CN107447665B - A kind of laying method of self-anchored suspension bridge construction cat road carrying rope - Google Patents

A kind of laying method of self-anchored suspension bridge construction cat road carrying rope Download PDF

Info

Publication number
CN107447665B
CN107447665B CN201710701769.XA CN201710701769A CN107447665B CN 107447665 B CN107447665 B CN 107447665B CN 201710701769 A CN201710701769 A CN 201710701769A CN 107447665 B CN107447665 B CN 107447665B
Authority
CN
China
Prior art keywords
rope
cat road
carrying rope
carrying
cat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710701769.XA
Other languages
Chinese (zh)
Other versions
CN107447665A (en
Inventor
朱道付
金仁才
孔炯
郑治飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710701769.XA priority Critical patent/CN107447665B/en
Publication of CN107447665A publication Critical patent/CN107447665A/en
Application granted granted Critical
Publication of CN107447665B publication Critical patent/CN107447665B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/02Suspension bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of self-anchored suspension bridge construction laying methods of cat road carrying rope, it is related to field of bridge construction, it is characterized in that by tower top steel platform on the king-tower of the suspention of main push-towing rope laying, the tower crane of Construction of Pylon and cable saddle lifting, in advance by the grouping of cat road carrying rope setting, it will be below cat road carrying Suo Yunzhi king-tower with towboat, it is lifted again with tower crane and suspention, it realizes the aerial laying of cat road carrying rope and is fixed in corresponding fixed point, other cat roads of suspension bridge carrying rope laying is similarly completed, to complete the aerial laying work of cat road carrying rope;Its construction procedure are as follows: one, preparation of construction;Two, cat road carries rope group pair;Three, rope is applied in the air;Four, cat road carrying rope adjustment.The present invention can reduce construction personnel and lay the aerial work of cat road carrying Suo Suoxu and the time that water route is iceound, improve construction efficiency, guarantee construction speed, have good economic benefit and social benefit.

Description

A kind of laying method of self-anchored suspension bridge construction cat road carrying rope
Technical field
The present invention relates to field of bridge construction, and in particular to a kind of laying of self-anchored suspension bridge construction cat road carrying rope Method.
Background technique
Cat road is under main rope of suspension bridge and to be parallel to a kind of linear temporary construction aerial platform of main push-towing rope, and cat road is held The core component that rope is operation platform is carried, generally by eight wirerope in being arranged in parallel with main push-towing rope and both ends are anchored at king-tower respectively On the anchoring part at end and bridge bank end, the carrying rope center line after forming is lower than main push-towing rope center line 1500mm or so, to facilitate constructor Such as strand traction is completed on the road Yuan Mao, adjusts stock, shaping to enter saddle, jam-packed, cord clip and hoist cable installation, box beam lifting and main push-towing rope to twine The construction tasks such as silk, protective coating.
Cat road carrying rope installation conventional method be using laying main rope of suspension bridge suspention, by the road Gen Jiangmao carry rope from Bridge bank end is drawn to anchoring on king-tower, or is towed from bridge bank end to being attached anchoring, above method from king-tower with towboat by root Operation is more in construction space-time, and the water route iceound time is long, and construction efficiency is low, directly restricts construction speed.
Currently, retrieving the patent of similar title about the self-anchored suspension bridge construction laying method of cat road carrying rope Design, as China national Patent Office's on April 29th, 2009 announce " a kind of space self-anchored type suspension cable funicular system construction method ", Announce in publication No. CN101418542A and on October 10th, 2012 " guide cable crosses river and the integrated construction party of Traction sysytem Method ", two similar to the laying method in construction patents without specifically describing cat road carrying rope.
Summary of the invention
The purpose of the present invention is to propose to a kind of self-anchored suspension bridge construction laying methods of cat road carrying rope, reduce construction Personnel lay the aerial work of cat road carrying Suo Suoxu and the time that water route is iceound, improve construction efficiency, guarantee construction speed.
To achieve the above object, the invention provides the following technical scheme:
A kind of laying method of self-anchored suspension bridge construction cat road carrying rope of the present invention, it is characterized in that: being applied by main push-towing rope If suspention, Construction of Pylon tower crane and cable saddle lifting king-tower on tower top steel platform, in advance by cat road carrying rope setting point Wirerope is placed in parallel by group by arrangement spacing, and will have been put down with anchor beam, adjusting yoke, connecting rod, rope card respectively at its both ends Row is put and Justified wirerope connects to form cat road carrying rope, is carried in the cat road of grouping under Suo Yunzhi king-tower with towboat Side, then lifted with tower crane and suspention, realize the aerial laying of cat road carrying rope and be fixed in corresponding fixed point, similarly complete Other cat roads of suspension bridge carry rope laying, to complete the aerial laying work of cat road carrying rope;
The cat road carrying rope includes anchorage, anchor beam under cat road carrying rope upper fixed seat, cat road carrying rope, adjusts and draw Bar, connecting rod, rope card and wirerope;Cat road carrying rope installation front suspension, tower crane, the tower top steel platform on king-tower have had use Condition, cat road carry anchorage and the road king-tower Shang Mao under the road Suo Mao carrying rope upper fixed seat and cat road carrying rope and carry on rope Workbench below fixing seat has been arranged in place, construction procedure are as follows: one, preparation of construction;Two, cat road carries rope group pair;Three, Deposited rope in the air;Four, cat road carrying rope adjustment;
Wherein:
Step 1: preparation of construction:
According to the linear of main rope of suspension bridge, the both ends for calculating cat road carrying rope carry under rope in the road bridge An Duanmao respectively Anchorage and the road king-tower Shang Mao carrying rope upper fixed seat position dimension and suspention carrying rope both ends carry under rope in suspention respectively Suspention at anchorage and tower top steel platform carries rope upper fixed seat position dimension;Cat road carries rope centered on main push-towing rope center line And parallel and position lower than main push-towing rope center line 1500mm is to calculate cat road to carry rope installation theoretical position;
Anchorage synchronizes embedded when bridge bank end dissipates cable saddle foundation construction under cat road carrying rope, and cat road carries rope upper fixed seat Synchronous in concrete construction of main tower to implement, anchorage is in the main push-towing rope Anchor Foundation concrete construction of bridge bank end under suspention carrying rope Synchronous construction, suspention carrying rope upper fixed seat are directly welded and fixed with tower top steel platform column side;
Cat road carrying rope is symmetrically laid with king-tower to bridge bank end by group, is laterally pulled with reducing the imbalance that king-tower is subject to Power;
Before cat road carries rope installation, it is ensured that suspention carrying rope has been fixed in anchorage and suspention carrying rope under suspention carrying rope It between upper fixed seat, and suspends sport car in midair and has been suspended on suspention carrying rope, traction rope winds 3 from the reel of angle mill hoist engine After circle, diverted wheel is fixed on the suspention left and right end of sport car, and suspention sport car moves back and forth and crane hook descending stroke has been expired The road Zu Mao carries the laying demand of rope, and the workbench below tower top steel platform and cat road carrying rope upper fixed seat has installed Finish;
Step 2: cat road carries rope group pair:
The wirerope of the every road Zu Mao carrying rope is 8, is placed in parallel by arrangement spacing, the two ends of each wirerope are all made of Anchor beam, adjusting yoke, connecting rod, rope card are formed by connecting;Wherein, the rope end of each wirerope of cat road carrying rope through rope card and is adjusted Pull rod is fixed, and then the adjusting yoke other end is connect with anchor beam, then the fixed connecting rod on anchor beam, i.e. completion cat road carries rope The group pair of one end;Equally according to said method complete the group pair of this cat road carrying rope other end;Then the carrying of other roads Zu Mao is completed again The group pair at rope both ends;Connecting rod on the both ends anchor beam of cat road carrying rope for carried respectively with cat road rope upper fixed seat and Cat road carries anchorage under rope and connects;
Step 3: applying rope in the air:
The cat road carrying rope that assembling finishes is transported to below king-tower with towboat, is separately connected cat road carrying rope both ends with hoist cable Anchor beam center at, with the hoist cable of crane hook fixed bridge bank end anchor beam, promoted at crane hook to suspention sport car, hoist cable moved To suspention sport car, then crane hook back hook, connection cat road are carried at the hoist cable on other end anchor beam, are slowly promoted tower crane and are hung Hook, the road Shi Mao carrying rope are gradually promoted, and in suspention sport car and tower crane to carrying off, cat road carrying rope progressively disengages towboat, continues Crane hook is promoted, so that anchor beam is moved at cat road carrying rope upper fixed seat, is then held the connecting rod on anchor beam with Mao Dao It carries rope upper fixed seat to be fixedly connected, completes to fix at cat road carrying rope king-tower;It starts angle and grinds hoist engine, suspend sport car in midair in traction rope Drive under it is mobile towards bridge bank end, under the action of suspending the tractive force and suspention sport car sliding force of sport car in midair, cat road is carried under rope End anchor beam is moved under the cat road carrying rope on scattered cable saddle basis at anchorage, and the connecting rod on anchor beam is casted anchor with cat road carrying rope Gu seat is fixedly connected, complete to fix at the scattered cable saddle of cat road carrying rope;Similarly other cat roads carrying rope is completed with the above laying method Laying work;
Step 4: cat road carrying rope adjustment:
In order to guarantee the balance of king-tower horizontal force, upstream and downstream and the road across Duan Mao carrying rope should all terminate in place, and Bands shape is carried to cat road at any time during adjustment and king-tower displacement is monitored;
Cat road carries rope should carry out live adjustment according to its sky cable absolute altitude, to guarantee that cat road carrying bands type and main push-towing rope are unloaded Line style is almost the same;Chain block is set between anchor beam and adjusting yoke, adjusting yoke is cooperated by chain block, completes steel The elastic state adjustment of cord, keeps every steel wire rope tension consistent, and the wirerope adjustment of cat road carrying rope is using the side pulled by root Formula carries out.
Further, anchorage and suspention carrying under the road step 1 Zhong Mao carrying rope upper fixed seat, cat road carrying rope Anchorage is all made of length 1000mm under rope upper fixed seat, suspention carrying rope, and specification is made of the rail of QU80, in rail one end The through-hole that diameter is 62mm is opened up at the center web of the rail 90mm, by aperture end towards outside when rail is embedded, anchorage depth, angle are combined Construction site condition determines that stress load is pressed maximum cat road carrying rope respectively, suspended in midair on carrying rope with 3D simulation and Force Calculation 3 times of safety coefficients of load are calculated.
Further, the step 2 adjusting yoke and the equal one end of connecting rod are connection wire rod and the long 600mm of thread, The other end is that the body of rod bends to annulus closing form, and bending internal diameter is 100mm, and adjusting yoke diameter is 42mm, and length is equal 800mm, connection shank diameter are 60mm, the equal 1000mm of length;
The 20# I-shaped steel part that the anchor beam is two pieces length 3800mm forms, and I-steel is by length direction and by two works Word steel between the two away from being arranged for 65mm mode, and is symmetrical with I-steel length direction center line by web is parallel, wing plate is concordant Line, the distance centered on equidistant 450mm is pressed on the wing plate surface of wherein side, is welded with 8 pieces of centers and opens up diameter 45mm through-hole, outside Shape is having a size of 150mm × 150mm, and the backing plate of thickness 40mm, pressing 2200mm on its another side wing surface is spacing, is welded with 2 pieces It is 62mm through-hole that center, which opens up diameter, and outer dimension is 150mm × 150mm, and the backing plate of thickness 40mm welds two I-steel solid It is shaped as anchor beam;
The road Liang Zumao carrying rope is arranged under a piece main rope of suspension bridge and is to be arranged symmetrically with king-tower, the every road Zu Mao carrying rope Wirerope one end is folded to wirerope after passing through adjusting yoke closed circle backward and is overlapped 1000mm in parallel along its length, with 6 Rope end and wirerope, are fixed together every 100mm, then will be installed with 8 adjusting yoke screw rod ends of wirerope by a rope card, It is welded with from the length direction of anchor beam in the gap of the wing plate opposite side of 8 pieces of backing plates, is used in combination respectively parallel across backing plate central through hole Nut is attached with anchor beam, and the nut of adjusting yoke should be at maximal regulated position at this time.Then by the screw rod end of connecting rod It is welded with from the length direction of anchor beam in the intermediate space of the wing plate side of 8 pieces of backing plates, respectively by two connecting rods from the another of anchor beam Two pieces of backing plate central through holes of side setting are pierced by, and are realized connecting rod and anchor beam with nut and connected, and the above completion cat road is held The group pair for carrying Suo Yiduan equally according to said method completes the group pair of this cat road carrying rope other end.
Further, step 3 pin shaft passes through the annulus of cat road carrying rope upper fixed seat through-hole and connecting rod, complete It carries at cat road and is fixed at rope king-tower;The annulus that block hole and connecting rod are anchored under cat road carrying rope is equally passed through with pin shaft, it is complete It dissipates at cat road carrying rope and is fixed at cable saddle.
Compared with prior art, the laying side of a kind of self-anchored suspension bridge proposed by the invention construction cat road carrying rope Method reduces aerial work and water route iceound time, improves construction efficiency, ensure that construction speed.
Detailed description of the invention
Fig. 1 is a side anchor in a kind of laying method of self-anchored suspension bridge construction proposed by the invention cat road carrying rope Heavy stone used as an anchor schematic diagram;
Fig. 2 is king-tower area in a kind of laying method of self-anchored suspension bridge construction proposed by the invention cat road carrying rope Domain schematic diagram;
Fig. 3 is suspention and tower crane arrangement signal in a kind of laying method of self-anchored suspension bridge construction cat road carrying rope Figure;
The road Tu4Shi Mao carries rustling sound end combination diagram;
The road Tu5Shi Mao carries rope and lays schematic diagram one;
The road Tu6Shi Mao carries the fixed schematic diagram of Suo Yiduan;
Fig. 7 is Fig. 6 top view;
The road Tu8Shi Mao carries rope and lays schematic diagram two;
Fig. 9 is Fig. 8 top view;
In figure: 1, anchorage 2, suspention carrying rope upper fixed seat 3, cat road carry anchorage under rope under suspention carrying rope 4, cat road carrying rope upper fixed seat 5, tower top steel platform 6, deflecting roller 7, workbench 8, tower crane 9, king-tower 10, angle mill volume Raise machine 11, suspention sport car 12, traction rope 13, suspention carrying rope 14, main push-towing rope 15, anchor beam 16, adjusting yoke 17, connection Bar 18, hoist cable 19, chain block 20, towboat 21, pin shaft 22, crane hook 23, cat road carry rope 24, main push-towing rope anchorage Basis 25 dissipates cable saddle basis 26, rope card.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Unless otherwise defined, the technical term or scientific term used herein should be in disclosure fields and has The ordinary meaning that the personage of general technical ability is understood.Used in disclosure patent application specification and claims "upper", "lower", "left", "right" etc. are only used for indicating relative positional relationship, after the absolute position for being described object changes, then should Relative positional relationship also correspondingly changes.
By taking the bridge of Luodian County 1 as an example, which is (102+71) m self-anchored suspension bridge, and planning bridge floor clear span is 23m (net -15m+2 × pavement 4m), the long 180m of bridge.Girder uses concrete box girder, and king-tower uses rectangular section double tower, is reinforcing bar Concrete structure, full-bridge set two main push-towing ropes altogether, and main push-towing rope uses anchoring hot-cast anchor system, and after main push-towing rope dissipates cable saddle, main push-towing rope is in radiation Shape is scattered.Main push-towing rope main span is 92m, and rise 9.05m, sag ratio 1/10.2, main push-towing rope end bay is 62m, rise 4.2m, sag ratio 1/ 14.8.The wirerope group that this engineering cat road carries 8 φ 54 (6 × 37S-IWR) of Suo Caiyong becomes one group, is needed altogether according to construction Lay four roads Zu Mao carrying rope.
The cat road carrying rope 23 includes anchorage 3 under cat road carrying rope upper fixed seat 4, cat road carrying rope, anchor beam 15, adjusts Save pull rod 16, connecting rod 17, rope card 26 and wirerope, Specific construction step are as follows:
Step 1: preparation of construction (as shown in Figure 1, Figure 2, Figure 3 shows):
According to the linear of main rope of suspension bridge 14, determined according to the actual conditions of design drawing and construction site through relevant calculation The road Chu Mao carries rope 23, suspention carrying 13 both ends of rope 9 road Chu Mao of anchorage 3 and king-tower in the case where the road bridge An Duanmao carries rope respectively It is fixed on carrying 4 position dimension of rope upper fixed seat and anchorage 1 under suspention carrying rope and the suspention carrying rope at tower top steel platform 5 2 position dimensions of seat.Cat road carries rope 23 centered on 14 center line of main push-towing rope simultaneously in parallel and lower than 14 center line 1500mm's of main push-towing rope Position is to calculate cat road to carry the installation theoretical position of rope 23.
Anchorage 3 dissipates at bridge bank end under cat road carrying rope synchronizes embedded, cat road carrying Suo Shanggu when cable saddle basis 25 is constructed Reservation 4 is synchronous in 9 concrete construction of king-tower to be implemented, and anchorage 1 is mixed in bridge bank end main push-towing rope Anchor Foundation 24 under suspention carrying rope Synchronous construction when solidifying soil construction, suspention carrying rope upper fixed seat 2 are directly welded and fixed with 5 column side of tower top steel platform.
Cat road carrying rope 23 is symmetrically laid with king-tower 9 to bridge bank end by group, to reduce the uneven side that king-tower 9 is subject to To pulling force.
Before cat road carries the installation of rope 23, suspention carrying rope 13 has been fixed in anchorage 1 and suspention carrying under suspention carrying rope It between rope upper fixed seat 2, and suspends sport car 11 in midair and has been suspended on suspention carrying rope 13, traction rope 12 is from the volume of angle mill hoist engine 10 On cylinder after 3 circle of winding, diverted wheel 6 is fixed on the suspention left and right end of sport car 11, and suspention sport car 11 moves back and forth and crane hook 22 descending strokes have met the laying demand of cat road carrying rope 23,4 lower section of tower top steel platform 5 and cat road carrying rope upper fixed seat Workbench 7 installed.
Anchorage 3 and suspention carrying rope upper fixed seat 2, suspention under the cat road carrying rope upper fixed seat 4, cat road carrying rope Anchorage 1 is all made of length 1000mm under carrying rope, and specification is made of the rail of QU80, at the center web of the rail 90mm of rail one end The through-hole that diameter is 62mm is opened up, by aperture end towards outside when rail is embedded, anchorage depth, angle combination construction site condition, It is determined with 3D simulation and Force Calculation, stress load presses 3 times that maximum cat road carries rope 23, suspends load on carrying rope 13 in midair respectively Safety coefficient is calculated.
Step 2: cat road carries rope group to (as shown in Figure 4):
Cat road carry rope 23 wirerope two ends using anchor beam 15, adjusting yoke 16, connecting rod 17, rope card 26 connection and At.Cat road carries 23 rope end of rope and fixes through rope card 6 with adjusting yoke 16, and then 16 other end of adjusting yoke is connect with anchor beam 15, Both ends anchor beam 15 carries rope upper fixed seat 4 by pin shaft 21 with cat road respectively and cat road carries anchorage 3 under rope and connect.
The adjusting yoke 16 and the equal one end of connecting rod 17 are connection wire rod and the long 600mm of thread, the other end are bar Body bends to annulus closing form, and bending internal diameter is 100mm, and 16 diameter of adjusting yoke is 42mm, the equal 800mm of length, connecting rod 17 diameters are 60mm, the equal 1000mm of length.
The 20# I-shaped steel part that the anchor beam 15 is two pieces length 3800mm forms, and I-steel is by length direction and by two I-steel is by web is parallel, wing plate is concordant, between the two away from being arranged for 65mm mode, and with I-steel length direction center line for pair Claim line, wherein side wing plate surface by distance centered on equidistant 450mm, being welded with 8 pieces of centers, to open up diameter logical for 45mm Hole, outer dimension are 150mm × 150mm, and the backing plate of thickness 40mm, pressing 2200mm on its another side wing surface is spacing, is added Welding 2 pieces of centers and opening up diameter is 62mm through-hole, and outer dimension is 150mm × 150mm, the backing plate of thickness 40mm, by two I-steel It is welded and fixed to form anchor beam 15.
The lower arrangement road Liang Zumao of a piece main rope of suspension bridge 14 carries rope 23 and is to be arranged symmetrically with king-tower 9, and every road Zu Mao is held Load rope 23 is arranged in parallel by 8 wirerope to be formed, and wirerope one end is folded to steel wire after passing through 16 closed circle of adjusting yoke backward It restricts and rope end and wirerope is fixed together, so by overlapping 1000mm with 6 rope cards 26 every 100mm in parallel along its length It will be installed with 8 adjusting yokes, the 16 screw rod end of wirerope afterwards, the wing plate opposite side of 8 pieces of backing plates is welded with from the length direction of anchor beam 15 Gap in, be attached respectively parallel across backing plate central through hole and with nut and anchor beam 15, at this time the spiral shell of adjusting yoke 16 Mother should be at maximal regulated position.The screw rod end of connecting rod 17 is then welded with to the wing of 8 pieces of backing plates from the length direction of anchor beam 15 In the intermediate space of plate side, two pieces of backing plate central through holes that two connecting rods 17 are arranged from the other side of anchor beam 15 are worn respectively Out, and connecting rod 17 and anchor beam 15 are realized with nut and is connected, the above group pair for completing cat road carrying 23 one end of rope equally presses this Method completes the group pair of this cat road carrying 23 other end of rope.
Step 3: applying rope (as shown in Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9) in the air:
The cat road carrying towboat 20 of rope 23 that assembling finishes is transported to 9 lower section of king-tower, before the transport of towboat 20, in conjunction with cat road Carrying rope 23 is constructed whole arrangement, is applied in advance with port prison, harbour affairs, navigation channel department, publication navigation ban notice, it is ensured that cat road carrying rope The closing of navigation channel involved in 23 laid processes.
It is separately connected with hoist cable 18 at 15 center of anchor beam at cat road carrying 23 both ends of rope, with 22 fixed bridge bank end of crane hook The hoist cable 18 of anchor beam 15 is promoted at crane hook 22 to suspention sport car 11, hoist cable 18 is moved on suspention sport car 11, then tower crane 22 back hook of suspension hook, connection cat road carry at the hoist cable 18 on 23 other end anchor beam 15 of rope, slowly promote crane hook 22, the road Shi Mao Carrying rope 23 is gradually promoted, and in suspention sport car 11 and tower crane 8 to carrying off, cat road carrying rope 23 progressively disengages towboat 20, continues Crane hook 22 is promoted, cat road carrying 4 through-hole of rope upper fixed seat and 17 annulus of connecting rod is passed through with pin shaft 21, completes the carrying of cat road It is fixed at 23 king-tower 9 of rope.It starting angle and grinds hoist engine 10, suspention sport car 11 is mobile towards bridge bank end under the drive of traction rope 12, Under the action of the tractive force and suspention 11 sliding force of sport car that suspend sport car 11 in midair, cat road carrying 23 lower end anchor beam 15 of rope is moved to scattered rope Under the cat road carrying rope on saddle basis 25 at anchorage 3,3 through-hole of anchorage and connection under cat road carrying rope equally are passed through with pin shaft 21 17 annulus of bar, carrying rope 23 in completion cat road dissipates to be fixed at cable saddle.Similarly other cat roads carrying rope 23 is completed with the above laying method Laying work.
Step 4: cat road carrying rope adjustment (as shown in Figure 7):
In order to guarantee the balance of 9 horizontal force of king-tower, upstream and downstream and the road across Duan Mao carrying rope 23 should all terminate in place, And linear to the cat road carrying rope 23 at any time and displacement of king-tower 9 is monitored during the adjustment.
Cat road carries rope 23 should carry out live adjustment according to its sky cable absolute altitude, to guarantee cat road carrying 23 line style of rope and main push-towing rope 14 unloaded line styles are almost the same.Chain block 19 is set between anchor beam 15 and adjusting yoke 16, is cooperated by chain block 19 Adjusting yoke 16 completes the adjustment of tightness of steel wire rope state, keeps 8 steel wire rope tensions consistent, and cat road carries the wirerope tune of rope 23 It is whole to be carried out by the way of being pulled by root.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (4)

1. a kind of self-anchored suspension bridge construction laying method of cat road carrying rope, it is characterized in that: by the suspention of main push-towing rope laying, Tower top steel platform on the king-tower of tower crane and the cable saddle lifting of Construction of Pylon, in advance by the grouping of cat road carrying rope setting, by steel wire Rope is placed in parallel by arrangement spacing, and use anchor beam, adjusting yoke, connecting rod, rope card by laid parallel respectively at its both ends and Justified wirerope connects to form cat road carrying rope, with towboat by the cat road carrying Suo Yunzhi king-tower lower section of grouping, then uses Tower crane and suspention lift, and realize the aerial laying of cat road carrying rope and are fixed in corresponding fixed point, similarly complete suspension bridge Other cat roads carry rope laying, to complete the aerial laying work of cat road carrying rope;
Cat road carrying rope (23) includes anchorage (3), anchor beam under cat road carrying rope upper fixed seat (4), cat road carrying rope (15), adjusting yoke (16), connecting rod (17), rope card (26) and wirerope, laying method include the following steps:
Step 1: preparation of construction:
According to the linear of main rope of suspension bridge (14), the both ends for calculating cat road carrying rope (23) carry in the road bridge An Duanmao respectively Anchorage (3) and king-tower (9) road Shang Mao carrying rope upper fixed seat (4) position dimension and suspention carrying rope (13) both ends point under rope Suspention carrying rope upper fixed seat (2) position dimension under rope at anchorage (1) and tower top steel platform (5) is not carried in suspention;Cat Road carries rope (23) centered on main push-towing rope (14) center line and parallel and position lower than main push-towing rope (14) center line 1500mm is meter The road Suan Mao carries rope (23) and installs theoretical position;
Anchorage (3) dissipates at bridge bank end under cat road carrying rope synchronizes embedded, cat road carrying Suo Shanggu when cable saddle basic (25) is constructed Reservation (4) is synchronous in king-tower (9) concrete construction to be implemented, and anchorage (1) is in bridge bank end main push-towing rope anchorage base under suspention carrying rope Synchronous construction when plinth (24) concrete construction, suspention carrying rope upper fixed seat (2) directly with tower top steel platform (5) column side into Row is welded and fixed;
Cat road carrying rope (23) is symmetrically laid with king-tower (9) to bridge bank end by group, to reduce the imbalance that king-tower (9) is subject to Lateral force;
Before cat road carrying rope (23) is installed, it is ensured that suspention carrying rope (13) has been fixed in suspention and carries anchorage (1) under rope and hang Hang carrying rope upper fixed seat (2) between, and suspend in midair sport car (11) be suspended on suspention carrying rope (13) on, traction rope (12) from Angle is ground on the reel of hoist engine (10) after 3 circle of winding, and diverted wheel (6) is fixed on suspention sport car (11) left and right end, and suspention is run Vehicle (11) moves back and forth and crane hook (22) descending stroke has met the laying demand that cat road carries rope (23), and tower top steel is flat Workbench (7) below platform (5) and cat road carrying rope upper fixed seat (4) has installed;
Step 2: cat road carries rope group pair:
The wirerope of the every road Zu Mao carrying rope (23) is 8, is placed in parallel by arrangement spacing, the two ends of each wirerope are all made of Anchor beam (15), adjusting yoke (16), connecting rod (17), rope card (26) are formed by connecting;Wherein, each steel wire of cat road carrying rope (23) The rope end of rope is fixed through rope card (6) and adjusting yoke (16), and then adjusting yoke (16) other end is connect with anchor beam (15), then The fixed connecting rod (17) on anchor beam (15), the i.e. group pair of completion cat road carrying rope (23) one end;Equally according to said method complete this The group pair of cat road carrying rope (23) other end;Then the group pair at other roads Zu Mao carrying rope (23) both ends is completed again;The cat road The connecting rod (17) on the both ends anchor beam (15) of rope (23) is carried for holding respectively with cat road carrying rope upper fixed seat (4) and cat road Anchorage (3) under rope is carried to connect;
Step 3: applying rope in the air:
Cat road carrying rope (23) that assembling finishes is transported to below king-tower (9) with towboat (20), is separately connected cat with hoist cable (18) Road carries at anchor beam (15) center at rope (23) both ends, with the hoist cable (18) of crane hook (22) fixed bridge bank end anchor beam (15), It is promoted at crane hook (22) to suspention sport car (11), hoist cable (18) is moved in suspention sport car (11), then crane hook (22) back hook, connection cat road carry at the hoist cable (18) on rope (23) other end anchor beam (15), slowly promote crane hook (22), The road Shi Mao carrying rope (23) is gradually promoted, and in suspention sport car (11) and tower crane (8) to carrying off, cat road carries rope (23) and gradually takes off From towboat (20), crane hook (22) are continued to lift up, so that anchor beam (15) is moved at cat road carrying rope upper fixed seat (2), so The connecting rod (17) on anchor beam (15) is fixedly connected with cat road carrying rope upper fixed seat (2) afterwards, completes cat road carrying rope (23) King-tower is fixed at (9);Angle mill hoist engine (10) is started, sport car (11) is suspended in midair and is moved under the drive of traction rope (12) towards bridge bank end Dynamic, under the action of suspending the tractive force and suspention sport car (11) sliding force of sport car (11) in midair, cat road carries rope (23) lower end anchor beam (15) be moved under the cat road carrying rope of scattered cable saddle basic (25) at anchorage (3), by anchor beam (15) connecting rod (17) with Anchorage (3) is fixedly connected under cat road carrying rope, completes to fix at the scattered cable saddle of cat road carrying rope (23);Similarly with the above laying side Method completes the laying work of other cat roads carrying rope (23);
Step 4: cat road carrying rope adjustment:
In order to guarantee the balance of king-tower (9) horizontal force, upstream and downstream and the road across Duan Mao carrying rope (23) should all terminate in place, And linear to cat road carrying rope (23) at any time during the adjustment and king-tower (9) displacement is monitored;
Cat road carries rope (23) should carry out live adjustment according to its sky cable absolute altitude, to guarantee cat road carrying rope (23) line style and main push-towing rope (14) unloaded line style is almost the same;Chain block (19) are set between anchor beam (15) and adjusting yoke (16), by pulling calabash Reed (19) cooperates adjusting yoke (16), completes the adjustment of tightness of steel wire rope state, keeps every steel wire rope tension consistent, cat road carries rope (23) wirerope adjustment is carried out by the way of pulling by root.
2. a kind of laying method of self-anchored suspension bridge construction cat road carrying rope according to claim 1, it is characterized in that: The road the step 1 Zhong Mao carries anchorage (3) and suspention carrying rope upper fixed seat under rope upper fixed seat (4), cat road carrying rope (2), anchorage (1) is all made of length 1000mm under suspention carrying rope, and specification is made of the rail of QU80, in rail one end web of the rail The through-hole that diameter is 62mm is opened up at the center 90mm, by aperture end towards outside when rail is embedded, anchorage depth, angle combine construction Field condition determines that stress load presses maximum cat road carrying rope (23), suspention carrying rope respectively with 3D simulation and Force Calculation (13) 3 times of safety coefficients of load are calculated on.
3. a kind of laying method of self-anchored suspension bridge construction cat road carrying rope according to claim 2, it is characterized in that: One end is connection wire rod and the long 600mm of thread, the other end are for the step 2 adjusting yoke (16) and connecting rod (17) The body of rod bends to annulus closing form, and bending internal diameter is 100mm, and adjusting yoke (16) diameter is 42mm, the equal 800mm of length, connects Extension bar (17) diameter is 60mm, the equal 1000mm of length;
The 20# I-shaped steel part that the anchor beam (15) is two pieces length 3800mm forms, and I-steel is by length direction and by two works Word steel between the two away from being arranged for 65mm mode, and is symmetrical with I-steel length direction center line by web is parallel, wing plate is concordant Line, the distance centered on equidistant 450mm is pressed on the wing plate surface of wherein side, being welded with 8 pieces of centers and opening up diameter is 45mm through-hole, Outer dimension is 150mm × 150mm, and the backing plate of thickness 40mm, pressing 2200mm on its another side wing surface is spacing, is welded with 2 It is 62mm through-hole that block center, which opens up diameter, and outer dimension is 150mm × 150mm, and the backing plate of thickness 40mm welds two I-steel Fixation forms anchor beam (15);
The road Liang Zumao carrying rope (23) is arranged under a piece main rope of suspension bridge (14) and is to be arranged symmetrically with king-tower (9), every road Zu Mao Wirerope one end of carrying rope (23) is folded to wirerope after passing through adjusting yoke (16) closed circle backward and puts down along its length Row overlapping 1000mm, blocks (26) with 6 ropes, rope end and wirerope is fixed together every 100mm, then will be installed with wirerope 8 adjusting yoke (16) screw rod ends, be welded with from the length direction of anchor beam (15) in the gap of the wing plate opposite side of 8 pieces of backing plates, It is attached respectively parallel across backing plate central through hole and with nut and anchor beam (15), the nut of adjusting yoke (16) should be located at this time In maximal regulated position;The screw rod end of connecting rod (17) is then welded with to the wing plate of 8 pieces of backing plates from the length direction of anchor beam (15) In the intermediate space of side, two connecting rods (17) are arranged from the other side of anchor beam (15) respectively two pieces of backing plate central through holes It is pierced by, and connecting rod (17) and anchor beam (15) is realized with nut and are connected, the above group pair for completing cat road carrying rope (23) one end, Equally according to said method complete the group pair of this cat road carrying rope (23) other end.
4. a kind of laying method of self-anchored suspension bridge construction cat road carrying rope according to claim 3, it is characterized in that: The step 3 passes through the annulus of cat road carrying rope upper fixed seat (4) through-hole and connecting rod (17) with pin shaft (21), completes cat road It is fixed at carrying rope (23) king-tower (9);Equally anchorage (3) through-hole and connecting rod under cat road carrying rope are passed through with pin shaft (21) (17) annulus is completed to fix at the scattered cable saddle of cat road carrying rope (23).
CN201710701769.XA 2017-08-16 2017-08-16 A kind of laying method of self-anchored suspension bridge construction cat road carrying rope Active CN107447665B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710701769.XA CN107447665B (en) 2017-08-16 2017-08-16 A kind of laying method of self-anchored suspension bridge construction cat road carrying rope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710701769.XA CN107447665B (en) 2017-08-16 2017-08-16 A kind of laying method of self-anchored suspension bridge construction cat road carrying rope

Publications (2)

Publication Number Publication Date
CN107447665A CN107447665A (en) 2017-12-08
CN107447665B true CN107447665B (en) 2019-01-22

Family

ID=60492650

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710701769.XA Active CN107447665B (en) 2017-08-16 2017-08-16 A kind of laying method of self-anchored suspension bridge construction cat road carrying rope

Country Status (1)

Country Link
CN (1) CN107447665B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643057B (en) * 2018-06-20 2019-08-20 大连理工大学 A kind of interim anchor cable in girder of suspension bridge erection process balances construction method
CN109554968B (en) * 2019-01-14 2024-02-20 中国十七冶集团有限公司 Device for laying carrier cable of aerial cableway and construction method thereof
CN109914258B (en) * 2019-04-08 2024-01-23 中国铁建大桥工程局集团有限公司 Self-anchored suspension bridge catwalk bearing cable steering structure
CN110438880B (en) * 2019-08-21 2021-04-20 中国水利水电第八工程局有限公司 Construction method and construction system for erecting cat track cable of large-span suspension bridge
CN110761196A (en) * 2019-11-06 2020-02-07 中国葛洲坝集团第二工程有限公司 Adjustable catwalk anchoring and connecting device
CN112195784B (en) * 2020-09-15 2022-06-17 中交第二公路工程局有限公司 Catwalk sag adjustment system and adjustment method for erecting main cable by adopting air spinning method
CN117776001B (en) * 2024-02-26 2024-05-03 贵州省公路工程集团有限公司 Suspension bridge pin joint type sling lifting system and installation method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6429507A (en) * 1987-07-24 1989-01-31 Ishikawajima Harima Heavy Ind Method of supporting catwalk for suspension bridge cable erection in method of air spinning construction
CN101514543B (en) * 2009-03-16 2011-07-20 中交第二公路工程局有限公司 Mobile trolley used for erecting and removing surface of construction catwalk of suspension bridge
CN102021887A (en) * 2010-09-16 2011-04-20 长沙理工大学 Suspender tensioning method of double-tower single-span self-anchored suspension bridge with high-cross dip and spatial cable
CN201952738U (en) * 2011-01-30 2011-08-31 中交三航局第三工程有限公司 Catwalk suitable for self-anchored double-cable-plane suspension bridge
CN102392418A (en) * 2011-12-01 2012-03-28 中交二公局第二工程有限公司 Span-division erection construction method of construction catwalk of multi-tower suspension bridge
CN205329550U (en) * 2015-12-15 2016-06-22 中交一公局第三工程有限公司 Suspension bridge catwalk system

Also Published As

Publication number Publication date
CN107447665A (en) 2017-12-08

Similar Documents

Publication Publication Date Title
CN107447665B (en) A kind of laying method of self-anchored suspension bridge construction cat road carrying rope
CN101476293B (en) Non-stand construction method for large bridge arch rib
CN103088750B (en) Especial-big span suspension bridge of uniparted hyperboloid space rope net main cable and construction method thereof
CN202090286U (en) Traction system suitable for self-anchored type double cable plane suspension bridge
CN105565176B (en) A kind of asymmetric cable crane of single column
KR101171039B1 (en) Partially and fully earth-anchored cable-stayed bridge using main span prestressing appratus and construction method for the same
CN101418542B (en) Cable system construction method of spatial self-anchored rope-suspension bridge
CN201943007U (en) Constant amplitude frame beam crane capable of being used in combination with movable support frame
CN103938552B (en) Steel truss arched bridge self-balancing cantilever construction method and the spacing bearing of main pier
CN106758767B (en) A kind of suspension bridge segmented cat road and its construction method
CN101224856A (en) Long-span load-carrying cable lifting machine and mounting method therefor
CN106245527B (en) A kind of erection method of dicyclic suspender and Long span cat road track cable
CN107190627A (en) Part earth anchored suspension bridge and its construction method
CN103882812A (en) Construction method for midspan main beams of cable-stayed bridge
CN109537729A (en) A kind of construction method suitable for single-layer bidirectional Orthogonal Cable net
CN212025936U (en) Equipment for mounting continuous steel strand stay cable at tower end of cable-stayed bridge
CN203755129U (en) Hybrid-beam cable-stayed and suspension coordinated bridge
CN106988229A (en) A kind of hybrid structure of arch and beam continuous rigid frame bridge button hangs branch convolution constructing device and method
CN106012841A (en) Cable crane and installation method thereof
CN106884371B (en) A kind of non-uniform beam and suspension cable combined bridge structural system
CN101476286A (en) Railway bridge deck prestressed concrete vertical and horizontal girder lattice type floating system construction method
CN107012797B (en) A kind of construction system that Support Method is combined with stayed knotting method and method
CN206346120U (en) A kind of pin-connected panel tower with suspended cable system
CN205529915U (en) Ladder type masts type hangs pieces together loop wheel machine
CN208733454U (en) CFST Arch Bridge external prestressing tie-rod system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant