CN107419739A - A kind of novel building bottom plate dewatering construction method - Google Patents

A kind of novel building bottom plate dewatering construction method Download PDF

Info

Publication number
CN107419739A
CN107419739A CN201710487816.5A CN201710487816A CN107419739A CN 107419739 A CN107419739 A CN 107419739A CN 201710487816 A CN201710487816 A CN 201710487816A CN 107419739 A CN107419739 A CN 107419739A
Authority
CN
China
Prior art keywords
osmos tube
foundation trench
aqueducts
construction
osmos
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710487816.5A
Other languages
Chinese (zh)
Other versions
CN107419739B (en
Inventor
张仲林
高贯伟
李牧
金京华
成功
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201710487816.5A priority Critical patent/CN107419739B/en
Publication of CN107419739A publication Critical patent/CN107419739A/en
Application granted granted Critical
Publication of CN107419739B publication Critical patent/CN107419739B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • E02D31/12Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure

Abstract

The present invention provides a kind of novel building bottom plate dewatering construction method, belongs to architectural engineering dewatering construction technical field, the present invention 1)First before the construction of building bottom cushion, osmos tube position is positioned, excavates osmos tube foundation trench, osmos tube is then laid and backfills;2)Parcel closing, DN25 aqueducts pouring molding together with concrete floor are carried out to the DN25 aqueducts for reserving osmos tube top;3)Osmos tube is connected by DN25 aqueducts, and every a string at least two outlets guide to underground water in catch pit nearby, and are discharged to municipal pipeline by water pump.The present invention synchronous with building construction of bottom plates can be carried out, and intert operation, can arrange cross construction, and it is short to take time duration.

Description

A kind of novel building bottom plate dewatering construction method
Technical field
The present invention relates to architectural engineering dewatering construction technology, more particularly to a kind of novel building bottom plate dewatering construction method.
Background technology
With the continuous development of modernization construction, big and small infrastructure, it is necessarily required to these underground structures Let out drainage pressure-reducing control technology to be studied, realize the purpose of structural anti-buoyancy, how under minimum cost, solve these drainings Pressure release problem, it is the key point that effective exploitation underground space needs consider to make its influence minimum to surrounding enviroment.
In the engineering construction of reality, when architectural engineering underground structure is if in the part less than Soil Surrounding water level When, the entirety or part of structure will be acted on by buoyancy, usually through uplift pile is played, by the friction of pile body and soil layer Power resists axial tension to offset soil reclaimed water to buoyancy caused by structure.Uplift pile is widely used in big basement and resisted Floating, towering buildings or structures resistance to plucking, tidal quay platform resistance to plucking, rock anchorage base, the Large Ship Dock bottom plate of suspension bridge and cable-stayed bridge Pile foundation and dead load test pile in rock anchorage base etc..But due to uplift pile long construction period, construction cost is high, for engineering Construction period has a great influence.
The content of the invention
In order to solve problem above, the present invention provides a kind of simple, low cost, shortens the duration, be cost-effective and be easy to The novel building bottom plate dewatering construction method of quality control on construction.
A kind of basement bottom board precipitation system and its construction method:
(1)First before the construction of building bottom cushion, osmos tube position is positioned according to drawing unwrapping wire, excavates osmos tube foundation trench, Then lay osmos tube and backfill;
(2)With sealing compound parcel closing, D25 aqueducts are carried out to reserving the D25 aqueducts on osmos tube
(3)Osmos tube is connected by DN25 aqueducts, and every a string at least two outlets guide to underground water in catch pit nearby, and Municipal pipeline is discharged to by water pump.
The step(1)In osmos tube foundation trench excavation method be:Osmos tube position is positioned according to drawing unwrapping wire, excavation oozes Saturating pipe foundation trench size is 500mm × 500mm × 700mm, and side wall and hole bottom surface dust are removed totally, and osmos tube foundation trench is located at base pad Under layer, completed before bottom cushion is constructed.
For more preferable draining, filtering, not blocking, osmos tube uses DN100 coating steel pipes, the Ф 10 of pipe periphery perforate 20, Pipe range 600mm, for pitch-row between 7~12cm, DN100 galvanized pipes are suitable for reading to be provided with necking, and D25 aqueducts are drawn at necking, are added One section of D25 aqueduct is accessed before work, in inside pipe wall and outer wall brushing asphalt caulk after the completion of osmos tube perforate, then it is closely knit with non-woven fabrics Swathe, after swathing, in non-woven fabrics outer layer brushing asphalt caulk again, carry out preservative treatment.
Preferably, the step(1)In osmos tube lay and backfill construction technology be:In the osmos tube base excavated One 300mm × 300mm × 700mm wooden model is put into groove, first at osmos tube foundation trench bottom before osmos tube is put into osmos tube foundation trench 50mm thickness cobblestones are laid in portion, and osmos tube is placed in osmos tube foundation trench between two parties;Particle diameter 10mm is backfilled between osmos tube and wooden model ~30mm grading cobble, coarse sand is backfilled between wooden model and osmos tube foundation trench wall;Wooden model is ejected with reinforcing bar after the completion of backfill, then Loaded filter is tamped.
Preferably, the step(2)In aqueduct construction technique be:Slab Waterproof Construction sealing compound is to pre- The DN25 aqueducts on osmos tube are stayed to carry out parcel closing, DN25 aqueducts are erected in the middle part of bottom plate and bottom plate bearing rod colligation Firmly, the pouring molding together with concrete floor.
Preferably, the catch pit is the reserved hole of construction of bottom plates, masterplate sizing is installed before concreting.
Preferably, installing water pump after the completion of the catch pit cleaning, water pump sets a ball float automatic water pumping device for water, in water Position automatically turns on water pump after reaching certain altitude, the automatic closing water pump after water level decreasing.
Preferably, connecing 1 manometer and 2 taps on the aqueduct, a tap is normally opened, a tap Opened in heavy rain or wet season, tap and manometer are installed by catch pit side wall.
The beneficial effects of the invention are as follows
1st, it synchronous with building construction of bottom plates can be carried out using construction method of the present invention, the installation of precipitation system, intert operation, Cross construction can be arranged, it is short to take time duration.
2nd, the material that precipitation system of the present invention uses is simple plumbing traditional construction material, and cost is low, can be on the spot Materials, and it is environmentally safe, security is good.
3rd, groundwater pressure can be viewed according to real-time pipeline pressure monitoring table, is adjusted according to pressure size and monitoring location Level of ground water is saved, avoids producing excessive disturbing influence surrounding enviroment to building level of ground water.
4th, preservative treatment is carried out to termination osmos tube with asphalt caulk, anti-corrosive durability is good, reduces later maintenance cost.
Brief description of the drawings
Fig. 1 is the scheme of installation of the present invention;
Fig. 2 is the osmos tube foundation trench detail drawing of the present invention;
Fig. 3 is the osmos tube detail drawing of the present invention.
In figure:1 osmos tube, 2 osmos tube foundation trenches, 3 DN25 aqueducts, 4 catch pits, 5 manometers, 6 it is flat when the normally closed fire hose Head, 7 it is flat when normally opened tap, 8 bottom cushions, 9 concrete floors, 10 building grounds, 11 grading cobbles, 12 coarse sands, 13 infiltration Pipe foundation trench wooden model, 14 DN100 coating steel pipes, 15 asphalt caulks, 16 non-woven fabrics, 17 apertures, 18 neckings.
Embodiment
More detailed elaboration is carried out to present disclosure below:
As shown in Figures 1 to 3, a kind of novel building bottom plate dewatering construction method, comprises the following steps:
(1)First before the construction of building bottom cushion 8, osmos tube position is positioned according to drawing unwrapping wire, excavates osmos tube foundation trench 2, then lay osmos tube 1 and backfill.
(2)Parcel closing is carried out to reserving the D25 aqueducts 3 on osmos tube 1 with sealing compound, D25 aqueducts 3 are erected at bottom In the middle part of plate, the pouring molding together with concrete floor 9.
(3)Osmos tube 1 is connected by DN25 aqueducts 3, and every a string at least two outlets guide to underground water nearby catchments In hole 4, and municipal pipeline is discharged to by water pump.
As shown in figure 1, the step(1)In the excavation method of osmos tube foundation trench 2 be:Osmos tube is positioned according to drawing unwrapping wire 1 position, it is 500mm × 500mm × 700mm to excavate the size of osmos tube foundation trench 2, and side wall and hole bottom surface dust remove clean, osmos tube The chi of foundation trench 2 is located under bottom cushion 8, is constructed preceding completion in bottom cushion 8.
As shown in figure 3, osmos tube 1 is using DN100 coating steel pipes 14, pipe periphery perforate mouth 17, the Ф 10 of hole 20, pipe range 600mm, for pitch-row between 7~12cm, DN100 galvanized pipes 14 are suitable for reading to be provided with necking 18, and D25 aqueducts 3 are drawn at necking 18, One section of D25 aqueduct 3 of access, in inside pipe wall and outer wall brushing asphalt caulk 15 after the completion of the perforate of osmos tube 1, then uses nonwoven before processing Cloth 16 is closely knit to be swathed, and after swathing, in the outer layer of non-woven fabrics 16 brushing asphalt caulk 15 again, carries out preservative treatment.
As shown in Fig. 2 the step(1)In osmos tube 1 lay and backfill construction technology and be:In the osmos tube excavated One 300mm × 300mm × 700mm osmos tube foundation trench wooden model 13 is put into foundation trench 2, before osmos tube 1 is put into osmos tube foundation trench 2 First in the bottom of osmos tube foundation trench 2 laying 50mm thickness gradings cobble 11, osmos tube 1 is placed in osmos tube foundation trench 2 between two parties;Osmos tube Particle diameter 10mm~30mm grading cobble 11, osmos tube foundation trench wooden model 13 and infiltration are backfilled between 1 and osmos tube foundation trench wooden model 13 Coarse sand 12 is backfilled between the wall of pipe foundation trench 2;Osmos tube foundation trench wooden model 13 is ejected with reinforcing bar after the completion of backfill, then loaded filter is rammed It is real.
As shown in figure 1, the step(2)In the construction technique of D25 aqueducts 3 be:Slab Waterproof Construction seals Cream carries out parcel closing to reserving the D25 aqueducts 3 on osmos tube, and D25 aqueducts 3 are erected in the middle part of bottom plate and bottom plate bearing rod Colligation is firm, the pouring molding together with concrete floor 9.
The catch pit 4 as shown in Figure 1 is the reserved hole of construction of bottom plates, and masterplate sizing is installed before concreting.
The catch pit 4 installs water pump as shown in Figure 1 after the completion of clearing up, and water pump sets a ball float automatic water pumping device for water, Water level automatically turns on water pump after reaching certain altitude, the automatic closing water pump after water level decreasing.
Usually normally closed tap 6, usually normally opened tap 7 and manometer 5 are connect on the aqueduct as shown in Figure 1, it is normally closed Tap 6 is only opened in heavy rain or wet season;Usually normally closed tap 6, usually normally opened tap 7 and manometer 5 by collection Puddle side wall installation.

Claims (8)

1. a kind of novel building bottom plate dewatering construction method, it is characterised in that comprise the following steps:
1)First before the construction of building bottom cushion, osmos tube position is positioned according to drawing unwrapping wire, excavates osmos tube foundation trench, so Osmos tube is laid afterwards and is backfilled;
2)Parcel closing is carried out to the DN25 aqueducts for reserving osmos tube top with sealing compound, DN25 aqueducts are set up in the soleplate Portion, the pouring molding together with concrete floor;
3)Osmos tube is connected by DN25 aqueducts, and when hydraulic pressure is larger, every a string at least two outlets guide to underground water nearby In catch pit, and municipal pipeline is discharged to by water pump.
2. the method according to claim 1, it is characterised in that the step(1)In osmos tube foundation trench excavation method For:Osmos tube position is positioned according to drawing unwrapping wire, it is 500mm × 500mm × 700mm to excavate osmos tube foundation trench size, side wall and Cheat bottom surface dust to remove totally, osmos tube foundation trench is located under bottom cushion, completes before bottom cushion is constructed.
3. the method according to claim 1, it is characterised in that the step(1)In osmos tube processing method be:Ooze Saturating pipe uses DN100 coating steel pipes, and the Ф 10 of pipe periphery perforate 20, pipe range 600mm, for pitch-row between 7~12cm, DN100 is zinc-plated Steel pipe is suitable for reading to be provided with necking, and DN25 aqueducts are drawn at necking, and one section of DN25 aqueduct of access, osmos tube perforate are complete before processing After in inside pipe wall and outer wall brushing asphalt caulk, then swathed with non-woven fabrics is closely knit, after swathing, in non-woven fabrics outer layer brushing pitch again Paint, carry out preservative treatment.
4. the method according to claim 1, it is characterised in that the step(1)In osmos tube lay and backfill apply Work method is:One 300mm × 300mm × 700mm wooden model is put into the osmos tube foundation trench excavated, is put into and oozes in osmos tube 50mm grading cobbles first are laid in osmos tube foundation trench bottom before saturating pipe foundation trench, osmos tube is placed in osmos tube foundation trench between two parties;Ooze Particle diameter 10mm~30mm grading cobble is backfilled between pipe and wooden model thoroughly, coarse sand is backfilled between wooden model and osmos tube foundation trench wall;Return Wooden model is ejected with reinforcing bar after the completion of filling out, then loaded filter is tamped.
5. the method according to claim 1, it is characterised in that the step(2)In DN25 aqueduct installations Method is:Slab Waterproof Construction carries out parcel closing with sealing compound to reserving the aqueduct on osmos tube, and DN25 aqueducts are set up Portion and bottom plate bearing rod colligation are firm in the soleplate, the pouring molding together with concrete floor.
6. the method according to claim 1, it is characterised in that catch pit is the reserved hole of construction of bottom plates, is poured in concrete Installation masterplate sizing before building.
7. according to the method for claim 6, it is characterised in that water pump is installed, water pump sets floating after the completion of catch pit cleaning Ball automatic water pumping device for water, water pump is automatically turned on after water level reaches certain altitude, the automatic closing water pump after water level decreasing.
8. the method according to claim 1, it is characterised in that connect 1 manometer and 2 taps on aqueduct, one Individual tap is normally opened, and a tap is only opened in heavy rain or wet season, and tap and manometer are pacified by catch pit side wall Dress.
CN201710487816.5A 2017-06-23 2017-06-23 A kind of building bottom plate dewatering construction method Active CN107419739B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710487816.5A CN107419739B (en) 2017-06-23 2017-06-23 A kind of building bottom plate dewatering construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710487816.5A CN107419739B (en) 2017-06-23 2017-06-23 A kind of building bottom plate dewatering construction method

Publications (2)

Publication Number Publication Date
CN107419739A true CN107419739A (en) 2017-12-01
CN107419739B CN107419739B (en) 2019-04-19

Family

ID=60427217

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710487816.5A Active CN107419739B (en) 2017-06-23 2017-06-23 A kind of building bottom plate dewatering construction method

Country Status (1)

Country Link
CN (1) CN107419739B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114293578A (en) * 2021-12-31 2022-04-08 广西建工第五建筑工程集团有限公司 Basement drainage and water level monitoring system and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2746058A1 (en) * 1977-10-13 1979-04-26 Komp Hermann Josef Dipl Ing Draining surroundings of buildings without construction work - using tubes projecting into soil connected to automatic pumping system
CN101705691A (en) * 2009-10-30 2010-05-12 南通建工集团股份有限公司 Construction method of dewatering well under foundation slab in foundation pit
CN202706063U (en) * 2012-06-15 2013-01-30 南京工业大学 Waterproof moistureproof system for basement
CN205152970U (en) * 2015-10-23 2016-04-13 金磐集团有限公司 Underground structure oozes drainage system
CN106065627A (en) * 2016-07-06 2016-11-02 上海建工四建集团有限公司 Building base plate drainage system and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2746058A1 (en) * 1977-10-13 1979-04-26 Komp Hermann Josef Dipl Ing Draining surroundings of buildings without construction work - using tubes projecting into soil connected to automatic pumping system
CN101705691A (en) * 2009-10-30 2010-05-12 南通建工集团股份有限公司 Construction method of dewatering well under foundation slab in foundation pit
CN202706063U (en) * 2012-06-15 2013-01-30 南京工业大学 Waterproof moistureproof system for basement
CN205152970U (en) * 2015-10-23 2016-04-13 金磐集团有限公司 Underground structure oozes drainage system
CN106065627A (en) * 2016-07-06 2016-11-02 上海建工四建集团有限公司 Building base plate drainage system and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114293578A (en) * 2021-12-31 2022-04-08 广西建工第五建筑工程集团有限公司 Basement drainage and water level monitoring system and construction method thereof
CN114293578B (en) * 2021-12-31 2023-10-20 广西建工第五建筑工程集团有限公司 System for monitoring drainage and water level of basement and construction method thereof

Also Published As

Publication number Publication date
CN107419739B (en) 2019-04-19

Similar Documents

Publication Publication Date Title
CN105201002B (en) A kind of underground structure oozes drainage system and its construction method
CN101298782B (en) Method and system for basement engineering water proof and water drain
CN102454167B (en) The construction method of especially big & deep open caisson
CN201896316U (en) System for reducing and draining confined water in deep foundation pit of rock foundation
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN204530732U (en) A kind of structure of the precipitation based on basement elevator shaft plash
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN109797769B (en) Collapsible loess area underground comprehensive pipe gallery foundation structure and construction method thereof
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN112144584A (en) Self-flowing drainage pressure-limiting anti-floating structure and construction method
CN105569094A (en) Water discharge and drainage system and construction method adopting basement bottom plate water buoyant force releasing method
CN101936032A (en) Method for mounting and constructing polyethylene double-wall corrugated water discharge pipe
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN109372016A (en) Basement bottom plate rear pouring tape structure and construction method under high artesian
CN105544622A (en) Floating resisting device, and seepage insulation device and drainage path checking device thereof for underground building
CN105970882B (en) Solve the structure and its building method of face dam construction time dam body reverse osmosis water problems
CN202440826U (en) Waterproof system for high-water level basement foundation slabs
CN205077527U (en) Drainage system is dredged to basement bottom plate release water buoyancy method
CN107419739B (en) A kind of building bottom plate dewatering construction method
CN206289732U (en) A kind of active antiseepage basement shear wall
CN214245855U (en) Water-proof pressure-control anti-floating structure
CN209353360U (en) The anti-floating drainage arrangement of basement structure
CN214657275U (en) Self-flowing drainage pressure-limiting anti-floating structure
CN110565774B (en) Construction method of basement open drainage system with weak permeability soil
CN114293578A (en) Basement drainage and water level monitoring system and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant