity, pile foundation Bedrock Geology condition and churning driven service behaviour index and determine.2- 3 meters of height as a casing, while a drilling stroke of rig is also served as, be advantageous to the drilling progress of rig, be beneficial to Positioning between drill bit and stake position.
Preferably, the top of the casing is provided with first connecting portion, all shields in addition to the casing of head sections The bottom of cylinder is provided with second connecting portion, passes through the second of the first connecting portion of previous casing and latter casing between adjacent casing Connecting portion is connected.
It can between each other connect, can also be not connected between casing, by the way of connection, be advantageous in step (4) The extraction of casing, save the engineering time.
Preferably, the internal diameter of the first connecting portion is less than the internal diameter of the second connecting portion, and first connection The first screwed hole is provided with portion, the second screwed hole is provided with second connecting portion, between first connecting portion and second connecting portion It is bolted.It is simple to operate.
Preferably, being provided with hanging hole in the first connecting portion, hook, institute are hinged with the outside of the second connecting portion State and be attached between first connecting portion and second connecting portion by linking up with hanging hole.It is simple to operate.
Preferably, the casing includes the two panels casing piece being hinged, casing piece is away from pin joint described in two panels One end is connected by buckling piece.In the vertical direction is detachably connected between casing, can also be beaten in the transverse direction of casing in itself Open, by the technical scheme, during drilling, after the drill bit of rig often bores the depth of a casing height, covered again without taking out drill bit If next casing, and directly casing can be put, greatly save drilling time.
Preferably, after the completion of pile-casting making, before use, carry out casing preassembling:The casing machined is being applied Work scene carries out preassembling, examines casing to connect horizontal, vertical limiter positional accuracy and reliability, ensures that casing can be by anticipation Requirement embedment and extract.
Preferably, whole casing is numbered after the completion of preassembling, when pressing preassembling during subsequent construction Numbering carries out casing spreading and dismounting.
Preferably, also including the maintenance to casing and casing quantity configuration, to ensure that rig can work continuously, machine is improved Tool utilization rate of equipment and installations, casing is covered according to rig rate of penetration and pile foundation filling concrete, pipe-pulling speed reasonable disposition 1.5-2, with Meet that rig can start the drilling of next pile base pile hole in a pile base in perfusion.
Preferably, the extraction of casing, is ejected casing merogenesis with hydraulic push bench, single push pipe length is single-unit casing Length.
Preferably, vertical fin or spiral ridge are provided with the outer surface of the casing.The setting of fin, it is existing Help drilling construction, accelerate the progress of drilling, and can enough reduces resistance when casing is extracted.
By implementing above-mentioned technical proposal, the present invention is effectively overcome in the construction bridges stake of fracture belt weak broken stratum Base drills easy collapse hole, the difficulty of easy undergauge, pore-forming hole wall by the synchronous casing that follows up timely protection, in drilling process no longer There is the hole wall collapse caused by tomography geology is broken, so as to efficiently solve the collapse hole occurred in drilling process, bit freezing etc. There is the problems such as excessive velocities in sediment after problem and pore-forming borehole cleaning;Bad ground pile foundation construction quality has been effectively ensured, it is ensured that The security of pile foundation construction, has saved the engineering time, improves efficiency of construction, reduces cost.
Brief description of the drawings
Accompanying drawing 1 is the schematic diagram of casing in one embodiment of the invention;
Accompanying drawing 2 is the connection diagram of casing shown in accompanying drawing 1;
Accompanying drawing 3 is casing schematic diagram in another embodiment of the present invention;
Accompanying drawing 4 is the top view of casing in another embodiment of the present invention.
In figure, 1- casings;11- first connecting portions;12- second connecting portions;The screwed holes of 111- first;112- hanging holes;121- Second screwed hole;122- is linked up with;The vertical fins of 13-.
Embodiment
Below in conjunction with the accompanying drawings and specific embodiment, the present invention is described in further detail.
Embodiment 1:
A kind of casing external member for Bridge Pile Foundation Construction, including multiple casings 1, shown in the Structure Figure 1 of casing 1, casing 1 Top is provided with first connecting portion 11, and the bottom of all casings 1 in addition to the casing 1 of head sections is provided with second connecting portion 12, the internal diameter of first connecting portion 11 is less than the internal diameter of the second connecting portion 12, and the is provided with the first connecting portion 11 One screwed hole 111, the second screwed hole 121 is provided with second connecting portion 12, is bolted between adjacent casing 1, it is such as attached Shown in Fig. 2.
A kind of full casing follow-up step construction method of bridge pile foundation, it is soft to be mainly used in Earthquake Fault Zone complicated geological layer, soil layer It is weak to crush, include rich in the stratum such as underground water, easy collapse hole, its specific method:(1) casing design and fabrication:Consider pile foundation The factors such as drilling diameter, casing intensity, pile foundation Bedrock Geology condition and churning driven service behaviour index, calculated according to foregoing experience Formula, casing material use 30mm roll of steel plate, are 2m per segmental length;(2) first section casing installation:To examine qualified casing with Drilling bit of rotary-digging drilling rig is connected, and when bit direction is consistent with drill bit drilling direction, casing fastens with drill bit, works as opposite direction Can unlock drill bit and casing during rotation state, facilitate and drill bit is carried in borer drilling procedure go out boring mud.Examine after mounting Concentricity, the perpendicularity of head section casings and drilling bit of rotary-digging drilling rig, ensure perpendicularity of the casing in follow-up drilling process;(3) protect Cylinder Follow-up type bored pile:According to the stake position after setting-out, by bit central align piles position, vertical drilling, using stake position ground as base Quasi- face, when the upper surface of casing is higher by reference plane H, next casing is connect, until reaching projected depth;Pore-forming hole wall by The timely protection of synchronous follow-up casing, no longer there is the hole wall collapse caused by tomography geology is broken in drilling process, so as to There is the problems such as excessive velocities in sediment after the problems such as efficiently solving the collapse hole occurred in drilling process, bit freezing and pore-forming borehole cleaning; (5) pile foundation filling concrete and casing are extracted:Crept into after stake holes to projected depth, by technical requirements, carry out borehole cleaning, lay stake Base steel reinforcement cage, concrete perfusion.During filling concrete, shield is calculated according to concrete perfusion quantity and steel pile casting diameter Cylinder Transducers Embedded in Concrete length, with hydraulic push bench by Follow-up type casing merogenesis top when casing Transducers Embedded in Concrete length meets to require Go out, be advisable in principle by single-unit casing length of single push pipe length.
Embodiment 2:
A kind of casing external member for Bridge Pile Foundation Construction, including multiple casings 1, the top of casing 1 are provided with first connecting portion 11, the bottom of all casings 1 in addition to the casing 1 of head sections is provided with second connecting portion 12, first connecting portion 11 it is interior Footpath is less than the internal diameter of the second connecting portion 12, and hanging hole 112 is provided with the first connecting portion 11, second connecting portion 12 Outside is hinged with hook 122, as shown in Figure 3, is attached between adjacent casing 1 by hook 122 with hanging hole 112.Casing 1 Outer surface on be provided with vertical vertical fin 13, as shown in Figure 4.
A kind of full casing follow-up step construction method in bridge pile foundation difficulty pore-forming stratum, including:(1) casing design and fabrication:It is comprehensive Close and consider the factors such as pile foundation drilling diameter, casing intensity, pile foundation Bedrock Geology condition and churning driven service behaviour index, according to preceding Empirical formula is stated, casing is rolled using 30mm steel plates and formed, and is 3m per segmental length;(2) casing examination is assembled:To processing Into casing carry out preassembling at the construction field (site), examine casing to connect horizontal, vertical limiter positional accuracy and reliability, ensure Casing can be embedded to and extracted by the requirement of anticipation.Whole casing is numbered after the completion of preassembling, during subsequent construction Casing spreading and dismounting are carried out by numbering during preassembling;(3) first section casing installation:Preassembling is examined into qualified casing and rotation Dig drill bit of drilling machine to be connected, when bit direction is consistent with drill bit drilling direction, casing fastens with drill bit, when opposite direction is revolved Can unlock drill bit and casing when turning state, facilitate and drill bit is carried in borer drilling procedure go out boring mud.Examine after mounting first Concentricity, the perpendicularity of casing and drilling bit of rotary-digging drilling rig are saved, ensures perpendicularity of the casing in follow-up drilling process;(4) casing Follow-up type bored pile:According to the stake position after setting-out, by bit central align piles position, vertical drilling, on the basis of the ground of stake position Face, when the upper surface of casing is higher by reference plane H, connect next casing, pore-forming hole wall by synchronous the timely of casing of following up Protect, no longer occur the hole wall collapse caused by tomography geology is broken in drilling process, so as to efficiently solve drilling process There is the problems such as excessive velocities in sediment after the problems such as collapse hole of middle appearance, bit freezing and pore-forming borehole cleaning;(5) pile foundation filling concrete and Steel pile casting is extracted.Crept into after stake holes to projected depth, by technical requirements, carry out borehole cleaning, lay pile foundation steel bar cage, irrigate coagulation Soil.During filling concrete, casing Transducers Embedded in Concrete length is calculated according to concrete perfusion quantity and steel pile casting diameter, Follow-up type casing merogenesis is ejected with hydraulic push bench when casing Transducers Embedded in Concrete length meets to require, in principle with single top Length of tube is that single-unit casing length is advisable;(6) casing maintenance and casing quantity configuration.To ensure that rotary drilling rig can work continuously, Plant equipment utilization rate is improved, according to rotary drilling rig rate of penetration and pile foundation filling concrete, pipe-pulling speed reasonable disposition 1.5 ~ 2 Follow-up type casing is covered, to meet that rotary drilling rig can start the drilling of next pile base pile hole in a pile base in perfusion.
It is of the invention effective to overcome in the easy collapse hole of fracture belt weak broken stratum construction bridges pile foundation boring, easy undergauge Difficulty, bad ground pile foundation construction quality is effectively ensured, it is ensured that the security of pile foundation construction, improve efficiency of construction, drop Low cost.
Embodiment 3:
A kind of casing external member for Bridge Pile Foundation Construction, including multiple casings 1, the top of casing 1 are provided with first connecting portion 11, the bottom of all casings 1 in addition to the casing 1 of head sections is provided with second connecting portion 12, first connecting portion 11 it is interior Footpath is less than the internal diameter of the second connecting portion 12, and hanging hole 112 is provided with the first connecting portion 11, second connecting portion 12 Outside is hinged with hook 122, is attached between adjacent casing 1 by hook 122 with hanging hole 112.Set on the outer surface of casing 1 It is equipped with spiral ridge.
A kind of full casing follow-up step construction method in bridge pile foundation difficulty pore-forming stratum, including:(1) casing design and fabrication:It is comprehensive Close and consider the factors such as pile foundation drilling diameter, casing intensity, pile foundation Bedrock Geology condition and churning driven service behaviour index, according to preceding Empirical formula is stated, casing is rolled using 30mm steel plates and formed, and is 2.5m per segmental length;(2) casing examination is assembled:To processing The casing of completion carries out preassembling at the construction field (site), examines casing to connect horizontal, vertical limiter positional accuracy and reliability, protects Casing is demonstrate,proved to be embedded to and extracted by the requirement of anticipation.Whole casing is numbered after the completion of preassembling, in subsequent construction process In numbering when pressing preassembling carry out casing spreading and dismounting;(3) first section casing installation:By preassembling examine qualified casing with Drilling bit of rotary-digging drilling rig is connected, and when bit direction is consistent with drill bit drilling direction, casing fastens with drill bit, works as opposite direction Can unlock drill bit and casing during rotation state, facilitate and drill bit is carried in borer drilling procedure go out boring mud.Examine after mounting Concentricity, the perpendicularity of head section casings and drilling bit of rotary-digging drilling rig, ensure perpendicularity of the casing in follow-up drilling process;(4) protect Cylinder Follow-up type bored pile:According to the stake position after setting-out, by bit central align piles position, vertical drilling, using stake position ground as base Quasi- face, when the upper surface of casing is higher by reference plane H, connect next casing, pore-forming hole wall by the synchronous casing that follows up and When protect, no longer occur the hole wall collapse caused by tomography geology is broken in drilling process, crept into so as to efficiently solve There is the problems such as excessive velocities in sediment after the problems such as collapse hole that occurs in journey, bit freezing and pore-forming borehole cleaning;(5) pile foundation filling concrete And steel pile casting is extracted.Crept into after stake holes to projected depth, by technical requirements, carry out borehole cleaning, lay pile foundation steel bar cage, perfusion is mixed Solidifying soil.During filling concrete, casing Transducers Embedded in Concrete length is calculated according to concrete perfusion quantity and steel pile casting diameter Degree, Follow-up type casing merogenesis is ejected with hydraulic push bench when casing Transducers Embedded in Concrete length meets to require, in principle with list Secondary push pipe length is that single-unit casing length is advisable;(6) casing maintenance and casing quantity configuration.To ensure that rotary drilling rig can continuously be made Industry, plant equipment utilization rate is improved, according to rotary drilling rig rate of penetration and pile foundation filling concrete, pipe-pulling speed reasonable disposition 1.5 ~ 2 sets of Follow-up type casings, to meet that rotary drilling rig can start the brill of next pile base pile hole in a pile base in perfusion Enter;(7) construction that (3)-(6) continue to complete remaining bridge pile foundation is repeated.

Claims (9)

1. a kind of full casing follow-up step construction method of bridge pile foundation, it is characterised in that comprise the following steps:(1) casing design with Make:Using multiple casings, can mutually be dismantled between each casing;(2) first section casing installation:By head section casings and drill bit of drilling machine It is connected;(3) casing Follow-up type bored pile:It is vertical to bore by drill bit of drilling machine center align piles position according to the stake position after setting-out Enter, the face on the basis of the ground of stake position, when the upper surface of casing is higher by reference plane H, connect next casing, until it is deep to reach design Degree;(4) pile foundation filling concrete and casing are extracted:Crept into after stake holes to projected depth, lay pile foundation steel bar cage, irrigate coagulation Soil, during filling concrete, casing Transducers Embedded in Concrete length is calculated according to concrete perfusion quantity and casing diameter, treated When casing Transducers Embedded in Concrete length meets to require, casing is extracted.
2. the full casing follow-up step construction method of a kind of bridge pile foundation according to claim 1, it is characterised in that the casing is adopted Rolled and formed with 30mm steel plates, be 2-3m per segmental height.
3. the full casing follow-up step construction method of a kind of bridge pile foundation according to claim 1, it is characterised in that the casing Top is provided with first connecting portion, and the bottom of all casings in addition to the casing of head sections is provided with second connecting portion, phase It is connected between adjacent casing by the first connecting portion of previous casing with the second connecting portion of latter casing.
A kind of 4. full casing follow-up step construction method of bridge pile foundation according to claim 1, it is characterised in that the casing bag The two panels casing piece being hinged is included, the one end of casing piece away from pin joint is connected by buckling piece described in two panels.
5. the full casing follow-up step construction method of a kind of bridge pile foundation according to claim 3, it is characterised in that described first connects The internal diameter of socket part is less than the internal diameter of the second connecting portion, and the first screwed hole is provided with the first connecting portion, and second connects The second screwed hole is provided with socket part, is bolted between first connecting portion and second connecting portion.
6. the full casing follow-up step construction method of a kind of bridge pile foundation according to claim 3, it is characterised in that described first connects Hanging hole is provided with socket part, is hinged with hook on the outside of the second connecting portion, the first connecting portion and second connecting portion it Between be attached by linking up with hanging hole.
7. the full casing follow-up step construction method of a kind of bridge pile foundation according to claim 1, it is characterised in that in pile-casting making After the completion of, before use, carry out casing preassembling.
8. the full casing follow-up step construction method of a kind of bridge pile foundation according to claim 1, it is characterised in that also include to shield The maintenance of cylinder and casing quantity configuration.
9. the full casing follow-up step construction method of a kind of bridge pile foundation according to claim 1, it is characterised in that the casing Vertical fin or spiral ridge are provided with outer surface.
CN201710661866.0A 2017-08-04 2017-08-04 A kind of full casing follow-up step construction method of bridge pile foundation Pending CN107476301A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710661866.0A CN107476301A (en) 2017-08-04 2017-08-04 A kind of full casing follow-up step construction method of bridge pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710661866.0A CN107476301A (en) 2017-08-04 2017-08-04 A kind of full casing follow-up step construction method of bridge pile foundation

Publications (1)

Publication Number Publication Date
CN107476301A true CN107476301A (en) 2017-12-15

Family

ID=60597534

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710661866.0A Pending CN107476301A (en) 2017-08-04 2017-08-04 A kind of full casing follow-up step construction method of bridge pile foundation

Country Status (1)

Country Link
CN (1) CN107476301A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797581A (en) * 2018-08-07 2018-11-13 中国十七冶集团有限公司 A kind of bridge pile foundation churning driven construction assembled steel pile casting structure and its installation method
CN108951614A (en) * 2018-08-02 2018-12-07 长江勘测规划设计研究有限责任公司 A kind of spigot-and-socket drilled pile steel pile casting and its construction method
CN109519175A (en) * 2018-12-30 2019-03-26 浙江工业大学 A kind of rectangular top pipe and its construction method
CN110067508A (en) * 2019-03-26 2019-07-30 陕西华山路桥集团有限公司 A kind of novel spiral-digging pore method for boulder bed
CN110952558A (en) * 2019-12-13 2020-04-03 中建三局第一建设工程有限责任公司 Automatic embedding device and system for pile foundation casing
CN111021413A (en) * 2019-12-31 2020-04-17 青岛时代建筑设计有限公司 Reverse construction method based on assembly type concept
CN111101865A (en) * 2019-12-30 2020-05-05 深圳市盛业地下工程有限公司 High efficiency drilling equipment
CN112177555A (en) * 2020-10-22 2021-01-05 中国能源建设集团陕西省电力设计院有限公司 Detachable wellhead reinforcing and protecting device
CN112554783A (en) * 2020-11-12 2021-03-26 北京建工土木工程有限公司 Dry hole-forming drilling machine for construction in underground narrow space and construction method
CN113718798A (en) * 2021-10-09 2021-11-30 中建八局第二建设有限公司 Construction method for layered construction pore-forming of rock-socketed secant pile in riprap region near sea
CN115247419A (en) * 2021-04-28 2022-10-28 广州市建筑科学研究院有限公司 Full-length steel casing concrete cast-in-place pile construction equipment and method without slurry discharge
CN112177555B (en) * 2020-10-22 2024-06-11 中国能源建设集团陕西省电力设计院有限公司 Detachable wellhead reinforcing and protecting device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102146672A (en) * 2011-03-15 2011-08-10 中铁六局集团有限公司 Method for constructing pile foundation in karst area
CN103266599A (en) * 2013-05-13 2013-08-28 汇通路桥建设集团有限公司 Construction method of rotating drilling dry-drilled piles of sand soil interlayer foundation
CN104831708A (en) * 2015-03-20 2015-08-12 深圳市工勘岩土集团有限公司 Foundation excavation retaining and protecting cast-in-situ bored pile construction method and equipment thereof
CN105735251A (en) * 2016-01-26 2016-07-06 赵立财 Bridge pile foundation rotary excavating drilling rig cutting type whole guard barrel follow-up pile forming construction method and system
CN105970918A (en) * 2016-03-23 2016-09-28 中铁四局集团钢结构有限公司 Pile foundation hole forming construction process under large-particle-size cobble sandy soil and severe water seepage geological condition

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102146672A (en) * 2011-03-15 2011-08-10 中铁六局集团有限公司 Method for constructing pile foundation in karst area
CN103266599A (en) * 2013-05-13 2013-08-28 汇通路桥建设集团有限公司 Construction method of rotating drilling dry-drilled piles of sand soil interlayer foundation
CN104831708A (en) * 2015-03-20 2015-08-12 深圳市工勘岩土集团有限公司 Foundation excavation retaining and protecting cast-in-situ bored pile construction method and equipment thereof
CN105735251A (en) * 2016-01-26 2016-07-06 赵立财 Bridge pile foundation rotary excavating drilling rig cutting type whole guard barrel follow-up pile forming construction method and system
CN105970918A (en) * 2016-03-23 2016-09-28 中铁四局集团钢结构有限公司 Pile foundation hole forming construction process under large-particle-size cobble sandy soil and severe water seepage geological condition

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951614A (en) * 2018-08-02 2018-12-07 长江勘测规划设计研究有限责任公司 A kind of spigot-and-socket drilled pile steel pile casting and its construction method
CN108951614B (en) * 2018-08-02 2023-12-01 长江勘测规划设计研究有限责任公司 Socket type bored pile steel pile casing and construction method thereof
CN108797581A (en) * 2018-08-07 2018-11-13 中国十七冶集团有限公司 A kind of bridge pile foundation churning driven construction assembled steel pile casting structure and its installation method
CN109519175A (en) * 2018-12-30 2019-03-26 浙江工业大学 A kind of rectangular top pipe and its construction method
CN110067508A (en) * 2019-03-26 2019-07-30 陕西华山路桥集团有限公司 A kind of novel spiral-digging pore method for boulder bed
CN110952558A (en) * 2019-12-13 2020-04-03 中建三局第一建设工程有限责任公司 Automatic embedding device and system for pile foundation casing
CN111101865A (en) * 2019-12-30 2020-05-05 深圳市盛业地下工程有限公司 High efficiency drilling equipment
CN111021413B (en) * 2019-12-31 2021-05-28 青岛时代建筑设计有限公司 Reverse construction method based on assembly type concept
CN111021413A (en) * 2019-12-31 2020-04-17 青岛时代建筑设计有限公司 Reverse construction method based on assembly type concept
CN112177555A (en) * 2020-10-22 2021-01-05 中国能源建设集团陕西省电力设计院有限公司 Detachable wellhead reinforcing and protecting device
CN112177555B (en) * 2020-10-22 2024-06-11 中国能源建设集团陕西省电力设计院有限公司 Detachable wellhead reinforcing and protecting device
CN112554783A (en) * 2020-11-12 2021-03-26 北京建工土木工程有限公司 Dry hole-forming drilling machine for construction in underground narrow space and construction method
CN115247419A (en) * 2021-04-28 2022-10-28 广州市建筑科学研究院有限公司 Full-length steel casing concrete cast-in-place pile construction equipment and method without slurry discharge
CN113718798A (en) * 2021-10-09 2021-11-30 中建八局第二建设有限公司 Construction method for layered construction pore-forming of rock-socketed secant pile in riprap region near sea

Similar Documents

Publication Publication Date Title
CN107476301A (en) A kind of full casing follow-up step construction method of bridge pile foundation
CN103244051B (en) A kind of combined down-hole hammer drilling tool and pile forming method thereof
CN103485336B (en) Drilling pile drilling construction method of bead-type karst area
CN105649012B (en) Upper-soft lower-hard ground subway station building enclosure drilled pile construction method
CN106245626A (en) A kind of hard formation churning driven enters method
CN101570971B (en) Rock mass pile foundation pore-forming preboring construction method
CN104295239A (en) Method for using rotary drilling rig to drill into hard rock stratum
CN106121657A (en) A kind of multifunctional numerical control shaft sinking device and construction method
CN107237323A (en) Major diameter super thick boulder bed forming hole method
CN101586340A (en) Preconditioning process of continuous wall for weak weathering terrane grooving construction
CN111335306A (en) Rapid construction method for deep and thick hard rock section drilled pile
CN104912065B (en) Dowel pile construction method under water
CN107339122B (en) Construction method for treating goaf by steel pipe column
CN104832082A (en) Pneumatic DTH hammer reverse circulation slagging construction process for rotary drilling rig
CN106246099A (en) Spiral soil compaction down-the-hole embedding rock device and pile making method
CN106930276A (en) The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles
CN110043312A (en) A kind of control method of grouting filling ground settlement range
CN109667537A (en) A kind of drilling process of prospecting filling land pebble solution cavity
CN107327306A (en) Tunnel excavation construction method is superimposed under the conditions of the shallow embedding of city
CN203584301U (en) Hole guide equipment
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN108397128A (en) A kind of bridge construction perforating device and its drilling method
CN213812473U (en) Device suitable for karst wetland earth's surface and ground water level monitoring
CN207453902U (en) A kind of full circle swinging all casing drill
CN105200994A (en) Construction method for reserved shield crossing composite foundation pit support device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171215

RJ01 Rejection of invention patent application after publication