A kind of large revolving body cover flange numerical control alignment device and method Download PDFInfo
- Publication number
- CN107414700A CN107414700A CN201710700044.9A CN201710700044A CN107414700A CN 107414700 A CN107414700 A CN 107414700A CN 201710700044 A CN201710700044 A CN 201710700044A CN 107414700 A CN107414700 A CN 107414700A
- Authority
- CN
- China
- Prior art keywords
- flange
- numerical control
- revolving body
- support platform
- installation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B25—HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
- B25B—TOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
- B25B11/00—Work holders not covered by any preceding group in the subclass, e.g. magnetic work holders, vacuum work holders
Abstract
A kind of large revolving body cover flange numerical control alignment device and method, belong to mechanical manufacturing field, including the large revolving body being placed on Numerical control bracket, and equipment is installed in the flange numerical control positioned at large revolving body both ends.Transverse shifting track centerline in flange numerical control installation equipment bag overlaps with large revolving body center line;Vertically moving track can move in numerical control on transverse shifting track, and flange support platform is used for the cover flange that is connected, and numerical control can be moved on long rails.Mounting disc is first directed at installation with flange support platform, cover flange is directed at installation with mounting disc;Longitudinally, laterally rotary flange support platform again, coaxial positioning, axially position are realized respectively, and complete the alignment installation of one end cover flange;Finally complete the alignment installation of other end end socket flange.The present invention can solve the problem that the both ends cover flange alignment issues of large revolving body, realize the accurate installation of large revolving body both ends cover flange, and automaticity is high, and labor intensity is low.
Description
Technical field
The invention belongs to mechanical manufacturing field, more particularly to a kind of end flanges alignment device of large revolving body two and method.
Background technology
Large revolving body component diameter, length are big, and cover flange alignment assembling in both ends is difficult.At present, to large revolving body
Both ends cover flange is aligned more using driving lifting, the method for manual-alignment, and labor intensity is big, and assembly period is grown, assembly precision
It is low.
Chen Peng etc. proposes one kind in patent " a kind of large scale equipment lifting alignment device " and is related to power equipment technology neck
The problem of large scale equipment in domain lifts by crane alignment methods, and this method improves existing large-scale lifting operation difficulty, ensure lifting precision, section
Human-saving material resources.Cao Zhonghua etc. passes through copper tapered sleeve in patent " a kind of shafting flange pilot hole align structures and alignment methods "
Cooperation with boring rod, realize on two adpting flanges that pilot hole is aligned, assembling is time saving and energy saving, and operating efficiency is high, without manually repeatedly
Regulation.Cao Zhiyun etc. proposes a kind of game equipment track in patent " a kind of game equipment track splicing line-up jig and method "
Splice line-up jig and method, for the docking of both sides orbitron, solve game equipment track installation middle orbit termination mismatch,
The problems such as deviation, improve alignment precision.
The content of the invention
The problem of existing for prior art, the present invention propose a kind of end flanges alignment methods of large revolving body two, use
In the end flanges alignment device of large revolving body two.
In order to achieve the above object, the technical scheme is that:
A kind of end flanges alignment device of large revolving body two, including Numerical control bracket 1, large revolving body 2, flange numerical control installation
Equipment 3.Described large revolving body 2 is placed on Numerical control bracket 1, and Numerical control bracket 1 is used to support large revolving body 2.
Described flange numerical control installation equipment 3 is integral device, including transverse shifting track 4, vertically moves track 5 and method
Blue support platform 6 and digital control system, flange numerical control installation equipment 3 are located at the left and right ends of large revolving body 2, and transverse shifting rail
The center line of road 4 overlaps with the center line of large revolving body 2.The described track 5 that vertically moves passes through guideway and transverse shifting track 4
Connection, numerical control it can be moved on transverse shifting track 4.Described flange support platform 6 is by guideway and vertically moves rail
Road 5 connects, and numerical control can be moved on long rails 5, and flange support platform 6 is used for the cover flange that is connected, flange support
Platform 6 connects through mounting disc realization with cover flange, is first bolted cover flange and mounting disc, then will installation
Disk is bolted with flange support platform 6.
Using said apparatus the end flanges of large revolving body two are aligned with the method for installation, is comprised the following steps:
(1) mounting disc is directed at installation with flange support platform 6
Mounting disc is mounted by means of bolts in flange support platform 6, and ensures the flange groove and method of mounting disc
The groove of blue support platform 6 overlaps.
(2) cover flange is directed at installation with mounting disc
Cover flange is connected by bolt with installation reel flanges, ensures cover flange groove and the flange groove of mounting disc
Overlap, cover flange is fixedly connected by mounting disc with flange support platform 6, and the circumferentially positioned information of cover flange is accurately passed
It is delivered in flange support platform 6.
(3) flange support platform 6 is vertically moved
After cover flange is fixed in flange support platform 6, the digital control system that equipment 3 is installed by numerical control drives method
Blue support platform 6 track 5 that moves longitudinally is moved to the cover flange position coaxial with large revolving body 2, realizes coaxial positioning.
(4) transverse shifting flange support platform 6
Track 4 is laterally moved by the digital control system driving flange support platform 6 of numerical control installation equipment 3 and is moved to installation
The position that disk contacts with the shaft shoulder, realizes axially position.
(5) installed along the support shaft of large revolving body 2 and screw mounting disc fixing nut, mounting disc is fixed on large-scale time
After in the support shaft of swivel 2, the connection between flange support platform 6 and mounting disc is removed, completes the alignment of one end cover flange
Installation.
(6) repeat the above steps, realize the alignment installation of other end end socket flange.
Advantage of the invention is that:Solve the both ends cover flange alignment issues of large revolving body, can realize large-scale time
The accurate installation of both ends cover flange is turned, automaticity is high, and labor intensity is low.
Brief description of the drawings
Fig. 1 is cover flange aligning equipment layout drawing in large revolving body both ends of the present invention.
In figure:1 Numerical control bracket, 2 large revolving bodies, 3 flange numerical controls installation equipment, 4 transverse shifting tracks, 5 vertically move
Track, 6 flange support platforms.
Embodiment
Below in conjunction with the embodiment of technical scheme and accompanying drawing, in detail the narration present invention.
A kind of end flanges alignment device of large revolving body two, including Numerical control bracket 1, large revolving body 2, flange numerical control installation
Equipment 3, large revolving body 2 are placed on Numerical control bracket 1, and Numerical control bracket 1 is used to support large revolving body 2;Flange numerical control is installed
Equipment 3 includes transverse shifting track 4, vertically moves track 5 and flange support platform 6 and digital control system, and flange numerical control installation is set
Standby 3 are located at the left and right ends of large revolving body 2, and the center line of transverse shifting track 4 overlaps with the center line of large revolving body 2.It is vertical
It is connected, numerical control can be moved on transverse shifting track 4 with transverse shifting track 4 by guideway to moving track 5.Flange branch
Support platform 6 is connected by guideway with vertically moving track 5, numerical control can be moved on long rails 5, flange support platform 6
For the cover flange that is connected, flange support platform 6 connects through mounting disc realization with cover flange, first by cover flange
It is bolted with mounting disc, then mounting disc and flange support platform 6 is bolted.
Using said apparatus the end flanges of large revolving body two are aligned with the method for installation, is comprised the following steps:
(1) mounting disc is directed at installation with flange support platform 6
Mounting disc is mounted by means of bolts in flange support platform 6, and ensures the flange groove and method of mounting disc
The groove of blue support platform 6 overlaps.
(2) cover flange is directed at installation with mounting disc
Cover flange is connected by bolt with installation reel flanges, ensures cover flange groove and the flange groove of mounting disc
Overlap, cover flange is fixedly connected by mounting disc with flange support platform 6, and the circumferentially positioned information of cover flange is accurately passed
It is delivered in flange support platform 6.
(3) flange support platform 6 is vertically moved
After cover flange is fixed in flange support platform 6, the digital control system that equipment 3 is installed by numerical control drives method
Blue support platform 6 track 5 that moves longitudinally is moved to the cover flange position coaxial with large revolving body 2, realizes coaxial positioning.
(4) transverse shifting flange support platform
Track 4 is laterally moved by the digital control system driving flange support platform 6 of numerical control installation equipment 3 and is moved to installation
The position that disk contacts with the shaft shoulder, realizes axially position.
(5) installed along the support shaft of large revolving body 2 and screw mounting disc fixing nut, mounting disc is fixed on large-scale time
After in the support shaft of swivel 2, the connection between flange support platform 6 and mounting disc is removed, completes the alignment of one end cover flange
Installation.
(6) repeat the above steps, realize the alignment installation of other end end socket flange.
Claims (2)
- A kind of 1. end flanges alignment device of large revolving body two, it is characterised in that the described end flanges of large revolving body two alignment Device includes Numerical control bracket (1), large revolving body (2), flange numerical control installation equipment (3), and large revolving body (2) is located at numerical control branch On frame (1), Numerical control bracket (1) is used to support large revolving body (2);Described flange numerical control installation equipment (3) include transverse shifting track (4), vertically move track (5) and flange support is put down Platform (6), digital control system, flange numerical control installation equipment (3) are located at large revolving body (2) left and right ends, and transverse shifting track (4) Center line overlaps with large revolving body (2) center line;The described track (5) that vertically moves passes through guideway and transverse shifting track (4) connect, numerical control can be moved on transverse shifting track (4);Described flange support platform (6) passes through guideway and longitudinal direction Moving track (5) connects, and numerical control can be moved on track (5) is vertically moved, flange support platform (6) is used to connect end socket method Orchid, cover flange are connected with mounting disc, and mounting disc is connected with flange support platform (6).
- 2. using the device described in claim 1 end flanges of large revolving body two are directed at the method for installation, it is characterised in that with Lower step:1) mounting disc is directed at installation with flange support platform (6)Mounting disc is fixedly mounted in flange support platform (6), and ensures the flange groove and flange support platform of mounting disc (6) groove overlaps;2) cover flange is directed at installation with mounting discCover flange is connected with installation reel flanges, ensures that cover flange groove overlaps with the flange groove of mounting disc, end socket method Orchid is fixedly connected by mounting disc with flange support platform (6), and the circumferentially positioned information transmission of cover flange to flange is supported On platform (6);3) flange support platform (6) is vertically movedAfter cover flange is fixed in flange support platform (6), the digital control system driving flange of equipment 3 is installed by numerical control Support platform (6) track (5) that moves longitudinally is moved to the cover flange position coaxial with large revolving body (2), realizes coaxial Positioning;4) transverse shifting flange support platform (6)Track (4) is laterally moved by the digital control system driving flange support platform (6) of numerical control installation equipment 3 and is moved to installation The position that disk contacts with the shaft shoulder, realizes axially position;5) installed along the support shaft of large revolving body (2) and screw mounting disc fixing nut, mounting disc is fixed on huge revolving After in the support shaft of body (2), connection of the flange support platform (6) between mounting disc is removed, completes pair of one end cover flange Quasi- installation;6) repeat the above steps, realize the alignment installation of other end end socket flange.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710700044.9A CN107414700A (en) | 2017-08-18 | 2017-08-18 | A kind of large revolving body cover flange numerical control alignment device and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710700044.9A CN107414700A (en) | 2017-08-18 | 2017-08-18 | A kind of large revolving body cover flange numerical control alignment device and method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107414700A true CN107414700A (en) | 2017-12-01 |
Family
ID=60438156
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710700044.9A Withdrawn CN107414700A (en) | 2017-08-18 | 2017-08-18 | A kind of large revolving body cover flange numerical control alignment device and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107414700A (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01103240A (en) * | 1987-10-16 | 1989-04-20 | Mitsubishi Heavy Ind Ltd | Automatic walking type fastening/loosening device for flange bolt |
CN102513959A (en) * | 2011-12-08 | 2012-06-27 | 中核能源科技有限公司 | Installing and dismantling device of high temperature gas-cooled reactor discharging equipment |
CN103071999A (en) * | 2012-12-04 | 2013-05-01 | 宿州市达瑞塑业有限责任公司 | Automatic mounting device for steel wire pipe flange |
CN104588933A (en) * | 2014-12-11 | 2015-05-06 | 江苏振光电力设备制造有限公司 | Regulating mechanism for flange assembly machine |
CN205218368U (en) * | 2015-11-05 | 2016-05-11 | 山东豪迈机械制造有限公司 | Slow -speed shaft group is to device |
CN106670778A (en) * | 2017-02-27 | 2017-05-17 | 上海电机系统节能工程技术研究中心有限公司 | Stator and machine shell press-fitting device, method and system |
-
2017
- 2017-08-18 CN CN201710700044.9A patent/CN107414700A/en not_active Withdrawn
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01103240A (en) * | 1987-10-16 | 1989-04-20 | Mitsubishi Heavy Ind Ltd | Automatic walking type fastening/loosening device for flange bolt |
CN102513959A (en) * | 2011-12-08 | 2012-06-27 | 中核能源科技有限公司 | Installing and dismantling device of high temperature gas-cooled reactor discharging equipment |
CN103071999A (en) * | 2012-12-04 | 2013-05-01 | 宿州市达瑞塑业有限责任公司 | Automatic mounting device for steel wire pipe flange |
CN104588933A (en) * | 2014-12-11 | 2015-05-06 | 江苏振光电力设备制造有限公司 | Regulating mechanism for flange assembly machine |
CN205218368U (en) * | 2015-11-05 | 2016-05-11 | 山东豪迈机械制造有限公司 | Slow -speed shaft group is to device |
CN106670778A (en) * | 2017-02-27 | 2017-05-17 | 上海电机系统节能工程技术研究中心有限公司 | Stator and machine shell press-fitting device, method and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106426526B (en) | Suitable for high speed railway fragments-free track slab service sleeve automatic mounting machine device people | |
CN204800252U (en) | Exchange device of locomotive vehicle bogie | |
CN107558314A (en) | Utilize the method for track clamper transhipment track | |
CN209349807U (en) | Bracket assembling mechanism | |
CN218695430U (en) | Multi-station welding tool for forklift gantry | |
CN207155624U (en) | A kind of large revolving body cover flange numerical control alignment device | |
CN107414700A (en) | A kind of large revolving body cover flange numerical control alignment device and method | |
CN109763767A (en) | A kind of interior drilling machine constructed of subway tunnel | |
CN218904257U (en) | Petroleum pipeline coupling pre-twisting machine | |
CN210060307U (en) | Automatic assembling device for railway cantilever assembly | |
CN115815907A (en) | Portal frame type pipeline welding robot | |
CN113526372B (en) | Double pier body construction tower crane and viaduct construction method | |
CN210174877U (en) | Full-automatic 360-degree rotary table channel | |
CN109848464B (en) | Drilling execution component for tunnel drilling manipulator | |
CN104309617A (en) | Trolley capable of conveniently quickly adjusting installing position of pressure steel pipe and achieving transportation of pressure steel pipe | |
CN210596841U (en) | Cross connecting mechanism for cloud rail conveying system | |
CN110281971B (en) | Full-automatic 360-degree rotary turntable channel | |
CN210310383U (en) | Magnetic suspension vehicle suspension frame maintenance equipment | |
CN201588174U (en) | Fast articulated zero preload track connecting device | |
CN105562767B (en) | Large-scale I-steel drilling equipment | |
CN219880975U (en) | Outer strutting arrangement of major diameter penstock | |
CN219358533U (en) | Middle section main chord pin joint device | |
CN218642827U (en) | Drill rod surface repairing device for oil field | |
CN219364192U (en) | Tire type track laying machine | |
CN108517784B (en) | Anchor device of bridge girder erection machine for adapting to small curve girder erection |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20171201 |
|
WW01 | Invention patent application withdrawn after publication |